DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER...

34
U.S. GENERAL SERVICES ADMINISTRATION DESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE

Transcript of DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER...

Page 1: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

U.S. GENERAL SERVICES ADMINISTRATION

DESIGN AND CONSTRUCTIONat GSANATALIE HUBER, PE, PMPCHIEF ENGINEERPUBLIC BUILDINGS SERVICE

Page 2: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

AGENDA

■ PUBLIC BUILDINGS SERVICE

■ PORTFOLIO FEATURES

■ DESIGN PROGRAMS

■ PROJECT DELIVERY

Page 3: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

U.S. GENERAL SERVICES ADMINISTRATION

■ FEDERAL ACQUISTION SERVICES

■ PUBLIC BUILDINGS SERVICE

Page 4: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

PUBLIC BUILDINGS SERVICE PORTFOLIO

8,700 owned or leased buildings +375 million rentable square feet 500+ historic buildings

Page 5: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

GSA’S 11 REGIONS

Page 6: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

US COURTHOUSES

• Unique Requirements (US Courts Design Guide)– Security

– Adjacency and Circulation

– Barrier-Free Access

– Mechanical/ Electrical Systems

– Automation

– Acoustics

– Interior Finishes

• Administrative Office of the US Courts and GSA Collaboration

Page 7: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

JOHN JOSEPH MOAKLEY UNITED STATES COURTHOUSE, PEI COBB FREED & PARTNERS

Page 8: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

JOHN JOSEPH MOAKLEY UNITED STATES COURTHOUSE, PEI COBB FREED & PARTNERS

Page 9: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

UNITED STATES COURTHOUSE, LOS ANGELES, CALIFORNIA, SOM

Page 10: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

UNITED STATES COURTHOUSE, LOS ANGELES, CALIFORNIA, SOM

Page 11: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

LAND PORTS OF ENTRY

• 168 Land Ports of Entry

• 1,952 miles of border with Mexico, 47 ports

• 5,525 miles of border with Canada, 121 ports

• Design and Construction Challenges– Aging land port inventory (average age of ports is 42 years)

– Geographic limitations

– Short construction season (northern border)

– Limited labor market in remote areas

– Evolving security programs

– Securing the border without impeding commerce and trade

– Diverse stakeholders

• CBP and GSA Collaboration

Page 12: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

SAN YSIDRO LAND PORT OF ENTRY, MILLER HULL

Page 13: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

SAN YSIDRO LAND PORT OF ENTRY, MILLER HULL

Page 14: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

U.S. LAND PORT OF ENTRY, WARROAD, MINNESOTA, JULIE SNOW ARCHITECTS

Page 15: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

U.S. LAND PORT OF ENTRY, WARROAD, MINNESOTA, JULIE SNOW ARCHITECTS

Page 16: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

FEDERAL OFFICE BUILDINGS AND WORKPLACE SOLUTIONS

• Cost savings– Reduce the Footprint

– Energy Savings

• Sustainability– Sustainable Materials

– Daylighting Strategies

– Water Conservation

– Green Standards

• Productivity

• Technology– Cloud computing

– Telework

– Hoteling

Page 17: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

GSA REGION 2 HEADQUARTERS, GKV ARCHITECTS

Page 18: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

UNITED STATES PROBATION OFFICE, CHICAGO, GSA WITH MEKUS STUDIOS

Page 19: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

GSA REGION 6 HEADQUARTERS, GASTINGERWALKER&

Page 20: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

ENGINEERING AND TECHNICAL SUPPORT

Page 21: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

P100: GSA’S PERFORMANCE BASED FACILITIES STANDARDS

• Establishes design standards and criteria for new buildings, repair and alterations, modernizations, and work in historic structures

• Both performance based and prescriptive requirements

• Performance criteria– Four levels of performance: Base + three tiers

• Means to verify performance– Measuring and verifying

– Commissioning

• LEED Gold Certification

Page 22: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

SEISMIC PROGRAM

• Improve Seismic Resilience

• Seismic Risk Rating Database– Used to prioritize seismic

improvements

• Non-structural Seismic Improvements

• Seismic Event Preparedness and Response

Page 23: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

HIGH SEISMIC AREAS

Page 24: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

50 UNITED NATIONS PLAZA FEDERAL OFFICE BUILDING, HKS ARCHITECTS

Page 25: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

50 UNITED NATIONS PLAZA FEDERAL OFFICE BUILDING

BASEMENT SHEAR WALL FOUNDATION

Page 26: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

PIONEER COURTHOUSE, PORTLAND, OR

BASE ISOLATION SEISMIC UPGRADE

Page 27: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

BUILDING ENCLOSURES

• 2007 ASHRAE Study– 17,000 construction defect claims, of which

69% were due to moisture-related defects in building enclosures

• ASTM Study– $9 Billion annually spent in North America on

repairing and litigating damages from moisture intrusion

• Costs 3X more to correct a problem once it’s built

• Integrated Design approach to building enclosures and HVAC systems to meet energy targets

• Building Enclosure Commissioning

Page 28: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

ANTHONY J. CELEBREZZE FEDERAL BUILDING FACADE RENOVATION, THORNTON TOMASETTI

Page 29: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

GSA’S DESIGN EXCELLENCE PROGRAMPLANNING FOR QUALITY

Established in 1994 to enhance the quality of public architecture and encourage new approaches through:

■ Simplifying the evaluation process

■ Engaging private-sector design professionals (peers) with no vested interest in the process in the evaluation of proposals

■ Holding Peer Reviews of proposed design concepts

■ First Peer Review – From 3 Concepts to 1

■ Second Peer Review – Refinement of the Concept

Design Excellence Policies and Procedures: https://www.gsa.gov/designexcellence

Page 30: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

PROJECT DELIVERY METHOD TOOL

• Focus on 7 primary risk categories– Site and Project Startup Considerations

– Schedule Management

– Cost Management

– Control of Design Quality

– Integrated Design

– Green Management

– Project Management

• Delivery Methods– Traditional Design Bid Build

– Construction Manager as Constructor

– Design Build

– Design Build Bridging

Page 31: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

CONSTRUCTION EXCELLENCE

• Project Delivery Method Tool

• PDRI (Project Definition Rating Index)

• Construction Peer Review– 15%, 60%

– Private Sector Construction Expert Peers

• Formal Lessons Learned Session

Page 32: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

FY21 Budget Request: Construction and Acquisition of Facilities Program

– $459 million for Washington, DC DHS Consolidation at St. Elizabeth’s

– $80 million for Cleveland, OH FBI Field Office

– $85 million for Oklahoma City, OK FBI Field Office

– $99 million for Calexico West, CA U.S. Land Port of Entry Phase II B

– $28 million for Kansas City, MO Hardesty Federal Complex Remediation

– $9 million for Washington, DC Southeast Federal Center Remediation

Page 33: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

FY21 Budget Request: Major Repairs and Alterations Program

• New York, NY 201 Varick Street Federal Office Building $66M• New York, NY Jacob K. Javits Federal Office Building $10M• Chicago, IL Ralph H. Metcalfe Federal Building $124M• Philadelphia, PA Philadelphia U.S. Custom House $91M• Woodlawn, MD West High Low Rise $208M• Tacoma, WA Tacoma Union Station $46M• Cincinnati, OH Potter Stewart U.S. Courthouse $37M• Indianapolis, IN Major General Emmett J. Bean Federal Center $42M• Kansas City, MO Charles E. Whittaker U.S. Courthouse $57M• Indianapolis, IN Minton-Capehart Federal Building $18M• Washington, DC William Jefferson Clinton Complex $48M• Los Angeles, CA Federal Building - 11000 Wilshire Boulevard $26M• Kansas City, MO 8930 Ward Parkway Federal Building $22M• Austin, TX Austin Finance Center $36M• Cleveland, OH Carl B. Stokes U.S. Courthouse $28M• Various Locations, Southern Border LPOE Infrastructure Paving Program $11MSubtotal, Major Repair and Alterations Program $878M

Page 34: DESIGN AND CONSTRUCTION at GSADESIGN AND CONSTRUCTION at GSA NATALIE HUBER, PE, PMP CHIEF ENGINEER PUBLIC BUILDINGS SERVICE. AGENDA ... • Los Angeles, CA Federal Build ing - 11000

U.S. GENERAL SERVICES ADMINISTRATION

DESIGN AND CONSTRUCTION at GSANATALIE HUBER, PE, PMPCHIEF ENGINEERPUBLIC BUILDINGS SERVICE