DEPARTMENT OF TRANSPORTATION Richard T. Hammer, …

27
3/24/2017 SPECIFICATION Sussex NJDOT Maintenance Yard Vinyl Siding & Porch Repair 409 Route 23 North at County Route 565 Sussex, NJ 07461 STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt. Governor DEPARTMENT OF TRANSPORTATION Richard T. Hammer, Commissioner Date: MAY 9, 2017

Transcript of DEPARTMENT OF TRANSPORTATION Richard T. Hammer, …

SPECIFICATIONSussex NJDOT Maintenance Yard Vinyl Siding & Porch Repair
409 Route 23 North at County Route 565 Sussex, NJ 07461
STATE OF NEW JERSEY Honorable Chris Christie, Governor
Honorable Kim Guadagno, Lt. Governor
DEPARTMENT OF TRANSPORTATION Richard T. Hammer, Commissioner
Date: MAY 9, 2017
NJDOT Project Reference Number: __F1# 75609_
Project: Sussex NJDOT Vinyl Siding & Porch Repair. Project Site: Sussex NJDOT Yard 409 Route 23 North @ County Route 565 Sussex New Jersey 07461 Important Dates:
• Mandatory Site Visit: MAY 16, 2017 @ 10:00AM • Question Cut-Off: MAY 19, 2017 @ 10:00 AM • Answers to Bid Questions: Bidders are encouraged to monitor the website
daily for updates, changes and responses to questions through the submission due date.
• Bid Opening: MAY 26, 2017 @ 10:00 AM
Procurement Contact: Robert McNeil 609-530-5301 [email protected] Project Manager: Randy Stout 732-312-6628 [email protected]
TABLE OF CONTENTS
GENERAL BIDDING AND CONTRACT REQUIREMENTS PAGE NO. General Conditions 1 thru 10 Specifications and Scope of Work 11 thru 21 Instructions to Bidders 22 thru 24 ATTACHMENTS:
1 1/4/2017
GENERAL CONDITIONS
1. DEFINITIONS
A. The Contracting Agency for this project will be the New Jersey Department of Transportation (NJDOT). All matters dealing with this contract and payment should be directed to Randy Stout at 732-312-6628.
B. The Owner for this project will be the State of New Jersey, Department of Transportation.
C. The Using Agency Representative will also be Randy Stout.. For purposes of this
contract, he will act as the Owner’s project coordinator and inspector. He shall judge the quantity, quality, fitness and acceptability of all parts of the work. All work shall be coordinated with the Using Agency.
2. SUBMITTALS The following documents and/or materials are required and must be submitted by the
Contractor during the noted project periods: A. Bid Response Period: Informal Bid Proposal Form, identified within these specifications under
Instructions to Bidders, Item 1, Page IB-1. B. Pre-Construction Period: Business Registration Certificate from the Division of Revenue identified within
these specifications under Instructions to Bidders, Item 1F, Page IB-1 and specified under General Conditions, Item 14, Page GC-5.
Insurance Certificate identified within these specifications under Instructions to
Bidders, Item 1, Page IB-1 and specified under General Conditions, Item 3, Page GC-2.
C. Construction Period: If stipulated, provide selection samples, record samples, shop drawings, diagrams,
schedules, lists, illustrations, performance charts, catalog cuts, progress payments, and brochures.
D. Close-Out Period: Letter of Guarantee guaranteeing the quality and workmanship for a period of one
year from date of final acceptance of the project.
2 1/4/2017
Manufacturer’s guarantees and warranties. 3. INSURANCE REQUIREMENTS A. The Contractor shall submit insurance certificates in the following minimum
coverages: 1. Workman’s Compensation - $250,000 2. Comprehensive Liability a. Bodily Injury - $1,000,000 each occurrence. b. Property Damage - $1,000,000 each occurrence. 3. Vehicle Liability a. Bodily Injury - $1,000,000 each occurrence. b. Property Damage - $500,000 each occurrence. 4. USE OF PREMISES A. The Contractor shall coordinate requirements for available utilities/facilities with
the NJDOT Project Manager and the Local Facility Manager. B. The Contractor shall confine his apparatus, the storage of materials and
equipment, and the operation of his workmen to limits or directions of the Project Manager and the Local Facility Manager, and shall not unreasonably encumber the premises with his materials.
5. PROTECTION AND LIABILITY A. Protection and security of persons and property during the construction period
from loss by theft, vandalism, pilfering, fire, water, wind, etc., shall be provided by the Contractor as the conditions at the site warrant. The Contractor shall be responsible for securing his own plant, equipment, and all materials scheduled for the project.
B. If any direct or indirect damage is done to private or public property by or on
account of any act, omission, neglect, or misconduct in the execution of work on the part of the Contractor, such property shall be restored by the Contractor, at his expense, to a condition equal to or better than that existing before the damage was done, or he shall make good the damage in another manner, acceptable to the NJDOT.
6. MATERIALS QUALITY
3 1/4/2017
A. The Contractor shall furnish materials and equipment which will be efficient, appropriate, and have the capacity to secure a satisfactory quality of work and a rate of progress which will ensure the completion of the work within the time frame stipulated. Only new materials and equipment shall be incorporated into the work.
7. SUBSTITUTION A. In the event the Contractor should propose a substitution of the specified
equipment or materials, it shall be his responsibility to submit proof of equality and data of sufficient detail to enable the NJDOT to identify the particular product, the method of installation, and whatever else is required so a determination can be made as to its conformity to the product specified. The Contractor shall provide and pay for any tests, which may be directed by the NJDOT in order to evaluate such proposed substitution(s). Any material or product, which is not in full conformance with specifications, may be rejected.
B. The Contractor shall be allowed seven (7) working days from the date of contract
award to provide the necessary shop drawing(s), data and samples supporting any proposed substitution(s). Should the Contractor fail to provide the information within this period, the NJDOT shall exercise the option of either: allocating additional time for the information, or denying any further consideration of the substitution(s) whereby the Contractor must provide the equipment or material(s) specified.
C. Since substitutions are primarily for the financial benefit of the Contractor, a
credit change order shall accompany each request for substitution. 8. OTHER CONDITIONS A. By submitting a bid, the Bidder warrants that he has familiarized himself with all
provisions of the bidding documents and understands their intent and meaning. B. The failure or omission of the Bidder to examine forms, instruments, or plan and
specification documents, or to visit the site and acquaint himself with conditions there existing, and compute required amounts of labor and materials covering the complete job shall not relieve him from any obligation with respect to his bid.
C. Any oral interpretation, not documented in writing prior to bid opening or
referenced in the bid proposal, shall be considered as privileged information and, as such, not binding upon the NJDOT.
D. Conditions existing at the time of the inspection will be maintained by the
NJDOT as far as practical. The NJDOT assumes no responsibility for actual conditions where work is to occur. Starting of operations will be construed, as
4 1/4/2017
evidence that the Contractor has complied with the above requirements, and later claims for difficulties encountered which could have been foreseen will not be recognized.
E. In order to protect the lives and health of his employees, the Contractor shall
comply with all applicable statutes and pertinent provisions of the “Manual of Accident Prevention in Construction,” issued by the Associated General Contractors of America, Inc. He shall maintain an accurate record of all cases of death, occupational disease, and injury requiring medical attention or causing loss of time from work, arising out of and in the course of employment on work under the contract. The Contractor alone shall be responsible for the safety, efficiency, and adequacy of his plant, appliances, and methods, and for any damage or injury, which may result from his failure or his improper construction, maintenance, or operation.
F. The Contractor shall defend, protect, indemnify, and save harmless the State of
New Jersey from all claims, suits, actions, damages, and costs of every name and description arising out of or resulting from the performance of his work under this contract. This responsibility is not limited by the provisions of other indemnification provisions included elsewhere herein.
9. TIME OF COMPLETION A. Work to be completed, inspected and approved within 45 calendar days from the
Notice to Proceed. B. No activities will be permitted on weekends or holidays unless otherwise
approved by the Project Manager and the Local Facility Manager. 10. LIQUIDATED DAMAGES A. The Contractor agrees that, from the compensation otherwise to be paid, the
NJDOT will assess liquidated damages in the amount of $250 for each calendar day thereafter that the work included under this contract remains uncompleted as specified under the Time of Completion which sum is agreed upon as the proper proportionate measure of liquidated damages which the NJDOT will sustain per diem, by failure of the Contractor to progress or complete his work under this contract at the time stipulated, and the sum is not to be construed as in any sense a penalty.
B. The above liquidated damages shall be interpreted as partial reimbursement to the
NJDOT resulting from the legal fees and the cost of additional engineering services, and other expenses of the NJDOT because of non-compliance by original dates, but shall not be considered as including costs of legal fees and the cost of additional services in connection with claims, arbitration, litigation,
5 1/4/2017
default or insolvency of the Contractor. 11. TERMINATION FOR CONVENIENCE A. The NJDOT may, at any time, terminate the Contract in whole or in any part for
the Division’s convenience and without cause when the NJDOT in their discretion, views termination in the public interest.
B. Upon receipt of the Termination for Convenience, the Contractor shall complete
only items specified in the order and in accordance with the contract documents.
C. The Contractor will only be paid for items of work partially or completely finished at either the contract price or mutually agreed price.
12. NEW JERSEY PREVAILING WAGE ACT A. The Contractor must comply with the New Jersey Prevailing Wage Act Laws of
1963, Chapter 150, (N.J.S.A. 34:11-56.25 et seq.) and all amendments thereto, and this act is hereby made a part of every contract entered into on behalf of the State of New Jersey through the Division of Property Management and Construction, except those contracts which are not within the contemplation of the act.
B. The Contractor must submit their certified payroll with their invoice on the
PAYROLL CERTIFICATION FOR PUBLIC WORKS PROJECTS form. 13. THE PUBLIC WORKS CONTRACTOR REGISTRATION ACT A. At the time of the bid due date, the bidder and the subcontractors must be registered
in accordance with “The Public Works Contractor Registration Act” (N.J.S.A. 34:11-56.48 et seq).
B. All questions regarding registration should be addressed to:
Contractor Registration Unit New Jersey Department of Labor Division of Wage and Hour Compliance PO Box 389 Trenton, NJ 08625-0389 Telephone: 609-292-9464 Fax: 609-633-8591
14. In accordance with Public Law 2001, Chapter 134, all contractors and subcontractors providing goods/services to State agencies and authorities are required to provide the contracting agency or authority with proof of registration with the Department of Treasury, Division of Revenue. The basic registration process involves the filing of Form NJ-Reg.
6 1/4/2017
which can be filed online at www.state.nj.us/njbgs/services.html or call (609) 292-7077 or (609) 292-1730.
15. The Prime Contractor shall take all necessary and reasonable steps to ensure that Small Business Enterprises (SBE) as defined in N.J.A.C. 17:14-1.2 have the maximum opportunity to compete for and perform contracts.
GOALS FOR THIS CONTRACT
A. This contract includes a goal of awarding 25 percent of the total contract value to either Prime or Subcontractors that qualify as small businesses with gross revenues of up to one million and small businesses with revenues that do not exceed the annual revenue standards established by the Federal standard at 13 C.F.R. 121.201.
B. Aspirations shall be made to allocate a portion of the twenty-five (25) percent
value in accordance with the following ethnic goals: African American 6.3% and Asian American 4>34%.
C. Only SBE’s properly certified by the date of bid with the Division of Minority
& Women Business Development will be considered in determining whether the Contractor has met the Contract goals.
D. A database of certified SBE firms is available for review from the Division of
Minority & Women Business Development (Telephone: 609-292-2146; Website: http://www.nj.gov/njbusiness/contracting/services). This database is to be used as source of information only, and does not relieve the Prime Contractor of the responsibility of seeking out other SBE's.
SUBMISSION OF CONTRACTOR'S SBE PLAN
A. The Prime Contractor who is named the apparent successful bidder shall
submit to the NJDOT for approval, no later than 10 State business days after Notification from the New Jersey Dept. of Transportation the following:
1. SBE Form A - Schedule of SBE Participation. The Prime Contractor shall
list all SBE’s that will participate in the contract including type of work, actual dollar amount and percent of total Contract to be performed; and ethnicity.
2. SBE Form B - Affidavit of SBE status which is a statement under oath by the SBE that the firm is properly certified as an SBE.
7 1/4/2017
3. Request for Exemption - In the event the Prime Contractor is unable to meet the specified goals, Prime Contractor must submit a written request for an exemption from the goals as defined herein.
4. The name of the Prime Contractor's SBE liaison officer who shall be the
person within the Prime Contractor's organization primarily responsible for implementing the Prime Contractor's SBE program.
4. NJDOT in its sole discretion may request additional information from the
Prime Contractor prior to award of the contract in order to evaluate the Prime Contractor's compliance with the SBE requirements of the bid proposal. Such information must be provided within the time limits established by NJDOT.
REASONABLE OUTREACH EFFORTS
A. The Prime Contractor that fails to meet the goals for small businesses shall document the reasonable outreach efforts it has made to meet the goals. Evidence of “good reach effort includes but is not limited to:
1. The Firm shall request listings of SBE’s from the Division (609) 292-2146
and/or the Division of Property Management and Construction and attempt to contact same.
2. The firm shall keep specific records of its efforts, including records of all
requests made to the Division, the names of the SBE’s contacted, and the means and results of such contacts, including without limitation receipts from certified mail and telephone records.
3. The Firm shall actively solicit and shall provide the Division of Property
Management and Construction with proof of solicitations of SBE’s for the provision of Services; including advertisements in general circulation media, professional service publications and small business, minority- owned business or women-owned business focus media.
4. The Firm shall provide evidence of efforts made to identify categories of
Services capable of being performed by SBE’s. 5. The Firm shall provide all potential subcontractors and sub-consultants
that the Firm has contacted pursuant to 2 or 3 above with detailed information regarding the scope of work of the subject contract.
6. The Firm shall provide evidence of efforts made to use the goods and/or
services of available community organizations, consultant groups, and local, State, and Federal agencies that provide assistance in the recruitment and placement of SBE’s. Furthermore, the Firm shall submit proof of its subcontractors’ and/or sub-consultants’ SBE registrations on the form
8 1/4/2017
attached to the Informal Bid Proposal Form as SBE Form A and shall complete such other forms as may be required by the Division of Property Management and Construction for State reporting as to participation.
RESPONSIBILITY AFTER CONTRACT AWARD
A. The Prime Contractor shall advise NJDOT of any change regarding the work to
be performed by an SBE whose name was submitted on the SBE Form A for the purpose of meeting the Contract goals.
B. If an SBE that was to be used by the Prime Contractor to meet one of the goal
does not perform the work, the Prime Contractor shall attempt to replace the SBE with a similarly situated SBE. If the Prime Contractor fails to replace the SBE with a similarly situated SBE, it shall document to NJDOT the reasons for such failure and NJDOT may review the Prime Contractor's subcontracting practices to determine if it is engaging in unlawful discrimination.
DOCUMENTATION
A. NJDOT may at any time require such information as it deems necessary
to ascertain the compliance of any Prime Contractor with the terms of these provisions.
B. The Prime Contractor shall keep such records as are necessary to
determine compliance with its SBE obligations. The records kept by the Contractor must contain information that demonstrates:
1. The names of the SBE’s contacted for Work on the Contract; 2. The type of work to be done or services to be performed by all SBE
contractors on the Contract; 3. The actual dollar amount of work awarded to SBE’s; 4. The progress and efforts being made in seeking out and utilizing SBE’s.
This would include solicitations, quotes, and bids regarding work items, supplies, and leases;
5. Documentation of all correspondence, contacts, and telephone calls, used
to obtain the services of SBE’s on the Contract. C. As required by NJDOT the Prime Contractor shall submit reports
pertaining to contracts and business transactions with SBE’s. D. All such records shall be maintained for a period of three years following
final payment and shall be available for inspection by the NJDOT.
9 1/4/2017
SANCTIONS
Failure of the Prime Contractor to carry out the requirements set forth in these General Conditions shall constitute a breach of contract for which NJDOT may terminate the contract or pursue such other remedy as NJDOT deems appropriate. The Prime Contractor shall physically include the provisions set forth in these General Conditions in all contracts.
16. PROCUREMENT REFORM
A. PUBLIC LAW 2005, CHAPTER 51 - RESTRICTIONS ON POLITICAL
CONTRIBUTIONS – In accordance with Public Law 2005, Chapter 51, any bidder(s) awarded a contract on or after October 15, 2004, shall be required to submit a Certification and Disclosure of Political Contributions for all Business Entities. The successful contractor will be required to complete the necessary forms. Public Law 2005, Chapter 51 prohibits State departments, agencies and authorities from entering into a contract that exceeds $17,500 with an individual or entity that has made a contribution to a political party committee. Public Law 2005, Chapter 51 further requires the disclosure of all contributions to any political organization organized under section 527 of the Internal Revenue Code that also meets the definition of a “continuing political committee” within the meaning of N.J.S.A. 19:44A-3(n) and N.J.A.C. 19:25-1.7. The successful bidder shall also be required to adhere to all continuing obligations contained in Public Law 2005, Chapter 51 regarding contributions and disclosures as required in Public Law 2005, Chapter 51.
B. PUPLIC LAW 2005, Chapter 92 - In accordance with Public Law 2005, Chapter 92 (N.J.S.A. 52:34-13.2 et seq., superseding Executive Order 129 (2004)), all bidders submitting a proposal shall be required to submit a Source Disclosure Certification that all services will be performed in the United States. The bidder shall disclose the location by country where services under the contract will be performed and any subcontracting of services under the contract and the location by country where any subcontracted services will be performed. The Source Disclosure Certification is attached to the bid proposal form.
C. PUBLIC LAW 2005, Chapter 271 – All bidders submitting a proposal shall be
required to complete a Vendor Certification and Political Contribution Disclosure Form for those projects not required to be publicly advertised. This form will be attached to the bid proposal form.
PUBLIC LAW 2005, Chapter 92 can be viewed in its entirety at http://www.state.nj.us/infobank/circular/eom129.htm All pay-to-play Public Laws and documents are posted on the website http://www.nj.gov/dca/lgs/p2p
17. AFFIRMATIVE ACTION
A. If awarded a contract, your company/firm shall be required to comply with the requirements of N.J.S.A. 10:5-31 et seq. and N.J.A.C. 17:27
11 1/4/2017
SPECIFICATIONS – SCOPE OF WORK The New Jersey Department of Transportation would like to obtain a quote for the following work to be accomplished at the NJDOT, Sussex Yard 409 Route 23 North Sussex New Jersey 07461 Scope of Work to be accomplished:
1. Hours of work allowed, Monday—Friday 730AM—4:00PM Zero exceptions 2. Porches, Remove and install new 1.5” Wolmanized Decking to front and Rear porches 3. Remove and install new Wolmanized stairs on Front both sides and Rear 4. Remove and install New 4 x 4 Wolmanized front porch support beams. 5. Install Triple Center Soffit Vents to underside of front porch 6. On rear Porch add 8 x 8 or larger to support back porch and bump out. 7. Remove shutters, 8. Wrap house with a vapor barrier, Typar, or equivalent. 9. All exposed wood will be wrapped as see in spec. 10. New shutters to be installed, color tbd. 11. Vendor to supply own way to dispose of all old material. 12. All sections below 13. Any Questions will be answered at site meeting
SECTION 07 46 33 VINYL AND POLYMER SIDING
PART ONE – GENERAL 1.1 RELATED DOCUMENTS
A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions, and other Division 1 Specification Sections, apply to this Section.
1.2 SECTION INCLUDES
1.3 RELATED SECTIONS
1.4 REFERENCES
A. ASTM D 635 – Standard Test Method for Rate of Burning and/or Extent and Time of
Burning of Plastics in a Horizontal Position
12 1/4/2017
B. ASTM D 638 – Standard Test Method for Tensile Properties of Plastics C. ASTM D 648 – Test Method for Deflection Temperature of Plastics under Flexural
Load D. ASTM D 696 – Standard Test method for Coefficient of Linear Thermal Expansion
of Plastics between -30 Degrees C and 30 Degrees C E. ASTM D 790 – Standard Test Methods for Flexural Properties of Un-reinforced and
Reinforced Plastics and Electrical Insulating Materials F. ASTM D 1435 – Standard Practice Method for Outdoor Weathering of Plastics G. ASTM D 1929 – Standard Test Method for Ignition Properties of Plastics H. ASTM D 2843 – Standard Test Method for Density of Smoke from the Burning or
Decomposition of Plastics I. ASTM D 3679 – Standard Specifications for Rigid Poly (Vinyl Chloride) (PVC)
Siding J. ASTM D 4101 – Standard Specification for Propylene Plastic Injection and Extrusion
Materials K. ASTM D 4216 – Standard Specification for Rigid Poly (Vinyl Chloride) (PVC)
Compounds and Related Plastic Building Product Compounds L. ASTM D 4226 – Standard Test Method for Impact Resistance of PVC Building
Products M. ASTM D 4477 – Standard Specification for Rigid Poly (Vinyl Chloride) (PVC) Soffit N. ASTM D 5206 – Standard Windload Resistance Test O. ASTM E 84 –Standard Test method for Surface Burning Characteristics of Building
Materials P. ASTM E 119 – Standard Test Methods for Fire Tests on Building Construction and
Materials 1.5 PERFORMANCE REQUIREMENTS
A. PVC Fire Resistance: Provide vinyl siding products that meet or exceed the following ratings: 1. Flame spread index 20, fuel contribution o, smoke development rating 360, per
ASTM E 84. 2. Self-ignition temperature: 824 degrees F (440 degrees C) per ASTM D 1929. 3. Fire endurance classification of 1 hour, per ASTM E 119 as wall assembly.
B. Siding: TPO Fire Resistance: Provide thermoplastic polyolefin siding products that meet or exceed the following ratings: 1. Minimum self-ignition temperature of 650 degrees F (343 degrees C), per ASTM
D1929. 2. Smoke density rating of 40, per ASTM D 2843.
1.6 SUBMITTALS
A. Submit under provisions of Section 01300 B. Product Data: Manufacturer’s data sheets on each product to be used, including:
1. Preparation instructions and recommendations 2. Storage and handling requirements and recommendations 3. Installation methods
13 1/4/2017
C. Selection Samples: For each finish product specified, two complete sets of color chips representing manufacturer’s full range of available colors and patterns.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: Provide installer with not less than three years of experience with products specified or has obtained Master Craftsman credentials from siding manufacturer.
1.8 DELIVERY, STORAGE AND HANDLING
A. Store products in manufacturer’s unopened packaging until ready for installation.
1.9 PRODUCT CONDITIONS
A. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer’s absolute limits.
1.10 WARRANTY
A. Provide manufacturer’s standard lifetime limited warranty on siding products. PART TWO – PRODUCTS 2.1 MATERIALS
A. Polymer Siding Thermoplastic Polyolefin (TPO): Provide siding materials made of modified polypropylene copolymer with cell classification of PP300A11220F00W2020103, as defined by ASTM D 4101, meeting or exceeding the following properties. 1. Tensile strength: 3,500 psi (24,133 kPa), per ASTM D 638 2. Tensile modulus: 180,000 psi (1,241,100 kPa), per ASTM D 638 3. Flexural modulus: 180,000 psi (1,241,100 kPa), per ASTM D 790 4. Coefficient of linear thermal expansion: .000053 in/in/degree F, per ASTM D 696 5. Deflection temperature at 264 psi (1820 kPa): 160 degrees F (71 degrees C) 6. Style: Double Six Siding: Color: As selected by Architect from manufacturer’s standards
B. Vinyl Carpentry Accessories
1. Provide matching vinyl accessories as specified or required. a. Undersill trim b. Fascia c. 2 ½ inch (64 mm) Metal Starter Strip d. Simulated Corner Boards
14 1/4/2017
C. Fasteners: Provide galvanized steel nails as recommended by manufacturer of siding
products. D. Wood Furring: 1” x 2” pine, spruce or fir. E. Insulation Board: 3/4” polystyrene ridged insulation board.
PART THREE – EXECUTION 3.1 EXAMINATION
A. Do not begin installation until substrates have been properly prepared. B. If substrate preparation is the responsibility of another installer, notify Architect of
unsatisfactory preparation before proceeding. 3.2 PREPARATION
A. Remove projecting corner boards, window and door trim. B. Examine, clean, and repair as necessary any substrate conditions which would be
detrimental to proper installation. C. Do not begin installation until unacceptable conditions have been corrected.
3.3 INSTALLATION
A. Install furring strips vertical at 16” on center over existing wood siding. Shim furring at corners and at openings as required to provide a smooth plane for siding.
B. Infill between furring to provide backing for siding. C. Install products in accordance with the latest printed instructions of the manufacturer. D. Install products with all components true and plumb. E. Nail horizontal panels by placing nail in center of slot. Nail vertical panels by placing
first nail at top of top slot and remaining nails in center of slots. Drive nails straight, leaving 1/16 inch (1.6mm) space between nail head and flange of panel.
F. Allow apace between both ends of siding panels and trim for thermal movement. Overlap horizontal panel ends one-half the width of factory pre-cut notches.
G. Stagger lap joints in horizontal siding in uniform pattern as successive courses of siding are installed.
H. Install J-channel and flashing to accommodate successive courses of vertical siding. Install wood shims at building corners to bring cut edges of vertical siding out to correct plane.
3.4 PROTECTION
A. Protect installed products until completion of project. B. Touch-up, repair or replace damaged products before Substantial Completion
3.5 CLEANING
A. At completion of work, remove debris caused by siding installation from project site.
15 1/4/2017
PART 1 – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section Includes: 1. Installation of sealants and backing rods at sealant joints in the building
façade. B. Scope: Provide all materials, labor, equipment, and appliances required to complete
work of this Section, including, but not necessarily limited to, the following: 1. Cleaning and priming of joints as required by Manufacturers installation
instructions. 2. Installation of joint sealants at exterior intersections with metal frames.
1.3 REFERENCES
A. ASTM C 321 - Standard Test Method for Bond Strength of Chemical-Resistant Mortars.
B. ASTM C 920 - Standard Specification for Elastomeric Joint Sealants. C. FS (Federal Specification) TT-S-00227E (COM-NBS) - Interim Federal Specification
for Sealing Compound: Elastomeric Type, Multi-Component (for Caulking, Sealing, and Glazing in Buildings and Other Structures.
D. FS (Federal Specification) TT-S-00230C - Interim Federal Specification for Sealing Compound: Elastomeric Type, Single Component (for Caulking, Sealing, and Glazing in Buildings and Other Structures.
E. FS (Federal Specification) TT-S-001543 (COM-NBS) - Interim Federal Specification for Sealing Compound: Silicone Rubber Base (for Caulking, Sealing, and Glazing in Buildings and Other Structures.
1.4 QUALITY ASSURANCE
A. Performance: Except as otherwise indicated, joint sealers are required to establish
and maintain airtight and waterproof continuous seals on a permanent basis, within recognized limitations of wear and aging as indicated for each application. Failures of installed sealers to comply with this requirement will be recognized as failures of materials and workmanship.
B. Applicator Qualifications: Contractor and job foreman must have a minimum of five (5) years experience installing sealant.
17 1/4/2017
C. Pre-Installation Compatibility and Adhesion Tests: Contractor shall be responsible for verifying with sealant manufacturer that all sealants to be used are compatible with and will satisfactorily adhere to all substrates. Tests shall be conducted in the field and witnessed by the Contracting Officer.
D. Adhesion Test: During installation, in the presence of, and when and where directed by the Contracting Officer conduct pull test on each joint type. Test is to be performed by slicing across the joint and then cutting both sides of the joint two inches, separating the sealant from the adjoining material. The sealant shall then be pulled in the direction of the joint. The sealant should break rather than separate from the adjoining material.
1.5 SUBMITTALS
A. Submit under provisions of Division 1. B. Manufacturer's Technical Data, Guides, and Application Procedures C. Submit samples illustrating colors. D. Submit laboratory tests or data validating product compliance with performance
criteria specified. E. Submit a copy of the Manufacturer’s warranty.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Deliver products in original factory packaging bearing identification of product, manufacturer, and batch number. Provide Material Safety Data Sheets for each product.
B. Store products in a location protected from freezing, damage, construction activity, precipitation, and direct sunlight in strict accordance with manufacturer's recommendations.
C. Condition products to approximately 60 to 70 degrees F (16 to 21 degrees C) for use in accordance with manufacturer's recommendations.
D. Handle all products with appropriate precautions and care as stated on Material Safety Data Sheet.
1.7 PROJECT CONDITIONS
A. Do not use products under conditions of precipitation or freezing weather. Use
appropriate measures for protection and supplementary heating to ensure proper curing conditions in accordance with manufacturer's recommendations if application during inclement weather occurs.
B. Ensure substrate is dry. C. Protect adjacent work from contamination or damage.
1.8 WARRANTY
18 1/4/2017
2.1 MANUFACTURERS
A. Single Source: All materials, including joint sealers, cleaners, and primers shall be of a single source manufacturer.
B. Acceptable Manufacturers: 1. Dow Corning 2. Sika 3. Tremco 4. Approved Equal
2.2 MATERIALS
A. One-part, low modulus, elastomeric sealant: DOW CORNING 790 Silicone Building Sealant, SIKA Sikasil WS 290 or TREMCO Spectrem 1, Conforming to ASTM C920, Type S, Grade 25, Use NT, M, G, A, and O.
2.3 ACCESSORIES
A. Primer: As required by sealant manufacturer. B. Joint Cleaner: Non-corrosive and non-staining type recommended by sealant
manufacturer and compatible with joint forming materials. C. Backer Rod: Open or closed-cell polyethylene rod designed for use with cold-applied
joint sealants for on-grade or below-grade applications. 1. Comply with ASTM C 1330. 2. Size required for joint design.
D. Bond Breaker: Pressure-sensitive tape polyethylene or Teflon recommended by
sealant manufacturer. E. Masking Tape: Pressure-sensitive paper tape.
2.4 COLOR
A. Sealant Colors: Selected by Contracting Officer from manufacturer's master color system.
PART 3 – EXECUTION 3.1 EXAMINATION
A. Inspect all areas involved in work to establish extent of work, access, and need for protection of surrounding construction and public spaces.
B. Conduct pre-application inspection of site verification with an authorized manufacturer's representative.
C. The drawings generally indicate locations of joint sealers. The contractor shall examine the building prior to bidding to determine the quantity and location of all
19 1/4/2017
sealant joints. The contractor shall be responsible for the preparation and replacement of joint sealers in ALL joints whether shown on the drawings or not.
3.2 PREPARATION
A. Remove loose materials and foreign matter which impair adhesion of joint filler. B. Clean joints by grinding, sandblasting, or wire brushing to expose a sound surface
free of contamination and laitance. C. Ensure structurally sound surfaces, dry, clean, free of dirt, moisture, loose particles,
oil, grease, asphalt, tar, paint, wax, rust, waterproofing, curing and parting compounds, membrane materials, and other foreign matter.
D. Prime the bond line using Prime Coat where required by the sealant manufacturer installation instructions or as required for proper adhesion, allowing a minimum of one hour drying and cure time before installing sealant. Primer should be within shelf life and poured from containers onto rags, or into applicator bottles that can be poured onto rags. If brushes are used, primer should be poured a small amount at a time into another open container to avoid contaminating primer and to minimize primer being exposed too long. Pour out no more than can be applied in 30 minutes. If primer becomes cloudy or contaminated, discard. Prime no more substrate than can be sealed in one day or shift.
E. Where the possibility of joint filler staining of adjacent areas or materials exists, mask joints prior to application.
1. Do not remove masking tape before joints have been tooled and initial cure of joint filler has taken place.
2. Work stained due to failure of proper masking precautions will not be accepted.
3.3 INSTALLATION
A. Solvent clean aluminum and any other non-porous surfaces with recommended solvent using the “Two Cloth Cleaning Method”.
B. Apply primer according to manufacturer’s instructions. C. Back-Up Material:
1. Install backer rod using blunt or rounded tools to assure uniform depth (+/- 1/8”) without puncturing or twisting. Closed cell rod shall be a minimum 20% oversized. Open cell rod shall be a minimum 50% oversized. Install bond breaker tape in shallow joints.
2. Install polyethylene joint filler in joints wider than 1/4 inch (6 mm) to back-up material per manufacturer's recommendations.
D. Bond Breaker: Install bond-breaker strip in joint to be sealed on top of back-up
material to prevent adhesion of sealant to back-up material; install per manufacturer's recommendations.
E. Sealant: 1. Mask or protect adjacent areas that are not to receive sealant.
20 1/4/2017
2. Apply sealant in joints using a pressure gun with nozzle cut to appropriate size. Deposit sealant in a uniform and continuous bead with no gaps or air pockets.
3. Tool joints to require configuration with a blunt instrument as soon as possible after installation, but before sealant begins to skin over. Remove all masking materials immediately after tooling.
4. Apply materials only within manufacturer's specified application life period. Discard sealant after application life is expired or if prescribed application period has elapsed.
F. Joints shall have a minimum width to depth ratio of 2:1. Finished joint cross section
shall have an hourglass shape. 3.4 CLEANING
A. Remove uncured sealant and joint filler with Reducer 990, xylene, toluene, or MEK. Remove cured sealant and joint filler by razor, scraping, or mechanically.
B. Remove all debris related to application of sealants from job site in accordance with all applicable regulations for hazardous waste disposal.
3.5 SCHEDULE OF JOINT SEALERS
A. General-Purpose Exterior Applications: 1. Sealant: Silicone. 2. Applications:
a. Joints and recesses between adjacent constructions and frames, sills, and sub- sills of louvers, and trim.
b Around penetrations in exterior walls. c. Top edges of surface mounted counterflashing. d. Where necessary to prevent infiltration of water or air into or through
exterior building envelope.
END OF SECTION
INSTRUCTIONS TO BIDDERS BID
A. Bids for the work described herein will be received by the New Jersey Department of Transportation (NJDOT), located at 1035 Parkway Avenue, Finance & Administration Building, via e-mail to the attention of the NJDOT Buyer referenced throughout this solicitation
B. Bids are to be submitted on Informal Bid Proposal Form, herewith provided. Bids
not submitted on this form and in accordance with the instructions contained therein shall be considered non-responsive and shall be rejected. Bids submitted without endorsement shall also be considered non-responsive. Facsimile submittals will not be accepted.
C. Bidders shall submit a lump sum base bid for the entire work described herein. The
amount shall be entered on the Informal Bid Proposal Form, where the appropriate description has been provided. Bids shall reflect the equipment and/or material(s) specified. Substitution shall only be considered after completion of the bidding process.
D. Bids must be received by the New Jersey Department of Transportation (NJDOT) before the closing date and time, as stated on the Informal Bid Proposal Form.
E. Public Works Bidders are required to be registered with the Department of Labor,
Contractor Registration Unit at the time of the bid due date. This requirement is in accordance with the Public Works Contractor Registration Act.
F. Bidders shall submit with their Informal Bid Proposal, the Small Business Enterprise
Form A and Form B as specified in General Conditions. G. Bidders shall submit with their Informal Bid Proposal Form the Source Disclosure
Certification for Public Law 2005, Chapter 92 as specified in General Conditions, and the Vendor Certification and Political Contribution Disclosure Form, Public law 2005, Chapter 271 as specified in General Conditions.
H. Before contract award, contactor must submit to NJDOT, an insurance certificate as
per requirements and business registration certificate from the Division of Revenue as per requirements.
23 1/4/2017
NJDOT Contact Person: Randy Stout New Jersey Department of Transportation Division of Procurement P.O. Box 600 Trenton, NJ 08625 Email: [email protected] Office: 732-312-6628 NJDOT Buyer: Senior Robert McNeil New Jersey Department of Transportation Division of Procurement P.O. Box 600 Trenton, NJ 08625 Email: [email protected] Office: 609-530-5301 IMPORTANT DATES & INFORMATION General Description of Project: NJDOT: Sussex Yard, Vinyl Siding and Porch Repair Mandatory Site Visit: To view the building, discuss the intent of this project and go over this Scope of Work prior to submitting a written quote, there will be a Mandatory Site Visit on: MAY 16, 2017 @ 10:00 AM. You must be present at this site visit in order to submit a bid Question Cut-Off Date: MAY 19, 2017 @ 10:00 AM. Bidders are encouraged to monitor the website daily for updates, changes and responses to questions through the bid opening date. Bid Opening: MAY 26, 2017@ 10:00 AM.
General
1. Upon issuance of a Purchase Order to the successful bidder, a written schedule shall be submitted to NJDOT Representative so that all furniture and wall items can be moved out of the way to allow work to proceed and be completed in a timely manner.
2. Upon completion of all work associated with this project, the contractor shall be
responsible for the removal and offsite disposal of all job related debris.
3. Work hours shall primarily be completed after regular business hours, this may include weeknights and weekends. Some painting may be able to take place during regular business hours in spaces not occupied by employees.
Permits The contractor shall be responsible for obtaining all required permits, if required, with the Department of Community Affairs (DCA). At the completion of the project and before final payment will be made, all job related debris shall be removed from the site and the site shall be cleaned and restored to a condition such that it is equal to or better than it was before the project started.
General Safety and Health Requirements The New Jersey Department of Transportation (NJDOT) will provide information to contractors regarding site conditions that might raise health and safety concerns that are unusual or unique to NJDOT. It is the responsibility of the contractor to protect their employees, subcontractors, and suppliers by providing a safe place of employment. The NJDOT does not establish nor enforce safety practices for the benefit of a contractor, subcontractor, supplier or their employees. This does not exempt contractors from complying with all other occupational safety and health requirements. Non-NJDOT entities are responsible for conforming to acceptable safety and health practices for the protection of NJDOT employees and property. Please see attached NJDOT Safety Standard Operating Procedure, “Contractor Safety Requirements” for more information. Award
A. Award of contract will be based upon the lowest responsible bid. B. The New Jersey Department of Transportation (NJDOT) reserves the right to
reject all bids C. Results of the bidding will be made available upon request. D. Award of contract shall not be interpreted to mean approval to proceed with
construction activities.
PART ONE – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions, and other Division 1 Specification Sections, apply to this Section.
1.2 SECTION INCLUDES
1.3 RELATED SECTIONS
1.4 REFERENCES
A. ASTM D 635 – Standard Test Method for Rate of Burning and/or Extent and Time of Burning of Plastics in a Horizontal Position
B. ASTM D 638 – Standard Test Method for Tensile Properties of Plastics
C. ASTM D 648 – Test Method for Deflection Temperature of Plastics under Flexural Load
D. ASTM D 696 – Standard Test method for Coefficient of Linear Thermal Expansion of Plastics between -30 Degrees C and 30 Degrees C
E. ASTM D 790 – Standard Test Methods for Flexural Properties of Un-reinforced and Reinforced Plastics and Electrical Insulating Materials
F. ASTM D 1435 – Standard Practice Method for Outdoor Weathering of Plastics
G. ASTM D 1929 – Standard Test Method for Ignition Properties of Plastics
H. ASTM D 2843 – Standard Test Method for Density of Smoke from the Burning or Decomposition of Plastics
I. ASTM D 3679 – Standard Specifications for Rigid Poly (Vinyl Chloride) (PVC) Siding
J. ASTM D 4101 – Standard Specification for Propylene Plastic Injection and Extrusion Materials
1.5 PERFORMANCE REQUIREMENTS
1.9 PRODUCT CONDITIONS
A. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer’s absolute limits.
1.10 WARRANTY
A. Provide manufacturer’s standard lifetime limited warranty on siding products.
PART TWO – PRODUCTS
PART THREE – EXECUTION
1.1 RELATED DOCUMENTS
A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
A. This Section Includes:
1. Installation of sealants and backing rods at sealant joints in the building façade.
B. Scope: Provide all materials, labor, equipment, and appliances required to complete work of this Section, including, but not necessarily limited to, the following:
2. Installation of joint sealants at exterior intersections with metal frames.
A. ASTM C 321 - Standard Test Method for Bond Strength of Chemical-Resistant Mortars.
B. ASTM C 920 - Standard Specification for Elastomeric Joint Sealants.
C. FS (Federal Specification) TT-S-00227E (COM-NBS) - Interim Federal Specification for Sealing Compound: Elastomeric Type, Multi-Component (for Caulking, Sealing, and Glazing in Buildings and Other Structures.
D. FS (Federal Specification) TT-S-00230C - Interim Federal Specification for Sealing Compound: Elastomeric Type, Single Component (for Caulking, Sealing, and Glazing in Buildings and Other Structures.
E. FS (Federal Specification) TT-S-001543 (COM-NBS) - Interim Federal Specification for Sealing Compound: Silicone Rubber Base (for Caulking, Sealing, and Glazing in Buildings and Other Structures.
A. Performance: Except as otherwise indicated, joint sealers are required to establish and maintain airtight and waterproof continuous seals on a permanent basis, within recognized limitations of wear and aging as indicated for each application. Fail...
B. Applicator Qualifications: Contractor and job foreman must have a minimum of five (5) years experience installing sealant.
C. Pre-Installation Compatibility and Adhesion Tests: Contractor shall be responsible for verifying with sealant manufacturer that all sealants to be used are compatible with and will satisfactorily adhere to all substrates. Tests shall be conducted ...
D. Adhesion Test: During installation, in the presence of, and when and where directed by the Contracting Officer conduct pull test on each joint type. Test is to be performed by slicing across the joint and then cutting both sides of the joint two ...
A. Submit under provisions of Division 1.
B. Manufacturer's Technical Data, Guides, and Application Procedures
C. Submit samples illustrating colors.
D. Submit laboratory tests or data validating product compliance with performance criteria specified.
E. Submit a copy of the Manufacturer’s warranty.
A. Deliver products in original factory packaging bearing identification of product, manufacturer, and batch number. Provide Material Safety Data Sheets for each product.
B. Store products in a location protected from freezing, damage, construction activity, precipitation, and direct sunlight in strict accordance with manufacturer's recommendations.
C. Condition products to approximately 60 to 70 degrees F (16 to 21 degrees C) for use in accordance with manufacturer's recommendations.
D. Handle all products with appropriate precautions and care as stated on Material Safety Data Sheet.
A. Do not use products under conditions of precipitation or freezing weather. Use appropriate measures for protection and supplementary heating to ensure proper curing conditions in accordance with manufacturer's recommendations if application during...
B. Ensure substrate is dry.
C. Protect adjacent work from contamination or damage.
A. Provide manufacturer's twenty-year limited warranty against failure of structural adhesion, staining, and weatherseal.
A. Single Source: All materials, including joint sealers, cleaners, and primers shall be of a single source manufacturer.
B. Acceptable Manufacturers:
A. One-part, low modulus, elastomeric sealant: DOW CORNING 790 Silicone Building Sealant, SIKA Sikasil WS 290 or TREMCO Spectrem 1, Conforming to ASTM C920, Type S, Grade 25, Use NT, M, G, A, and O.
A. Primer: As required by sealant manufacturer.
B. Joint Cleaner: Non-corrosive and non-staining type recommended by sealant manufacturer and compatible with joint forming materials.
C. Backer Rod: Open or closed-cell polyethylene rod designed for use with cold-applied joint sealants for on-grade or below-grade applications.
1. Comply with ASTM C 1330.
2. Size required for joint design.
D. Bond Breaker: Pressure-sensitive tape polyethylene or Teflon recommended by sealant manufacturer.
E. Masking Tape: Pressure-sensitive paper tape.
A. Sealant Colors: Selected by Contracting Officer from manufacturer's master color system.
A. Inspect all areas involved in work to establish extent of work, access, and need for protection of surrounding construction and public spaces.
B. Conduct pre-application inspection of site verification with an authorized manufacturer's representative.
C. The drawings generally indicate locations of joint sealers. The contractor shall examine the building prior to bidding to determine the quantity and location of all sealant joints. The contractor shall be responsible for the preparation and repla...
A. Remove loose materials and foreign matter which impair adhesion of joint filler.
B. Clean joints by grinding, sandblasting, or wire brushing to expose a sound surface free of contamination and laitance.
C. Ensure structurally sound surfaces, dry, clean, free of dirt, moisture, loose particles, oil, grease, asphalt, tar, paint, wax, rust, waterproofing, curing and parting compounds, membrane materials, and other foreign matter.
D. Prime the bond line using Prime Coat where required by the sealant manufacturer installation instructions or as required for proper adhesion, allowing a minimum of one hour drying and cure time before installing sealant. Primer should be within sh...
E. Where the possibility of joint filler staining of adjacent areas or materials exists, mask joints prior to application.
1. Do not remove masking tape before joints have been tooled and initial cure of joint filler has taken place.
2. Work stained due to failure of proper masking precautions will not be accepted.
A. Solvent clean aluminum and any other non-porous surfaces with recommended solvent using the “Two Cloth Cleaning Method”.
B. Apply primer according to manufacturer’s instructions.
C. Back-Up Material:
1. Install backer rod using blunt or rounded tools to assure uniform depth (+/- 1/8”) without puncturing or twisting. Closed cell rod shall be a minimum 20% oversized. Open cell rod shall be a minimum 50% oversized. Install bond breaker tape in shall...
2. Install polyethylene joint filler in joints wider than 1/4 inch (6 mm) to back-up material per manufacturer's recommendations.
D. Bond Breaker: Install bond-breaker strip in joint to be sealed on top of back-up material to prevent adhesion of sealant to back-up material; install per manufacturer's recommendations.
E. Sealant:
1. Mask or protect adjacent areas that are not to receive sealant.
2. Apply sealant in joints using a pressure gun with nozzle cut to appropriate size. Deposit sealant in a uniform and continuous bead with no gaps or air pockets.
3. Tool joints to require configuration with a blunt instrument as soon as possible after installation, but before sealant begins to skin over. Remove all masking materials immediately after tooling.
4. Apply materials only within manufacturer's specified application life period. Discard sealant after application life is expired or if prescribed application period has elapsed.
F. Joints shall have a minimum width to depth ratio of 2:1. Finished joint cross section shall have an hourglass shape.
A. Remove uncured sealant and joint filler with Reducer 990, xylene, toluene, or MEK. Remove cured sealant and joint filler by razor, scraping, or mechanically.
B. Remove all debris related to application of sealants from job site in accordance with all applicable regulations for hazardous waste disposal.
a. Joints and recesses between adjacent constructions and frames, sills, and sub-sills of louvers, and trim.
b Around penetrations in exterior walls.
c. Top edges of surface mounted counterflashing.