Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

8
6/19/13 1 C Creative Thinkers, Cleverly Disguised as Engineers. Design of a 35 Story Building In Los A ngeles Using the LADBS Performance Based Design Methodology LA Tall Building Structural Design Council Conference May 3, 2013 C Creative Thinkers, Cleverly Disguised as Engineers. Contents  Project Summary  Summary of Design Development Options  Computer Modelling  Aspects  Main Results   Advantag es  Material Savings  Summary

description

stood

Transcript of Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

Page 1: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 1/8

6/19/13

1

C

Creative Thinkers, Cleverly Disguised as Engineers.

Design of a 35 Story Building In

Los Angeles Using the LADBS

Performance Based Design

Methodology

LA Tall Building Structural Design Council

Conference

May 3, 2013

C

Creative Thinkers, Cleverly Disguised as Engineers.

Contents

•  Project Summary

•  Summary of Design

Development Options

•  Computer Modelling Aspects

•  Main Results

•   Advantages

•  Material Savings

• 

Summary

Page 2: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 2/8

6/19/13

2

C

Creative Thinkers, Cleverly Disguised as Engineers.

Project Summary

•  888 Olive Street Los Angeles (9th & Olive)

•  35 Story Tower – 358 ft.

above grade

•  4 story podium over 2 level

basement

•  700,000 sq. ft. ofsuspended structure.

•  Reinforced Concrete

C

Creative Thinkers, Cleverly Disguised as Engineers.

Stage 1

Conventional Design• Dual System• Concrete Shearwalls

• Special Moment Resisting Frames• Linear Dynamic Analysis

Page 3: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 3/8

6/19/13

3

C

Creative Thinkers, Cleverly Disguised as Engineers.

Stage 2

Performance Based• First Trial• Concrete Shearwalls only

• Capacity Design – Cross Sectional Analysis

• Too many walls

C

Creative Thinkers, Cleverly Disguised as Engineers.

Stage 3

Performance Based• Optimized Structural Performance• Non-Linear Analysis PERFORM 3D

• Iterations during Peer Review• Modified coupling beams combined

with shearwalls for best combination

Page 4: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 4/8

6/19/13

4

C

Creative Thinkers, Cleverly Disguised as Engineers.

Modelling Aspects•  Fibers – Walls

•  Shear springs – Headers•  Beams – column/slab outriggers

•  Shell (in-plane) – Slabs (podium)

•  Upper and Lower bound stiffness

T1 = 5.8s

C

Creative Thinkers, Cleverly Disguised as Engineers.

Modelling Aspects•  Input Earthquake Ground Motions

 –  MCE level

 –  7 Pairs (spectral matching)

 –  PEER GM Database

 –  NEHRP Class C

Page 5: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 5/8

6/19/13

5

C

Creative Thinkers, Cleverly Disguised as Engineers.

Main Results•  Shear forces Elevator Core

C

Creative Thinkers, Cleverly Disguised as Engineers.

Main Results•  Maximum Drift

!"#$% '(")*" +(,* -. /012

!"

#

"

$

%

&

'#

'"

'$

'%

'&

"#

""

"$

"%

"&

(#

("

($

!#)#$ !#)#" #)## #)#" #)#$

!"#$%

        3      *      4      *        5

*+'

*+"

*+(

*+$

*+,

*+%

*+-

.*/0

.*/01234*5

.*/0!234*5

!"#$% '(")*" +(,* -. /012

!"

#

"

$

%

&

'#

'"

'$

'%

'&

"#

""

"$

"%

"&

(#

("

($

!#)#( !#)#" !#)#' #)## #)#' #)#" #)#(

!"#$%

        3      *      4      *        5

*+'

*+"

*+(

*+$

*+,

*+%

*+-

.*/0

.*/01234*5

.*/0!234*5

Page 6: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 6/8

6/19/13

6

C

Creative Thinkers, Cleverly Disguised as Engineers.

Main Results•  Coupling Beams dissipate

most energy

C

Creative Thinkers, Cleverly Disguised as Engineers.

Main Results•  Core walls governed by

maximum shear stress

Page 7: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 7/8

6/19/13

7

C

Creative Thinkers, Cleverly Disguised as Engineers.

 Advantages•  PBD allow us to Optimize the

performance of elements of theLateral Force Resisting System

•  NLDA better captures changinginelastic damage state of thestructure

•  Directly addresses the level ofredundancy & safety of thestructure

•  Increased Useable space due toelimination of frame beams andcolumns of Dual System

•  More flexibility for parkingcirculation

•  More flexibility for distribution ofMech/Elec systems

• 

Reduction of Materials fromConventional Dual System

C

Creative Thinkers, Cleverly Disguised as Engineers.

Material Savings•  Reduction in Materials

from Stage 1 to Stage 3

 –  Concrete 6,000 Cu. Yds

 –  Rebar 3.2 M lbs

 –  Formwork 27,000 s.f.

•  15% reduction in total

structural materials

Stage 1 – Dual System

Stage 3 - PBD

Page 8: Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

7/17/2019 Design of a 35 Story Building in Los Angeles Using the LADBS Performance Based Design Methodology

http://slidepdf.com/reader/full/design-of-a-35-story-building-in-los-angeles-using-the-ladbs-performance-based 8/8

6/19/13

8

C

Creative Thinkers, Cleverly Disguised as Engineers.

Summary

•  Performance Based Design(PBD) better captures thecomplex sway effects of tallbuildings

•  PBD directly addresses the levelof redundancy & safety of thebuilding structure

•  PBD is a good alternative forowners to increase useablespace and reduce constructionmaterials.

•  PBD takes advantage of

Leading Edge Design tools andmethods, and latest knowledgein tall building design.