Dependable production 2014 - MDHzoomin.idt.mdh.se/course/KPP202/HT2014/Le16_141028... · TPM -...
Transcript of Dependable production 2014 - MDHzoomin.idt.mdh.se/course/KPP202/HT2014/Le16_141028... · TPM -...
Dependable production OEE, TPM, and RCM
Antti Salonen [email protected]
2 © Antti Salonen
Planned production time
Start-up problem
Set-up Break-downs
Planned stopps
Cleaning
Period with small-stops Period with reduced speed
Production
Productive time Unproductive time
How a production shift may look!
KPP202 141014
3 © Antti Salonen
Purpose: ● Show the disturbances that reduces the productivity of the equipment ● Show how effective the equipment is used by measuring loss factors ● Show that improving actions are adequate. ● Aid in planning of resources and workload
Overall Equipment Effectiveness
KPP202 141014
4 © Antti Salonen
The six big losses
● Failures and break-downs ● Set-up and adjustments
● Idling and minor stoppages
● Reduced speed
● Defects and rework
● Start-up losses
KPP202 141014
5 © Antti Salonen
Quality rate Performance rate Availability
X X
The OEE-value indicates the total effectiveness in production
What is OEE?
KPP202 141014
6 © Antti Salonen
Value adding
operative time
Overall Equipment Effectiveness (OEE) = Availability x Performance rate x Quality rate
Availability = Planned prod. time – Unplanned stop time
Planned prod. time
Performance rate =
Bought CT x items produced
Available operative time
Quality rate =
Items produced - Defects Items produced
Scheduled working time
Planned production time
Available operative time
Net operative
time
Planning related stopps
Def
ects
Unp
lann
ed
stop
ps
Spee
d lo
ss Idling and minor stoppage
Reduced speed
Defects and rework
Start-up losses
Set-up and adjustments
Failures and breakdowns
OEE calculations Planning factor =
Scheduled time – Planning related stop time
Scheduled time
= (Planning factor) x
KPP202 141014
7 © Antti Salonen
Quality rate = Items produced – defect items 412 pieces - 16 pieces
Items produced 412 st = 0,96 =
Availability = Planned production time – unplanned stop time 400 min - 90 min Planned production time 400 min
= 0,775 =
Performance rate = Bought cycle time x items produced 0,6 min/piece x 412 pieces
Available operative time 310 min = 0,797 =
PfOEE = 0,83 x 0,775 x 0,797 x 0,96 x 100 (%) = 49,2%
OEE calculations
Scheduled working time – planning related stop time Scheduled working time
Planning factor = 480 min - 80 min
480 min = 0,83 =
OEE = 0,775 x 0,797 x 0,96 x 100 (%) = 59,3%
KPP202 141014
8 © Antti Salonen
Three levels of measurement
How to measure ? Depending on purpose and aim with the measuring, the following three levels may be used: Level 1 Total utilization = Pftot x A x P x Q
This level indicates how a plant is utilized compared to maximum available time (24hrs/day, 365 days/year) Level 2 Asset effectiveness = Pf x A x P x Q
This level indicates how effective an asset is used regarding planned working hours Level 3 Equipment effectiveness = A x P x Q
This level indicates how effective a specific equipment is used.
KPP202 141014
9 © Antti Salonen
Calculation of Pftot Theoretical available time (24h/day, 365 days/year) – planning related stop time
Theoretical available time (24h/day, 365 days/year) Planning related stop time is time loss that doesn’t affect the equipment effectiveness. For example hollidays, breaks, meeting time, education, cleaning, waiting time due to surrounding equipment, PM, planned modifications, lack of orders, personell or material. Note. The use of 24h/day, 365 days/year for definition of Theoretical available time is common within process industries where heavy investments occur.
OEE: Total planning factor
KPP202 141014
10 © Antti Salonen
Calculation of Pf Theoretical production time (scheduled) – planning related stop time Theoretical production time (scheduled) Theoretical production time is the scheduled production time when the facility is manned. E.g. 3-shift (ca 110 hours/week), daytime (40 hours/week) Planning related stop time is time loss that doesn’t affect the equipment effectiveness. For example hollidays, breaks, meeting time, education, cleaning, waiting time due to surrounding equipment, PM, planned modifications, lack of orders, personell or material.
OEE: Planning factor
KPP202 141014
11 © Antti Salonen
Quality rate = Items produced – defect items Items produced
Availability = Planned production time – unplanned stop time
Planned production time
Performance rate = Bought cycle time x items produced
Available operative time
PfOEE = Pf x A x P x Q x 100 = %
OEE calculations
Scheduled workingtime – planning related stop time Scheduled working time
Planning factor =
OEE = A x P x Q x 100 = %
KPP202 141014
12 © Antti Salonen
OEE calculation
Calculate the OEE and PfOEE for a production unit under the following conditions: Work hours: 2-shifts, monday– friday Shif hours: Morning shift 06:00 – 14:12
Afternoon shift 13:48 – 22:00, on fridays, the shift ends at 20:00 Breaks: 30 minutes lunch every shift, with no production Meetings: Department meeting every Thursday at 12:48 – 13:48 with no production Preventive maintenance: Every day at 13:48 – 14:00 Production rate: The bought cycle time is 6 minutes per piece. Events during the studied week: Break downs: monday, 08:30 – 10:00
wednesday, 07:00 – 10:12 thursday, 15:30 – 17:24
Produced pieces: 523 of which 3 scrapped beccause of defects.
Availability = Planned prod. time – Unplanned stop time
Planned prod. time
Performance rate =
Bought CT x items produced
Available operative time
Quality rate =
Items produced - Defects Items produced
Planning factor = Scheduled time – Planning related stop time
Scheduled time
KPP202 141014
13 © Antti Salonen
OEE: Calculation Scheduled working time 4x16h + 14h = 78h
Planning related stops 2x5x0,5h + 1h + 5x0,2h = 7h
Planning factor (Pf) (78-7h) / 78 = 0,910 Pf = 91,0%
Planned production time 78h-7h = 71h
Unplanned stop time 1,5h + 3,2h + 1,9h = 6,6h
Availability (A) (71 – 6,6) / 71 = 0,907 A = 90,7%
Available operative time 71h – 6,6h = 64,4h
Bought cycle time 6 min / 60 = 0,1h
Produced items 523 st
Performance rate (P) (0,1x523) / 64,4 = 0,812 P = 81,2%
Scrap 3 st.
Quality rate (Q) (523 – 3) / 523 0,994 Q = 99,4%
PfOEE 0,910x0,907x0,812x0,994 0,666 PfOEE = 66,6%
OEE 0,907x0,812x0,994 0,732 OEE = 73,2%
KPP202 141014
14 © Antti Salonen
The following has to be explored: ● Manual loading time included?
● Other limiting factors affecting the cycle time?
● Can several products be produced during one cycle?
● Do different products have different cycle times?
Defining Cycle time
KPP202 141014
15 © Antti Salonen
Defining bought cycle time
● Cycle time according to equipment specification ● Cycle time according to product specification
● Lowest CT in similar equipment
● Lowest CT tested in the equipment
● Theoretically calculated CT
● Lowest measured CT
● Actual CT recalculated with ambition
KPP202 141014
16 © Antti Salonen
Performance rate, P - when producing products with different CT’s
Product Theoretical CT, CTT (min/piece) Produced amount, P (piece) CTT x P (min) Sum CTT x P (min) Available operative time*, T.O.T (min) P = (Sum CTT x P) /T.O.T (%)
0,6 0,7 0,8 0,9 100 150 50 50 60 105 40 45
250 300 83%
P1 P2 P3 P4
* Planned production time – Unplanned stops
KPP202 141014
17 © Antti Salonen
Increased OEE leads to….
● Less disturbances which in turn may lead to • Improved planning ability • Reduced risk of quality problems • More time for developing work
● Released capacity which in turn may lead to • Alternative to capacity investments • Increased flexibility • Decreased operative time • Decreased number of equipments
KPP202 141014
18 © Antti Salonen
Time for a break?
KPP202 141014
19 © Antti Salonen
OEE in Swedish industry (2002)
10
20
30
40
50
% OEE Interval
35-45 45-55 55-65 65-75 75-85 85-95 % OEE
Electronics Power Chemical
P & P
Steel Mining
Manufacturing industry
60% Average
80%
88% Improvement potential
Practically achievable
KPP202 141014
20 © Antti Salonen
Average OEE = 60,4%
Utilization
Results from a study of 30 Swedish sub suppliers in automotive industry (Nutek, 2008)
For comparison, a number of similar companies in other countries were studied:
Average OEE in other countries = 77%
KPP202 141014
21 © Antti Salonen
39% of the companies measure and analyze time-loss and cause of failures
86% of the companies perform systematic preventive maintenance
Average OEE = 60,4%
Utilization
More findings from the study of 30 Swedish sub-suppliers in automotive industry (Nutek, 2008)
14% of the companies measure and analyze time-loss and cause of disturbances
25% of the companies perform CBM
KPP202 141014
22 © Antti Salonen
My own observations
Poor utilization of the possibilities of analyzing data from CMMS
Most companies fail to regard dependability aspects when investing
Few companies use systematic RCA (Root Cause Analysis)
Few companies use systematic maintenance concepts
Few companies measure the cost of lost production
KPP202 141014
23 © Antti Salonen
Concepts for increasing the dependability of production equipment
TPM; Total Productive Maintenance
RCM; Reliability Centered Maintenance
KPP202 141014
24 © Antti Salonen
TPM – what’s that?
● Total Productive Maintenance ● Total Process Management
● Total Production Management
● And so on….
KPP202 141014
25 © Antti Salonen
TPM - definition
“TPM can be defined as a systematic work method aiming to develop disturbance free processes at lowest possible cost through the commitment of all co-workers” (LCP-Consultants)
KPP202 141014
26 © Antti Salonen
TPM as a philosophy
● focuses on daily maintenance in manufacturing industries ● is built on total employee involvement
● born in the Japanese automobile industry.
KPP202 141014
27 © Antti Salonen
TPM – Total Productive Maintenance
● Total Effectiveness ● Total Preventive Maintenance
● Total Commitment
KPP202 141014
28 © Antti Salonen
Why TPM?
● Replace routine with development ● Increased commitment from all co-workers
● Continuous improvements
● Foreseeable operations
● Improved safety and environment
KPP202 141014
29 © Antti Salonen
TPM Structure
Effectiveness
Continuous improvements
Autonomous maintenance
Planned maintenance
Ear
ly e
quip
men
t man
agem
ent
Qua
lity
mai
nten
ance
Effe
ctiv
e ad
min
istra
tion
Saf
ety,
hyg
iene
and
env
ironm
ent
Education
Organisation and pilot
Policy and goals
Develop a master plan
Management’s decision
Evaluation and new goals
Preparation Implementation
Education and training
Kick-off
KPP202 141014
30 © Antti Salonen
Group activities
Cross functional improvement group
Autonomous maintenance group
Target oriented cross functional group
KPP202 141014
31 © Antti Salonen
Improvement tools
FTA
Identify and evaluate potential weaknesses
Identify causes of failures and their logic connections
Identify, prioritize and analyze failures
Reduce all chronic loss to zero
7QC/QM
PM-analysis
FMEA
KPP202 141014
32 © Antti Salonen
Autonomous maintenance
KPP202 141014
33 © Antti Salonen
Autonomous maintenance
● Teach the operators to react on cause instead of result ● By increased kompetence and understanding the operators may:
● Eliminate minor stoppages
● Prevent break-downs
● Secure implemented improvements
● Improve quality, safety, and environment
● In the long run operators start to perform maintenance tasks
● Daliy inspections replaces repair and low frequent controls ● Implemented through seven well-defined steps
● Takes long time to implement, often years
KPP202 141014
34 © Antti Salonen
1. Basic cleaning and order
2. Counter meassures at the problem source
3. Standards for cleaning and lubrication
4. General inspection training
5. Autonomous inspection
6. Organize the work environment
7. Autonomous maintenance
Equipment focusing step. Secures the basic condition of the equipment
Focuses the operators. They learn advanced inspection and maintenance techniques
Factory focusing step. From maintenance to control.
Description Competence Repair skills
Understands the relation between
maintenance and product quality
Understands the functions and structure
of the machines
Can find defects and understand the principles for improvements of the equipment
The seven-step ladder
KPP202 141014
35 © Antti Salonen
Planned maintenance
Maintenance planning
Maintenance control
Spare part control
Economy control
Implementation of planned maintenance leads to: - Increased MTBF and MTBM - Decreased MTTR, MWT and M - Closer to 0-faults, 0-stops and 0-accidents
Information feedback
Act
iviti
es fo
r im
prov
ed
mai
nten
ance
effe
ctiv
enes
s
Cor
rect
ive
Mai
nten
ance
Pre
vent
ive
Mai
nten
ance
Res
torin
g M
aint
enan
ce
Impr
ovem
ent M
aint
enan
ce
Con
ditio
n B
ased
Mai
nten
ance
Activities for improved OEE
KPP202 141014
36 © Antti Salonen
Early equipment management
LCC
Early detection of problems
Experience development MP-design
Basic properties
Acquisition process
Project
Goal and requirements
Structure and process thinking
The included activities are aiming for new equipment to be: • Reliable and producing non defective products. • Easy to mend and set up, and fast to start after set-up changes. • Easy to maintain, and fast to localize faults and repair. • Easy to clean, lubricate and inspect. • Resource efficient and safe.
The process has to goals: • To reach stable, full speed production at start-up. • To, as far as possible, meet the detailed requirements for the equipment.
KPP202 141014
37 © Antti Salonen
Quality maintenance
KPP202 141014
38 © Antti Salonen
Results of TPM at Volvo
Productivity Breakdowns reduced with 90%
OEE increased from 50% to 90%
MTBF increased from 30 minutes to 8 hours
Quality Scrap reduced with 90%
Cost of quality control reduced with 67%
Customer complaints reduced with 75%
Costs Production cost reduced with 30%
Delivery precision Capital bound in WIP and finished goods decreased with 50%
Fulfillment actual/desired delivery time increased to 90%
Delivery precision actual/promised time increased to 100%
Safety Accidents resulting in personal injuries reduced to 0
Accidents resulting in pollution reduced to 0
Commitment Ten times as many suggested improvements
Time for education and training increased with 100%
KPP202 141014
39 © Antti Salonen
RCM has been defined as…
Reliability Centered Maintenance: “a process used to determine what must be done to ensure that any physical asset continues to do what its users want it to do in its present operating context.” (Moubray, 1997, p.7)
RCM – what’s that?
KPP202 141014
40 © Antti Salonen
RCM
Reliability Centered Maintenance, RCM Focuses on construction and development of products and manufacturing systems maintainability and to develop an effective and resource parsimoniuos PM before the product or system is up and running, born in the aircraft industry
KPP202 141014
41 © Antti Salonen
RCM
● RCM is sprung from MSG (Maintenance Steering Group) that has been developed since the 1960s’, for the purpose of the aircraft industry.
● RCM have since also been developed to be used in e.g. the power industry, energy industry, and in some cases also the manufacturing industry.
KPP202 141014
42 © Antti Salonen
RCM
● With RCM methodology one handle the maintenance objectives as early as in the development phase on a consciously, rationally, and planned base. ● One analyses potential failure that can occur on the
developed systems, structures, or components. ● Faults can be classified as obvious or hidden, safety
critical or of considerable financial character.
KPP202 141014
43 © Antti Salonen
RCM is basically about answering… ● …what are the functions and associated performance standards of
the asset in its present operating context? ● …in what ways does it fail to fulfill its functions? ● …what causes each functional failure? ● …what happens when each failure occurs? ● …in what way does each failure matter? ● …what can be done to predict or prevent each failure? ● …what should be done if a suitable proactive task cannot be found? This can be performed through e.g. FMEA and FTA
RCM
KPP202 141014
44 © Antti Salonen
Further reading
Sherwin, D., (2000), “A review of overall models for maintenance management”, Journal of Quality in Maintenance Engineering, Vol. 6, pp. 138-164.
KPP202 141014