Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge)...

16
Design-Build Project Management October 12, 2016 DESIGN-BUILD PROJECT MANAGEMENT Duane Milligan, P.E. Short Course 2016 October 12, 2016

Transcript of Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge)...

Page 1: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

DESIGN-BUILD PROJECT MANAGEMENT

Duane Milligan, P.E.

Short Course 2016

October 12, 2016

Page 2: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Table of Contents

5

6-8

9-12

13-15

3-4Introduction

Key Differences

Team Structure

Example: Horseshoe

Lessons Learned

1

2

3

4

5

2

Page 3: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Introduction

TxDOT Design-Build History

– Texas Turnpike Authority (TTA)

• 1991 Legislation for Exclusive Development Agreements

– Was not used

– 1997 TTA transferred to TxDOT

• Legislative authority came with it

– 2003 HB 3588 renamed to Comprehensive Development Agreements (CDA’s)

• an agreement with a private entity that, at a minimum, provides for the

design and construction of a transportation project and may also provide for

the financing, acquisition, maintenance or operation

• CDA’s are at a minimum Design-Build or possibly more

3

Page 4: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Introduction

• Design-Build is simply a project delivery method

• DB has been intertwined with concessions and toll roads because of the

history

– 2011 SB 1420 authorizes TxDOT to use pure Design-Build

• Dallas Horseshoe Project first under new legislation

– Example for discussion

4

Page 5: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Key Differences

Three main differences between DB and DBB

– Procurement Process

• Not low bid, includes Engineering

– Design

• Reviews for contract compliance

– Risk

• More risk allocated to DB Contractor

Otherwise, not drastically different from traditional projects

– Working on Spec. Book

5

Page 6: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Team Structure

Can change with project phases

– Procurement

• Project Manager

– Division Support

– District Support

– Delivery

• Design

• Construction

6

Page 7: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Team Structure

Staffing

– Small but engaged TxDOT staff

• Well rounded individuals (construction and design)

– Utilize in multiple roles

– Consultant support

• Design Review

• Inspection & Testing

• Schedule Review

– Payment based on schedule

7

Page 8: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Team Structure

TxDOT Roles

– Design Review

• Concurrence/Approvals

– Compliance with Contract

»Not preferential

– Approval of Lane Closures

– Public Information

• Coordination with DB Contractor PI

– Construction

• OV Testing and Inspection

8

Page 9: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Example: Horseshoe

Dallas Horseshoe Project

– Original PS&E scope for consultant

– Design-Build Legislation

• Decision to use DB

– 30% Level Design due to Levees

– Excess contract value used for review

– OVT&I contract for construction tasks

• OV Testing & Inspection

– Supplemented TxDOT forces

– 10% testing level and similar on inspection

– QA firm responsible for Guide Schedule

• Statistical Analysis

• Schedule

• Auditing

• Document Control

9

Page 10: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Example: Horseshoe

10

Independent Quality Firm (IQF) is hired by DB Contractor and reports to both TxDOT and DB Contractor

– IQF develops a Construction Quality Management Plan (CQMP) that is reviewed and approved by TxDOT and

FHWA.

– CQMP spells out testing, inspection, hold points, non conformance procedures, etc.

Owner Verification is oversight on the IQF

– OVT authors a quarterly report submitted to FHWA for review to show statistical analysis and consistency in

IQF and OVT testing results

Independent Assurance verifies certifications and serves as referee during a dispute with IQF and OVT

Quality Control

DB Contractor

Quality Assurance Plan (QAP) TxDOT

Acceptance Program

Independent Assurance Program CSTM&P

Independent Quality Firm DB Contractor

Owner Verification TxDOT

CSTM&P – Construction Division, Materials & Pavements Section

Page 11: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

GEC served as extension of staff/

assisted as needed

Lead Roadway Engineer

GEC served as extension of staff/

assisted as needed

Lead Bridge Engineer

District Traffic Ops served as extension of staff/

assisted as needed

Lead Traffic Engineer

Materials Manager

OVT&I Consultant

IA- District Lab/CSTM&P

Construction Oversight Manager/Chief Inspector

Deputy Project Manager

Project Manager

Example: Horseshoe

11

GEC served as extension of staff during Design phase

OVT&I was a separate consultant contract

IA is the District Lab/CSTM&P

Page 12: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Example: Horseshoe

PM leads coordination with various groups:

– District ROW

– District Utility Section

• Reviewed all utility agreements and submittals

– District Traffic Ops

• Reviewed pavement marking & signing plans, ITS plans, signal plans, illumination plans, overhead signing plans

– District DBE Coordinator

• Reviewed all DBE commitments, CUFs, monthly progress reports, and outreach activities

– District Advanced Planning

• Reviewed revisions to the schematic, environmental documents

– Public Information Office

• Reviews news releases and public involvement activities

– Area Office

• Coordinates adjacent project activities

– Construction Division and Bridge Division

• Specialty inspection items (Calatrava bridge)

– FHWA

12

Page 13: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Lessons Learned

Not that different from Design-Bid-Build projects

– Still building the same types of bridges and pavement structures

– Still use the spec book but in conjunction with the Design Build Agreement

– Still use the Roadway Design Manual and AASHTO LRFD, except as spelled out in

the Technical Provisions

13

Page 14: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Lessons Learned

Important that the TxDOT project team is fully engaged

– Engage the local municipalities early on during the schematic phase and keep them engaged through procurement and implementation

– Closely manage GEC and OVT firms

• Ensure design review is for contract requirements and not preferences

• Ensure material testing is monitored closely and increase as needed to address non-validations

– Determine quickly if there is a quality issue or a statistical analysis/validation issue

– Although risk is transferred to Design-Build Contractor, the stakeholder involvement is not completely transferred.

– At the end of the agreement, TxDOT retains ownership

14

Page 15: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Lessons Learned

Keep moving during the procurement

– Procurement typically takes 9 months to a year

– Advance ROW during that time

– Advance long lead time utilities during that time

– Advance agreements with the local municipalities

15

Page 16: Design-build Project Management · PDF file•Specialty inspection items (Calatrava bridge) – FHWA 12. Design-Build Project Management October 12, 2016 Lessons Learned Not that different

Design-Build Project Management October 12, 2016

Questions?

16