Depot Drive Access Improvements - Alaska Railroad

4
Feb 19 2020 Depot Drive Access Improvements Project Scope The Alaska Railroad (ARRC) is enhancing vehicle access and pedestrian safety by construct- ing a new roadway, Depot Drive. The project area is fully within the ARRC land reserve, and is located between Christensen Drive to the south, the main line track to the north, the Anchorage Historic Depot to the east and the 49th State Brewing Company facility to the west. The project will ehance access by improving the intersection between the depot’s west-end ac- cess roadway (the beginning of Depot Drive), and West 1st Avenue where it turns into Christensen Drive. The project replaces an existing retaining wall along Christensen Drive with a new 250-foot- long sheet pile retaining wall placed closer to the Christensen Drive roadway. Land between existing and new retaining walls will be cleared and leveled, making room to straighten the intersection. The project will also widen the Depot Drive transportation corridor to support upgrading about 1,500 feet of the gravel access road into a paved commercial-industrial secondary street. Roadway improvements include an 8-foot wide pedestrian walkway, new street lighting and trespass mitiga- tion involving a safety barrier and fencing. Purpose and Need The project will expand space to accommodate continued growth in rail passenger operations. Bus access is currently hampered by the gravel access roadway’s pinched and curved intersection, which makes bus maneuvering difficult. ROADWAY AND PEDESTRIAN IMPROVEMENTS Typical cross-section of commercial-industrial secondary street along the retaining wall area.

Transcript of Depot Drive Access Improvements - Alaska Railroad

Feb 192020

Depot Drive Access Improvements

Project ScopeThe Alaska Railroad (ARRC) is enhancing

vehicle access and pedestrian safety by construct-ing a new roadway, Depot Drive. The project area is fully within the ARRC land reserve, and is located between Christensen Drive to the south, the main line track to the north, the Anchorage Historic Depot to the east and the 49th State Brewing Company facility to the west.

The project will ehance access by improving the intersection between the depot’s west-end ac-cess roadway (the beginning of Depot Drive), and West 1st Avenue where it turns into Christensen Drive. The project replaces an existing retaining wall along Christensen Drive with a new 250-foot-long sheet pile retaining wall placed closer to the Christensen Drive roadway. Land between existing

and new retaining walls will be cleared and leveled, making room to straighten the intersection.

The project will also widen the Depot Drive transportation corridor to support upgrading about 1,500 feet of the gravel access road into a paved commercial-industrial secondary street. Roadway improvements include an 8-foot wide pedestrian walkway, new street lighting and trespass mitiga-tion involving a safety barrier and fencing.

Purpose and NeedThe project will expand space to accommodate

continued growth in rail passenger operations. Bus access is currently hampered by the gravel access roadway’s pinched and curved intersection, which makes bus maneuvering difficult.

ROADWAY AND PEDESTRIAN IMPROVEMENTS Typical cross-section of commercial-industrial secondary street along the retaining wall area.

Depot Drive Access Improvements • Page 2

DEPOT

WEST 1ST AVE

DEPOT DRIVE

CHRISTENSEN DRIVE

The project is in line with master community devel-opment planning for the Ship Creek area. It supports future roadway improvements that promote commer-cial development through better vehicle and pedes-trian connectivity. Upgraded lighting and a pedestrian walkway address pedestrian safety.

Project Goals• Provide vehicle and pedestrian connectivity

within the Ship Creek area

• Promote Ship Creek area development

• Increase safety and discourage trespass onto railroad operating areas

• Improve and define passenger operations areas next to the track

Status Corridor Expansion (Retaining Wall)

In 2018, LCG Lantech Inc. provided conceptual and preliminary engineering work in support of widen-ing the corridor. ARRC also obtained permitting to install a new retaining wall, remove the old retaining wall, and perform earth work. Contractors installed the new retaining wall during spring / summer 2019.

Roadway ConstructionCRW Engineering conducted an Alternatives

Analysis for roadway and intersection construction. ARRC approved the preferred alternative in late 2019. Design considers landscaping, snow storage,

CORRIDOR EXPANSION BEGINS WITH NEW RETAINING WALL

Above: A new retaining wall is installed during summer 2019. The 49th State Brewery is in the background.

Right: The new retaining wall as seen from along Christensen Drive sidewalk. The depot is in the background.

Below: The retaining wall that was replaced.

fire access, commercial vehicle operations, private vehicle access, trespass and public safety factors.

A phased approach accommodates planned development by nearby railroad leaseholders, including the Downtown Edge condo-minium construction project, and improvements to the 49th State Brewery facility and parking areas.

Depot Drive Access Improvements • Page 3

Scheduled for 2020, the first phase includes intersection improvements and roadway con-struction from the depot, west to the end of the retaining wall. Some trespass mitigation work is part of the first phase.

Phase II is scheduled for completion in 2021. It will extend roadway construction by about 250 feet southwest of the retain-ing wall. The extension provides additional access to the 49th State Brewery and other future developments.

LandscapingProject landscaping will follow

phased construction. Landscaping plans (shown on page 4) incor-porate features found in nearby railroad facility landscaping, such as within the Pedestrian Plaza at Ship Creek Avenue and North C Street.

The pedestrian experience is enhanced with picnic tables, benches and trash receptacles strategically placed along the pathway. These are surrounded with berry and rose shrubs, large boulders, concrete planters, peren-nial iris, and ground covered by grasses and wildflowers.

PHASED ROADWAY AND INTERSECTION CONSTRUCTION PLAN

Depot Drive Access Improvements • Page 4

SITE LIGHT (SEE ELEC)(TYP)

UTILITIES (SEE CIVILKSEE ELEC)(TYP)

.... .... 4' DEPTH TOPSOIL AND SCHEDULE A SEED

MIX TO LIMITS OF DISTUR BA

LANDSCAPE LEGEND 1 DECIDUOUS TREE DECIDUOUS TREES L6 (TYP)

SYM BOL AB BR LA TIN NAME COMMON NAME

0· MALUS 'DOLGO' DOLGO CRABAPPLE \

r

r

/

© PTE POPULUS TREMU LOIDES COLUMNAR SWEDISH , 'ERECTA' ASPEN

SHRU BS SYM BOL

G)

0 ® 0*

ROPE FENCE (TYP.)

ALIGN ROPE FENCE WITH EDGE OF PAVEMENT. KEEP 3' CLEAR OF PAVEMENT AND 1' CLEAR OF BOU LDERS.

't---a'=--t--,S=H=RU',=

B / (TYP.) ,, ./

PLANTING BED /

---oO-/--/'" DEPOT DRIVE PHASE 1: /

ADD/ALT (SEE CIVIL) X"

2 SHRU B L6 (TYP) PERENNIALS

ABBR LATIN NAME COMMON NAME AB BR. LATIN NAME AA AMELANCHIER ALNIFOLIA DWARF SERVICEBERRY 1£; IS IRIS SETOSA

VAR. PUMILA cs CORNUS SERICEA KELSEY'S DWARF

'KELSEYI' RED-OSIER DOGWOOD RA ROSA ACICULARIS PRICKLY ROSE RR ROSA RUGOSA 'HANSA' RUGOSA ROSE w VACCINIUM VITIS-IDAEA LINGON BERRY

0 � ■ -:� -■ ■ ■ ■ ■ ■

♦•. 1 �oo -.... 7,'}.• -PHASE I: BASIC BID LIMITS

♦-I

I / STA 21+87.87 •

/ -.

PERENNIAL (TYP.)

COMMON NAME WILD FLAG IRIS

/ �

SPACING 18'SPACING

MISCELLANEOUS SYM BOL DESCRIPTION □ 4'TOPSOILAND SCHEDULE A

MOWA BLE SEED MIX +

+

rum TABLE

� BENCH

O TRASH RECEPTACLE

� CONCRETE PLANTER CU R B

- - - - - - LANDSCAPE EDGING -�-- ROPE FENCE

BOU LDER - 5' 0 MIN.

NOTES

0 )i� -z

w � ci

�I�

N

E9 10�·====�== 0 10' 20·

►--, m..,

Ol I "' < Ol "' � "' "' 0

SHEET NO.

LS

0 N

� i5 2 :::, u 0 0

5 ti

5 u

"' "'

Landscaping trees include the Dolgo Crabapple, Paper Birch, vivid Red Maple and distinctive Columnar Swedish As-pen. Protection and security are woven in, to include rope fencing, chain link fencing and concrete barriers that feature iconic Alas-kan graphic images.

Cost and FundingCorridor Expansion (Retaining Wall)• Concept and preliminary engineering, retaining wall design and installation

cost is about $850,000, funded 100% by the Alaska Railroad as part of ARRC’s 2019 capital budget.

Roadway Construction and Landscaping• Roadway construction, including intersection improvements, is estimated to

cost about $2.5 million, funded 100% by the Alaska Railroad. ARRC has bud-geted $1.7 million for 2020.

PROJECT LANDSCAPING

Landscaping planned along the project corridor, between the depot, west to the end of the new retaining wall.

Landscaping planned along the project corridor, between the end of

the new retaining wall, west to the 49th State Brewery facility.