Design Criteria 1

17
60-F5222SJ010101 DETAILED DESIGN STAGE PROJECT NAME PHASE II 2x300MW PUTTALAM COAL POWER PROJECT DETAIL DESIGN DESCRIPTION AND VOLUME LIST NORTHWEST ELECTRIC POWER DESIGN INSTITUTE 12/2011 XIAN

description

design

Transcript of Design Criteria 1

  • 60-F5222SJ010101 DETAILED DESIGN STAGE

    PROJECT NAME PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    DETAIL DESIGN DESCRIPTION AND VOLUME LIST

    NORTHWEST ELECTRIC POWER DESIGN INSTITUTE

    12/2011 XIAN

  • PROJECT

    PHASE II 2X300MW PUTTALAM COAL POWER PROJECT OWNER

    CEYLON ELECTRICITY BOARD

    POYRY ENERGY LTD

    EPC CONTRACTOR

    CHINA NATIONAL MACHINERY & EQUIPMENT

    IMPORT & EXPORT CORPORATION

    SUBCONTRACTOR

    NORTHWEST ELECTRIC POWER

    DESIGN INSTITUTE

    Document No. : F5222S-J0101-01 Rev : 1

    Document Title :

    DETAIL DESIGN DESCRIPTION AND VOLUME LIST

    DOCUMENT STATUS AP

    Date Revision Designed by Checked by Reviewed by Approved by

    12/2011 0

    04/2012 1

  • TABLE OF CONTENTS

    1.0 GENERAL .......................................................................................... 1

    2.0 DESIGN BASIS .................................................................................. 1

    3.0 BASIC TECHNICAL DATA ............................................................. 1

    4.0 DESIGN CRITERION ....................................................................... 5

    5.0 NWEPDI NUMBERING SYSTEM ................................................... 9

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    1

    1.0 General

    The Puttalam Coal Power Plant is located near the village of Panaiyadi on the

    Kalpitiya Peninsula, approximately 12 km west of the city of Puttalam. The Project is

    a coal fired Power Station in stages with an ultimate planned capacity of 900 MW. The

    scope of the phase II covers the installation of the first condensing turbo generator and

    coal fired Units with a capacity of 2x300 MW, along with the associated power

    transmission system, site infrastructure and auxiliary systems. The project also

    includes coal supply facilities as well as coal storage and ash disposal.

    2.0 Design basis

    2.1 EPC contract between CMEC and CEB.

    2.2 Basic design documentation confirmed by CEB

    2.3 Technical agreement of main equipment and auxiliary equipment

    3.0 Basic technical data

    3.1 Fuelimported bituminous coal Coal quality and ash content analysis

    NAME SYMBOL UNIT DESIGN

    COAL

    CHECK

    COAL 1

    CHECK

    COAL 2

    High calorific value as

    received basis Qv.ar MJ/kg 26.4 25.3 24.7

    Industrial analysis

    Total moisture content as

    received basis Mt % 12.0 16.0 19.0

    Moisture content as air

    dried basis Mad % 6.0

    Ash content as received

    basis Aar % 11.0 15.0 10.1

    Volatile matter content as

    received basis Var % 27.0 25.0 24.9

    Elementary analysis

    Carbon content as

    received basis Car % 65.0 60.0 60.5

    Hydrogen content as

    received basis Har % 3.8 3.6 3.4

    Oxygen content as

    received basis Oar % 6.2 3.0 5.1

    Nitrogen content as

    received basis Nar % 1.5 1.7 1.4

    Sulphur content as

    received basis Star % 0.5 0.7 0.5

    Grindability factor

    HGI 50 42 50

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    2

    NAME SYMBOL UNIT DESIGN

    COAL

    CHECK

    COAL 1

    CHECK

    COAL 2

    Ash deformation

    temperature DT

    Ash softening temperature ST 1250 1170 1250 Ash melting temperature FT 1325 1300 1325

    SiO2 % 61.0 58.0 61.0

    AI2O3 % 25.0 21.6 25.0

    Fe2O3 % 4.0 8.0 4.0

    CaO % 3.5 5.0 3.5

    K2O % 0.6 0.8 0.6

    TiO2 % 1.3 1.3 1.3

    Na2O % 0.3 1.2 0.3

    MgO % 0.7 0.5 0.7

    SO3 % 2.7 2.7 2.7

    MnO2 %

    Specific resistance of ash 1012

    3.2 Ignition and combustion supporting oil

    Type of oilLight diesel oil Kinematic viscosity(37.8) : 1.5~5.0 centistokes

    Ash content: 0.02%

    Sulphur content: 1.0%

    Flash point: >60

    Calorific value: 10500 kcal/kg

    3.3 Cooling water quality

    Recycled water source: sea water

    Open cycle cooling water: Recycled water

    Closed cycle cooling water: Demineralized water

    3.4 Ambient conditions

    Average atmospheric temperature: 27.5 Highest atmospheric temperature: 34 Lowest atmospheric temperature: 21 Average relative humidity: 75%

    Design atmospheric pressure: 100.57kpa

    Average annual rainfall: 1200mm

    Highest wind speed: 47.2m/s

    Average wind speed:4.17m/s

    Seismic intensity: Grade 7

    Design seismic intensity: 7(MSK-64)

    Average temperature of sea water: 28

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    3

    Highest temperature of sea water: 31 Lowest temperature of sea water: 11.2 Design temperature of sea water: 31 3.5 Main equipment technical data

    3.5.1 Boiler

    Boiler supplied by HBC: subcritical parameter, natural circulation, all steel structural, balance

    draft, dry slagging, hypaethral placement above operating floor, imported bituminous coal

    fuel.

    Boiler model: HG-1025/17.3-YM

    Thermal parameter 300MW

    Superheated

    steam

    BMCR t/h 1025

    Steam pressure (BMCR) Mpa(g) 17.3

    Steam temperature (BMCR) 541

    Reheated

    steam

    Steam pressure (BMCR) Mpa (g) 3.99/3.79

    Steam temperature (BMCR) 337.8/541

    Feed water temp.(BMCR 282.1

    3.5.2 Turbine

    Turbine supplied by HTC: subcritical parameter, two-cylinder and two drainages, medium

    reheat, condensing turbine.

    Turbine model: N300-16.7/538/538

    Turbine main thermal parameter as follows:

    CP: constant pressure

    CP: constant pressure

    HPB: high pressure heater broken

    MS: main steam

    RS: reheated steam

    Temp.: temperature

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    4

    THA TRL VWO TMCR 75% 50% 40% 30%

    HPB CP SP CP SP CP SP CP SP

    Power output MW 300 300 331.537 315.965 225 225 150 150 120 120 90 90 300

    Heat consumption

    kJ/kW.h 7898.1 8002.7 7879.6 7889.8 8050.6 7953.6 8442.1 8401.8 8753.7 8723.5 9154.3 9125.8 8172.2

    MS pressure MPa(a) 16.7 16.7 13.49 16.7 9.8 16.7 7.85 16.7 5.85 16.7

    RS pressure MPa(a) 3.349 3.443 3.746 3.459 2.488 2.435 1.698 1.678 1.4 1.384 1.09 1.08 3.48

    MS temperature 538 531.7 531.6 523.5 523.3 514 513.8 538

    RS temperature 538 511.1 510.7 492.8 492.5 473.7 473.4 538

    RS flow rate t/h 759.76 780.75 851.21 784.95 561.92 553.35 387.68 386.11 322.4 321.41 253.49 252.25 779.34

    Back pressure kPa(a) 7.0 9.7 7.0 6.55 6.55 7.0

    Exhaust flow rate t/h 583.17 598.02 645.54 600.49 444.67 437.76 317.36 314.38 268.24 265.34 214.84 211.56 618.74

    Supply water rate % 0 3.8 0 0 0 0 0 0 0 0 0 0 0

    Final feed water temp. 39.4 45.6 39.4 39.4 39.4 39.4 39.4 39.4 39.4 39.4 38.2 38.2 39.4

    Generator power MW 300 300 331.537 315.965 225 225 150 150 120 120 90 90 300

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    5

    3.5.3 Generator

    Generator supplied by HEC.

    Generator main technical parameter as follows:

    Name Unit Design value Test value Insure value

    Generator model QFSN-300-2

    Rated capacity SN MVA 353 353 353

    Rated power PN MW 300 300 300

    MAX output power Pmax MW 332 332 332

    Rated power factor cosN 0.85 0.85

    Stator rated voltage UN kV 20 20

    Stator rated current IN A 10190 10190

    Rated frequency fN Hz 50 50

    Rated speed nN r/min 3000 3000

    Rated voltage for excitation UfN (90) V 365

    Rated current for excitation IfN A 2642 2500

    Stator coil connection mode YY/Y

    Full load efficiency % 99.019 99.02 98.9

    4.0 Design criterion

    This project is an expansion project (phase II). Phase II covers two units with a capacity of 2x300MW. The

    total capacity of phase I and phase II will be 3x300MW.

    4.1 Brief introduction of power plant main building

    4.1.1

    Phase II is on the right extension side of phase I

    a) Longitudinal arrangement of steam turbine generator. Turbine towards fixed side.

    b) Boiler house is all steel structural, hypaethral placement above operating floor (12.6m)

    c) Turbine house is concrete structural

    d) Central control building between unit2 and unit 3

    4.1.2 Turbine house platform

    a) Feed water pump, OCCW pump, main oil tank, main oil cooler, CCCW heat exchange

    device, vacuum pumps etc. are on the ground floor (0m).

    b) Ground floor (0m), middle floor (6.3m), operating floor (12.6m) in turbine house

    c) Steam turbine generator on the operating floor.

    4.1.3 Deaerator building (RC frame)

    a) CCCW pump, condensate polishing unit on 0m floor of deaerator building

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    6

    b) No.3 HP heater, No.6 LP heater, pipe drain flash tank etc. on 6.3m floor of deaerator

    building.

    c) No.1 no.2 HP heater, No.5 LP heater on 12.6m floor of deaerator building.

    d) Deaerator, CCCW tank, continuous blowdown flash tank etc. on 22.5m floor of deaerator

    building.

    4.1.4 Bunker bay

    a) Coal mill on 0m floor

    b) Coal feeder on 12.6m floor

    c) Coal conveyor belt on 37.8m floor

    4.1.5 Boiler house

    a) Hypaethral placement above operating floor (12.6m)

    b) Concrete structure on operating floor (12.6m)

    c) Primary air fan, seal air fan, slag conveyor, IBD tank etc. on 0m floor of boiler house.

    d) Forced draft fan, precipitator, induced draft fan, chimney on end part of boiler house.

    4.2 Combustion system, pulverizing system and auxiliary equipments

    4.2.1 Coal consumption

    Coal consumption is calculated on the basis of BMCR condition, design coal, 20 hours/day,

    6000 hours/year.

    Capacity

    Name

    One unit

    Per hour coal consumptiont/h 110.4

    Per day coal consumption t/d 2208

    Per year coal consumptionkt/a 662.4

    4.2.2 Pulverizing system and auxiliary equipments

    a) Five coal mill on site per unit, one of them standby.

    b) coal feeder seal air fan etc. auxiliary equipment assorted.

    Coal mill Coal feeder

    Manufacturer

    Model HP863 CS67194.2024HP

    Quantity/per boiler 5 5

    Power outputT/h Basic output47.1

    Output beyond wear life35.5

    660

    Motor speedr.p.m 982

    Motor power kW 400 3

    Motor voltage V 6000 380

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    7

    4.2.3 air-flue gas system and auxiliary equipments

    a) Balance draft

    b) Junkers air preheater

    c) Primary air system, secondary air system, air-flue gas system

    4.2.3.1 Primary air system

    a) Supply hot air and pressured cold air for coal mill.

    b) Two 50% capacity primary air fan per unit

    4.2.3.2 Secondary air system

    a) Supply air for combustion

    b) Two 50% capacity forced draft fan per unit

    4.2.3.3 Air-flue gas system

    a) Flue gas firstly flow out of boiler end heating surface, then air preheater, precipitator,

    FGD, finally flow out of chimney into air.

    4.2.3.4 Auxiliary equipments

    a) Primary air fan: 2/per boiler

    b) Forced draft fan: 2/per boiler

    c) Induced draft fan: 2/per boiler

    d) Air preheater: 2/per boiler

    e) Precipitator: 2/per boiler

    4.2.4 Ignition oil system

    a) Two stage ignition system

    b) Light diesel oil

    c) Mechanical atomizing burner

    4.3 Thermal system and auxiliary equipments

    4.3.1 Main reheat & bypass steam system

    Please see drawing F5222S-J0801-01 for system detail

    4.3.2 Extraction steam system

    The turbine has eight (8) pressure stages of non-regulating extraction steam. The No.1,2&3

    extraction steam stages supply steam to three (3) HP heaters respectively. The No.4 extraction

    steam stage supply steam to auxiliary steam header and deaerator. The No.5,6,7&8 extraction

    steam stages supply steam to four (4) LP heaters respectively.

    4.3.3 Auxiliary steam system

    The Auxiliary Steam System (AS) is designed to provide steam for the following services

    under various operating load condition of the thermal power plant.

    a) Steam for deaerator preheating, load rejection and cutting off

    b) Back-UP steam for turbine seal system

    c) Steam for air preheater soot blowers

    d) Steam for coal mill fire fighting

    e) Steam for boiler heating

    f) Steam for boiler system (standby connection)

    4.3.4 Feed water system

    The function of the boiler feed-water system is to deliver feed-water from the outlet of

    deaerator feed-water tank to the inlet of boiler economizer inlet header. In the process of

    handling the feed-water is heated by the extraction steam from the steam turbine to improve

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    8

    the cycle efficiency.

    The system also supplies the feed-water to the boiler super heater, attemperator to moderate

    the superheated steam temperature. Besides, feed-water tapped from the feed-water pump

    intermediate stage is sent to the two sides of attemperator before the steam repeaters to protect

    the reheater from overheat.

    The feed-water system also supplies feed-water to turbine HP. By-pass system, acting as

    attemperator water to reduce the main steam temperature.

    4.3.5 Condensate water system

    The main function of the system is that pumping the condensate from hot well to the deaerator,

    controlling, heating, deaerating of the condensate and taking other necessary actions in

    delivering in order to ensure the safe and operation, increase the efficiency of heat circulation.

    Two condensate pumps (one operation and one standby) each with 100% capacity, 3 LP

    heaters and one gland seal condenser are equipped in the system. There are several of

    desuperheater spray and miscellaneous water upstream of gland seal condenser. The control

    valve controlling the water level of deaerator, recirculating piping of min. condensate flow are

    equipped downstream of the gland steam condenser. In addition there is a control valve

    controlling the make-up water entering into the hot well, one condensate storage tank and one

    condensate transfer pump completed in the system to guarantee the operation water level in

    the condenser.

    4.3.6 HP heater drain & vent system

    Please see drawing F5222S-J1301-01 for detail

    4.3.7 LP heater drain & vent system

    Please see drawing F5222S-J1305-01 for detail

    4.3.8 Cooling water system

    Please see drawing F5222S-J1801-01, J1901-01, and J2001-01 for detail.

    4.3.9 Condenser vacuum system

    Please see drawing F5222S-J1501-01 for detail.

    4.3.10 Turbine lube oil conditioning & storage system

    Please see drawing F5222S-J2101-01 for detail.

    4.3.11 Boiler drain & blowdown system

    Please see drawing F5222S-J0601-01 for detail

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    9

    5.0 NWEPDI numbering system

    5.1 General regulation:

    60 - F 522 2 s X XX XX - XX

    SUB-BOOK (DRAWING) CODE

    BOOK CODE

    VOLUME CODE DEPARTMENT CODE DESIGN STAGE PROJECT STAGE PROJECT CODE

    PROJECT SORT REPRESENT NWEPDI

    For this project:

    Project Sort is F which means power generation

    Project Code is 522

    Project Stage is 2

    Design Stage: S represents engineering design

    Department Code: J represents Mechanical Department

    D represents Electrical Department

    H represents Chemical Department

    K represents I&C Department

    T represents Civil & Architecture Department

    S represents Water Supply & Hydraulic Structure Department

    N represents HVAC Department

    Z represents General layout Department

    C represents Ash Handling Department

    M represents Coal Handling Department

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    10

    5.2 Volume list

    No. Volume no. Name of volume

    Mechanical part

    1 F5222S-J0101 DETAIL DESIGN DESCRIPTION AND VOLUME LIST

    2 F5222S-J0102 EQUIPMENT LIST

    3 F5222S-J0103 MATERIAL LIST

    4 F5222S-J0106 KKS CODE DESCRIPTION & EQUIPMENT LIST FOR THERMO-MECHANICAL PART

    5 F5222S-J0201 GENERAL ARRANGEMENT OF MAIN HOUSE

    6 F5222S-J0301 ERECTION DRAWING OF AUX.EQUIPMENT IN TURBINE HOUSE

    7 F5222S-J0302 ERECTION DRAWING OF AUX.EQUIPMENT IN BOILER HOUSE

    8 F5222S-J0303 ERECTION DRAWING OF PLATFORM & LADDER IN TURBINE HOUSE

    9 F5222S-J0304 ERECTION DRAWING OF PLATFORM AND LADDER FOR IN BOILER HOUSE

    10 F5222S-J0305 ERECTION DRAWING OF MAINTENANCE & HOISTING FACILITY IN TURBINE HOUSE

    11 F5222S-J0306 ERECTION DRAWING OF MAINTENANCE & HOISTING FACILITY IN BOILER HOUSE

    12 F5222S-J0401 P&ID COAL PULVERIZING SYSTEM

    13 F5222S-J0404 ERECTION DRAWING OF PULVERIZED COAL PIPE

    14 F5222S-J0501 P&ID AIR AND FLUE GAS SYSTEM

    15 F5222S-J0502 ERECTION DRAWING OF COLD PRIMARY AIR DUCT

    16 F5222S-J0503 ERECTION DRAWING OF HOT PRIMARY AIR DUCT

    17 F5222S-J0504 ERECTION DRAWING OF SECONDARY COLD AIR DUCT

    18 F5222S-J0505 ERCTION DRAWING OF BOILER SECOND HOT AIR DUCT

    19 F5222S-J0506 ERECTION DRAWING OF SEAL AIR DUCT OF COAL MILL AND COAL FEEDER

    20 F5222S-J0507 ERECTION DRAWING OF FLAME DETECTOR COOLING AIR DUCT

    21 F5222S-J0508 ERECTION DRAWING OF FLUE DUCT

    22 F5222S-J0601 P&ID BOILER DRAIN AND BLOWDOWN SYSTEM

    23 F5222S-J0602 ERECTION DRAWING OF BOILER DRAIN AND VENT PIPE

    24 F5222S-J0603 ERECTION DRAWING OF BOILER EMERGENCY DRAIN WATER PIPE

    25 F5222S-J0604 ERECTION DRAWING OF BOILER BLOWDOWN PIPE

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    11

    26 F5222S-J0607 ERECTION DRAWING OF PIPE RELATE TO CONTINUOUS BLOWDOWN FLASH TANK

    27 F5222S-J0608 ERECTION DRAWING OF INTERMITTENT BLOWDOWN TANK PIPE

    28 F5222S-J0801 P&ID MAIN REHEAT&BYPASS STEAM SYSTEM

    29 F5222S-J0802 ERECTION DRAWING OF MAIN STEAM PIPE

    30 F5222S-J0803 ERECTION DRAWING OF HOT REHEAT STEAM PIPE

    31 F5222S-J0804 ERECTION DRAWING OF COLD REHEAT STEAM PIPE

    32 F5222S-J0805 ERECTION DRAWING OFHP BYPASS STEAM PIPE

    33 F5222S-J0806 ERECTION DRAWING OF LP BYPASS STEAM PIPE

    34 F5222S-J0808 ERECTION DRAWING OF STEAM SUPPLY PIPE FROM MAIN STEAM & COLD REHEAT PIPE TO GLAND SEAL

    35 F5222S-J0809 ERECTION DRAWING OF HP CASING COOLING STEAM PIPE

    36 F5222S-J0901 P&ID EXTRACTION STEAM SYSTEM

    37 F5222S-J0902 ERECTION DRAWING OF NO.1 EXTRACTION STEAM PIPE

    38 F5222S-J0903 ERECTION DRAWING OF NO.2 EXTRACTION STEAM PIPE

    39 F5222S-J0904 ERECTION DRAWING OF NO.3 EXTRACTION STEAM PIPE

    40 F5222S-J0905 ERECTION DRAWING OF NO.4 EXTRACTION STEAM PIPE

    41 F5222S-J0906 ERECTION DRAWING OF NO.5 EXTRACTION STEAM PIPE

    42 F5222S-J0907 ERECTION DRAWING OF NO.6 EXTRACTION STEAM PIPE

    43 F5222S-J1001 P&ID AUXILIARY STEAM SYSTEM

    44 F5222S-J1002 ERECTION DRAWING OF AUXILIARY STEAM PIPE

    45 F5222S-J1003 ERECTION DRAWING OF THE AUXILIARY STEAM INNER STEAM SOURCE PIPE

    46 F5222S-J1004 ERECTION DRAWING OF AUX. STEAM IN TURBINE HOUSE

    47 F5222S-J1005 ERECTION DRAWING OF AUXILIARY STEAM PIPE FOR BOILER HOUSE

    48 F5222S-J1008 ERECTION DRAWING OF THE AUXILARY DRAINS AND VENT PIPE

    49 F5222S-J1101 P&ID FEED WATER SYSTEM

    50 F5222S-J1102 ERECTION DRAWING OF LP FEED WATER PIPE

    51 F5222S-J1103 ERECTION DRAWING OF IP FEED WATER PIPE

    52 F5222S-J1104 ERECTION DRAWING OF HP FEED WATER PIPE

    53 F5222S-J1105 ERECTION DRAWING OF FEED WATER RECYCLE PIPE

    54 F5222S-J1106 ERECTION DRAWING OF FEED WATER ATTEMPERATING WATER PIPE

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    12

    55 F5222S-J1107 ERECTION DRAWING OF FEED WATER MISCELLANEOUS PIPE

    56 F5222S-J1201 P&ID CONDENSATE SYSTEM

    57 F5222S-J1202 ERECTION DRAWINGS OF CONDENSATE PIPE

    58 F5222S-J1205 ERECTION DRAWING OF PIPE RELATED TO CONDENSATE STORAGE TANK

    59 F5222S-J1206 ERECTION DRAWINGS OF DEAERATOR FILL & BOILER FILL PIPE

    60 F5222S-J1207 ERECTION DRAWING OF CONDENSATE DESUPERHEATING PIPE

    61 F5222S-J1208 ERECTION DRAWING OF CONDENSATE DISCHARGE WATER PIPE

    62 F5222S-J1209 ERECTION DRAWINGS OF CONDENSATE MISCELLANEOUS WATER PIPE

    63 F5222S-J1301 P&ID HP HEATER DRAINS & VENTS SYSTEM

    64 F5222S-J1302 ERECTION DRAWING OF HP HEATER DRAIN PIPE

    65 F5222S-J1303 ERECTION DRAWING OF DEAERATOR DRAIN & OVERFLOW PIPE

    66 F5222S-J1304 ERECTION DRAWING OF HP HEATER&DEAERATOR VENT PIPE

    67 F5222S-J1305 P&ID LP HEATER DRAINS & VENTS SYSTEM

    68 F5222S-J1306 ERECTION DRAWING OF LP HEATER DRAIN PIPE

    69 F5222S-J1307 ERECTION DRAWING OF LP HEATER VENT PIPE

    70 F5222S-J1308 ERECTION DRAWINGS OF HIGH & NON-PRESSURE DISCHARGE WATER PIPE

    71 F5222S-J1401 P&ID OF TURBINE GLAND STEAM SYSTEM

    72 F5222S-J1402 ERECTION DRAWINGS OF TURBINE MAIN BODY DRAIN PIPE

    73 F5222S-J1403 ERECTION DRAWINGS OF TURBINE SEALS GLAND-SUPPLY STEAM PIPE

    74 F5222S-J1404 ERECTION DRAWINGS OF TURBINE SEALS AND VALVE LEAK-OFF PIPE

    75 F5222S-J1405 ERECTION DRAWING OF THE GLAND STEAM CONDENSER DRAIN AND VENT PIPE

    76 F5222S-J1406 ERECTION DRAWING OF PIPE RELATED TO TURBINE START UP

    77 F5222S-J1501 P&ID AIR EVACUATION SYSTEM

    78 F5222S-J1502 ERECTION DRAWING OF CONDENSER VACUUM PIPES

    79 F5222S-J1503 ERECTION DRAWING OF CONDENSER WATER BOX VACUUM PIPES

    80 F5222S-J1505 ERECTION DRAWING OF CONDENSER DRAIN FLASH TANK RELATED PIPE

    81 F5222S-J1801 P&ID CIRCULATING WATER SYSTEM

    82 F5222S-J1802 ERECTION DRAWING OF CIRCULATING WATER PIPE

    83 F5222S-J1803 ERECTION DRAWING OF CONDENSER BALL CLEANING PIPE

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    13

    84 F5222S-J1901 P&ID OCCW SYSTEM

    85 F5222S-J1903 ERECTION DRAWING OF OCCW PIPE IN TURBINE HOUSE

    86 F5222S-J2001 P&ID CLOSED COOLING WATER SYSTEM

    87 F5222S-J2002 ERECTION DRAWING OF CLOSED CIRCULATING COOLING WATER PIPE IN BOILER HOUSE

    88 F5222S-J2003 ERECTION DRAWING OF CCCW PIPE IN TURBINE HOUSE

    89 F5222S-J2101 ERECTION DRAWING OF P&ID TURBINE LUBE OIL CONDITIONING &STORAGE SYSTEM

    90 F5222S-J2102 ERECTION DRAWING OF LUBE OIL CONDITIONING PIPE

    91 F5222S-J2103 ERECTION DRAWING OFLUBE OIL STORAGE TANK PIPE

    92 F5222S-J2104 ERECTION DRAWING OF LUBE OIL TANK EXHAUST PIPE

    93 F5222S-J2105 ERECTION DRAWING OF LUBE OIL TANK EMERGENCY OIL DISCHARGE PIPE

    94 F5222S-J2201 ERECTION DRAWING OF TURBINE LUBE OIL PIPE

    95 F5222S-J2202 ERECTION DRAWING OF GENERATOR LUBE & SEAL OIL PIPE

    96 F5222S-J2203 ERECTION DRAWING OF GENERATOR H &CO2 PIPES

    97 F5222S-J2204 ERECTION DRAWING OF GENERATOR STATOR COOLING WATER PIPE

    98 F5222S-J2205 ERECTION DRAWING OF GENERATOR COOLING AIR DUCT

    99 F5222S-J2301 P&ID COMPRESSED AIR SYSTEM

    100 F5222S-J2302 ERECTION DRAWING OF INSTRUMENT COMPRESSED AIR PIPE

    101 F5222S-J2303 ERECTION DRAWING OF SERVICE COMPRESSED AIR PIPE

    102 F5222S-J2304 ERECTION DRAWING OF AIR COMPRESSOR ROOM EQUIPMENT AND PIPE

    103 F5222S-J2305 ERECTION DRAWING OF COMPRESSED AIR PIPES IN PLANT AERA

    104 F5222S-J2401 ERECTION DRAWING OF AIR PREHEATER WASHING WATER PIPES

    105 F5222S-J2501 FLOW DIAGRAM OF NITROGEN SYSTEM

    106 F5222S-J2607 ERECTION DRAWING OF FUEL OIL AND COMPRESSED AIR PIPES IN PLANT AERA

    107 F5222S-J2608 BOILER IGNTTING OIL SYSTEM FLOW DIAGRAM

    108 F5222S-J2609 ERECTION DRAWING OF BOILER IGNITING OIL PIPE

    109 F5222S-J2612 LAYOUT OF EQUIPMENT AND PIPE MGO FOR JETTY

    110 F5222S-J2801 ERECTION DESCRIPTION OF INSULATION AND MATERIAL LIST

    111 F5222S-J2802 ERECTION DESCRIPTION AND STRUCTURE DRAWING OF INSULATION

    112 F5222S-J2901 G.A DRAWING OF DIESEL GENERATOR ROOM

  • PHASE II 2x300MW PUTTALAM COAL POWER PROJECT

    14

    113 F5222S-J3201 WORKING DRAWING OF CASE