DESIGN PROJECT FOR PAVEMENT

112
PROJECT REPORT (Design project January-May 2015) Life cycle cost analysis and Design of rigid and flexible pavement of National Highway Submitted by Sukhdarshan Singh - 101102073 Rohit Mathur - 101102059 Sushobhit K Choudhary 101102075 Sunmeet Singh Gujral 101102074 Vidhu Mangal 101102081 Sudhanshu Gupta 101102072 Under the Guidance of Mr. Tanuj Chopra Assistant Professor Thapar University DEPARTMENT OF CIVIL ENGINEERING THAPAR UNIVERSITY, PATIALA (Declared as Deemed-to-be-University u/s 3 of the UGC Act, 1956) December 2014

Transcript of DESIGN PROJECT FOR PAVEMENT

Page 1: DESIGN PROJECT FOR PAVEMENT

PROJECT REPORT

(Design project January-May 2015)

Life cycle cost analysis and Design of rigid and flexible pavement

of National Highway

Submitted by

Sukhdarshan Singh - 101102073

Rohit Mathur - 101102059

Sushobhit K Choudhary – 101102075

Sunmeet Singh Gujral – 101102074

Vidhu Mangal – 101102081

Sudhanshu Gupta – 101102072

Under the Guidance of

Mr. Tanuj Chopra

Assistant Professor

Thapar University

DEPARTMENT OF CIVIL ENGINEERING

THAPAR UNIVERSITY, PATIALA

(Declared as Deemed-to-be-University u/s 3 of the UGC Act, 1956)

December 2014

Page 2: DESIGN PROJECT FOR PAVEMENT

DECLARATION

We hereby declare that the design project work entitled “Life cycle cost analysis and design

of rigid and flexible pavement of National Highway” is an authentic record of our own work

carried out at Thapar University, Patiala as requirements of design project work under the

guidance of Mr. Tanuj Chopra, during January to May, 2015.

Rohit Mathur

Sushobhit K Choudhary

Sunmeet Singh Gujral

Vidhu Mangal

Sudhanshu Gupta

Sukhdarshan Singh

Date: 5/08/2015

Certified that the above statement made by the students is correct to the best of our

knowledge and belief.

Faculty Coordinator

Mr. Tanuj Chopra

Assistant Professor

(Civil Engg. Dept.)

Thapar University

Patiala (Punjab)

Page 3: DESIGN PROJECT FOR PAVEMENT

ACKNOWLEDGEMENT

Every project big or small is successful largely due to the effort of a number of wonderful

people who have always given their valuable advice or lent a helping hand. We sincerely

appreciate the inspiration, support and guidance of all those people who have

been instrumental in making this project a success.

We are extremely grateful to “Thapar University” for the confidence bestowed in us

and entrusting our project entitled “Life cycle cost analysis and design of rigid and flexible

pavement of National Highway”.

At this juncture we feel deeply honored in expressing our sincere thanks to Mr. Tanuj

Chopra (Faculty advisor), Dr. Vikas Pratap Singh (Design project incharge) and Dr. Naveen

Kwatra (Head, Civil Engg. Dept.) for making the resources available at right time and

providing valuable insights leading to the successful completion of our project.

We would also like to thank all the faculty members of Thapar University for their

critical advice and guidance without which this project would not have been possible.

Last but not the least we place a deep sense of gratitude to our family members

and our friends who have been constant source of inspiration during the preparation of this

project work.

Page 4: DESIGN PROJECT FOR PAVEMENT

CONTENTS

Topic Page no.

1. Introduction 1 - 5

2. Literature survey

- Design of rigid pavement 7 - 22

- Design of flexible pavement 23 - 41

3. Methodology and analysis

- HDM – 4 43 - 69

- Soil stabilization 70 - 104

4. Concluding remarks 105

5. References 106

Page 5: DESIGN PROJECT FOR PAVEMENT

1 | P a g e

INTRODUCTION

Roads form the spine of any emerging economy – India is no exception. The economic

benefits of a newly constructed/ improved road, both in terms of direct and indirect benefits,

are immense. Of late, in addition to giving a fillip to the economy, highway projects have

emerged as an attractive investment option as well for the private sector. The standardization

of documents and processes by the Committee on Infrastructure, Govt.of India has further

assisted in streamlining of the processes involved in the Public-Private Partnership (PPP)

mode of project implementation in various infrastructure sectors. Over the last few years,

PPP modes have gained significant acceptance as a mechanism for development of

infrastructure in India.

Pavement Management System (PMS)

A pavement Management System helps in making informed decisions enabling the

maintenance of the network in a serviceable and safe condition at a minimum cost to both the

agency and the road users. To adequately meet this requirement, well-documented

information is essential to make defensible decisions on the basis of sound principles of

engineering and management. The objective of establishing a PMS is to improve the

efficiency of this decision making, expand its scope, provide feedback about the

consequences of decisions, and ensure consistency of decisions made at different levels

within an organization.

The elements and products of a Pavement Management System include:

• An inventory of pavements in the network

• A database of information pertinent to past and current pavement condition.

• An analysis program which, among other things, makes use of prediction models for

forecasting pavement condition in the future or in the design horizon.

• Long range budgeting provisions.

• Prioritizing the annual work program.

• A basis for communication of the agency's plans.

• A feedback system. The basic modules of PMS include the following:

• A database that contains inventory, condition, traffic, and historical data

Page 6: DESIGN PROJECT FOR PAVEMENT

2 | P a g e

• A Pavement Analysis Program (PAP), which determines the condition of a pavement and

selects a maintenance action based on its condition and other criteria.

Also, it establishes an annual work program and estimates the budget required. A number of

reports are generated from the analysis. Many other modules are established which supply the

necessary inputs for the PMS analysis. Deterioration models, maintenance and rehabilitation

policies, their unit costs, and vehicle operating costs are such inputs. Deterioration models,

which form an important element of PMS analysis, comprise this study. Thus, a Pavement

Management System can be applied in the areas of planning, budgeting, scheduling,

performance evaluation, and research. It can be used for prioritization, funding, setting

strategies, selecting alternatives, identifying problem areas, simplifying communications with

the legislature, and providing general and specific information which is useful to decision

makers and management.

In order to discuss the benefits and uses of a PMS, it is first necessary to understand the

major components of PMS. The primary purposes of any PMS are:

1) To improve the efficiency of making decisions.

2) To provide feedback as to the consequences of these decisions.

3) To ensure consistency of decisions made at different levels within the same organization.

4) To improve the effectiveness of all decisions in terms of efficiency of results.

Concept of pavement maintenance management system (PMMS)

Pavement Maintenance Management System (PMMS) is a scientific tool for managing so as

to make the best possible use of resources available or to maximize the benefit for society.

Thus, PMMS can be used in directing and controlling maintenance resources for optimum

benefit.

A Maintenance Management System of a city is composed of a group of interrelated

management tools designed to provide a basis for planning, scheduling, operating and

controlling the highway maintenance effort with economy and effectiveness. The use of this

system places continuity emphasis on the economic utilization of personnel, equipment and

materials, with the available resources.

Page 7: DESIGN PROJECT FOR PAVEMENT

3 | P a g e

The maintenance activities need to be considered in a more flexible and integrated decision-

making framework. The system should be capable of handling the various aspects in a

systematic manner, in view of the changing conditions. There is a strong need to gradually

introduce new technologies like Geographic Information System (GIS), Global Positioning

System (GPS), work scheduling, reports and inventory management. These will enable the

highway agencies to perform tasks better, more economically, effectively and of higher

quality. A Maintenance Management is the process of coordinating and controlling a

comprehensive set of activities in order to maintain pavements, so as to make the best

possible use of resources available.

Thus the aspects related to maintenance are the activities undertaken to preserve the surface

condition and structural quality of pavement. A Pavement Maintenance Management System

provides a systematic, objective and consistent procedure to evaluate existing and future

pavement condition.

A PMMS also provides a means to help manage pavement maintenance expenditure more

economically and efficiently. They provide an objective approach to pavement management

and allow for multiple budget options and assist in project formulation for maintenance and

rehabilitation works.

This study aims to initiate a Pavement Maintenance Management System (PMMS) in which

it provides a systematic process of maintaining, upgrading and operating the city pavements

and tools to facilitate a more flexible approach that can enable to perform tasks better, more

economically, effectively and of higher quality. A PMMS typically uses a pavement rating

system called Pavement Condition Index (PCI), as the basis from which current and future

pavement condition can be evaluated. From the estimated future pavement condition,

multiple budget and maintenance can be run to the most cost effective maintenance solutions

for the pavements. Pavement maintenance determine management systems are designed to

manage maintenance and rehabilitation activities to optimize pavement condition with

available funds.

The use of (PMMS) is becoming increasingly more prevalent due to benefits achieved. It

considers current and future pavement condition, priorities, funding, and can reduce

pavement deterioration, this helps maintain pavement structural capacity, and may extend

pavement life by slowing or limiting future pavement degradation. Pavement condition can

be quantified by the pavement condition rating (PCR) which rates the pavement according to

Page 8: DESIGN PROJECT FOR PAVEMENT

4 | P a g e

the extent and severity of distress types present (cracking, ravelling. bleeding, shoving).

Pavement Condition Rating ranges from 100 to zero.

A major goal of (PMMS) is to keep pavement condition in the upper (PCR) range of (60-90)

by limiting surface structural degradation to keep down rehabilitation cost. These procedures

is to provide a consistent reasonably objective and systematic procedure for establishing

priorities, scheduling and budgeting highway maintenance and rehabilitation requirements.

These pavement Maintenance Management Systems (PMMS) were developed to provide

management tools to the local municipal agencies in: a) prioritizing those road sections that

are in need of maintenance. Predicting the long term performance of maintenance

alternative. c) Estimating costs of pavement maintenance strategies with a view to selecting

an optimum strategy.

The maintenance management requires careful planning and implementation, efficient

reporting methods, easy information retrieval, and accurate assessment of maintenance

practices and problems. A maintenance management system as a whole involves managing

highway maintenance, which includes the pavement. The pavement management system

involves managing the pavement system, including its maintenance. The two concepts are

complementary. In some organizations, pavement maintenance and rehabilitation will be

handled through a pavement management concept. In others, the maintenance section will

carry the prime responsibility, with input from the pavement management group.

Highway Development and Management System (HDM-4) developed by the World bank is a

powerful pavement management software tool capable of performing technical and economic

appraisals of road projects, investigating road investment programs, and an analysing road

Page 9: DESIGN PROJECT FOR PAVEMENT

5 | P a g e

network preservation strategies. Its effectiveness is dependent on the proper calibration of its

predictive models to local conditions. The scope of the new HDM-4 tool have been

broadened considerably beyond traditional project appraisals, to provide a powerful system

for the analysis of road management and investment alternatives.

In addition to updating the HDM-III technical relationships for vehicle operating costs, and

pavement deterioration for flexible and unsealed pavements, new technical relationships have

been introduced to model rigid concrete pavement deterioration, accident costs, traffic

congestion, energy consumption and environmental effects. The HDM-4 incorporates three

dedicated applications tools for project level analysis, road work programming under

constrained budgets, and for strategic planning of long term network performance and

expenditure needs. It is designed to be used as a decision support tool within a road

management system. Standard data import and export facilities are provided for linking

HDM-4 to various database management systems.

Local adaptation and calibration of HDM-4 models can be achieved by specifying default

data sets that represent pavement performance and vehicle resource consumption in the

country where the model is being used. The HDM-4 software applications developed to cater

for the following components within the highway management process: Strategic Planning,

Work Programming, and Project Preparation. Strategic planning involves the analysis of the

road system as a whole, typically requiring the preparation of long term, or strategic,

planning estimates of expenditure for road development and preservation under various

budgetary and economic scenarios. Work Programming involves the preparation, under

budget constraints, of multi-year road work and expenditure programmes in which sections of

the network likely to require improvement, are identified and prioritized. Project preparation

is the final stage where the economic benefits of road schemes are analysed prior to

implementation.

Page 10: DESIGN PROJECT FOR PAVEMENT

6 | P a g e

LITERATURE SURVEY

AND DESIGN OF RIGID

AND FLEXIBLE

PAVEMENT

Page 11: DESIGN PROJECT FOR PAVEMENT

7 | P a g e

DESIGN OF RIGID PAVEMENT

General

The design for rigid pavement has been done as per the IRC Guidelines for

the Design of Plain Jointed Rigid Pavements for Highways IRC: 58-2002.

As per IRC-58, the following steps are followed for the design of rigid pavement.

Following these steps, the design of rigid pavement has been performed.

Design Traffic

Traffic Volume

As per IRC: 58-2002, in case of four-lane and multi-lane divided

carriageways, design traffic may be taken as 25 percent of the total traffic in the

direction of predominant traffic.

Page 12: DESIGN PROJECT FOR PAVEMENT

8 | P a g e

Axle load Spectrum

Axle load spectrum has been used to estimate the expected number of applications

of different axle load classes during the design period, as recommended by IRC:

58-2002. It has been determined based on the axle load survey data available.

Axle Load Spectrum from Axle Load Survey

Single Axle Load

Axle Load class

(t)

Cumulative

number of Axles

No of

Axles % age

0-9 205 205 46.28

9-11 272 67 15.12

11-13 332 60 13.54

13-15 362 30 6.77

15-17 369 7 1.58

17-19 375 6 1.35

19-21 379 4 0.90

21-23 379 0 0.00

23-25 379 0 0.00

25-27 379 0 0.00

27-29 379 0 0.00

Summation 379 85.55

Tandem Axle Load

Axle Load class

(t)

Cumulative

number of Axles

No of

Axles % age

0-14 17 17 3.84

14-18 22 5 1.13

18-22 33 11 2.48

22-26 51 18 4.06

26-30 56 5 1.13

30-34 61 5 1.13

34-38 63 2 0.45

Page 13: DESIGN PROJECT FOR PAVEMENT

9 | P a g e

38-42 64 1 0.23

42-46 64 0 0.00

46-50 64 0 0.00

Summation 64 14.45

Total No. of Single Axle & Tandem Axles = 443

Design of Rigid Pavement

Design of rigid pavement as per IRC: 58-2002 is based on the following data:

1. Design life = 30 years

2. Subgrade CBR = 8%

3. Load Safety Factor = 1.2

4. Compressive Strength of Concrete (28 days) = 40 MPa

5. Temperature variation for Jammu & Kashmir = 15.8oC

6. Modulus of Elasticity for concrete (E) = 3,00,000 kg/cm2

7. Poisson‟s ratio for concrete (µ) = 0.15

8. Thickness of DLC base (assumed) = 15 cm

9. Thickness of GSB drainage layer (assumed) = 15 cm

10. K-value of subgrade (for to 8% CBR) = 5.0 kg/cm2/cm

(from table-2 of IRC:58-2002)

11. Effective K-value over GSB layer (15cm Thick) = 5.8kg/cm2/cm

(from table-3 of IRC:58-2002)

12. Effective K-value over DLC layer (15cm Thick) = 41.7 kg/cm2/cm

( from table-4 of IRC:58-2002)

13. As graphs between Flexural stress and slab thickness given in IRC: 58-2002 are

available for a maximum k-value of 30.0 kg/cm2/cm, the same are used for the

design of pavement.

14. K-value considered for design over DLC layer = 30.0 kg/cm2/cm

Page 14: DESIGN PROJECT FOR PAVEMENT

10 | P a g e

15. Temperature Stress

ƒt = CtE

2

ƒt = Temperature stress in the edge region

Δt = Maximum temperature differential during day between top and

bottom of the slab.

α = Co-efficient of thermal expansion of concrete

C = Bradbury‟s co-efficient – can be taken from Table 3, IRC-58

against value of L/l & W/l.

L = Slab length

W = Slab Width

l = Radius of relative stiffness

16. Corner Stress

ƒc =

2.1

2

21

3

l

a

h

P

ƒc = Load stress on corner

Where,

a = Radius of load contact, cm, assumed circular.

=

P = Wheel Load, kg

S = c/c distance of two tyres in dual wheel assembly, 31 cm

q = Tyre pressure, 8 kg/cm2

17. Concrete flexural strength at 28 days is given by:

ƒfl = 0.70 (ƒck)0.5

… from IS:456-2000

Page 15: DESIGN PROJECT FOR PAVEMENT

11 | P a g e

Where,

ƒfl = Flexural strength at 28 days (MPa)

ƒck = Characteristic compressive strength at 28 days (MPa)

For ƒck = 400 kg/ cm2

ƒfl = 0.7 (40)0.5

= 45 kg/ cm2

A. Slab Thickness Design

1. Thickness of concrete slab (assumed) h = 28 cm

2. Radius of relative stiffness, cm, l = 4

1

2

3

)1(12

K

Eh

= 65.772 cm

3. Load Safety Factor = 1.2

4. Cumulative Number of Standard Axles = 108890000

5. Total Number of rear axle applications = 27222500

(Considering 25% of cumulative numbers)

Fatigue Analysis for expected load repetitions

a) Single Axle Load

Axle

load(AL),

tones

ALx1.2

Stress,

kg/cm2

from

charts

Stress

Ratio

Expected

Repetition,

n

Fatigue

life, N

Fatigue life

consumed

(1) (2) (3) (4) (5) (6)

Ratio

(5)/(6)

20 24 23.234 0.52 245250 2914518.33 0.08414770

18 21.6 21.459 0.48 367875 1763964.11 0.20855016

16 19.2 19.486 0.44 430550 Infinity 0.0000

14 16.8 17.462 0.39 1844825 Infinity 0.0000

12 14.4 15.379 0.35 3689650 Infinity 0.0000

Page 16: DESIGN PROJECT FOR PAVEMENT

12 | P a g e

10 12.0 13.231 0.30 4120200 Infinity 0.0000

8 9.6 10.984 0.25 12611300 Infinity 0.0000

Summation 1.103427

b) Tandem Axle Load

Axle

load(AL),

tones

ALx1.2

Stress,

kg/cm2

from

charts

Stress

Ratio

Expected

Repetition,

n

Fatigue

life, N

Fatigue life

consumed

(1) (2) (3) (4) (5) (6)

Ratio

(5)/(6)

36 43.2 20.46 0.46 122625 11326279.5 0.01082659

32 38.4 15.24 0.34 307925 Infinity 0.0000

28 33.6 13.76 0.31 307925 Infinity 0.0000

24 28.8 12.10 0.27 1106350 Infinity 0.0000

20 24.0 10.41 0.24 675800 Infinity 0.0000

16 19.2 8.92 0.20 307925 Infinity 0.0000

12 14.4 7.37 0.17 1046400 Infinity 0.0000

Summation 0.01082659

Total fatigue life consumed = 1.1143 (>1, Hence, design is unsafe)

Page 17: DESIGN PROJECT FOR PAVEMENT

13 | P a g e

Now, considering thickness of concrete slab, h= 30 cm

Radius of relative stiffness, cm, l = 4

1

2

3

)1(12

K

Eh

= 69.26 cm

Load Safety Factor = 1.2

Cumulative Number of Standard Axles = 108890000

Total Number of rear axle applications = 27222500

(Considering 25% of cumulative numbers)

Fatigue Analysis for expected load repetitions

c) Single Axle Load

Axle

load(AL),

tones

ALx1.2

Stress,

kg/cm2

from

charts

Stress

Ratio

Expected

Repetition,

n

Fatigue

life, N

Fatigue life

consumed

(1) (2) (3) (4) (5) (6)

Ratio

(5)/(6)

20 24 21.130 0.48 245250 2914518.33 0.08414770

18 21.6 19.523 0.44 367875 Infinity 0.0000

16 19.2 17.712 0.40 430550 Infinity 0.0000

14 16.8 15.856 0.36 1844825 Infinity 0.0000

12 14.4 13.948 0.32 3689650 Infinity 0.0000

Page 18: DESIGN PROJECT FOR PAVEMENT

14 | P a g e

10 12.0 11.984 0.27 4120200 Infinity 0.0000

8 9.6 9.933 0.22 12611300 Infinity 0.0000

Summation 0.0841

d) Tandem Axle Load

Axle

load(AL),

tones

ALx1.2

Stress,

kg/cm2

from

charts

Stress

Ratio

Expected

Repetition,

n

Fatigue

life, N

Fatigue life

consumed

(1) (2) (3) (4) (5) (6)

Ratio

(5)/(6)

36 43.2 18.71 0.42 122625 Infinity 0.0000

32 38.4 13.84 0.31 307925 Infinity 0.0000

28 33.6 12.49 0.28 307925 Infinity 0.0000

24 28.8 10.95 0.25 1106350 Infinity 0.0000

20 24.0 9.39 0.21 675800 Infinity 0.0000

16 19.2 8.06 0.18 307925 Infinity 0.0000

12 14.4 6.64 0.15 1046400 Infinity 0.0000

44 0 Infinity 0.0000

Summation 0.0000

Page 19: DESIGN PROJECT FOR PAVEMENT

15 | P a g e

Total fatigue life consumed = 0.0841 (< 1, Hence, design is

safe)

o Edge Stress Analysis

Assuming contraction joint spacing of 4.5 m

L = 4.5 m = 450 cm

l = 69.26 cm

L / l = 6.49

From IRC-58, Bradbury‟s Coefficient, C = 0.9739

Temperature differential = 15.8o

So, Edge Warping stress, ƒt = EαtC/2 = 23.08 kg/cm2

The highest axle load stress (from previous tables for fatigue analysis)

ƒe = 21 kg/cm2

Total stress = 23.08+21

= 44.08 kg/cm2 (< 45 kg/cm

2)

Hence, Design is safe.

o Corner Stress Analysis

98th

percentile axle load = 27900 kg (See Annexure)

Design wheel load (P) = 0.5 x 98th

percentile axle load =

13950 kg

Slab thickness, h = 30 cm

Radius of equivalent circular contact area,

Page 20: DESIGN PROJECT FOR PAVEMENT

16 | P a g e

a = =32.294

cm

Radius of relative stiffness, l = 69.26 cm

Corner Stress at design wheel load,

ƒc =

2.1

2

21

3

l

a

h

P=18.287 kg/cm

2 (<45kg/cm

2)

Hence, design is safe.

So adopt 30 cm PQC + 150 DLC as pavement for the section.

As DLC cannot be put directly over subgrade, it is proposed to have a 150 mm GSB

drainage layer below DLC.

B. Dowel Bar Design

Design Parameters:

98th

percentile wheel load = 13950 kg

Design load transfer = 40%

Slab thickness, h = 30 cm

K-value for base = 30 kg/cm3

E = 3 x 105 kg/cm

2

µ = 0.15

Fck = 400 kg/cm2 for M-40 Grade

Assume a dowel bar diameter, b = 3.6 cm

Moment of Inertia of dowel, I = πb4/64

= 8.24 cm4

Modulus of dowel concrete interaction, k = 41500 kg/cm2/cm

Modulus of Elasticity of dowel steel, E = 2,000,000 kg/cm2

Page 21: DESIGN PROJECT FOR PAVEMENT

17 | P a g e

Relative stiffness of dowel, β = = 0.218

Permissible bearing stress in concrete,

Fb = = 275.48 kg/cm2

Assumed Length of dowel bar = 50 cm

B.1 For Expansion Joint

Joint width, Z = 2 cm

Assumed dowel bar spacing for expansion joint, s = 12 cm

Distance of first dowel bar from the pavement edge = 6 cm

Distance up to which dowel bars are effective in

load transfer from the point of load application, l = 69.26 cm

Number of dowel bars participating in load transfer when wheel load is just over

the dowel bar close to the edge of the slab = 1+l/s = 6

Assuming the load transferred by the first dowel is Pt and assuming that the load on

dowel bar at a distance of l from the first dowel to be zero, the total load capacity

factor transferred by dowel bar system

= (1+

+

+

+

+

) =3.4Pt

Load carried by the outer dowel bar, Pt =

= 1641.176 kg

Page 22: DESIGN PROJECT FOR PAVEMENT

18 | P a g e

Check for Bearing Stress

Bearing stress in dowel bar = (Pt k) x (2+βz) / (4β3EI)

= { }

= 242.937 (< 275.48 Kg/cm2)

Hence Dowels of 36mm diameter plain round mild steel bars, 500mm long are

provided at 12 cm spacing in the expansion joints.

B.2 For Contraction Joint

Joint width, Z = 0.5 cm

Assumed dowel bar spacing for expansion joint, s = 15 cm

Distance of first dowel bar from the pavement edge = 7.5 cm

Distance up to which dowel bars are effective in

load transfer from the point of load application, l = 69.26 cm

Number of dowel bars participating in load transfer when wheel load is just over

the dowel bar close to the edge of the slab = 1+l/s = 5

Assuming the load transferred by the first dowel is Pt and assuming that the load on

dowel bar at a distance of l from the first dowel to be zero, the total load capacity

factor transferred by dowel bar system

= (1+

+

+

+

) =2.834 Pt

Page 23: DESIGN PROJECT FOR PAVEMENT

19 | P a g e

Load carried by the outer dowel bar, Pt =

= 1968.94 kg

Check for Bearing Stress

Bearing stress in dowel bar = (Pt k) x (2+βz) / (4β3EI)

= { }

= 252.33 (< 275.48 Kg/cm2)

Hence Dowels of 36mm diameter plain round mild steel bars, 500mm long are

provided at 15 cm spacing in the expansion joints.

C. Tie Bar Design

Slab width, b = 3.5 m

Number of lanes to be tied = 1.0

Co-efficient of friction between sub-bar and slab, ƒ = 1.5

Density of concrete = 2400 kg/m3

Weight of 300 mm thick concrete slab, W = 0.3 x 2400 = 720 kg/m

2

Type of steel for tie bars: TMT deformed steel bars

Allowable bond stress for deformed steel bars, B = 24.6 kg/cm2

Allowable tensile stress for deformed steel bars, S = 2000 kg/cm2

Assuming diameter of tie bar = 12 mm

Length and Spacing of tie bars:

Area of steel required per m width of joint to resist the frictional force at slab

bottom, As =

=

=1.89 cm

2/m

Area of cross-section for bar, A = π x 0.25 x (1.2)2

= 1.13 cm2

Perimeter for the bar P = 3.77 cm

i Spacing = A/As = 100 x 1.13/ 1.89 = 60 cm

Page 24: DESIGN PROJECT FOR PAVEMENT

20 | P a g e

ii Length of tie bar = BP

SA2 =

= 48.73 cm

We increase the length by 10 cm for loss of bond due to painting and another 5 cm

for tolerance in placement.

Therefore, the length is 48.73+10+5=63.73 cm, Say 65 cm.

Hence, following values are adopted for tie bars (deformed):

Diameter of bar = 12 mm

Spacing = 600 mm

Length = 650 mm

The tie bar is to be placed at mid depth inside the joint.

D. Summary of Design

Grade of concrete for PCC surfacing : M-40

Minimum flexural strength of PCC surfacing at 28 days

: 4.5 MPa

Concrete Pavement Thickness h1 : 300 mm

Dry Lean Concrete Thickness h2 : 150 mm

Granular Sub-base Thickness h3 : 150 mm

Dowel Bars (MS) Dia Ddowel : 36 mm

Length of Dowel Bars ldowel : 500 mm

Spacing of Dowel Bars

For Expansion Joint : 120 mm

For Contraction Joint : 150 mm

Tie Bar (deformed steel) Dtie : 12 mm

Tie Bar Length : 650 mm

Tie Bar Spacing : 600 mm

Page 25: DESIGN PROJECT FOR PAVEMENT

21 | P a g e

Drawings for Rigid Pavement inside Tunnels

Pavement Joint Plan

Transverse Contraction Joint

Page 26: DESIGN PROJECT FOR PAVEMENT

22 | P a g e

Longitudinal joints

Notes:

1. ALL DIMENSIONS ARE IN MILLIMETERS

2. THE DOWEL BARS SHALL BE PLACED AT 300 CENTERS. THIS

SPACING SHALL BE VARIED WHERE NECESSARY SO THAT NO

DOWEL BAR IS WITHIN 150 OF A JOINT PARALLEL TO THE BARS.

3. CONTRACTION JOINTS SHALL BE PLACED AT 4500 CENTERS.

4. DOWEL BARS TO BE COVERED BY THIN PLASTIC SHEATH FOR

MIN.OF 2/3 LENGTH FROM ONE END.

5. SUPPORT CHAIRS FOR DOWEL BARS ARE OMITTED FOR CLARITY.

Page 27: DESIGN PROJECT FOR PAVEMENT

23 | P a g e

DESIGN OF FLEXIBLE PAVEMENT

General

In order to achieve the stated objectives of the traffic study, the following surveys

were undertaken to obtain the traffic data. Detailed traffic surveys were conducted

in December of 2011. Hereinafter, the year 2011 is called the „Base year‟.

o Classified traffic volume count (CTVC) data collection for seven days (twenty

four hours continuous) at three locations.

o Origin and destination (O-D) survey for one day (twenty four hours

continuous) at two proposed toll plaza locations.

o Turning movement count (TMC) data collection at two major junctions for

one day (twenty four hours continuous).

o Axle load survey for one day (twenty four hours continuous) at two locations.

Design traffic for pavement design:

According to clause number 4.4.2 of IRC: SP: 84-2009, the pavement of the

main highway shall be designed for the cumulative number of standard axles of

8.16 tons over the design.

The design traffic is considered in terms of the cumulative number of standard

axles (in the lane carrying maximum traffic) to be carried during life of the road.

This can be computed using the following equation:

N = 365 x [(1+r)n – 1] x A x D x F

r

where ,

N = Cumulative number of standard axles to be catered for in the design in

terms of Million Standard Axles (MSA) or CMSA.

A = Initial traffic in the year of completion of construction in terms of the

number of commercial vehicles per day (CVPD).

Page 28: DESIGN PROJECT FOR PAVEMENT

24 | P a g e

D = Lane distribution factor. According to IRC: 37-2001 and its draft version

of 2011. The lane distribution factor for four-laning project is 0.75.

F = Vehicle damage factor (VDF).

n = Design life in years.

r = Annual growth rate of commercial vehicles.

Vehicle damage factor:

The vehicle damage factor (VDF) is a multiplier to convert the number of

commercial vehicles of different axle loads and axle configurations to the

number of standard axle load repetitions .It is defined as equivalent number of

standard axles per commercial vehicle .For design purposes , the variation in axle

loads is determined by reducing the actual axle loads to an „Equivalent Standard

axle Load‟ or ESAL .An equivalency is a convenient way of indexing the wide

spectrum of actual loads to one selected standard value .ESAL is determined by

the relationships recommended in IRC:37-2001 & draft revision of IRC:37-2011

on „Guidelines for the design of flexible pavement‟. An excerpt is presented here:

1. Single axle with single wheel on either side: Equivalence factor = (Axle load in

kg/6,600)4

2. Single axle with dual wheel on either side: Equivalence factor = (Axle load in

kg/8,160)4

3. Tandem axle with dual wheel on either side: Equivalence factor = (Axle load in

kg/14,968)4

4. Tridem axle with dual wheel on either side: Equivalence factor = (Axle load in

kg/22,900)4

The relationship is referred to as „Fourth Power Rule‟ ,which states that the

damaging effect of an axle load increases as the fourth power of the weight of an

axle .In order to convert axle loads from the survey data into ESAL ,each axle of

each category of vehicle is multiplied by the equivalence factor of that type of

axle .The output may be called the „damage‟ caused by that particular axle on the

pavement.

Page 29: DESIGN PROJECT FOR PAVEMENT

25 | P a g e

Damages by all axles are then summed up to find the total damage by that type

of vehicle. The total damage id divided by the number of vehicles of that category

to obtain the average damage ,which is also called the Vehicle Damage

Factor(VDF) of that category of vehicle.

VDF = Total damage

Number of vehicles damaged

Lane distribution factor:

Distribution of commercial traffic in each direction and in each lane is required

for determining the total equivalent standard axle load applications to be

considered in the design. In the absence of adequate and conclusive data, the

following distribution may be assumed until more reliable data on placement of

commercial vehicles on the carriageway lanes are available:

1. Single-lane roads Traffic tends to be more channelized on single-lane roads

than two-lane roads and to allow for this concentration of wheel load

repetitions, the design should be based on total number of commercial

vehicles in both directions.

2. Two-lane single carriageway roads The design should be based on 50 per

cent of the total number of commercial vehicles in both directions. If vehicle

damage factor in one direction is higher, the traffic in the direction of higher

VDF is recommended for design.

3. Four-lane single carriageway roads The design should be based on 40 per

cent of the total number of commercial vehicles in both directions.

4. Dual carriageway roads The design of dual two-lane carriageway roads

should be based on 75 per cent of the number of commercial vehicles in each

direction. For dual three-lane carriageway and dual four-lane carriageway,

the distribution factor will be 60 per cent and 45 per cent respectively.

Page 30: DESIGN PROJECT FOR PAVEMENT

26 | P a g e

VDF tables:

1. Standard bus

Page 31: DESIGN PROJECT FOR PAVEMENT

27 | P a g e

2. Two axle vehicle

Page 32: DESIGN PROJECT FOR PAVEMENT

28 | P a g e

3. Three axle vehicle (with tandem axle)

Page 33: DESIGN PROJECT FOR PAVEMENT

29 | P a g e

Page 34: DESIGN PROJECT FOR PAVEMENT

30 | P a g e

Page 35: DESIGN PROJECT FOR PAVEMENT

31 | P a g e

Page 36: DESIGN PROJECT FOR PAVEMENT

32 | P a g e

4. Four axle vehicle (with tandem axle)

Page 37: DESIGN PROJECT FOR PAVEMENT

33 | P a g e

Page 38: DESIGN PROJECT FOR PAVEMENT

34 | P a g e

Page 39: DESIGN PROJECT FOR PAVEMENT

35 | P a g e

5. Five axle vehicle

Page 40: DESIGN PROJECT FOR PAVEMENT

36 | P a g e

Page 41: DESIGN PROJECT FOR PAVEMENT

37 | P a g e

6. Five axle vehicle

Page 42: DESIGN PROJECT FOR PAVEMENT

38 | P a g e

7. Six axle vehicle

Page 43: DESIGN PROJECT FOR PAVEMENT

39 | P a g e

8. LCV – 4 wheeler

Page 44: DESIGN PROJECT FOR PAVEMENT

40 | P a g e

9. LCV – 6 wheeler

Page 45: DESIGN PROJECT FOR PAVEMENT

41 | P a g e

Million standard axle (MSA) chart:

336.1776 msa is traffic of both side of the carriageway.

So, one side traffic = 336.1776/2 = 168 msa

To determine the pavement composition at different section of highway, design

charts are referred as given in IRC 37-2012 or IITPAVE software can be used to

determine the composition. Corresponding to msa value and CBR percentage, the

thickness of pavement can be obtained from design charts.

Page 46: DESIGN PROJECT FOR PAVEMENT

42 | P a g e

CBR of subgrade = 15 %

Million standard axles (msa) = 150

From plate 8 of IRC 37:2012;

Pavement composition corresponding to 150 msa and 15 % CBR is:

Granular Sub-base (GSB) = 200 mm

Base course (WMM) = 250 mm

Dense Bituminous Macadam (DBM) = 100 mm

Bituminous Concrete (BC) = 50 mm

Total pavement thickness = 600 mm

Page 47: DESIGN PROJECT FOR PAVEMENT

43 | P a g e

METHODOLOGY

AND

ANALYSIS

Page 48: DESIGN PROJECT FOR PAVEMENT

44 | P a g e

Highway Development and Management System (HDM-4) developed

by the World bank is a powerful pavement management software tool capable of performing

technical and economic appraisals of road projects, investigating road investment programs,

and an analysing road network preservation strategies. Its effectiveness is dependent on the

proper calibration of its predictive models to local conditions. The scope of the new HDM-4

tool have been broadened considerably beyond traditional project appraisals, to provide a

powerful system for the analysis of road management and investment alternatives.

In addition to updating the HDM-III technical relationships for vehicle operating costs, and

pavement deterioration for flexible and unsealed pavements, new technical relationships have

been introduced to model rigid concrete pavement deterioration, accident costs, traffic

congestion, energy consumption and environmental effects. The HDM-4 incorporates three

dedicated applications tools for project level analysis, road work programming under

constrained budgets, and for strategic planning of long term network performance and

expenditure needs. It is designed to be used as a decision support tool within a road

management system. Standard data import and export facilities are provided for linking

HDM-4 to various database management systems.

Local adaptation and calibration of HDM-4 models can be achieved by specifying default

data sets that represent pavement performance and vehicle resource consumption in the

country where the model is being used. The HDM-4 software applications developed to cater

for the following components within the highway management process: Strategic Planning,

Work Programming, and Project Preparation. Strategic planning involves the analysis of the

road system as a whole, typically requiring the preparation of long term, or strategic,

planning estimates of expenditure for road development and preservation under various

budgetary and economic scenarios. Work Programming involves the preparation, under

budget constraints, of multi-year road work and expenditure programmes in which sections of

the network likely to require improvement, are identified and prioritized. Project preparation

Page 49: DESIGN PROJECT FOR PAVEMENT

45 | P a g e

is the final stage where the economic benefits of road schemes are analysed prior to

implementation.

ROLE OF HDM-4 IN HIGHWAY MANAGEMENT: When

considering the HDM-4 applications, it is convenient to view the highway management

process in terms of the following functions

• Planning

• Programming

• Operations

Planning: This involves an analysis of the road system as a whole, typically requiring the

preparation of long term, or strategic, planning estimates of expenditure for road development

and preservation under various budgetary and economic scenarios. Predictions may be made

of expenditure under selected budget heads, and forecasts of highway conditions in terms of

key indicators, under a variety of funding levels. The physical highway system is usually

characterized at the planning stage by lengths of road, or percentages of the network, in

various categories defined by parameters such as road class or hierarchy, traffic

flow/capacity, pavement and physical condition. The results of the planning exercise are of

most interest to senior policy makers in the road sector, both political and professional. Work

will often be undertaken by a planning or economics unit within a road agency.

Programming: This involves the preparation, under budget constraints, of multi-year road

works and expenditure programmes in which those sections of the network likely to require

maintenance, improvement, or new construction, are identified in a tactical planning exercise.

Ideally, cost-benefit analysis should be undertaken to determine the economic feasibility of

each set of works. The physical road network is normally considered at the programming

stage on a link- by-link basis, with each link characterised by pavement sections and

geometric segments, defined by their physical attributes. The programming activity produces

estimates of expenditure, under different budget heads, for different treatment types and for

different years for each road section. Budgets are typically constrained, and a key aspect of

programming is to prioritise works to find the best value for money in the case of a

constrained budget

Page 50: DESIGN PROJECT FOR PAVEMENT

46 | P a g e

Operations: These activities cover the on-going operation of a road agency. Decisions

about the management of operations are made typically on a daily or weekly basis, including

the scheduling of work to be carried out, monitoring in terms of labour, equipment and

materials, the recording of work completed, and the use of this information for monitoring

and control. Activities are normally focused on individual road sections with measurements

often being made at a relatively detailed level. Operations are normally managed by sub-

professional staff, including works supervisors, technicians, clerks of works, and others.

GENERAL

Pavement management as a process based on the integration of system principles,

engineering and economic evaluation is supposed to have begun in the late 1960's. The first

PMS model were developed in the mid-seventies, and presently many highways authorities in

developed countries are using a systematic and objective method to determine pavement

condition and programming maintenance in response to observed conditions. Presently most

advanced PMS are those applied in North America.

Methodology and Data Base Collection Methodology of the study:

The following steps outline the methodology used for the developing the cost effective

maintenance strategies for the BPP network by periodic evaluation of the pavement both

structurally as well as functionally:-

-Identification of the urban network for which the PMMS is to be developed. I will

Preparation of an inventory of all the pavement sections such as section length, carriageway

width, and shoulder width, temperature and rainfall characteristics.

-Collection of the data related to characteristics of the vehicle fleet using the and also the

collection of the traffic volume to ascertain the traffic related characteristics of all the

pavement sections.

-Collection of the periodic pavement condition data in terms of various pavement distresses

such as cracking area, potholing area, rutting, roughness, structural deflection using standard

measures and equipment‟s. Calculation of the Pavement Serviceability Index.

-Calculation of the remaining service life of the pavement sections of the network.

Page 51: DESIGN PROJECT FOR PAVEMENT

47 | P a g e

Data collection based upon the requirement of HDM-4

The effectiveness of any PMMS is dependent upon the data being used (Nashville

Department of Transport 2007). Primary types of data needed include pavement condition

ratings, costs, roadway construction and maintenance history as well as traffic loading. A

major emphasis of any PMS is to identify and evaluate pavement conditions and determine

the causes of deterioration. To accomplish this, a pavement evaluation system should be

developed that is rapid, economical and easily repeatable. Pavement condition data must be

selected periodically to document the changes of pavement condition.

ROAD NETWORK DATA The road network data collection is carried out based upon the

data requirements of HDM-4, and it consisted of obtaining secondary data from the past

records and relevant government publications, and collecting current data from the selected

pavement sections by carrying out field studies.

The road network data includes the location data that describes the position and geometry of

the pavement section, and the attribute data, which describes the road characteristics or

inventory associated with it. The road network data collection in the field is divided under the

following heads:

• Inventory data

• Structural evaluation (Structural capacity)

• Functional evaluation (Pavement condition and riding quality).

Steps for data input in HDM-4 :

Page 52: DESIGN PROJECT FOR PAVEMENT

48 | P a g e

Page 53: DESIGN PROJECT FOR PAVEMENT

49 | P a g e

Page 54: DESIGN PROJECT FOR PAVEMENT

50 | P a g e

Page 55: DESIGN PROJECT FOR PAVEMENT

51 | P a g e

Page 56: DESIGN PROJECT FOR PAVEMENT

52 | P a g e

Page 57: DESIGN PROJECT FOR PAVEMENT

53 | P a g e

Page 58: DESIGN PROJECT FOR PAVEMENT

54 | P a g e

Page 59: DESIGN PROJECT FOR PAVEMENT

55 | P a g e

Page 60: DESIGN PROJECT FOR PAVEMENT

56 | P a g e

Page 61: DESIGN PROJECT FOR PAVEMENT

57 | P a g e

Page 62: DESIGN PROJECT FOR PAVEMENT

58 | P a g e

Page 63: DESIGN PROJECT FOR PAVEMENT

59 | P a g e

Page 64: DESIGN PROJECT FOR PAVEMENT

60 | P a g e

Page 65: DESIGN PROJECT FOR PAVEMENT

61 | P a g e

Page 66: DESIGN PROJECT FOR PAVEMENT

62 | P a g e

Page 67: DESIGN PROJECT FOR PAVEMENT

63 | P a g e

Page 68: DESIGN PROJECT FOR PAVEMENT

64 | P a g e

Page 69: DESIGN PROJECT FOR PAVEMENT

65 | P a g e

Page 70: DESIGN PROJECT FOR PAVEMENT

66 | P a g e

OUTPUT:

Page 71: DESIGN PROJECT FOR PAVEMENT

67 | P a g e

Page 72: DESIGN PROJECT FOR PAVEMENT

68 | P a g e

Page 73: DESIGN PROJECT FOR PAVEMENT

69 | P a g e

Page 74: DESIGN PROJECT FOR PAVEMENT

70 | P a g e

Page 75: DESIGN PROJECT FOR PAVEMENT

71 | P a g e

SOIL STABILIZATION

INTRODUCTION

Site feasibility study for geotechnical projects is of far most beneficial before a project can

take off. Site survey usually takes place before the design process begins in order to

understand the characteristics of subsoil upon which the decision on location of the project

can be made. The following geotechnical design criteria have to be considered during site

selection –

Page 76: DESIGN PROJECT FOR PAVEMENT

72 | P a g e

1. Design load and function of the structure.

2. Type of foundation to be used.

3. Bearing capacity of subsoil.

In the past, the third bullet played a major in decision making on site selection. Once the

bearing capacity of the soil was poor, the following were options:

1. Change the design to suit site condition.

2. Remove and replace the in situ soil.

3. Abandon the site.

Abandoned sites due to undesirable soil bearing capacities dramatically increased, and the

outcome of this was the scarcity of land and increased demand for natural resources. Affected

areas include those which were susceptible to liquefaction and those covered with soft clay

and organic soils. Other areas were those in a landslide and contaminated land. However, in

most geotechnical projects, it is not possible to obtain a construction site that will meet the

design requirements without ground modification. The current practice is to modify the

engineering properties of the native problematic soils to meet the design specifications.

Nowadays, soils such as, soft clays and organic soils can be improved to the civil engineering

requirements. This state of the art review focuses on soil stabilization method which is one of

the several methods of soil improvement.

Soil stabilization aims at improving soil strength and increasing resistance to softening by

water through bonding the soil particles together, water proofing the particles or combination

of the two. Usually, the technology provides an alternative provision structural solution to a

practical problem. The simplest stabilization processes are compaction and drainage (if water

drains out of wet soil it becomes stronger). The other process is by improving gradation of

particle size and further improvement can be achieved by adding binders to the weak soils.

Soil stabilization can be accomplished by several methods. All these methods fall into two

broad categories namely;

1. Mechanical stabilization –

Page 77: DESIGN PROJECT FOR PAVEMENT

73 | P a g e

Under this category, soil stabilization can be achieved through physical process by altering

the physical nature of native soil particles by either induced vibration or compaction or by

incorporating other physical properties such as barriers and nailing.

2. Chemical stabilization –

Under this category, soil stabilization depends mainly on chemical reactions between

stabilizer (cementitious material) and soil minerals (pozzolonic materials) to achieve the

desired effect.

Through soil stabilization, unbound materials can be stabilized with cementitious materials

(cement, lime, fly ash, bitumen or combination of these). The stabilized soil materials have a

higher strength, lower permeability and lower compressibility than the native soil. The

method can be achieved in two ways, namely; (1) in situ stabilization and (2) ex-situ

stabilization. Note that, stabilization not necessary a magic wand by which every soil

properties can be improved for better. The decision to technological usage depends on which

soil properties have to be modified. The chief properties of soil which are of interest to

engineers are volume stability, strength, compressibility, permeability and durability. For a

successful stabilization, a laboratory tests followed by field tests may be required in order to

determine the engineering and environmental properties. Laboratory tests although may

produce higher strength than corresponding material from the field, but will help to assess the

effectiveness of stabilized materials in the field. Results from the laboratory tests, will

enhance the knowledge on the choice of binders and amounts.

Page 78: DESIGN PROJECT FOR PAVEMENT

74 | P a g e

PAVEMENT DESIGN CATALOGUES

Five different combinations of traffic and material properties have been considered for which

pavement composition has been suggested in the form of design charts presented in Plates 1

to 24. Each combination has been supported with illustration to compare the proposed design

thickness in the design catalogue with that given by IITPAVE (Clauses 10.1 to 10.5). The

five combinations are as under:

1. Granular Base and Granular Subbase. (Cl 10.1) (Plate 1 to 8).

2. Cementitious Base and Cementitious Subbase of aggregate interlayer for crack relief.

Upper 100 mm of the cementitious subbase is the drainage layer. (Cl 10.2) (Plate 9

to 12).

3. Cementitious base and subbase with SAMI at the interface of base and the

bituminous layer. (Cl 10.3) (Plate 13 to 16).

4. Foamed bitumen/bitumen emulsion treated RAP or fresh aggregates over 250 mm

cementitious subbase (Cl 10.4) (Plate 17 to 20).

5. Cementitious base and granular subbase with crack relief layer of aggregate layer

above the cementitious base. (Cl 10.5) (Plate 21 to 24).

Page 79: DESIGN PROJECT FOR PAVEMENT

75 | P a g e

1. Granular Base and Granular Sub-base –

Fig 1.1 Bituminous Surfacing with Granular Base and Granular Sub-base.

Fig. 1.1 shows the cross section of a bituminous pavement with granular base and subbase. It

is considered as a three layer elastic structure consisting of bituminous surfacing, granular

base and subbase and the subgrade. The granular layers are treated as a single layer. Strain

and stresses are required only for three layer elastic system. The critical strains locations are

shown in the figure. For traffic > 30 MSA, VG 40 bitumen is recommended for BC as well as

DBM for plains in India. Thickness of DBM for 50 MSA is lower than that for 30 MSA for a

few cases due to stiffer bitumen. Lower DBM is compacted to an air void of 3% after rolling

with volume of bitumen close to 13 % (Bitumen content may be 0.5% to 0.6% higher than

the optimum). Thickness combinations up to 30 MSA are the same as those adopted in IRC:

37-2001.

Page 80: DESIGN PROJECT FOR PAVEMENT

76 | P a g e

CBR of Subgrade = 15%

Million Standard Axles (MSA) = 150

From Plate 8 of IRC 37:2012

Pavement Composition

Granular Sub-base (GSB) = 200 mm

Base Course (WMM) = 250 mm

Dense Bituminous Macadam (DBM) = 100 mm

Bituminous Concrete (BC) = 50 mm

Total Pavement Thickness = 600 mm

Page 81: DESIGN PROJECT FOR PAVEMENT

77 | P a g e

2. Bituminous Pavements with Cemented Base and Cemented Sub-base with Crack

Relief Interlayer of Aggregate –

Fig. 2.1 Bituminous Surfacing, Cement Treated Base and Cement Treated Sub-Base

with Aggregate Interlayer

Fig. 2.1 shows a five layer elastic structure consisting of bituminous surfacing, aggregate

interlayer layer, cemented base, cemented subbase and the subgrade. Material properties such

as modulus and Poisson‟s ratio are the input parameters apart from loads and geometry of the

pavement for the IITPAVE software. For traffic > 30 MSA, VG 40 bitumen is used for

preventing rutting. DBM has air void of 3% after rolling (Bitumen content is 0.5% to 0.6%

higher than the optimum). Cracking of cemented base is taken as the design life of a

pavement. For traffic greater than 30 MSA, minimum thickness of bituminous layer

consisting of DBM and BC layers is taken as 100 mm (AASHTO-1993) even though the

thickness requirement may be less from structural consideration. Residual life of the

bituminous layer against fatigue cracking is not considered since it cracks faster after the

fracture of the cemented base. Upper 100 mm of the cemented subbase (D) having the

gradation 4 of the Table V-1 of Annexure V is porous acting as the drainage layer over lower

cemented subbase (F). Coarse graded GSB of MORTH with fines less than 2% containing

about 2-3% cement can also be used.

Page 82: DESIGN PROJECT FOR PAVEMENT

78 | P a g e

CBR of Subgrade = 15%

Million Standard Axles (MSA) = 150

From Plate 12 of IRC 37:2012

Pavement Composition

Cementitious Sub-base (E=600 MPa) = 250 mm

Cementitious Base Course (E=3000 MPa) = 100 mm

Aggregate Layer (E=450 Mpa) = 100 mm

Dense Bituminous Macadam (DBM) = 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm

Total Pavement Thickness = 550 mm

Page 83: DESIGN PROJECT FOR PAVEMENT

79 | P a g e

3. Cemented Base and Cemented Sub-base with Sami at the Interface of Cemented

Base and the Bituminous Layer –

Fig. 3.1 Bituminous Surfacing with Cemented Granular Base and Cemented Granular

Sub-base with Stress Absorbing Membrane Interlayer (SAMI)

Fig. 3.1 shows a four layer pavement consisting of bituminous surfacing, cemented base,

cemented subbase and the subgrade. For traffic > 30 MSA, VG 40 bitumen is used. DBM

IRC: 37-2012 33 has air void of 3 per cent after rolling (Bitumen content is 0.5 per cent to 0.6

per cent higher than the optimum). Cracking of cemented base is taken as the life of

pavement. Minimum thickness of bituminous layer for major highways is recommended as

100mm as per the AASHTO93 guidelines. Stress on the underside of the bituminous layer

over un-cracked cemented layer is compressive. Upper 100 mm of the cemented subbase

having the gradation 4 of Table V-1 of Annex V is porous and functions as drainage layer

over the cemented lower subbase.

Page 84: DESIGN PROJECT FOR PAVEMENT

80 | P a g e

CBR of Subgrade = 15%

Million Standard Axles (MSA) = 150

From Plate 16 of IRC 37:2012

Pavement Composition

Cementitious Sub-base (E=600 MPa) = 250 mm

Cementitious Base Course (E=3000 MPa) = 150 mm

Dense Bituminous Macadam (DBM) = 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm

Total Pavement Thickness = 500 mm

Page 85: DESIGN PROJECT FOR PAVEMENT

81 | P a g e

4. Foamed Bitumen/Bitumen Emulsion Treated Rap/Aggregates Over Cemented

Sub-base –

Fig. 4.1 Bituminous Surfacing with RAP and Cemented Sub-base

Fig. 4.1 shows a four layer pavement consisting of bituminous surfacing, recycled layer

Reclaimed asphalt pavement, cemented subbase and the subgrade. VG 40 is used for traffic >

30 MSA. Even bitumen emulsion/foamed bitumen treated fresh aggregates can be used to

obtain stronger base of flexible pavements as per the international practice. DBM has air void

of 3 per cent after rolling (Bitumen content is 0.5 per cent to 0.6 per cent higher than the

optimum). Fatigue failure of the bituminous layer is the end of pavement life.

Page 86: DESIGN PROJECT FOR PAVEMENT

82 | P a g e

CBR of Subgrade = 15%

Million Standard Axles (MSA) = 150

From Plate 20 of IRC 37:2012

Pavement Composition

Cementitious Sub-base (E=600 MPa) = 250 mm

Treated RAP (E=600 MPa) = 140 mm

Dense Bituminous Macadam (DBM) = 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm

Total Pavement Thickness = 490 mm

Page 87: DESIGN PROJECT FOR PAVEMENT

83 | P a g e

5. Cemented Base and Granular Sub-base with Crack Relief Layer of Aggregate

Interlayer Above the Cemented Base –

Fig. 5.1 Bituminous Surfacing, Cement Treated Base and Granular Sub-base with

Aggregate Interlayer

For reconstruction of a highway, designers may have a choice of bituminous surface,

aggregate interlayer, cemented base while retaining the existing granular subbase. The

drainage layer in GSB is required to be restored in area where rainfall may damage the

pavements. It is modeled as a five layer elastic structure in IITPAVE software. In a two layer

construction of bituminous layer, the bottom layer should have an air void of 3 per cent after

the compaction by incorporating additional bitumen of 0.5 to 0.6 per cent. This would also

resist stripping due to water percolating from the top to the bottom of the bituminous layer or

rising from below. The aggregate interlayer acting as a crack relief layer should meet the

specifications of Wet Mix Macadam and if required, it may contain about 1 to 2 per cent

bitumen emulsion if the surface of the granular layer is likely to be disturbed by construction

traffic. Emulsion can be mixed with water to make the fluid equal to optimum water content

and added to the WMM during the processing.

Page 88: DESIGN PROJECT FOR PAVEMENT

84 | P a g e

CBR of Subgrade = 15%

Million Standard Axles (MSA) = 150

From Plate 24 of IRC 37:2012

Pavement Composition

Granular Sub-base (E=180 MPa) = 250 mm

Cementitious Base (E=5000 MPa) = 170 mm

Aggregate Layer (E=450 MPa) = 100 mm

Dense Bituminous Macadam (DBM) = 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm

Total Pavement Thickness = 620 mm

Page 89: DESIGN PROJECT FOR PAVEMENT

85 | P a g e

Pavement Stress – Strain Analysis and Optimization using IITPAVE

In this, we optimize the pavement design by minimizing their thicknesses so that the stress

and strain values at critical points almost reach their maximum allowable values.

Strength Parameter –

1) Cementitious Base –

In case of cementitious granular sub-base having a 7-day UCS of 1.5 to 3 MPa, the laboratory

based E value is given by the following equations:

Ecgsb = 1000 * UCS

Where UCS = 28 day strength of the cementitious granular material

2) Unbound base layer

When both sub-base and the base layers are made up of unbound granular layers, the

composite resilient modulus of the granular sub-base and the base is given as:

MR_granular = 0.2 * h0.45 *

MR subgrade

Where h = thickness of granular sub-base and base, mm

3) Subgrade –

MR subgrade = 17.6 * CBR0.64

= 17.6 * 150.64

= 99.588 MPa

4) Fatigue cracking in cementitious layers –

a. Fatigue life in terms of standard axles –

[

]

Page 90: DESIGN PROJECT FOR PAVEMENT

86 | P a g e

Where,

RF = Reliability factor for cementitious materials for failure against fatigue.

= 1 for Expressways, National Highways and other heavy volume roads.

= 2 for others carrying less than 1500 trucks per day.

N = Fatigue life of the cementitious material. (150 MSA)

E = Elastic modulus of cementitious material. (5000)

€t = tensile strain in the cementitious layer, microstrain.

[

]

b. Fatigue Equation for Cumulative Damage analysis –

Where,

Nfi = Fatigue life in terms of cumulative number of axle load of class i (150 MSA)

σt = tensile stress under cementitious base layer.

MRup = 28 day flexural strength of the cementitious base.

Page 91: DESIGN PROJECT FOR PAVEMENT

87 | P a g e

1. Granular Base and Granular Sub-base

Strain Analysis Using IIT Pave

Input Values –

Layer 1 – BC/SDBC + DBM

Layer 2 – Granular Base + GSB

Layer 3 – Subgrade

Page 92: DESIGN PROJECT FOR PAVEMENT

88 | P a g e

Output Values –

Max. Tensile Strain (epT) = 0.1583 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.1384 X 10-3

(< Allowable Strain =0.3704 X 10-3

)

Page 93: DESIGN PROJECT FOR PAVEMENT

89 | P a g e

After Optimization –

Max. Tensile Strain (epT) = 0.1768 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.1467 X 10-3

(< Allowable Strain =0.3704 X 10-3

)

Page 94: DESIGN PROJECT FOR PAVEMENT

90 | P a g e

Pavement Composition As Per IS 37 Optimized

Granular Sub-base (GSB) = 200 mm 200 mm

Base Course (WMM) = 250 mm 250 mm

Dense Bituminous Macadam (DBM) = 100 mm 85 mm

Bituminous Concrete (BC) = 50 mm 50 mm

Total Pavement Thickness = 600 mm 585 mm

Page 95: DESIGN PROJECT FOR PAVEMENT

91 | P a g e

2. Bituminous Pavements with Cemented Base and Cemented Sub-base with Crack

Relief Interlayer of Aggregate –

Strain Analysis Using IIT Pave

Input Values –

Layer 1 – SDBC + DBM

Layer 2 – Aggregate Layer

Layer 3 – CT Base

Layer 4 – CT Sub-base

Layer 5 – Subgrade

Page 96: DESIGN PROJECT FOR PAVEMENT

92 | P a g e

Output Values –

Max. Tensile Strain (epT) = 0.1261 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.1131 X 10-3

(< Allowable Strain =0.3704 X 10-3

)

Max. Tensile Stress (SigmaT) = 0.1952 (< Allowable Stress = 0.2969)

Page 97: DESIGN PROJECT FOR PAVEMENT

93 | P a g e

After Optimization –

Max. Tensile Strain (epT) = 0.1137 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.1702 X 10-3

(< Allowable Strain =0.3704 X 10-3

)

Max. Tensile Stress (SigmaT) = 0.2917 (< Allowable Stress = 0.2969)

Page 98: DESIGN PROJECT FOR PAVEMENT

94 | P a g e

Pavement Composition As Per IS 37 Optimized

Cementitious Sub-base (E=600 MPa) = 250 mm 250 mm

Cementitious Base Course (E=3000 MPa) = 100 mm 50 mm

Aggregate Layer (E=450 Mpa) = 100 mm 50 mm

Dense Bituminous Macadam (DBM) = 50 mm 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm 50 mm

Total Pavement Thickness = 550 mm 450 mm

Page 99: DESIGN PROJECT FOR PAVEMENT

95 | P a g e

3. Cemented Base and Cemented Sub-base with Sami at the Interface of Cemented

Base and the Bituminous Layer –

Strain Analysis Using IIT Pave

Input Values –

Layer 1 – SDBC + DBM

Layer 2 – CT Base

Layer 3 – CT Sub-base

Layer 4 – Subgrade

Page 100: DESIGN PROJECT FOR PAVEMENT

96 | P a g e

Output Values –

Max. Tensile Stress (SigmaT) = 0.2379 (< Allowable Stress = 0.2969)

Max. Vertical Strain (epZ) = 0.1 X 10-3

(< Allowable Strain =0.3704 X 10-3

)

Page 101: DESIGN PROJECT FOR PAVEMENT

97 | P a g e

After Optimization –

Max. Tensile Stress (SigmaT) = 0.2869 (< Allowable Stress = 0.2969)

Max. Vertical Strain (epZ) = 0.1178 X 10-3

(< Allowable Strain =0.3704 X 10-3

)

Page 102: DESIGN PROJECT FOR PAVEMENT

98 | P a g e

Pavement Composition As Per IS 37 Optimized

Cementitious Sub-base (E=600 MPa) = 250 mm 250 mm

Cementitious Base Course (E=3000 MPa) = 150 m 120 mm

Dense Bituminous Macadam (DBM) = 50 mm 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm 50 mm

Total Pavement Thickness = 500 mm 470 mm

Page 103: DESIGN PROJECT FOR PAVEMENT

99 | P a g e

4. Foamed Bitumen/Bitumen Emulsion Treated Rap/Aggregates Over Cemented

Sub-base –

Strain Analysis Using IIT Pave

Input Values –

Layer 1 – BC/SDBC + DBM

Layer 2 – Treated RAP + CT Sub-base

Layer 3 – Subgrade

Page 104: DESIGN PROJECT FOR PAVEMENT

100 | P a g e

Output Values –

Max. Tensile Strain (epT) = 0.1137 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.64 X 10-4

(< Allowable Strain =0.3704 X 10-3

)

Page 105: DESIGN PROJECT FOR PAVEMENT

101 | P a g e

After Optimization –

Max. Tensile Strain (epT) = 0.1256 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.368 X 10-3

(< Allowable Strain =0.3704 X 10-3

)

Page 106: DESIGN PROJECT FOR PAVEMENT

102 | P a g e

Pavement Composition As Per IS 37 Optimized

Cementitious Sub-base (E=600 MPa) = 250 mm 120 mm

Treated RAP (E=600 MPa) = 140 mm 60 mm

Dense Bituminous Macadam (DBM) = 50 mm 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm 50 mm

Total Pavement Thickness = 490 mm 280 mm

Page 107: DESIGN PROJECT FOR PAVEMENT

103 | P a g e

5. Cemented Base and Granular Sub-base with Crack Relief Layer of Aggregate

Interlayer Above the Cemented Base –

Strain Analysis Using IIT Pave

Input Values –

Layer 1 – SDBC + DBM

Layer 2 – Aggregate Layer

Layer 3 – CT Base

Layer 4 – GSB

Layer 5 – Subgrade

Page 108: DESIGN PROJECT FOR PAVEMENT

104 | P a g e

Output Values –

Max. Tensile Strain (epT) = 0.156 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.8771 X 10-4

(< Allowable Strain =0.3704 X 10-3

)

Max. Tensile Stress (SigmaT) = 0.2383 (< Allowable Stress = 0.2969)

Page 109: DESIGN PROJECT FOR PAVEMENT

105 | P a g e

After Optimization –

Max. Tensile Strain (epT) = 0.1559 X 10-3

(< Allowable Strain =0.1780 X 10-3

)

Max. Vertical Strain (epZ) = 0.1096 X 10-4

(< Allowable Strain =0.3704 X 10-3

)

Max. Tensile Stress (SigmaT) = 0.2969 (< Allowable Stress = 0.2969)

Page 110: DESIGN PROJECT FOR PAVEMENT

106 | P a g e

Pavement Composition As Per IS 37 Optimized

Granular Sub-base (E=180 MPa) = 250 mm 250 mm

Cementitious Base (E=5000 MPa) = 170 mm 130 mm

Aggregate Layer (E=450 MPa) = 100 mm 100 mm

Dense Bituminous Macadam (DBM) = 50 mm 50 mm

Slightly Dense Bituminous Concrete (SDBC) = 50 mm 50 mm

Total Pavement Thickness = 620 mm 580 mm

Page 111: DESIGN PROJECT FOR PAVEMENT

107 | P a g e

CONCLUDING REMARKS:

In design of rigid pavement, different slab thicknesses were tried for fatigue life

consume corresponding to data obtained from axle load spectrum. Then according

to IRC 58:2002 specifications, dowel bars and tie bars were designed. An excel

sheet is also created from where the whole design procedure can be formulated.

In design of flexible pavement, axle load survey data was used to determine the

traffic characteristics and determine vehicle damage factor of each vehicle. Then

corresponding to the traffic data obtained from survey, design was done intending

for a duration of 22 years. But the pavement was finally designed for 20 years

design life due to traffic constraints and codal provisions. An excel sheet is also

created to simplify the design process. Finally the stresses were calculated using

IITPAVE software and compared with allowable stresses to check the long term

performance of pavement.

In HDM4, after giving traffic inputs, three alternatives were defined to determine

the life cycle cost analysis of pavement - 1st alternative was routine maintenance, 2

nd

alternative was overlay of 25mm SDBC and 3rd

alternative was the reconstruction of

pavement. Routine maintenance was scheduled annually and others were responsive

(i.e. conditional). The Project analysis period was of 15 years.

The result predicted motorized AADT value of 20000 by 2029. From the

average roughness graph it was observed that routine maintenance has to be done

every year from 2023 and pavement will have to be reconstruction in 2025 and the

cost of construction would be Rs.42, 00,000 per km. SDBC overlay would be in

2024, 2025 and 2029 with total estimated cost of Rs.84, 00,000 per km (for all the

three years).

In soil stabilization, the base and sub base were treated with different materials to

improve the soil characteristics. The obtained thickness were then optimized using

IIT PAVE to make the pavement economical and reduce the construction time.

Soil stabilization increases the strength of soil by binding the soil particles

together which decreases the required thickness of the pavement.

Page 112: DESIGN PROJECT FOR PAVEMENT

108 | P a g e

REFERENCES:

1. IRC 37:2012 – Guidelines for the design of flexible pavements.

2. IRC 58:2002 - Guidline for the Design of Plain Jointed Rigid pavements Design for

Highways

3. Highway Development and Management Model HDM-4 manual.

4. Highway engineering by “Khanna and Justo”.