DATE:- 8-03-15 S.NO TRADE TOTAL ON PLOT Temp facility 1 MASON 15 5 3 0 6 2 Carpenter 37 31 1 10 12 3 Painter 4 4 0 4 Scaffolder 20 20 0 5 Plumber 2 0 2 6 Lineman 6 0 5 7 Electrician 4 0 4 8 Steel Fixer 26 25 0 4 15 9 Rigger 15 14 1 10 HELPER 58 28 16 8 REQUIRED BY D PAUL FOR FOUNDATION REQUIRED BY M.SAEED FOR GTP BUILDING
-
Upload
nadim-jilani -
Category
Documents
-
view
2 -
download
0
description
project manpower
Transcript of Detailed Man Power
Sheet1DATE:- 8-03-15S.NOTRADETOTALON PLOTTemp facilityREQUIRED BY D PAUL FOR FOUNDATIONREQUIRED BY M.SAEEDFORGTP BUILDING1MASON1553062Carpenter3731110123Painter4404Scaffolder202005Plumber2026Lineman6057Electrician4048Steel Fixer262504159Rigger1514110HELPER5828168