Transcript of Developing a Comprehensive Energy Plan for Your Facility.
Developing a Comprehensive Energy Plan for Your Facility
PresenterRalph Graham, BS EET, MHA, CHFM
Director, Utilities ManagementUAB, Birmingham, ALServed on the ASHE Board 2009-2012Serving ASHE Task Force and CommitteesServing on AHA-CC Committee Since 2007Serving on AHA-CC BoardAlaSHE’s ASHE Advocacy/Sustainability LiaisonAlaSHE Member since 1996AlaSHE President 2000
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Agenda• Establish a Baseline• Evaluate Energy Conservation Efforts• Determine Program Objectives• Proposed Energy Conservation Program• Program Schedule• Program Costs and Savings• Case Studies• Next Steps
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
UAB Baseline• Operates and Maintains 12.2 Million Conditioned SF
• Total Utility Cost - $47.2 Million
• O&M Cost - $7.27 per SF
• Utility Cost - $3.87 per SF
• Energy Management Department Funded by 3.07% Utility Surcharge
Develop a Baseline
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Energy Efficiency Benchmarking• UAB Site EUI: 156 kBtu/SF
• 50th Percentile Site EUI Benchmark: 136 kBtu/SF
• 25th Percentile Site EUI Benchmark: 118 kBTU/SF
• 10th Percentile Site EUI Benchmark: 106 kBTU/SF
• Savings Opportunity: 32%
Develop a Baseline
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Prior Energy Conservation Program (ECP) Efforts
UAB Facility Management Replaced 10,000 Fixtures
in CY2013!
Energy Cost Reduction MeasureAnnual Savings ($/year)
Building Occupancy Schedules 1,500,000
Reduce Air Flow Setpoints 700,000
Retrofit Light Fixtures 300,000
Replace Water-Cooled Vacuum Pumps and Air Compressors 150,000
Install Variable Frequency Drives 40,000
Reclaim Fin Water 104,000
Meter Sewer Diversion 1,800,000
Replace Equipment 800,000
Retro-Cx Hospital Facilities 3,000,000
Modify Utility Rates and Riders 2,000,000
Total 10,394,000
Evaluate Prior Efforts
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Program Objectives• Reduce Energy Consumption to Lowest 10% of Peer Institutions• Reduce Greenhouse Gas Emissions by more than 25%• Reduce Annual Energy Costs by more than $15 Million• Improve Thermal Comfort, IAQ and Occupant Safety• Extend District Systems to New and Existing Buildings• Single Platform Instrumentation, Control and Electronics System• Upgrade Building Automation Systems• Sustain Energy Savings
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Proposed Energy Conservation Program
• Preliminary Program Cost Estimate: $112.1 Million
• Estimated Annual Program Savings: $15 Million
• Program Implemented in 4 Phases:
– Phase 1: Develop UAB Strategic Energy Plan
– Phase 2: Evaluate Energy Conservation Program Funding Methods
– Phase 3: Implement Energy Cost Reduction Measures
– Phase 4: Sustain Energy Consumption and Cost Savings
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Phase 1: Develop UAB Strategic Energy Plan
• Supply-Side Audits• Building Demand-Side
Audits• District Energy System
Demand-Side Audits• ICE Long-Range Plan• Campus Strategic
Energy Plan (StEP)• ICE Staff Assessment
& Benchmarking
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Phase 2: Evaluate Energy Conservation Program Funding Methods
• Alternative 1: Business as Usual
• Alternative 2: UAB Facilities Department Bond Issue
• Alternative 3: District Energy System Reserves with Reinvestment of Savings
• Alternative 4: Energy Savings Performance Contract
• Alternative 5: 3rd Party Asset Monetization
• Alternative 6: 3rd Party District Energy System Concession
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Alternative 1: Business as Usual
• Flat Rate for Steam and Chilled Water Consumption
• Individual Department Funded Energy Reduction Projects
• Conventional District Energy Systems Design
• Additional Plant Capacity Installed for Campus Growth
• Multiple Building Systems – Not Integrated
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Alternative 2: UAB Facilities Bond Issue
• Provides Funding by Sale of Tax-Exempt Bonds
• Bond Covers all Program Costs
• UAB Manages All Activities
• Bond Payment Allocated to Each Campus Department
• Steam and Chilled Water Rates Established by Cost of Service Studies
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Alternative 3:District Energy System Reserves
with Reinvestment of Savings• Invest in Highest
Payback Projects First
• Reinvest Savings to Fund Remaining Projects
• Self-Financed Program
• Slower Program Implementation Schedule
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Alternative 4: Energy Savings Performance Contract
• UAB Provides Financing
• Energy Savings Company (ESCO) Implements “Turnkey” Cost Reduction Measures
• ESCO Guarantees Annual Savings Contingent on Continued Contract with UAB
• Actual Savings are Measured & Verified through Pre-Approved Plan
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Alternative 5: 3rd Party Asset Monetization
• Provides Funding through Sale of UAB District Systems• Sale Price Structured to Cover Cost of Energy
Conservation Programs• 3rd Party Pays All Costs Associated with ECP Related to
District Energy Systems• UAB Continues to Operate District Energy Systems
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Alternative 6: 3rd Party District Energy System Concession
• Similar to Alternative 5
• 3rd Party does not Purchase the District Systems from UAB
• 3rd Party Purchases a Concession Right to Operate UAB’s Equipment and Systems
• Replacement of CEP Equipment by 3rd Party
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Phase 3: Implement Energy Cost Reduction Measures
• Supply-Side ECP• District Energy System Demand-Side ECP• Expansion of District Energy System• Building Demand-Side ECP• ICE System Upgrades
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Supply-Side ECP
• Negotiate Rates and Riders
• Removing Tax from Exempt Accounts
• Demand Response
• Other Utility Incentives
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
District Energy Demand-Side ECP• Rate Design for Fixed Cost Recovery
• Increase Chilled Water Temperature Difference
• Extend District Energy to New and Existing Buildings
• Install Most Cost-Effective
– Combined Heat and Power
– Heat Pump Chiller Heater
– Thermal Storage
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Building Demand-Side ECP• HVAC & BAS
Upgrades
• Retro-Commissioning
• Lighting Retrofits
UAB Colleges:
• School of Medicine
• College of Arts and Sciences
• College of Business
• College of Dentistry
• College of Education
• College of Engineering
• College of Health Professions
• College of Nursing
• College of Optometry
• College of Public Health
• UAB Hospital
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
ICE System Upgrades• Consolidate into Single ICE Platform
– Building BAS
– Plant PLC
– CAMS
– Metering System
• Integrate BAS and ADT Systems
• Unique Operator Passwords
• Energy Efficiency Programming
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Phase 4: Sustain Energy Consumption and Cost Savings
• Sustain Reduced Energy Consumption– Program Support– Remote Monitoring– Operator Training
• Maintain Achieved Energy Cost Savings– Measurement & Verification
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Remote Monitoring
• Regular Engineer and Controls Technician Review of ICE Systems
• Develop List of Issues
• Present Issues Log to UAB on a Monthly Basis
• Assist Personnel with Troubleshooting
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Measurement & Verification• Obtain and Compile Utility Bills for Each Building• Establish a Baseline• Obtain Daily Utility Meter Readings• Issue Daily Scorecard
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Daily M&V Scorecard
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Training O&M Staff
• Pre-Assessment of O&M Staff to Determine Training Requirements
• Develop Curriculum
• e-Learning Programs
• Comprehensive Training Program with Classroom and Field Training Sessions
• Post-Test O&M Staff to Assess Training Effectiveness and Determine if Additional Training is Required
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
ICE Standards• Standard Systems List
• Control Diagrams
• Points List
• Sequence/Programming Instructions
• Network Standards
• Utility Metering Applications
• Web Services
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Design & Commissioning
Standards
• Develop Design Standards
– HVAC
– TAB
– CEMS
– Information Technology
– Interior & Exterior Lighting
• Develop Commissioning Standards
• Develop Matrix to Identify Applicability of Standards to Project Type
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Utility Management Services• Review Each Utility Bill• Verify Utility Rates and Riders• Verify Proper Metering• Hedge Natural Gas Commodity• Participate in Demand Response Programs
Program
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Project Schedule*
Schedule
Phase Start Date Completion Date
Phase 1: Strategic Energy Plan 17-Feb-14 1-Oct-14
Phase 2: Evaluate Program Funding Methods 17-Feb-14 31-Jan-15
Phase 3: Implement Energy Cost Reduction Measures 1-Mar-14 31-May-16
Phase 4: Sustaining the Energy Consumption and Cost Savings 1-Mar-14 31-Dec-15
*Dates will be coordinated with UA BOT meetings and other approval requirements.
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Estimated Cost of Projects
* Project to be Reviewed for Economic Feasibility
Category Campus Parking Decks Hospital Research
District Energy
SystemsTotal
Retro-Commissioning 750,000 0 500,000 210,000 0 1,460,000
BAS Upgrades 13,000,000 280,000 10,400,000 8,750,000 0 32,430,000
Lighting Retrofits 4,800,000 650,000 3,150,000 1,350,000 0 9,950,000
HPCH Equipment * 2,500,000 0 4,000,000 2,000,000 0 8,500,000
Combined Heating and Power * 0 0 0 0 25,000,000 25,000,000
Expand District Energy Systems 0 0 0 0 12,000,000 12,000,000
Convert Chilled Water System to Variable Primary * 0 0 0 0 4,500,000 4,500,000
Demand Response Program * 0 0 0 0 8,000,000 8,000,000
Cost of Service Based District Energy System Cost Allocation 0 0 0 0 169,000 169,000
Other Projects 2,105,000 0 1,805,000 1,231,000 4,950,000 10,091,000
Total 23,155,000 930,000 19,855,000 13,541,000 54,619,000 112,100,000
Cost and Savings
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Alternative 2: Bond Financing Cash Flow Projection
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
-10,000,000
-5,000,000
0
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
35,000,000
40,000,000
-80,000,000
-40,000,000
0
40,000,000
80,000,000
120,000,000
160,000,000
200,000,000
240,000,000
280,000,000
320,000,000
Annual Energy Cost Savings ($)
Annual Program Operating Costs ($)
Annual Program Debt Service Payments ($)
Net Annual Savings ($)
Cumulative Program Savings ($)
Program Year
Annu
al C
osts
and
Sav
ings
($/y
ear)
Cum
ulati
ve P
rogr
am S
avin
gs ($
)
* Assumes tax-exempt bond for 20 year term at all inclusive interest rate of 4.5%
Cost and Savings
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Case Study: University of Arkansas System
Case Studies
Item Units TotalConditioned Floor Area SF 13,214,450
Total Investment in Energy Efficiency Projects $ 135,471,303Total Investment in Energy Efficiency Projects $/SF 10.25
Baseline Annual Utility Costs $ 38,545,487Baseline Annual Utility Costs $/SF 2.92Current Annual Utility Costs $ 21,978,078Current Annual Utility Costs $/SF 1.66
Annual Savings $ 16,567,410Annual Savings $/SF 1.25Annual Savings % 43
Average Simple Payback Years 8.18
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Next Steps• Approve and Execute
ECP Proposals
• Complete Hospital ECP Projects– Retro-Cx Surgery HVAC
Systems in North Pavilion
– Retro-Cx Remaining HVAC System in North Pavilion
– Retro-Cx Spain-Wallace
– Retro-Cx West Pavilion
– Pilot ADT Interface for WIC and North Pavilion
Next Steps
Agenda
Develop a Baseline
Evaluate Prior Efforts
Program
Schedule
Cost and Savings
Case Studies
Next Steps
Questions?