Design Responsibilities Outline Standard Design ... Responsibilities Outline ... revised, approved &...

13
1 Level 1: Section 03 – Version 3 © 2014 SBCA 1 Section 03: Design Responsibilities 2 Section Downloads Download & Print TTT I Sec 03 Slides TTT I Sec 03 Handouts 2 articles Shop Fabricated Wood Truss Specification TTBDRESP-D TTBPlace Version 2.1 3 Design Responsibilities Outline The Need for ANSI/TPI 1-2007 Chapter 2 Non-Conforming Specifications Definitions Defined Responsibilities Mandated RDP / No mandated RDP Truss Manufacturer Truss Designer Owner / Contractor 4 Standard Design Responsibilities TTBDRESP-D 5 The Need for Standard Design Responsibilities Inaccurate or erroneous contract specifications Perform services & supply items beyond the scope of truss design & manufacture 6 Non-Conforming Specifications

Transcript of Design Responsibilities Outline Standard Design ... Responsibilities Outline ... revised, approved &...

1Level 1: Section 03 – Version 3© 2014 SBCA

1

Section 03: Design Responsibilities

2

Section Downloads

Download & Print TTT I Sec 03 Slides

TTT I Sec 03 Handouts

2 articles

Shop Fabricated Wood Truss Specification

TTBDRESP-D

TTBPlace

Version 2.1

3

Design Responsibilities Outline

The Need for ANSI/TPI 1-2007 Chapter 2 Non-Conforming Specifications

Definitions

Defined Responsibilities Mandated RDP / No mandated

RDP

Truss Manufacturer

Truss Designer

Owner / Contractor4

Standard Design Responsibilities

TTBDRESP-D

5

The Need for Standard Design Responsibilities

Inaccurate or erroneous contract specifications Perform services & supply

items beyond the scope of truss design & manufacture

6

Non-Conforming Specifications

2Level 1: Section 03 – Version 3© 2014 SBCA

7

“All other truss bracing required during the erection or in the completed structure including the bracing connections to trusses and bracing anchorage is the responsibility of the Truss Designer & should be clearly denoted on the Truss Design Drawings.”

“Truss Manufacturer is also responsible for supplying all bracing & connections.”

Non-Conforming Specifications

8

“The Truss Designer is solely responsible for the safety & stability of the roof system & its component parts during erection.”

“This includes the addition of whatever shoring, temporary bracing, guys or tie-downs, which might be necessary.”

Non-Conforming Specifications

9

“The Truss Designer needs to provide a letter of verification that trusses are installed & braced properly.”

“The Truss Designer must design all beams & headers.”

“The Truss Designer must provide sealed Placement Diagrams.”

Non-Conforming Specifications

10

Development

11

Development

12

Quiz 1

3Level 1: Section 03 – Version 3© 2014 SBCA

Definitions

ANSI/TPI 1-2007 Chapter 2

Definitions are not in the Standard Responsibilities TTB

Most were not covered in Section 2 – Terminology

See Shop Fabricated Wood Truss specification

13

Trusspec

Building

A structure used or intended for supporting or sheltering any use or occupancy.

14

Building Code

As it applies to the structural safety of a Building, any set of standards set forth and enforced by a Jurisdiction for the protection of public safety.

15 16

Building Designer

The Owner of the Building or the person that contracts with the Owner for the design of the Framing Structural System and/or who is responsible for the preparation of the Construction Documents. When mandated by the Legal Requirements, the Building Designer shall be a Registered Design Professional. On professionally designed projects

On projects where there is no professional designer

Building Official

A person charged with the administration and enforcement of a Building Code, or a person, who in accordance with the Legal Requirements may impose Legal Requirements relating to the Trusses and/or the Submittal Package.

17

Building Permit

An official certificate of permission issued by a Jurisdiction to an Owner to construct, enlarge, or alter a Building.

18

4Level 1: Section 03 – Version 3© 2014 SBCA

Construction Documents

Written, graphic and pictorial documents prepared or assembled for describing the design (including the Framing Structural System), location and physical characteristics of the elements of a Building necessary to obtain a Building Permit and construct a Building.

19

Contract

A legally recognized agreement between two parties. A Contract will likely exist between the

Truss Manufacturer and its customer, which may be the Contractor or Owner, which sets forth the responsibilities applicable to the Truss Manufacturer.

20

21

Contractor

An Owner of a Building, or the person who contracts with the Owner, who constructs the Building in accordance with the Construction Documents and the Truss Design Drawings and Truss Placement Plans if applicable. The term "Contractor" shall include those subcontractors who have a direct contract with the Contractor to perform all or a portion of the construction.

Cover/Truss Index Sheet

A sheet that is signed and sealed, where required by the Legal Requirements, by the Truss Design Engineer and depending on the Legal Requirements shall be permitted to contain the following information:

Replaces sealing each individual Truss Design Drawing (allowed by IBC)

22

Cover/Truss Index Sheet (1) identification of the Building, including Building name and address,

lot, block, subdivision and city or county;

(2) Identification of construction documents by drawing number(s) with revision date; (3) specified building code;

(4) computer program used;

(5) roof dead and live loads;

(6) floor dead and live loads;

(7) wind load criteria from a specifically defined code (for example, ASCE 7) and any other design loads (such as ponding, mechanical loads, etc.);

(8) name, address, and license number of Registered Design Professional for the building, if known;

(9) a listing of the individual identification numbers and dates of each Truss Design Drawing referenced by the Cover/Truss Index Sheet; and

(10) name, address, date of drawing and license number of Truss Design Engineer. 23

Deferred Submittal

Those portions of the design that are not completed at the time of the application for the Building Permit and that are to be submitted to the Building Official within a specified period in accordance with the Legal Requirements .

24

5Level 1: Section 03 – Version 3© 2014 SBCA

Diagonal Bracing

Structural member installed at an angle to a Truss chord or web member and intended to temporarily and/or permanently stabilize Truss Members and/or Trusses. For further information see BCSI.

25

Framing Structural System

The completed combination of Structural Elements, Trusses, connections and other systems, which serve to support the Building's self weight, the specified loads.

26

Jurisdiction

The Governmental unit that is responsible for adopting and enforcing the Building Code.

27

Lateral Restraint

Also known as Continuous Lateral Restraint or CLR. A structural member installed at right angles to a chord or web member of a Truss to reduce the laterally unsupported length of the Truss member.

28

29

Applicable provisions of all statutes, laws, rules, regulations, ordinances, codes, or orders of any governmental authority.

Legal Requirements

30

A person having a legal or equitable interest in the property upon which a Building is to be constructed, and:

(1) either prepares, or retains the Building Designer or Registered Design Professional to prepare, the Construction Documents; and

(2) either constructs, or retains the Contractor to construct the Building.

Owner

6Level 1: Section 03 – Version 3© 2014 SBCA

Permanent Building Stability Bracing

Lateral force resisting system for the Building that resists forces from gravity, wind, seismic and/or other loads.

31

Permanent Individual Truss Member Restraint

Restraint that is used to prevent local buckling of an individual Truss chord or web member due to the axial forces in the individual Truss member.

32

Person

An individual or organization that may exist in accordance with the Legal Requirements.

33

Registered Design Professional

Architect or engineer, who is licensed to practice their respective design profession as defined by the Legal Requirements of the Jurisdiction in which the Building is to be constructed.

34

Structural Element

A single structural member (other than a Truss) that is specified in the Construction Documents.

35

Temporary Installation Restraint/Bracing

Lateral Restraint and Diagonal Bracing installed during construction for the purposes of holding Trusses in their proper location, plumb and in plane, until Permanent Individual Truss Member Restraint, Diagonal Bracing and Permanent Building Stability Bracing are completely installed.

36

7Level 1: Section 03 – Version 3© 2014 SBCA

37

An individual metal plate connected wood component manufactured for the construction of a Building.

Truss Truss Design Drawing

Written, graphic and pictorial depiction of an individual Truss that includes the information required in Sections 2.3.5.5 and 2.4.5.4.

38

Discussed Further in Section 10

39

A person who is licensed to practice engineering as defined by the Legal Requirements of the Jurisdiction in which the Building is to be constructed and who supervises the preparation of the Truss Design Drawings.

Truss Design Engineer Truss Designer

The person responsible for the preparation of the Truss Design Drawings.

Truss Technician

40

41

It is important to understand that Truss Technicians do not performing engineering design work. They specify design parameters such as: Dimensions

Lumber species & grades

Load duration factors

Truss Technician

42

Truss Manufacturer

Person or entity engaged in the manufacturing of Trusses.

8Level 1: Section 03 – Version 3© 2014 SBCA

43

Truss Placement Diagram

An illustration supplied at times by the Truss Manufacturer identifying the assumed location for each Truss.

Truss Submittal Package

Package consisting of each individual Truss Design Drawing, and, as applicable, the Truss Placement, the Cover/Truss Index Sheet, Lateral Restraint and Diagonal Bracing details designed in accordance with generally accepted engineering practice, applicable BCSI-defined Lateral Restraint and Diagonal Bracing details, and any other structural details germane to the Trusses.

44

45

Truss Technician vs. Engineer

TTT1 Sec 03 Handouts

46

Quiz 2

How the Truss Industry Practices Engineering

Truss Manufacturer (TM) can provide sealed Truss Design Drawings (TDD) in one of two ways:

1.By employing a PE, or

2.By contracting with a company that provides professional truss design engineering services

47

PE Employed by the TM

Truss design work is typically performed by truss technicians that work directly for the Truss Design Engineer (TDE)

All TDDs are reviewed, revised, approved & sealed by the TDE

48

9Level 1: Section 03 – Version 3© 2014 SBCA

PE Employed via Contract

Typically the contract is with the truss plate & truss design software companies

Specific design parameters provided by the Building Designer are communicated from the TM to the contracted TDE.

TDE inputs these design parameters, analyzes & undertakes the truss design

TDE has complete control over the design settings.

49 50

Logical (Ideal) Design/Build Process

1) Owner hires a design team to undertake the architectural & structural design

2) Structural design team decides to use trusses & gets the TM involved during the project design phase

51

Logical (Ideal) Design/Build Process

3) Trusses are designed per the loading requirements provided by the Registered Design Professional (RDP) for the project

4) Completed TDDs are provided to the RDP who takes this information & designs the transfer of loads to the structure below

Permanent bracing design is also completed at this time

52

Logical (Ideal) Design/Build Process

5) Contractor takes the completed set of plans & implements them

6) Building Official performs an inspection to ensure that all involved in the project have not missed a detail that needed to be installed

53

Typical Process

1) $$$$$ is the main issue

2) Owner bypasses the RDP & just hires a General Contractor (GC)

3) GC gets bids from a variety of TMs of varying expertise & chooses the cheapest

54

Typical Process4) Plans & specifications for the project are

highly variable with respect to completeness & detail

5) Truss Manufacturer is asked to: “make them work structurally”,

define the loads (if not defined), &

make sure that the building as designed meets the expectations of everyone involved

10Level 1: Section 03 – Version 3© 2014 SBCA

Truss Design Drawing

The standard contract that the TM makes is for the individual trusses

May or may not require sealing

55 56

Truss Placement Diagram

TTBPLACE-D

57

Truss Placement Diagram

58

The Truss Designer’s signature certifies that the individual truss designs are based on the positioning shown, and that the dimensions and loads shown on the referenced drawings match that positioning. The Truss Designer’s seal on the attached Truss Design Drawings indicates acceptance of professional engineering responsibility solely for the individual Truss Design Drawings shown. The suitability and use of this component for any particular building is the responsibility of the Building Designer, per ANSI/TPI 1-2002 Chapter 2. No building design or inspection is implied by the seals on the Truss Design Drawings or Truss Placement Diagram. Verification that position, dimensions, and loads for each truss matches the construction design documents and/or intent is the responsibility of the Building Designer. The Truss Designer is responsible for the correct application of the specified loading provided to him by the Building Designer and for the truss to truss connections.

The Truss Designer is NOT responsible for:

The transfer of lateral load from the roof to the shear walls, connection of trusses to the bearing support, the design of the bearing supports, temporary and permanent building bracing required in the roof and/or floor system, transfer of vertical loads down to the foundation, the design of the foundation and soil, analysis of the roof and/or floor diaphragms of the building, connection of roof and/or floor diaphragm to the truss, specifying loading used in the design of the trusses.

The Building Designer shall ascertain that the loads utilized on the Truss Design Drawings meet or exceed the loading imposed by the building code.

Truss Placement Diagram Sample Disclaimer

Truss Placement Diagram

sbcindustry.com

Technical Info

Tech Notes

Continuous lateral bracing

Seals and Truss Placement Diagrams

Jobsite handling and installation

59

Mandated RDP

ANSI/TPI 1-2007 Chapter 2, Section 2.3 2.3.1 REQUIREMENTS OF THE OWNER

2.3.2 REQUIREMENTS OF THE REGISTERED DESIGN PROFESSIONAL

2.3.3 REQUIREMENTS FOR THE PERMANENT MEMBER RESTRAINT/ BRACING OF TRUSS SYSTEMS

2.3.4 REQUIREMENTS OF THE CONTRACTOR

2.3.5 REQUIREMENTS OF THE TRUSS DESIGN ENGINEER

2.3.6 REQUIREMENTS OF THE TRUSS MANUFACTURER

60

11Level 1: Section 03 – Version 3© 2014 SBCA

No mandated RDP

ANSI/TPI 1-2007 Chapter 2, Section 2.4 2.4.1 REQUIREMENTS OF THE OWNER

2.4.2 REQUIREMENTS OF THE BUILDING DESIGNER

2.4.3 REQUIREMENTS FOR THE PERMANENT MEMBER RESTRAINT/ BRACING OF TRUSS SYSTEMS

2.4.4 REQUIREMENTS OF THE CONTRACTOR

2.4.5 REQUIREMENTS OF THE TRUSS DESIGNER

2.4.6 REQUIREMENTS OF THE TRUSS MANUFACTURER

61 62

Defined Responsibilities

Requirements of the Owner

Requirements of the Contractor

Requirements of the RDP/Building Designer

Requirements of the Truss Design Engineer/ Truss Designer

Requirements of the Truss Manufacturer

Requirements for the Permanent Member Restraint/ Bracing of Truss Systems

63

Owner Responsibilities

Obtain the Building Permit

Communicate to the Contractor or Truss Manufacturer any required special inspections or structural observations

Engage with: RDP/Building Designer to prepare the

Construction Documents

Contractor to store, handle, & install trusses

Review & Coordinate the Submittal Packages

64

Long Span Trusses

Special on-site inspections of trusses with a clear span of 60' or greater Owner will contract with a RDP

To design the Temporary Installation Restraint/Bracing & the Permanent Individual Truss Member Restraint & Diagonal Bracing

To provide special inspections to assure that the temporary & permanent bracing are installed properly in the case of long-span trusses

65

Contractor Responsibilities Provide Construction Documents to the Truss

Manufacturer Provide Truss Submittal Package to

RDP/Building Designer for review/ approval Properly restore, handle, install, restrain, &

brace trusses Pre- & Post-Installation Check Needed truss repairs?

66

RDP/Building Designer Responsibilities

Prepare the Construction Documents With required information to accurately design the

trusses for the Building

Review the Truss Submittal Packages for compatibility with the Building design

12Level 1: Section 03 – Version 3© 2014 SBCA

67

Truss Design Engineer/ Truss Designer Responsibilities

Prepare Truss Design Drawings that conform to ANSI/TPI 1

Responsible only for the truss

Referred to as a Truss Design Engineer when seal is required

Prepare repair designs

NOT responsible for specifying design loads for trusses

68

Communicate design criteria to Truss Designer

Provide sealed Truss Design Drawings prepared by the Truss Design Engineer where required

Manufacture trusses in accordance with given plans

Manufacture trusses in accord with approved Truss Design Drawings using quality criteria per ANSI/TPI 1

Prepare Truss Placement Diagrams where required by the Contract

Submit Truss Placement Diagrams to Contractor for approval

Truss Manufacturer Responsibilities

69

Storage, Handling, Installing & Bracing

Truss Designers & Manufacturers are NOTresponsible.

Contractor IS responsible.

70

Permanent Bracing RDP/ Building Designer is responsible for

the trusses’ permanent bracing design If the truss members need to be braced

(restrained)- determining the approximate location is the responsibility of the Truss Design Engineer/ Truss Designer

71

Permanent Individual Web Member Restraint

Compression Web Restraint

72

Web Buckling

13Level 1: Section 03 – Version 3© 2014 SBCA

73

Requirements for the Permanent Member Restraint/ Bracing of Truss Systems

TPI provides three methods for Permanent Individual Truss Member Restraint/Bracing Standard industry details per BCSI

Substitution with Reinforcement

Specific method specified by a RDP

In the absence of specific details, use the BCSI documents.

74

BCSI

Terminology changed to reflect BCSI language CLR vs. CLB

BCSI listed as a method to provide permanent individual truss member restraint/bracing

75

Standard Design Responsibilities

Chapter 2

76

Quiz 3

77

Feedback