Department of National Defence
Future of In-Service Support
“FISS”
Update to Pennant UGM
Presented to Pennant UGM:June 16, 2015, OttawaStephen Bobyn - PM FISS DGMEPM
Outline – Future In-Service Support
DND FISS Program
“raison d'être”
Naval Materiel ISS Context
DND FISS Program Overview
A Word on Transition
• Department of National Defence needs to evolve naval in-service support for ships and equipment Program Management;
• future fleet ship acquisition programs (AOPS, JSS, CSC)
• limited available resources
• materiel support difficult to optimize & align to operational requirements
• GoC and Defence Reforms/Initiatives
• National Shipbuilding Procurement Strategy (NSPS)• In-Service Support separately competed from acquisition
• Defence Procurement Strategy (DPS)• Industrial Technical Benefits (ITB) and Value Proposition (VP)
• Deficit Reduction Action Plan (DRAP)• Pressure on resources
• Defence Renewal (DR)• Identify and re-invest efficiencies• SBCA – Strategic Business Case Anaysis
FISS Program – “raison d'être”
7
ShipLCMM
(SRD_383)
System,Equipment
LCMM(SRD_48)
“Level 1” Design Authority
(SRD_656)
Class Pgm Mgmt(SDD 4.1.1)
“Level 2”System Authority
(SRD_673)
Eqpt Pgm Mgt(SDD 4.1.1)
ValueManagement
“Level 3”ServiceDelivery
(SDD 4.1.4)
Optimise Integrated Program to achieveoutcomes
Drive enabling BehaviorFocus enabling resources
Rationalize andOptimise work
Optimise work efficiency
n
n
OutputsOutcomes“Optimize”
ServiceDelivery
(SRD 3.3.4)
“LCMM, Plan”
“Execute”
Support Solutions within the
naval materiel ISS Model
Naval Materiel ISS Model
ShipLCMM
(SRD_383)
System,Equipment
LCMM(SRD_48)
“Level 1” Design Authority
(SRD_656)
Class Pgm Mgmt(SDD 4.1.1)
“Level 2”System Authority
(SRD_673)
Eqpt Pgm Mgt(SDD 4.1.1)
“Level 3”ServiceDelivery
(SDD 4.1.4)
“Optimize”
ServiceDelivery
(SRD 3.3.4)
“LCMM, Plan”
“Execute”
Support Solutions within the
naval materiel ISS Model
FISS SRD Functional
Elements
Naval Materiel ISS Model
1. RCN has access to fit, reliable and available naval materiel assetsin the right quantity, mix and condition to enable the readiness and employment of naval forces to fulfill obligations of Defence Services
2. Public resources optimally utilized to deliver defence capability
3. Competent crew to operate and maintain equipment
Ref: FISS Statement of Objectives/Outcomes – System Requirements Document (SRD)
Future ISS – System Outcomes
Outcomes of the ISS system needs to continually be the aim of the all
system practitioners (GoC/Industry) as the system is implemented
Future ISS Program Overview
(Phase 1)
System Description Document (SDD)
System Requirements Document (SRD)
FISS Program PhasesFISS Program Phases (Phase 3 effective 1 June 2015)
Phase 1: Establish requirements for a Future ISS system;
Phase 2: Develop the design of the Future ISS system•Major Surface Combatants Enterprise Continuous Improvement (MSC CIP),•Victoria Class Enterprise (VIC Class CIP), •Minor Warships Enterprise (MWS CIP), •AOPS/JSS In-Service Support (AJISS CIP)•Potential new CIPs (MEPM Transition, NEM Transition, CSC);
Phase 3: Iterative development, implementation and institutionalization of the
design of Future ISS system elements, including improvements to existing ISS
arrangements.
• Integrate system design and implementation via FISS PMP
• Coordinate FISS CIPs
• Implementation by best-practice Managing Successful Programmes (MSP)
Blueprints and Tranches
• 3 Workstreams, to mitigate COI moving forward• FISS Program Management Support
• FISS System Detailed Design
• FISS System Implementation
FISS Governance Structure
FISS Program is governed by NaMMS MB•Chaired by DGMEPM as Chief Engineer for RCN
•Increasing appetite to add interdepartmental
governance (PWGSC, IC, Industry) as per DPS
ISS System Description Document (SDD)
Purpose
• The ISS SDD provides a description of the In Service Support (ISS) sub-system as it currently exists and is expected to operate within the Naval Material Management System (NaMMS)
• The ISS SDD is a subordinate document to the NaMMS SDD*
* the NAMMS SDD has a much larger focus than ISS sub-system within the NaMMS
• Informs development of the future ISS Systems Requirement Document (FISS SRD)
ISS System Description Document (SDD)
• Describes the ISS System Elements
• ISS Program Management
• Life Cycle Materiel management
• Technical Schedule management
• Service Delivery
• Ship
• Describes ISS System Behaviour
• Manage tensions between operational requirements, Design Intent,
limited resources
• Identifies both internal and external ISS System interfaces
• Identifies organizational elements required for ISS, including Industry
Future ISS SRD - Purpose
• Provides a common understanding of the FISS system, through a goal-based, flexible, non- prescriptive requirements framework
• lexicon is defined in the glossary
• The principal output of the FISS system analysis is the FISS System Requirements Document (SRD), which consists of the following elements:
• Statement of Outcome/Objectives (SOO);
• Statement of Requirements (SOR); and
• ISS System Requirements.
• Hierarchical framework with requirements traceability from the outcomes in the SOO down through the SOR and to the more detailed requirements in the SRD
16
Future ISS SRD Structure
• Holistic enterprise approach
• The FISS system design encompasses full spectrum
of design, management, training and execution of all
engineering and maintenance activity *
• Includes what sailors do onboard at 1st level through
to 3rd level delivery by FMFs *
• Includes Capital Program Design for Supportability
* MARE Journal No 74 – Commodore’s Corner, Summer 2014
Phase 2 Scope: Phase 3 Planning• Develop FISS Phase 3 Program Management Plan
• Purpose: Integrate FISS System Design with CIPs
• Develop FISS Communications strategy• Internal
• External (Industry)
• External (OGD > IC, PWGSC)
• Identify Emerging opportunities/scope• MEPM CIP - Organisation response to FISS
• Formation CIP - Organisation response to FISS
• CSC CIP > Design for Supportability during Acquisition
• Strategy and Activity• 3 Workstreams, to mitigate COI moving forward
• FISS Program Management Support
• FISS System Detailed Design
• FISS System Implementation
• Best-practice Managing Successful Programmes (MSP) Blueprints and Tranches• Reflect New Rolling Wave approach – integrate system design and implementation
• Identify organisational requirements to support FISS Program • Demand to Strat HR Board
• Identify organisational requirements to deliver FISS System Requirements• Processes, Org Structure, Capabilities, Enablers
• Input to Strat HR Board
• Phase 2 Deliverables : Phase 3 Program Management Plan
FISS Charter Milestones Phase 1
FISS Definition
2014 2015 2016 2017 2018 2019
Knowledge Repository
Dec 14 Apr 15
Phase 3
Detailed Sub-
System Design
FIS
S
Mil
est
on
es
DR
/MS
I In
itia
tive
M
ile
sto
ne
s
ISS
C M
ile
sto
ne
s (F
ISS
Co
nti
nu
ou
s
Imp
rov
em
en
t P
roje
cts)
Other Initiatives to be considered•MA&S Transformation•Mat DR 2.3•ILS Transformation•RCN DR 1.3•NEMSI•DPS / DPI
Phase 4
Implementation
Apr 16
Phase 2
System
Design .
FISS System Design
Baseline System Def’nProjectClosure Report
MEPM DRAP target 444 FTEs
MEPM Reorg (SHRM)
BPR ISS SDL
NMAE.G. NaMMs PfM and other frameworks
HCM DieselAward
AJISS RFP
MWAV Renewal Commences
VISSC Renewal
AJISS AwardJSSDelivery
AOPS Delivery
IPMS Award
LM2500Renewal
UnderwaterISSC RFP
FISS SRD
AJISS Recommendations
FISS Sub-SystemElement Design
FMFCB Strat Review target (34 positions) FMF @ 900 FTE (DCRCN)
DR 1.3a & NEMSI IOC
Mar 17
MGMC Approval to Rescind DAOD 3022 (ISSCF) and replace
with new Sustainment DAOD
AJISS CIP
MSC CIP
MWS CIP
VIC CLASS CIP Current VISSC Improvement
Phase 3: Evolving Design – Tranche-based Implementation to ISS Blueprint 2025
Halifax Design Agent Award
HCCS ISSC Award
MSC East and West
HCCS ISSC RFP
Phase 2 Scope: FISS System Design• Define FISS System Preliminary Design to meet SRD
• Recognises System Requirements Document (SRD) as ‘system of record’ for all requirements that need to be satisfied
• Systems Engineering approach - requirements traceability rigour to ensure all FISS Program design activity aligned to delivering SRD Requirements
• SRD migrating to DOORS early Phase 3
• Strategy/Activity for SRD End-Statements
• Phase 2 System Design Deliverables
• SRD updated with end statements and verification questions
• WBS for all work to complete ISS System
• Bi-Annual SDD/SRD revisions to incorporate Internal, and Industry Feedback
• Phase 3 Plan – format similar to MEPM SDD Suite Functional Program Plan (FPP Level)
Phase 2 Scope: MSC Enterprise CIP• MSC Enterprise Continuous Improvement Project (CIP) scope
• Identify and implement contract ‘Bundling’ opportunities for HFX Class ISS contract renewals
• Identify and implement organisational requirements to deliver FISS System Requirements
• Strategy and Activity• Identify appropriate contract opportunities that could be combined
• Create flexibility in ISS contract SOWS (PWS) and T&C for bundling
• Align all ISSC renewals to FISS SRD requirements as best possible • SRD Requirements leveraged to generate ISS SOW (PWS) requirements
• Create flexibility in ISS contract SOWS (PWS) and T&C for (PWS) for innovation
• Develop common contract clauses across ISS contracts
• Conduct DR 2.3 SBCA for ISS Contract renewals• FISS Provides some Naval Materiel Enterprise-Level elements for SBCA
• Other SBCA elements tailored to specific contract context
• Identify and implement organisational requirements to deliver FISS System Requirements
• Processes, Org Structure, Capabilities, Enablers
• Input to Strat HR Board
• Phase 2 MSC CIP Deliverables• FISS-MSC Class CIP Charter Required
• Key contracts identified for charter scope
• MSC Org requirements to be determined
Phase 2 Scope: VIC Enterprise CIP
• VIC Enterprise Continuous Improvement Project (CIP) scope• Develop Ship level LCMM iaw FISS SRD
• Collaborate via Integrated Project Team (IPT)
• Identify and implement organisational requirements to deliver FISS System Requirements
• Strategy and Activity• Leverage existing flexibility within current ISS contract
• Collaborate with ISS provider to determine scope, plan and implement Ship Level LCMM concept for VIC Class
• Identify and implement organisational requirements to deliver FISS System Requirements
• Processes, Org Structure, Capabilities, Enablers• Input to Strat HR Board
• Phase 2 VIC Class CIP Deliverables• FISS-VIC Class CIP Charter
• SM Org requirements to be determined
Phase 2 Scope: MWS Enterprise CIP
• MWS Enterprise Continuous Improvement Project (CIP) scope• Develop FISS functional element Technical Schedule Management (TSM)
• Collaborate via Integrated Project Team (IPT)
• Identify and implement organisational requirements to deliver FISS System Requirements
• Strategy and Activity• Leverage existing flexibility within current ISS contract
• Collaborate with ISS provider to determine scope, plan, and implement Technical Schedule Management concept for Minor Warships
• Identify and implement organisational requirements to deliver FISS System Requirements
• Processes, Org Structure, Capabilities, Enablers• Input to Strat HR Board
• MWS CIP Deliverables• FISS-MWS Charter to be drafted
• DGMEPM, PWGSC, Industry signatories
Phase 2 Scope: AJISS CIP
• AJISS - FISS Continuous Improvement Project (CIP) scope• Direct and support AJISS procurement process
• Direct/Support NSPO in development of: • AJISS PWS (SOW) for AJISS RFP• AJISS Evaluation Strategy and content
• Strategy and Activity• FISS Webinar 25 March 2015 in advance of AIWG 4 to socialise FISS SRD concepts
and terminology with industry• Mitigate COI by making FISS SRD Public Domain• Facilitates Industry comprehension of AJISS
• FISS support to AJISS-Industry WG 31 Mar 2015 (AIWG 4)
• AJISS Identified as DR 2.3 as Sustainment Initiative M Team Pilot (Dec 2014) to leverage SISC aid in removing barriers
• Currently determining total DR 2.3 scope for AJISS > Naval Materiel Enterprise - Level ‘SBCA’
• AJISS CIP Deliverables• FISS-AJISS CIP Charter required
• AJISS PWS and Evaluation Strategy aligned to FISS
• Draft PWS to Industry June 2015
FISS Ph 2 Deliverable SummaryDescription Deliverables
Phase III Program Mgmt Plan
Phase III PMP• Complete SRD work breakdown• Populate and resource MS Project• Schedule and set milestones
• PMP
• SRD:• MS Project:
DOORsRequirements tracking
• All SRD requirements in DOORs and managed
• SRD in DOORS
MSC EnterpriseCIP
Charter between FISS and MSC to identify key contracts, enterprise-level SBCA criteria
• Charter• Key contracts Identified• MSC Org requirements to be
determined
VIC Enterprise CIP
Charter between FISS/MEPM and Babcock utilizing VISSC contract to develop key enablers.
• FISS-VIC Class CIP Charter• SM Org requirements to be
determined
MWSEnterprise CIP
Charter between FISS/MEPM and SNC-Lavalin utilizing MWAV contract to develop key enablers
• Charter 1
AJISS CIP
Charter between MEPM and MPD detailing FISS input to AJISS
• Charter• AJISS PWS and Eval Strat aligned to
FISS
FISS Industry Engagement - Webinar
• Webinar to Launch FISS RFI to Industry 25 Mar 15• Triggered in part to mitigate COI
• Excellent collaboration PWGSC/OSME/AJISS/FISS
• Approximately 100/145 registrants logged into Webinar
• Not directly associated with any procurement of ISS
• Excellent Industry participation, based upon• Large spectrum of ISS providers participated (SME to ISS Primes)
• Initial feedback - good questions pertinent to ISS Model, COI, how to determine
boundaries between Industry/DND service providers
• Over 75 downloads of RFI Documentation
• 8 written responses to date
• Four 1on1s conducted
FISS Industry Engagement – RFI Questions
1. Did the Naval Materiel ISS model aid in the understanding of the concepts?
2. Are there functions or requirements missing, that should be modified, or added/deleted and do you foresee challenges to implementation for FISS Functional Elements:
• Program Management
• LCMM
• TSM
• Service Delivery
• Ships
• Other
29
ShipLCMM
(SRD_383)
System,Equipment
LCMM(SRD_48)
“Level 1” Design Authority
(SRD_656)
Class Pgm Mgmt(SDD 4.1.1)
“Level 2”System Authority
(SRD_673)
Eqpt Pgm Mgt(SDD 4.1.1)
ValueManagement
“Level 3”ServiceDelivery
(SDD 4.1.4)
Optimise Integrated Program to achieveoutcomes
Drive enabling BehaviorFocus enabling resources
Rationalize andOptimise work
Optimise work efficiency
n
n
OutputsOutcomes“Optimize”
ServiceDelivery
(SRD 3.3.4)
“LCMM, Plan”
“Execute”
•Model represents DR 2.3
Enterprise approach
•Support Solutions within the
naval materiel ISS Model
Naval Materiel ISS Model•Business Cases to
determine appropriate mix
of DND/Hybrid/Industry
•DR 2.3 SBCA
Question 2: What factors
should be considered in
determining boundaries?
Question 4: How does Industry
demonstrate competency at all 3 levels?
Question 3: How does DND retain/evolve
as an ‘Intelligent Client ?
Question 1: How as a GoC/Industry
team do we become ‘OEM’ as the
Ship Level LCMM?
Question 5: How will hybrid
delivery be executed, and why?
FISS RFI Feedback Q #1 Naval Materiel ISS Model
• 4 of 7 companies found the model useful
• 3 made no comment
• Key Recommendation:
• add an acquisition layer to the bottom of the model (foundation)
• acquisition is much higher on the value chain (significant influence on through life costs)
Acquisition Value Management(Design for Supportability)
ISS Value Management
ISS System – Functional Element Model
DfS is an input
from Ship
Acquisition to
the ISS System
DfS is an ISS
requirement
within Basis of
Design
*http://www.bmpcoe.org/library/books/mil-hdbk-338b/e82.html
Design for Supportability Principles
• Best manufacturing practice indicates early supportability decisions during the design process have a considerable impact on LCC*
Queenston-ClassHarry DeWolf-Class
CSC
70% of LCC Locked in
during Concept Design
FISS Phase 3 Scope:• FISS Program Management Support
• Coordination of ongoing design and implementation work• Expand all Class Enterprise CIPS to include:
• Class Program Mgmt, Ship Level LCMM, Service Delivery
• Expand CIP charters to include development and Implementation of all enablers• Design Intent, SA, Intelligent Client, Advance Contracting, Commercial Oversight, Accredited Engineering
Organisation, Recognised Organisation, Total System Responsibility, IPT, Secondment, Duty Holder, Tier 0
• PM (risk, scope, schedule, finance, deliverables)• FISS SRD requirements management• Stakeholder engagement and management• Communications and change management• Management of contracted support
• FISS System Detailed Design • Achieved end state of FISS SRD line items (tracked in DOORS)• Create SRD Recommendation/Review Database• Update the SRD Annually – next update NaMMS MB Dec 2015• Definition, process development, concept designs etc.• Design step change ‘tranches’ towards FISS 2025 Blueprint• Identify appropriate tranches linked to CIP Triggers, SRD requirements, and benefits
• FISS Implementation (MSP Blueprint ‘tranches’ via CIP triggers)• Process Implementation• ISS contracting, modifications, renewals • Changes to organizational structure• Org Strategic HR response to FISS
FISS Phase 3 Scope: Potential New CIPs• MEPM Transition CIP
• Develop FISS enablers iaw FISS SRD and Concept Papers• Design Intent, Ship LCMM, Adv Contracting Frameworks, Strategic Transfer of GoC capability, Intelligent
Client, SA, Commercial Oversight, AEO, RO, COI, TSR, IPT, Secondment, Duty Holder
• Identify and implement organisational requirements to deliver FISS System Requirements
• Processes, Org Structure, Capabilities, Enablers
• Input to Strat HR Board
• Formation NEM Transition CIP• Develop and approve CIP Charter
• Develop Technical Schedule Management iaw FISS SRD
• Develop and Implement Naval Materiel Enterprise Model Hybrid Enablers• “McEvoy Paper”
• Support FISS System Design and Implementation• Process Mapping, Service Delivery lines, AJISS CIP
• Identify and implement organisational requirements to deliver FISS System Requirements
• Processes, Org Structure, Capabilities, Enablers
• Input to Strat HR Board
• CSC Continuous Improvement Project (CIP)• Support CSC Design Contract SOW
• Design for Supportability
• Basis for Design, Design Intent
• Aligns to emerging Sustainment DAOD, DR 2.3 Sustainment SBCA, and CSC Sustainment Strategy
FISS Phase 3: CIPS & Transition• Phase 3 Planning surfaces Transition can start ‘now’
• Highlights need for Transition Plan for Capital Acquisitions
• Highlights need for Org Transition Plan for existing ISS Contract Renewals
• Similar Industry Response required
Functions
Typical tasks
Sub-phases of CLC
CLC Phases
CLC
Materiel Support Concept
Initial Materiel Support
Plan (MSP)
MSP within ILSP
Fleet & Materiel Maintenance Management
Acquisition Phase Sustainment Phase
Capability Life-Cycle (CLC)
Disposal
ILS Analysis & Plans ILS Sustainment
Needs Requirement Acquisition In-service
Materiel Disposal Action
Tran
siti
on
P
lan
ILS Domain
Australian Capability Life Cycle Model*
* (DMSP Log) Transition Planning Guideline
FISS Program – Summary for UGM
• FISS Program entering Phase 3� Phase 1 – SDD, SRD
� Phase 2 – Phase 3 Plan concept , System Design, and CIPs
• Phase 3 will include • Develop ISS System Blueprint 2025, and intermediate Tranches• Internal DND Org requirements• Industry response aligned to deliver FISS Outcomes within ISS Contracts
• FISS Phase 3 Planning surfaces “Transition” can start as early as Design for Support• CSC Program still has opportunity for DfS
• The CIPs represent initiation of Transition for Capital Program Acquisitions
• The CIPs represent organisational Transition to ensure delivery of FISS SRD
• FISS Program requires both GoC and Industry alignment to execute FISS SRD• SDD, SRD documentation is available to Industry via email: [email protected]
• There is appetite to consider Supportability as early as possible in Capital Programs (Defence Renewal)