Development Engineering Innovation - SmartGrid of EMT Programs in... · Custom Components in PSCAD:...
Transcript of Development Engineering Innovation - SmartGrid of EMT Programs in... · Custom Components in PSCAD:...
Manitoba HVDC Research Centre
DevelopmentDevelopmentEngineering
Since 1981
Innovation
Manitoba HVDC Research Centre
Poland
PSCAD Seminar
J.C. Garcia, W. WiechowskiManitoba HVDC Research CentreWinnipeg, Manitoba, Canada
Manitoba HVDC Research Centre
Applications of EMT TypeApplications of EMT Type Programs in Smart Grids and
Distributed GenerationManitoba HVDC Research Centre
Manitoba HVDC Research Centre
Manitoba HVDC Research Centre
Winnipeg, Manitoba,Canada
S ft G Software Group
Research Laboratories
Classroom
40 S ff M b 40+ Staff Members
Winnipeg
Manitoba HVDC Research Centre
Manitoba HVDC Research Centre
Commercial Products PSCAD®/EMTDC™
DC Line Fault Locator System
Ice Vision ‐ Ice Detection System for AC Ice Melting Program
Training g General Power Systems
PSCAD
Engineering Services Engineering Services
Research Services
Manitoba HVDC Research Centre
PSCAD/EMTDC Users
Our users are utilities, manufacturers, industrial research centers, and consultants including three large HVDC equipment manufacturers ABB, Siemens, Areva, Toshiba, Mitsubishi, Hitachi, Fuji, and many others
More than 2 000 professional and 30 000 educationalMore than 2,000 professional and 30,000 educational licenses, in 76 countries worldwide
Manitoba HVDC Research Centre
Smart Grids & DGA popular definition of Smart Grids“Aggregate of multiple networks with multiple operators
employing varying levels of communication and employing varying levels of communication and coordination. Smart grids increase the connectivity, automation and coordination between these suppliers, consumers and networks that perform either long distance consumers and networks that perform either long distance transmission or local distribution tasks.”
A smart grid may include:A smart grid may include: “an intelligent monitoring system (communications) that
keeps track of all electricity flowing in the system”“ h bili f i i bl l i i h “the capability of integrating renewable electricity such as solar and wind (DG)”
Manitoba HVDC Research Centre
PSCAD & DG
Modernizing the grid to meet such requirements implies: A need for the revision on the distribution protection
system Sources of short circuit current (DG) where there was Sou ces o s o c cu cu e ( G) e e e e as
previously only load – Use of FCL’s Studies on the penetration of DG in the network Power quality (harmonics introduced by the use of Power quality (harmonics introduced by the use of
converters)
Manitoba HVDC Research CentreFault Current Limiters
Challenge: Network reconfigurations and the introduction of DG can
increase in short circuit levels
Solution(s): Replace breakers and busbar equipment (too costly $$$) Introduce devices that limit the short circuit current: Introduce devices that limit the short circuit current:
One time use: resistors triggered by explosive mechanisms
R bl S d t i t M ti d i Re-usable: Superconductor resistors, Magnetic devices (variable inductors)
Manitoba HVDC Research CentreCustom Components in PSCAD: FCL devices
Magnetic Fault Current Limiter
PSCAD implementation of a Super Conducting Fault Current Limiter
9
4
6
5 10 11
7 8
DC source
A2 3 1 A
B
2
2.5
9 10 11
RL1.0 [ohm]
FCLABC
DC(+) DC(-)
ABCSuperconducting
Q
1
1.5
B [T
]
P+jQ
Load
0
0.5
0 10000 20000 30000 40000 50000
H [A/m]
B USED
Manitoba HVDC Research CentreCustom Components in PSCAD: FCL devices
Fault Current Limiter
Need for reducing short circuit levels 9
4
6
5 10 11
7 8
Requirement for small voltage drop
9
2 3 1
10 11
Requirement for small voltage drop during normal operationand large voltage drop during short circuit
2AL 2nl
L
Manitoba HVDC Research CentreCustom Components in PSCAD: FCL devices
Fault Current Limiter
Need for reducing short circuit levels 9
9
2 3 1
4
6
5 10 11
10 11
7 8
0.60
0.80 Iwithout_FCL Iwith_FCL
Requirement for small voltage
0 60
-0.40
-0.20
0.00
0.20
0.40
AC li
ne c
urre
nt (k
A)
q gdrop during normal operationand large voltage drop during short circuit
-0.80
-0.60
Manitoba HVDC Research CentreLarge Scale Smart Grids
Smart Grid: “a grid that uses state of the art technology to re-route power in optimal ways to respond to a wide range of conditions”
When talking in large scale it means: Being able to control power flows in networks, FACTS,
HVDC LCC, HVDC VSC, To have the option of isolate trouble areas while minimizing
the impact to the whole network – HVDC, ex: the blackout in eastern North America - QuebecQ
Manitoba HVDC Research CentreMulti-terminal VSC in PSCADFive-terminal exampleFive terminal example
P = -401.2Q = -53.36V = 420.7
VA
T2aN
P = 2.398Q = -60.78V = 419.9
VA
640kV(+/-320kV) DC Network
AC DC
VSC T1
P t l
500km transmission Line
ACDC
P l
VSC T2T1aN
Bus1aN
AC2AC1 TLMIDMODD1 D2
VV P controlVac control
P controlVac controlPorder = 800MW Rectifier
T2P controlVac controlPorder = -400MW Inverter
150k
m c
able
500k
m tr
ansm
issi
on L
ine
P controlVac control
Cab
le14
Vs: 420.0PHs: 45.0
TL32
Vs: 420.0PHs: 0.0
P = 906.8Q = -107.5V = 420.3
VA
3a
Vac controlP control
VSC T4
DCAC
P = 3.399Q = -72.1V = 420
VA
P controlVac controlPorder = 1200MW Rectifier
T3Vdc controlVac controlInverter This is the DC slack bus to balance the total power
400km transmission Line ACDC
VSC T3
Vdc control Vac control
a
us3a
usa
AC4
Vs: 420.0PHs: 0.0
AC3
Vs: 420.0PHs: 0.0TL43
IslandedDC AC
VSC T5
P = 207.8Q = 77.5
V = 233.4
VA
5a
T5Islanded (fixed frequency with Vac control)Inverter Feed 200MW, 230 kV Load
12km
cab
le
Cab
le35
us5a
P+jQ66.667 /ph
25.0 /ph
Manitoba HVDC Research CentreMulti-terminal VSC in PSCADFive-terminal exampleFive terminal example
Advantages of VSC over LCC:
Multi-terminal operationDecoupled control of P and Q. There is no-longer need for a source of reactive power
C l l d tCan supply load centres
DisadvantagesNot yet implementedNot yet implementedNeed for DC interrupting devices (DC breakers)
Manitoba HVDC Research CentreMulti-terminal VSC in PSCADFive-terminal example
Factors to be taking into account when modeling:Development of control strategies, pole control and supervisory
t l Diff t t l d
Five terminal example
controls. Different control modes:1. Real Power P2. Reactive Power3 AC Voltage3. AC Voltage4. DC Voltage5. Islanded Operation
•Operation as an Statcom when islandedOperation as an Statcom when islanded
Manitoba HVDC Research CentreMulti-terminal VSC in PSCADFive-terminal example
Current technologies
PWM 2 d 3 l l t (ABB HVDC Li ht)
Five terminal example
PWM 2 and 3 level converters (ABB HVDC Light)Moving towards MMC
Modular Multilevel Converters (Siemens)Alstom VSC’s (previously Areva’s)Alstom VSC s (previously Areva s)
Manitoba HVDC Research CentreVSC in PSCAD: State of simulation technologytechnology
Modeling Multi-Level converters require modeling individually of each level.• Large computational burden• It creates the need for creating more computational efficient
algorithmsC t d l t f MMC d l f PSCAD ti• Current development of MMC model for PSCAD uses a time-varying Thevenin’s equivalent of the converter• It is not an approximated interfaced model, it is equivalent to
modeling the entire networkmodeling the entire network
-150
-100
-50
0
50
100
150
(kV)
Vout_M Vout_R
60
70
80
90
100
110
120
(kV)
Vout_M Vout_R
150
50
60
Manitoba HVDC Research CentreThevenin’s approach to MMC modelingmodeling
Ic13Ic1
FP13Vc13Vc1
FP1N1i1l
-
+
-
+
Ic15
Ic14
Ic3
Ic2
FP15
FP16
FP14
Vc16
Vc15
Vc14
Vc4
Vc3
Vc2
FP3
FP4
FP2
-
+
-
+
+ +
-
+
-
+
-
+TTU
VcTIcT
TTL(96)
Ic18
Ic17
Ic16
Ic6
Ic5
Ic4
FP17
FP18
FP19Vc19
Vc18
Vc17
Vc7
Vc6
Vc5FP5
FP6
FP7
-
-
+
-
+
+ +
-
+
-
+
-
TTL
Ic21
Ic20
Ic19
Ic9
Ic8
Ic7
FP20
FP21Vc21
Vc19
Vc20
Vc9
Vc8
Vc7
FP8
FP9
-
-
+
-
+
-
+
-
+
-
Ic24
Ic23
Ic22
Ic12
Ic11
Ic10
FP23
FP24
FP22
Vc24
Vc23
Vc22
Vc12
Vc11
Vc10
FP11
FP12
FP10
N1 n2l
-
+
-
+
-
+
-
+
-
+
-
+
Files:my_pscad_library.pslxSubMod96.pscxSubMod_EQUV.pscx
Manitoba HVDC Research Centre
DG: PhotoVoltaicsIn the stable region if the output power is less than the input power, the remainder shows itself in an increased DC-bus voltage which causes a subsequent decrease in power input creating an ultimately power input, creating an ultimately stable system without additional control mechanisms.
Va
D
V+V+
G
Tcell
V-
Solar Radiation(0-1000 W/m2)
Solar cell Vtemperature(0 -100 oC)
Manitoba HVDC Research Centre
DG: PhotoVoltaicsThe goal is to operate the PV system in an stable fashion while delivering maximum power: Maximum Photo-voltaic Power Tracking (MPPT)
Manitoba HVDC Research Centre
DG: PhotoVoltaicsConnection methods to the system
Manitoba HVDC Research Centre
• PSCAD is now used for a variety of ‘novel’ applications.
Wind, DFIG, VSC Solar PV ......
Manitoba HVDC Research Centre
However, basic ac system studies are still the most popular application of PSCAD.
Lightning (insulation coordination) Lightning (insulation coordination) GIS switching – Very Fast Transients (VFT) Switching over-voltages (SOV,TOV) Breaker TRV Breaker TRV Ferro resonance Other resonance issues (transformer , capacitor
banks )banks...) Protection and relaying related Motors and generators (starting, sub
synchronous resonance )synchronous resonance..) Power quality
Post contingency analysis – What went wrong and how do we avoid such events.how do we avoid such events.
Manitoba HVDC Research Centre
Few Interesting (recent) applications:..
1) Transformer Bushing failure in a power plant2) System black start restoration studies3) Fault current limiting devices3) Fault current limiting devices4) Protection
Manitoba HVDC Research Centre
Transformer Bushing failure in a power plant
Gas insulated bus-bars connect the GIS to the generator transformers.
Number of transformers failed over a period of about 2 years. Perform apparatus inspections and perform engineering
studies (simulations) to investigate the causes for the 380 kV transformer bushing failures.g
Manitoba HVDC Research Centre
Transformer Bushing failure in a power plant
• Transformers are connected to the switching station through long GIB’s.
Manitoba HVDC Research Centre
Transformer Bushing failure in a power plant
PSCAD model of a GIS station – Investigating very fast transients (VFT)
350
D724
a1
BUST781T
BUST771T
300[pF] Power Transformer
2[uH]
0.22.6
300[pF] Power Transformer
ET771
2[uH]
0.22.6
ET781
Transformer6[nF]
Transformer6[nF]
Manitoba HVDC Research Centre
Transformer Bushing failure in a power planta1
EART
80 [pF]
PT
25 [pF]
_D3Y_D3R_
DIS
CO
NN
EC
TOR
EART
THIN
G SW
ITCH
25 [pF]
25 [pF]
25 [pF]
Electrical studies:
Switching and temporary over voltages
BREAKERCB1B_CB1Y_CB1R_
THIN
G SW
ITCH
25 [pF]
25 [pF] Switching, and temporary over voltages Ferroresonance Harmonic impacts GIS Very Fast Transients
25 [pF]
25 [pF]
25 [pF]
EARTH
ING
SWITC
H
GIS Very Fast Transients.
b2
D1B_D1Y_D1R_
2.4 [pF]
2.4 [pF]
2.4 [pF]
b1
Manitoba HVDC Research Centre
Transformer Bushing failure in a power plant
1.50 Esov - PP9 Bushing
Switching transients
-0.50
0.00
0.50
1.00
PU
Time ... 0.000 0.010 0.020 0.030 0.040 0.050 0.060 0.070 0.080
-1.50
-1.00
GIS it hi l t d VFT MH
2.0
3.0
4.0 E_ST3_DER
2.00
2.50
3.00 E_GT1_2
GIS switching related VFT - MHz range
-3.0
-2.0
-1.0
0.0
1.0
-0.50
0.00
0.50
1.00
1.50
-4.0 -1.00
Manitoba HVDC Research Centre
System black start restoration studies
Getting a power system back into operation after ‘black-out-i t t k d h ld b f ll l d (Bl k is not an easy task and should be carefully planned (Black start restoration plans)
Some issues:
Can we energize lines , transformers and loads through available generating units?
System has very little damping due to low load. Resonance issues.
Manitoba HVDC Research Centre
System black start restoration studies
Restoration steps are determined and documented – step by step
System single line drawings are used to illustrate each step
Electrical studies are necessary to verify that the selected restoration actions (steps) can be implemented without damaging restoration actions (steps) can be implemented without damaging equipment
Manitoba HVDC Research Centre
System black start restoration studiesEng
QILWAH MIKHWAH
TLine_01_01
26.326 km
53.618 km38 km
BRKG
TimedBreakerLogic
Open@t0
#1 #2
P+jQ P+jQ
#1 #2
TLine_01_02
E3E1
TLine_01_a
Bil Jurshi
S / Hinhold
out
S2M
TLine_02_02TLine_02_01
TLine_02_03row1
NAMERAAD DUQAHQUNFUDAH TOWN
QUNFUDAH CPS THORYBAN
TLine_01_07
TLine_01_06
TLine_01_05row1
TLine_01_049 km95 km67 km 36 km
Etcps
E1
E2
#1 #2
Iqun
t
Iqunt
P+jQ
TLine_01_03
P+jQ
#1 #2
_ _
#1 #2
P+jQ
E3
E2
BRK
G
TLine_01_b
STe
3
AV
Tm
Tm0
Ef0
Tmw
Ef If
Ef0
VTIT 3
IfEfEf0
Vref
Exciter (ST3A)
Vref0
#1 #2
1 unit 80 MVA
TCPS
TLine_02_05
QUNFUDAH CPS THORYBAN
TLine_01_08
TLine_01_09
TLine_01_10
SUFFAHSABTAL JARAJ
49 km
47 km
86 km
Etcps
#1#2
P+jQ
TLine_02_04
TLine_02_05_2
P+jQ
#1#2
S / HTM01
S / Hinhold
out
G1 + sTD -
F+
G1 + sT
*13.333
W1
D -
F+
Tm0
1.0
TM01W1
TLine_02_07
TLine_01_11TLine_01_12
TLine_01_13
TLi 01 15
AL BIRKMAJARDAH
68 km
100 km
94 km
82 km
72 km
TLine_02_06
P+jQ
#1 #2
P+jQ
#1#2
a
VTIT 3
IfEfEf0
Vref
Exciter (ST3A)
Vref0
Ef0
P = 325.6Q = 227
V = 0.9996
A
Ef
S2M
S / Hinhold
out
STe
3
AV
Ef0 Ef If
Neuclear plant : Con...P1
5.73182
Q1
3.91242Ia
L2N
1 unit = 150 MVA
TLine_02_08
TLine_01_15
TLine_01_17MUHAIL NORTH 67 km
TLine_01_14
#1#2
P+jQ
aEa E132V
A
W
L2N
S2M
TIME
TIME
TM0
1.0
Te
Tm
Tm0Tmw
#1 #2
D -
F
+
W
*13.333
G1 + sTD -
F
+G
1 + sT
#1 #2
P+jQ
TLine_02_09TLine_01_16
MUHAIL
44 km
P+jQ
#1#2
S / Hinhold
outTM0
L2N
Manitoba HVDC Research Centre
System black start restoration studies
Transformer energizing:
Transformer Energizing
0.50
1.00
1.50 E_49900
Energizing a transformer from the HV side -1.50
-1.00
-0.50
0.00
PU
1 00
1.50
2.00 Itf
x 0.00 0.50 1.00 1.50 2.00 2.50 3.00
-1.50
-1.00
-0.50
0.00 0.50
1.00
kA
Transformer Energizing
0.00
0.50
1.00
1.50
PU
E_49900
-1.50
-1.00
-0.50
0.50
1.00
1.50
2.00 Itf
x 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00
-1.50
-1.00
-0.50
0.00 kA
Manitoba HVDC Research Centre
System black start restoration studies
Transformer energizing:
Energizing a transformer from the HV side
TLine1
TLine2
BRK#1 #3
#20.1
RL RRL X X280 km
Analog Graph
1.6k|Z+|(ohms)
X X
TLine2
220 km
0.6k
0.8k
1.0k
1.2k
1.4k
Ohm
s
Frequency 0 100 200 300 400 500 600
0.0
0.2k
0.4k
Manitoba HVDC Research Centre
System black start restoration studiesLong line energizing through small generating unitsSelf excitation issues
1.001.20
Vrms_machine
S / Hinhold
out
S2M
VsVrefVref0
0.00 0.20 0.40
0.60 0.80 1.00
PU
0.50 1.00 1.50
Ea - Machine terminal
Sudair Bus
#1 #2
Ia1
Ia2
Ib1
Ib2
BRKG
TimedBreakerLogic
Closed@t0
BRKG
BRKLSTe
3
AV
Tm
Tm0
Ef0
Tmw
Ef If
TM0
Ef
1e6VA
Esov
Vs
wP
PSS2B
P1
W
TL_SUD_P...
Ef0
VTIT 3
IfEfEf0
Exciter (ST4B)
Ea
-1.50 -1.00 -0.50
0.00
0.00 0.50 1.00 1.50 2.00
PU
Esov - PP9 Bushing
Closed@t0
BRKL
TimedBreakerLogic
Open@t0
TIME
TIME
S2M
L2N
W
Steam_Tur_1
w Tm1
Tm2Wref
Cvw
Wref
Cv
Steam Gov 4
B+
F
+
1.0
-1.50 -1.00 -0.50
-1.00 -0.50 0.00 0.50 1.00 1.50
PU
Ef - Machine field voltage
x 1 50 2 00 2 50 3 00 3 50 4 00 4 50 5 00 5 50
-1.50
0.99982
1.00002 W
x 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 5.50
Manitoba HVDC Research Centre
Breaker Transient Recovery Voltage - TRVRL RRL
Ib
Iflt
T_line
Main : Graphs
200
400
600 TRV
TimedFaultLogic ABC
C_LIM
+
30 [pF]
30 [pF]
30 [pF]
200
650 [pF]133.5
TRV
Vb
Va
I_C
B1
Limiting Reactor
0.1
BREA
1
TimedBreakerLogic
Closed@t0 BREA1
-400
-200
0
C_LIM
+
30 [pF]
30 [pF]
30 [pF]
000
650 [pF]
5 [pF]
g108
BREA
2
Main : Graphs
800 TRV_env_A30 TRV_env_A30 TRV TRV_env_A60 TRV_env_A60 TRV_env_A100 TRV_env_A100
x 0.180 0.190 0.200 0.210 0.220 0.230 0.240
-600
00
50 [pF]
DS
50 [pF]
DS
50 [pF]
DS
DS3
DS2
DS1
-800
-600
-400
-200
0
200
400
600
600
800 TRV_env_B30 TRV_env_B30 TRV TRV_env_B60 TRV_env_B60 TRV_env_B100 TRV_env_B100
50 [pF]
SA
250 [nF]
12000 [pF]
16000 [pF]
3#1
#2
-800
-600
-400
-200
0
200
400
400
600
800 TRV_env_C30 TRV_env_C30 TRV TRV_env_C60 TRV_env_C60 TRV_env_C100 TRV_env_C100
[ ]Sub Transient
Reactance
.599e-4
RL
0.00
085
x 0.1980 0.2000 0.2020 0.2040 0.2060 0.2080 0.2100 0.2120
-800
-600
-400
-200
0
200
400
Manitoba HVDC Research Centre
Breaker Transient Recovery Voltage - TRV
TimedFaultLogic ABC
Iflt
30TRV
Va
Main : Graphs
200
400
600 TRV
30 [pF]
30 [pF]
0 [pF]
V
I_C
B1
BRE
A1TimedBreakerLogic
Closed@t0 BREA1
-400
-200
0
Vb
x 0.180 0.190 0.200 0.210 0.220 0.230 0.240
-600
C_LIM
+
20000
650 [pF]
133.5 [pF]
Limiting Reactor
0.108
C_LIM
+
650 [pF]
Manitoba HVDC Research Centre
CT Saturation
Mal‐operation of an earth fault relay during f i itransformer energising.
Inrush current caused unequal saturation of the 3 CTs, resulting in a ‘burden’ current.
Is, g
PSCAD case:Earth_fault_relay.psc( i d Th Ct l d t F t fil )
BRK1
CO
U
SE
(required ThreCt.psl and a custom Fortran file) PI
UPLED
ECTIO
N
TimedF lt
E
BRK2
FaultLogic
1
2
3
Ea
Ia
ct_3_new _.f
0.01 [o
#1#2
Is
ohm]
Manitoba HVDC Research Centre
CT saturation studies
CT of phase A saturated during energising of a i l h f i di ib i f dsingle phase transformer in a distribution feeder.
Is
Main,CT1 : Graphs
12 0Ib
BRK1
CO
U
SE
-2.0
12.0
Ib (A
)
B1 PI
UPLED
ECTIO
N
TimedF lt
E
-0.25
2.00
B (T
)
B1
BRK2
FaultLogic
1
2
3
Ea
Ia
ct_3_new _.f
0.01 [o-20
120
Ia (A
mps
)
Ia
#1#2
Is
ohm] 0.00 0.20 0.40 0.60 0.80 1.00
Manitoba HVDC Research Centre
Open discussion and closing comments
Present your questions to PSCAD Developers and to your fellow PSCAD users.
Tell us of you PSCAD experience:- How can we do better?