Department of Civil Aviation (DCA) – Application for Installation of Tall Structure.pdf
description
Transcript of Department of Civil Aviation (DCA) – Application for Installation of Tall Structure.pdf
ATT-8
Department of Civil Aviation (DCA) – Application for Installation of Tall Structure
1. Application schedule: 1-2 months
2. Application for approval is required if:
(i) Construction of structure/building of any height is located within 15km radius from the nearest
airport;
(ii) Structure/building height is 100m & above and located 15km away from the nearest airport
3. Approval is not required and Consultant shall write in to DCA to inform about the construction
only, if:
(i) Structure/building height is less than 100m and located 15km away from the nearest airport
4. List of necessary documents to be submitted (under 1 submission):
(i) Cover letter from consultant
(ii) Locality & site plan
(iii) Drawings showing details of the proposed tall structure installation
(iv) Filled form
(v) Any other supporting documents as requested by DCA
Note: The duration of obtaining approval depends on the availability of the official and the
completeness of submitted documents.