External Service Delivery Plan – Agriculture, Food & Marine Sector
Department of Agriculture, Food and the Marine
Bord Iascaigh Mhara
Bord Bia
Marine Institute
Teagasc
External Service Delivery Plan
Overall strategy
In the context of the goals and objectives set out in the Department’s Statement of Strategy, to provide services to our customers in the most
efficient and effective way.
Proposed governance and resourcing
External Service Delivery is managed at a Divisional level throughout the Department and overseen by the Secretary General and
Management Advisory Committee.
Prioritisation process
Potential projects are assessed on a case-by-case basis.
Human resources
If an excess of human resources arises, the Department makes use of internal and external redeployment opportunities.
Background & current external service delivery
The Department has been, for many years, using external delivery extensively in a number of areas as outlined in the ‘Department specific’
functions listed below:
1. Registration & Movement
2. Disease Eradication
3. BSE & TSE
4. Single Payment Scheme
5. Certain Laboratory Work
6. Certain Veterinary Tasks
7. Animal By-Product Services
8. Forestry.
When combined with cross-Departmental functions, the total value of externally delivered services is almost €63 million, although not all of this
is paid directly by the Department.
The Department is increasingly looking towards external delivery for ‘Facilities Management’ and is currently in the process of renegotiating its
contract for the Backweston Campus. Cleaning and catering services across the Department’s extensive office network are almost exclusively
delivered externally.
The Department outsources some specialised IT functions but the trend in the past few years has been to in-source as much as possible in
order to cut costs. The Department has also become an IT shared services centre for outsourcing by other Government Departments and the
Department’s State Agencies. The Public Sector Reform Plan outlines other steps to be taken centrally to reduce the costs of ICT provision in
public bodies. The Department plans to continue using a judicious mixture of out-sourced and in-sourced delivery for IT.
Increasingly support functions are being delivered and considered for delivery outside the Department. The Department is proactively engaged
in the Shared Services Reform Programme with senior representation at Assistant Secretary level on the Payroll, Banking and Finance, HR
and Debt Management Shared Service Programme Boards. The Department was among the first phase of organisations that moved to the HR
Shared Services, Peoplepoint, earlier this year. The Department is participating in the review of debt management processes across the Civil
Service, including the processes related to the Rural Environmental Protection and Single Payment Schemes, with a view to determining the
most efficient delivery model. The Department’s representative chairs the Debt Management Project Board. The Department has also engaged
with DPER in various base-lining exercises including payroll and banking and finance.
Future external service delivery
As a general rule, the Department will seek to constantly review its delivery model for all activities, especially non-core and new activities. For
the purposes of considering current activities for external service delivery the following broad headings can be used; 1) Policy; 2) Scheme
administration 3) Farm inspections; 4) Regulatory inspections; 5) Meat inspections; 6) Disease Control; 7) Laboratories. The key
measurements used in considering whether activities are suitable for external delivery are cost and capability, i.e. whether it can be delivered
cheaper or better.
1) Policy: The core of any Government Department is policy and in terms of capability, it is not an area considered suitable for external
delivery.
2) Scheme administration: the Department has made significant progress in recent years improving the efficiency and effectiveness of
scheme delivery. In terms of suitability for outsourcing, the following factors need to be considered:
a) Capability; the various schemes are made up of different processes, many of which are unique to the Department and may not lend
themselves readily to external delivery. Currently the Department has unique capability in this area, especially in terms of adjusting
schemes arising from CAP reform. The Single Payment Scheme (SPS) is considered especially complex to deliver.
b) Risk; there is a very significant risk attached; would any benefits or savings justify the risk of disallowances to the State or payments not
being made?
c) Criticality and control; there is also an issue of how critical payment delivery is to the Department and whether outsourcing would cede
any control in this area.
d) Potential efficiencies; it is likely that further efficiencies in scheme delivery can be made in future; the increasing dependence of the
main schemes on the LPIS database, which is likely to be deepened by CAP reform, may point to an amalgamation of the
administration of the main schemes.
External service providers will say that issues such as capability and control can be addressed and that risk can be managed. However in
this context the recent KPMG report on the SPS commented, ‘Outsourcing to a third party; Not appropriate for DAFF at present due to
uncertainties in relation to long term future of SPS payments, and one off investment required to set up this model.’
While whole-scale outsourcing may not currently be an option, there may be elements within scheme administration that could be
considered, elements like those already delivered externally (i.e. the digitising of land parcels and the provision of remote sensing imagery).
3) Farm inspections: The Department has been pursuing a programme of reform including driving efficiencies and increased flexibility across
its inspections via the rationalisation of staffing, reform of structures and the application of ICT solutions. The Department has placed an
increasing emphasis on the application of risk assessment and audit based inspection methodologies, which is allowing for more effective
deployment of resources, while effecting cost reductions. In its ‘Integrated Reform Delivery Plan 2013’, the Department committed to a
review of the ‘Delivery of Inspections’ including the consideration of suitability for external service delivery.
It could be argued that farm inspections are suitable for external delivery in terms of being discreet, measurable blocks of work with fairly
standard processes and outcomes. There is evidence of capability in the market, i.e. the inspections for Bord Bia’s Quality Assurance
Scheme are delivered externally, although there may be issues with the more complex inspections that the Department has to fulfil.
Changes in current practice would bring a financial and reputational risk; see the reasons outlined at 2 (a-d) above. In addition, the
Department currently has the qualified and trained human resources to deliver the inspections. If the Department can no longer deliver its
inspection requirements from within its existing resources, and having exhausted all internal redeployment opportunities, external delivery
(perhaps via piece-rate and short-term contractual arrangements) should be re-examined. Moves to externally deliver inspections may also
have the potential to address some current issues around seasonality and flexibility.
4) Regulatory inspections: Regulation (EC) No 882/2004 requires each Member State to prepare a single ‘Integrated Multiannual National
Control Plan’ (MANCP). This plan must contain general information on the structure and organisation of the systems of official controls in
the areas of Food Law, Feed Law, Animal Health Rules, Animal Welfare Rules and Plant Health Rules. Regulation (EC) No 882/2004 is
currently being reviewed at EU level and the Department is currently engaged across the five areas above.
The Department is responsible for a significant number of specialist areas under the MANCP and this is likely to increase after the current
review. Due to the specialised and regulatory characteristics of these inspections, they would be particularly complex to deliver externally.
Again the application of risk assessment and audit based inspection methodologies, which is allowing for more effective deployment of
resources, is effecting internal cost reductions and inspections are being delivered within existing resources. However future demands may
put pressure on this current capability. If the Department can no longer deliver its inspection requirements from within its existing resources,
and having exhausted all internal redeployment opportunities, external delivery (perhaps via piece-rate and short-term contractual
arrangements) should be re-examined. Moves to externally deliver inspections may also have the potential to address some current issues
around seasonality and flexibility.
5) Meat inspections: The meat inspection service already relies heavily on external delivery via temporary veterinary inspectors. A lean
review of the Meat Inspection Service as it operates in processing plants is being finalised and is expected to recommend how greater
efficiencies may be leveraged, while ensuring that the Department continues to meet its regulatory obligations. An increasing emphasis on
the application of risk assessment and audit based inspection methodologies will allow for more effective deployment of resources, while
effecting cost reductions for industry. This work must be seen in the context of Food Harvest 2020 and food safety, including traceability
and transparency, being a source of competitive advantage for Irish meat.
6) Disease Control: As described below the TB and Brucellosis Eradication Programmes make extensive use of the testing of animals by
private veterinary practitioners (PVPS). The Department remains open to further use of PVPs and has recently moved the administration of
pet passports to the private sector.
7) Laboratories: Certain types of testing are being delivered externally. A review of the Regional Laboratory Structure is completed to draft
stage. This review identified the need to have a clear central strategic vision for the development and deployment of the Department’s
Laboratory Service as a whole. As a consequence the MAC has mandated a group to draw up a future vision statement for the Laboratory
Service.
Functions currently delivered externally
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Cross-Departmental Function – Facilities Management
1 Catering 4 buildings: Dublin, Portlaoise, Wexford
& Clonakilty
Local Yes HQ Ag. Hse Dublin
€15,000 - Department
pays premises costs only.
Services
Division
2 Cleaning 35 buildings countrywide: Cost vary in
buildings due to individual requirements
and input levels
Local and
Regional
Yes €789,092 Services
Division
3 Security 11 buildings: Services vary but include
lockup, key-holding & alarm call out.
Local and
Regional
Yes € 315,450 Services
Division
4 Security, maintenance, cleaning,
landscaping, transport, reception
catering and portering.
Current aggregated contracts for
Backweston Labs [Redacted]
Local Yes €1,892,060 Services
Division /
Laboratories.
5 Parking Parking services at Rossaveal Fishery
Harbour Centre are delivered by an
outside company
National Yes Contract is on a revenue-
sharing basis.
Sea Fisheries
Administration
Division
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Cross-Departmental Function – Information and Communication Technology
1 Help Desk & Deskside Support
2 System support 1,162,864.26 Information
Management
& Technology
Division (IMT)
3 System Integration
4 Network Administration
5 Print Service Management
6 Application Development 9,129,636.00 IMT
7 Application Testing
8 Application Management
9 Hosting
10 Cyber Security 32,133.77 IMT
11 IT Project Management 13,099.50 IMT
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
12 IT Audit Provision of IT Audit technical support to
Department’s IT Audit team.
National IT coverage
within this
Department
but a cross
Departmental
framework is
being put in
place for
audit support
services.
Up to €73K per annum Internal Audit
Unit
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Departmental Specific Function – Registration & Movement
1 Registration of bovine births, the
issuing of bovine passports and
the handling and processing of
notifications in relation to farm to
farm bovine movements and on-
farm deaths.
Handle, scan and data process circa
1.7million items of incoming post
Print and issue circa 3million items of
outgoing post within specified time
limits.1
Operate a call centre capable of
handling in excess of 100,000 phone
calls per annum.
National No – Unique €5.95million2 AIM Division
1 Bovine passport or error letter to be posted within 2 working days of receipt of a paper application.
Bovine passport, replacement passport or imported animal passport to be posted within 1 working day of receipt of an electronic file.
Certificate of compliance applications received by post or fax before 15:00 on a working day will result in a cert of compliance or an error letter being posted the same day.
Certificate of compliance applications received by post or fax after 15:00 on a working day will result in a cert of compliance or an error letter being posted the next working
day.
All movement and on-farm death notifications are processed within one working day of receipt.
2 This is the 2012 figure. There is a tender process on-going which should reduce the cost.
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
2 Supply of Bovine Animal Tags
and Birth registration
documents3
Production and delivery of
approximately 2million Tag Sets and
approximately 400,000 replacement
tags per annum to keepers.
New tag sets must be issued within 15
working days of receipt of a valid order
from the keeper.
Replacement tags must be issued within
3 working days of receipt of a valid
application for replacement tags from
the keeper
National No – Unique In the region of €5.8m.
This is an estimate as the
Dept does not pay for the
tags. Payments for tags
are made to the supplier
directly by keepers
AIM Division
3 Payment for the service delivered under this contract is made by herd keepers. The Department does not pay for the tags.
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
3 Handling, Processing and
verification of pig movement
notifications
All pig movements to and from the circa
2,500 pig holdings within Ireland are
obliged to be notified to the Department.
The external contractor receives,
reconciles, processes and notifies circa
28,000 reconciled movements annually
to the Department’s AIM database.
National No - Unique € 144,000 Animal Health &
Welfare Division
4 Issuing of Pet Passports Pet Passports are purchased from the
Department and issued directly by
Private Veterinary Practitioners to pet
owners. Circa 7,200 per annum.
National No – Unique No contract as the
process has been moved
in its entirety to the private
sector. This has resulted
in a significant staff saving
for the Department.
Animal Health &
Welfare Division
Departmental Specific Function – Disease Eradication
1 Testing of animals by private
veterinary practitioners (PVPS)
under the TB and Brucellosis
Eradication Programmes (DAFM
paid testing represents 25% of
volume of testing undertaken –
the balance paid for by farmers).
DAFM pays a fixed fee on a fee per test
basis (rate of fee set out in legislation)
Approx. 930 PVPs
1.77m DAFM paid tests.
National No - Unique € 8m approx ERAD Division
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
2 Badger Capture Programme:
contract with [Redacted]for
badger capture, culling and
vaccination duties under the TB
Eradication Programme.
[Redacted]
Fixed hourly rate based on number of
badgers captured/vaccinated.
Operatives work on a part time basis
over a 12 day cycle supervised by
DAFM staff.
[Redacted]operatives are required to
own, and have a licence to use a .22
calibre rifle
National No – Unique €3m ERAD Division
3. Contract with the [Redacted] for
Badger Post Mortem
Assessment. The PM procedure
includes,
(a) assessment of badger
carcase/ trauma score,
(b) harvesting specified
lymphatic tissue
Collection of badger carcasses from
various locations countrywide, delivery
to[Redacted]for PM and the disposal of
the carcasses following post mortem
assessment.
[Redacted]
[Redacted]
National No - Unique €0.35m (includes
collection and delivery of
badgers, PM assessment,
disposal of badger
carcasses).
ERAD Division
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
(c) reproductive assessment
(d) preparation of histology
slides.
Departmental Specific Function – BSE & TSE
1 Testing for BSE and Scrapie 80,000 tests National No - Unique €1.25m Milk and Meat
Hygiene & Animal
By-Products
Division
2 Collection and Rendering of
Fallen Bovines over 48 months
75,000 animals National No – Unique €5.8m Milk and Meat
Hygiene & Animal
By-Products
Division
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Departmental Specific Function – Single Payment
1 Maintenance of Land Parcel
Identification System (LPIS)
spatial database.
Map Digitisation of Land Parcel
Identification System (LPIS) based on
annual submission of mapping change
requests from approximately 25,000
SPS applicants.
Digitisation of land parcels involving
2,000 SPS applicants following ground
eligibility inspections.
Digitisation of 300,000 land parcels as a
result of LPIS review.
Maintenance of LPIS spatial database
involving 1.1 million land parcels.
Ongoing work includes re-digitisation of
land parcels and preparation of quality
reports required under EU regulations.
National No - Unique € 2m Single Payment
Unit
2 Remote sensing eligibility
inspections of all EU direct
payment schemes.
Undertaking [Redacted]remote sensing
(satellite) eligibility inspections and
National
No – Unique [Redacted] Single Payment
Unit
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
updating the LPIS database using the
findings of inspections.
Departmental Specific Function – Laboratories
1 Outsourcing of certain analytical
work.
Analysis of samples for a range of very
specific analytes which are not currently
part of the analytical scope of DAFM
Laboratories.
€92k is
centrally
administered
by the VPHR
Laboratory on
behalf of
Veterinary
Medicines
Division.
Specific to
the
implementati
on of EU
Regulations
and not x
departmental
.
€92k in 2012, €92k in
2013.
In addition Veterinary
Medicines Division
outsource work to the
[Redacted]
(€250k pa) and other
external labs approx.
€60k pa.
Veterinary
Medicines
National Residues
Control
Programme
(NRCP)
2 Outsourcing of the GMO NRL
functions and obligations.
Delivery of specific GMO analytical
functions.
Managed by
the Plant
Health
Laboratory
Specific for
compliance
with EU
regulations.
€15k pa Pesticide, Plant
Health and Seed
Testing
Laboratory
Division
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
3 Occasional requirements to
outsource specific analytical
tests where there is no in house
capacity to deliver at present.
This may relate to
- Botulism bio assay and
elisa testing
- DNA fingerprinting of
fallen stock
- Etc as the need arises
On an as required basis. The
requirement for these tests are sporadic
and in general are not predictable.
Managed as
the need
arises by the
relevant
Division
Relevant
Laboratory
Division
Departmental Specific Function – Veterinary Tasks
1 Meat Inspection Services Temporary Veterinary Inspectors (TVI’s)
who are private veterinary practitioners
assigned on a roster basis to slaughter
plants.
National No - Unique Approx € 16.25m in 2013 Milk and Meat
Hygiene & Animal
By-Products
Division
Departmental Specific Function – Animal By-Product Services
1 Laboratory testing services Necessary testing for GTH, insoluble
impurities, etc which cannot be carried
out in-house
National No – Unique €693 to date in 2013 Milk and Meat
Hygiene & Animal
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
By-Products
Division
2 Printing of commercial and other
documents
Printing of commercial document books,
record books, etc necessary for plants to
maintain the required records
National No – Unique €9240 to date in 2013 Milk and Meat
Hygiene & Animal
By-Products
Division
3 Translation services Translation of an Italian document
requested by the Vets – ABP being sent
from a rendering plant in ROI to Italy
National Yes €183.20 Milk and Meat
Hygiene & Animal
By-Products
Division
4 Training services Cre training National No – Unique €541.20 Milk and Meat
Hygiene & Animal
By-Products
Division
5 Printing of Animal Health
Certificates
25,000 certificates printed annually Local No – Unique €12,000 - €24,000 Milk and Meat
Hygiene & Animal
By-Products
Division
Departmental Specific Function – Forestry
No. Action/Deliverable Detailed Description (define scope,
volumes, headcount)
Level at
which
contract
administered
(eg. Local,
Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
1 Establishment a network of bait
traps and pheromone lures at 52
locations nationwide
The Forest Service is responsible for
implementing the forestry aspects of the
EU Plant Health Directive, Council
Directive 2000/29/EC of 8 May 2000 on
protective measures against the
introduction into the Community of
organisms harmful to plants or plant
products and against their spread within
the Community. These bait traps and
pheromone lures are required to meet
Irelands obligation under the regulation
Regional
National
No - Unique € 25,000 Forest Service
Inspectorate
2 The provision of a forest
pathology diagnostic service to
the Forest Service.
This involves laboratory sampling and
analysis of approximately 50-75
submitted samples. Please note that
these figures are indicative and are non-
binding.
Currently the most expensive samples
are €713, but many are less than that. In
reality the sample number is likely to be
under 50.
National No – Unique €35,000 Forest Service
Inspectorate
Areas currently being tested for External Service Delivery or in the process of being moved to external delivery
No. Action/Deliverable Detailed Description (define scope,
headcount, volumes, current data quality)
Key Steps for
Implementation
and Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsible
Owner
Cross-Departmental Function - Finance/Business Processes
Payroll
Financial Management
Banking
Debt Management
The Department is proactively engaged in the
Shared Services Reform Programme with
senior representation on the Payroll, Banking
and Finance, HR and Debt Management,
driven by Project Boards reporting to the
Reform Delivery Office.
Cross-Departmental Function – Inspections and enforcement, licensing
The Department is
currently evaluating the
feasibility and risks
associated with
outsourcing the land
eligibility and cross
compliance inspections
under the SPS.
Confirm the eligibility and area of land declared.
Confirm compliance with a range of cross
compliance requirements in respect of the
environment, food safety, animal traceability
and animal welfare
Inspection levels:
Land- 5% of applicants using remote sensing
and on the spot ground verification checks.
3% of bovine and ovine applicants
Feasibility now
being considered.
End Qtr 4, 2013
No No NA Integrated
Controls
Division
No. Action/Deliverable Detailed Description (define scope,
headcount, volumes, current data quality)
Key Steps for
Implementation
and Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsible
Owner
1% for other cross-compliance elements.
Cross-Departmental Function – Information and Communication Technology
Managed Print Service Move to 100% Managed Print Service for
DAFM and our shared services offerings. We
currently have a semi-Managed Print Service
which has accrued savings since 2010.
Preparing a tender
to the Framework
for the Supply of
Managed Print
Services (SS
0067/10)
Background data
being collated.
Proposed
commencement in
Q1 2014 for 4 + 1
years
Yes Yes € 300,000
over the
term of
the
contract
Services
Division
No. Action/Deliverable Detailed Description (define scope,
headcount, volumes, current data quality)
Key Steps for
Implementation
and Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsible
Owner
Departmental Specific Function – Import controls
Import controls - the
provision of unloading /
loading and handling
during physical veterinary
checks of consignments
of products of animal
origin at Dublin port BIP
The unloading and handling of consignments
during physical checks is done at present by
the landlord of the premises at which Dublin
port Border Inspection post (BIP) is located.
(Random physical checks are mandatory at a
frequency set under Commission Decision
94/360/EC). The fee is set by and paid directly
to the landlord by the importer [Redacted]
Performing the function this way has been
deemed inappropriate and unsatisfactory.
Estimated cost €60-€70K - to be recouped in
full via levy to be applied to all consignments in
an equitable manner
In the process of
implementing an
increase in fees
for veterinary
checks at the BIP.
Tender document
being prepared –
will go to the
market in Qtr 1,
2014
Yes Yes N/A
NDCC &
Veterinary
International
Division
BIM External Service Delivery Plan
Overall strategy
What is the objective? Reduction in in-house operating costs through utilisation of tendered, external service providers, provided same can be
delivered in an efficient and timely manner. This is especially important in light of both reduced headcount, its associated impact of loss of
corporate memory and overall budgetary constraints.
Proposed governance and resourcing
How does it fit with the shared services governance, (existing) larger reform governance ?
It should fit in with the overall strategy of the shared services governance programme currently under way.
How will projects be resourced and managed?
We will need some additional, external resources, in the short-term only, which may result in some additional short-term cost spikes but will
quickly lead to overall reduced recurring costs.
Prioritisation process
How are your potential projects prioritised for action (headcount reduction opportunity, expected saving, readiness, etc) ?
BIM’s headcount has reduced from 178 to 125 over the last 5 years. We are now at critical headcount levels to deliver the seafood support
service which we are mandated to do. We will need to embrace the external and shared service options as soon as they are working and proven.
Human resources
What is the strategy to deal with excess human resources? (Redeployment, VR/VER, offer TUPE transfer, etc)
Our only real options to deal with any further headcount reduction is either retirement or redeployment. The redeployment option, we feel, has
yet to deliver on its full potential.
Functions currently delivered externally No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Cross-Departmental Function – Facilities Management 1 Catering N/A N/A N/A
2 Cleaning Cleaning Contracted
externally
Centrally by BIM Yes €18,038
€762 cleaning supplies
[Redacted]
3 Security Security System—remote
Monitoring
Centrally by BIM Yes €2,786 Monitoring
€595 Intruder Alarm Maintenance
€301 keyholding
€27,888 Janitorial/Security--W39 Ltd
€27,744 Janitorial/Security--Lisneys
[Redacted]
4 Buildings maintenance Lisneys Centrally by BIM Yes €12,985 General Maintenance ,leaks,
painting, fire extinguishers, replacing
radiators, blockages, etc
€12,879—Lisney Management fee
[Redacted]
5 Reception N/A Centrally by BIM No [Redacted]
6 Maintenance Ad hoc requirement,
supplied by external
contractors
Centrally by BIM Yes €1,383 window cleaning
€5,201 janitorial supplies
€2,643 waste disposal
€481 pest control
€1,178 external landscaping
€3,700 fem hygiene
€1,575 water treatment
[Redacted]
7 Mech and elec Ad hoc requirement,
supplied by external
contractors
Centrally by BIM Yes €2,262 electrical maintenance
contract
€1,260 fire alarm maintenance &
monitoring
€2,277 lift maintenance
€1,834 mechanical maintenance
contract
€865 automatic doors/gates
maintenance contract
[Redacted]
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Cross-Departmental Function - Finance/Business Processes
1 Debt collection N/A N/A Yes N/A
2 Billing All fully automated—no
real scope for external
efficiency
N/A Yes N/A
3 Records management/scanning/filing All fully automated—no
real scope for external
efficiency
N/A N/A N/A
Cross-Departmental Function – Information and Communication Technology
1 Help Desk & Deskside Support Triliogy Technoligies —
Managed Service for
Helpdesk and Level 1 & 2
IT Support
Locally by BIM – managed
by IT Manager
Future partial
possibility
assuming
appropriate
SLA.
€78,818 [Redacted]
2 System support Various specialised
contracts in place with
different third parties.
Locally by BIM – managed
by IT Manager Partial
possibility
depending on
expertise
available
Total External Support
approximately €60,000 [Redacted]
3 System Integration N/A N/A [Redacted]
4 Network Administration N/A Locally by BIM – managed
by IT Manager Partial
possibility
depending on
expertise and
SLA available
[Redacted]
5 Print Service Management N/A N/A Yes [Redacted]
6 Application Development N/A No current projects N/A Yes [Redacted]
7 Application Testing N/A N/A N/A [Redacted]
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
8 Application Management N/A N/A No, local
knowledge
required
[Redacted]
9 Hosting Internal and External (BIM
website hosted y DAFM)
Local No further
requirement
[Redacted]
10 Cyber Security N/A N/A Partial
possibility
depending on
expertise
available
[Redacted]
11 IT Project Management N/A N/A Partial
possibility but
local
knowledge of
business
required
[Redacted]
12 Voice Comms Voice (fixed and mobile)
and data communications
Local Yes (already in
place)
€200,000 [Redacted]
Bord Bia External Service Delivery Plan Template
Overall strategy
What is the objective? e.g Reduce costs by €x by delivering services externally in a cost effective manner. Deliver current (or new) service with
reduced headcount.
Bord Bia’s mission is to drive through market insight and, in partnership with industry, the commercial success of a world class Irish food, drink
and horticulture industry. To deliver value for money for expenditure is a formal Bord Bia strategic objective. Cost efficiencies have reduced
non-pay operating costs by 42% since 2008.
Bord Bia uses external resources where they offer value and can release internal resources to priority areas. Cleaning, security, maintenance and
overseas payroll are outsourced. External resources are also engaged for programme delivery – e.g. Quality Assurance (QA) farm inspections
and the national roll-out of Food Dudes/school fruit scheme. The carbon footprinting of farms (a world first) has been added to the beef QA
scheme at no extra cost to the producer.
While managing a staff reduction programme, Bord Bia has supported change in five key areas: the development of Origin Green, the new
national umbrella food brand, with verifiable sustainability and quality credentials at its core; education initiatives to enhance industry leadership
and management capability; facilitation of co-opetition strategies to increase the capacity of food, drink and horticulture companies; innovation
to enhance growth and differentiation; and Food Works, an innovative initiative by Bord Bia, Teagasc and Enterprise Ireland to encourage
entrepreneurship through high-potential and strategic scale-ups.
Bord Bia continues to examine its cost base and resource allocation, and to evaluate alternatives to in-house delivery in order to ensure the most
cost-effective solution.
Proposed governance and resourcing
How does it fit with the shared services governance, (existing) larger reform governance?
How will projects be resourced and managed?
Bord Bia's experience of partnership and external service delivery underpins initiatives to support delivery of Food Harvest 2020 targets- €12
billion in food, drink and horticulture exports by 2020 (2013 = €9 billion). Bord Bia promotes innovative ways of developing industry financed
initiatives such as the Sustainability and Dairy QA Scheme; the recruitment of ten experienced, talented executives, in partnership with industry
as Ambassadors to build awareness of Origin Green with world-leading companies; the development of a food hub, a shared office facility that
enables Irish food and drink exporters to cost-effectively establish a presence in Shanghai, and benefit from shared services, market knowledge
and research; the Food Export Graduate and Fellowship Programmes which place graduates with companies and overseas to develop the export
capability of Irish food and drink companies.
Prioritisation process
How are your potential projects prioritised for action (headcount reduction opportunity, expected saving, readiness, etc)?
While achieving headcount reductions, Bord Bia continually looks for new ways to collaborate, for example, with Fáilte and Tourism Ireland to
attract overseas visitors; collaboration with Dublin City Council and the Temple Bar Traders Association to host Tail-Gate Event for the Navy
Notre Dame American Football game in Dublin last year; collaboration with the UK on three-year EU-supported mushroom campaign, and with
France and the UK on lamb promotion; collaboration with County Enterprise Boards to build the capabilities of Irish food and drink companies,
and with the overseas functions of Enterprise Ireland and Embassies in the provision of office accommodation et al; etc.
Human resources
What is the strategy to deal with excess human resources? (Redeployment, VR/VER, offer TUPE transfer, etc)
With a head office in Dublin and 10 overseas offices, Bord Bia does not have excess resources but continually reviews staff numbers (currently
90 whole time equivalent) to ensure priority service delivery to clients and stakeholders, while completing major projects and events. Staff have
been re-deployed to enable Bord Bia extend its reach to new markets in Scandinavia and Africa and to continue service to industry following
staff departures. Considerable flexibility has been demonstrated by employees in addressing the changing requirements of the business and this
adaptability will be relied upon in meeting future challenges.
The agility to pull together expert cross functional teams, through re-prioritisation and management of workload is both essential and necessary
to meet evolving priorities.
Functions currently delivered externally No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Cross-Departmental Function – Facilities Management 1 Catering 1 building:
Food Centre (Showcases,
events, workshops, brand
forum for Clients, Industry
Groups, overseas visitors,
etc); Canteen (Staff)
Local No - unique € 158,000 [Redacted]
2 Cleaning 1 building:
1,300 square metres
Local Yes € 47,000 [Redacted]
3 Security 1 building: Local Yes € 5,000 [Redacted]
4 Buildings maintenance Various Local Yes €13,000 [Redacted]
5 Reception In-house (1 WTE) Local No – local €0 [Redacted]
6 Maintenance Local No – local [Redacted]
7 Mech and elec Air Conditioning Local No – local €7,000 [Redacted]
8
Cross-Departmental Function - Procurement/logistics
1 Procurement In-house (1 WTE) Local No – local [Redacted]
Cross-Departmental Function - Human Resource 1 Payroll Payroll:
Irish: In-house (0.1 WTE)
Overseas: External delivery
Local No – local
€0
€68,000
[Redacted]
2 Training External delivery as reqd Local No – local [Redacted]
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
3 Recruitment In-house (1 WTE) Local No – local €0 [Redacted]
Cross-Departmental Function - Finance/Business Processes
1 Debt collection In-house (1 WTE) Local No – local €0 [Redacted]
2 Billing In-house (0.5 WTE) Local No – local €0 [Redacted]
3 Records management/scanning/filing In-house Local No – local €0 [Redacted]
Cross-Departmental Function – Inspections and enforcement, licensing
1 Quality inspections Quality Assurance Schemes
audits, etc
Local – outsourced by
public tender.
No – unique €4,340,000 [Redacted]
Cross-Departmental Function – Information and Communication Technology
1 Help Desk & Deskside Support Local Not yet –
Large scale [Redacted]
2 System support Various software support Local No - Unique €35,800 [Redacted]
3 System Integration Local Possibly
4 Network Administration Two on-site and remote Local Yes €75,000
5 Print Service Management Managed print service Local Yes €36,900 [Redacted]
6 Application Development System for Quality
Assurance Schemes
Local No – Unique €150,000 [Redacted]
7 Application Testing Local Not yet –
Large scale
8 Application Management Local Not yet –
Large scale
9 Hosting Local Not yet –
Large scale
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
10 Cyber Security Penetration Testing Local Yes €12,294 [Redacted] 11 IT Project Management Local No – local
Areas currently being tested for External Service Delivery or in the process of being moved to external delivery No. Action/Deliverable Detailed Description (define
scope, headcount, volumes,
current data quality)
Key Steps for
Implementation and
Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsible
Owner
Nil
The Marine Institute External Service Delivery Plan
Overall strategy
What is the objective?
To deliver services in a cost effective way with reduced headcount, and without increasing headcount.
Proposed governance and resourcing
How does it fit with the shared services governance, (existing) larger reform governance?
This fits well with the Government policy of outsourcing where possible.
How will projects be resourced and managed?
Outsourced projects only taken on where there is adequate internal management to ensure effective operation and value for money.
Prioritisation process
How are your potential projects prioritised for action (headcount reduction opportunity, expected saving, readiness, etc) ?
Funding availability with adequate in-house management resource to manage it, couple with value for money opportunities from the market
Human resources
What is the strategy to deal with excess human resources? (Redeployment, VR/VER, offer TUPE transfer, etc)
The Marine Institute has increasing service delivery requirements and therefore has no excess human resources
Functions currently delivered externally No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Cross-Departmental Function – Facilities Management 1 Catering 1building – Oranmore
headquarters 30,000 sq ft
including 54 laboratories
Centrally by the Marine
Institute
Unsure € 26,000 [Redacted]
2 Cleaning 1– Oranmore headquarters
30,000 sq ft including 54
laboratories
2 – Harcourt St
3 – Newport
Centrally by the Marine
Institute
Unsure 1 - €67,358
2- € 6,000
3- €4,171
[Redacted]
3 Security 1 building has security for 9
hours per day weekends and
bank holidays only
Centrally by the Marine
Institute
Yes € 36,521 [Redacted]
4 Buildings maintenance 1 building for 17 hours per
week
Centrally by the Marine
Institute
Unsure € 30,781 [Redacted]
7 Mech and elec 1 building with one full time
engineer and technical
support
Centrally by the Marine
Institute
Unsure €66,666 [Redacted]
8 Landscaping 1– Oranmore headquarters
2 – Newport
Yes 1- €15,776
2- €13,239 [Redacted]
Cross-Departmental Function - Finance/Business Processes
4 Internal Audit Services Centrally by the Marine
Institute
Yes €30,000 [Redacted]
Cross-Departmental Function – Inspections and enforcement, licensing
1 Residues Testing Implementation of the
Residues Directive – testing
of residues in farmed fish
Centrally by the Marine
Institute
Possibly –
very
specialised
€210,624 [Redacted]
2 E.coli Testing Outsourced microbiology
test laboratories to provide
E. coli testing services for
Centrally by the Marine
Institute
Possibly –
very
specialised
€80,947 [Redacted]
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
classification of shellfish
harvesting areas
3 Shellfish Shucking Dissection of shellfish
samples prior to bioassay
for food safety testing
Centrally by the Marine
Institute
No too
Specialised
€81,312 [Redacted]
4 Molecular Biology Expertise
Outsourcing of molecular
biology expertise
Centrally by the Marine
Institute
No too
Specialised
€65,340 [Redacted]
5 Post Sampling Note: 50% of this cost is
met from EU DCF funding
Centrally by the Marine
Institute
No too
Specialised
€163,000 [Redacted]
Cross-Departmental Function – Information and Communication Technology
1 Help Desk & Deskside Support Includes specialised support
for research vessels and
scientific equipment
Centrally by the Marine
Institute
No – local
specialised
service
required for
labs, vessels,
etc.
€160,000 [Redacted]
4 Network Administration WANs connecting Newport
(100Mb) and Harcourt
Street (100Mb) to Oranmore
and externally (1Gb)
External networks managed
by HEAnet
No – HEAnet
manages
contracts
€40,000 [Redacted]
6 Print Service Management Currently outsourced Centrally by the Marine
Institute
Possibly –
low-cost
solution
currently in
place
TBD [Redacted]
7 Hosting Data hosting by HEAnet,
some website services
HEAnet managed shared
service for research
organisations. Very low
cost.
Already a
shared service
managed by
HEAnet
€2,000 [Redacted]
8 Cyber Security An external IT-security
audit is carried out every 3
years.
Centrally – by Marine
Institute
Possibly, but
small-scale
€2,500 [Redacted]
Departmental Specific Function – Research Vessel Management
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
1 Research Vessel Management Operation of 2 research
vessels and 1 Remotely
Operated Vehicle includes
provision of ca. 60 staff and
managing a budget of ca.
€7m
Centrally by the Marine
Institute
No - Unique € 215,000 [Redacted]
Areas currently being tested for External Service Delivery or in the process of being moved to external delivery No. Action/Deliverable Detailed Description (define
scope, headcount, volumes,
current data quality)
Key Steps for
Implementation and
Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsi
ble
Owner
Nil
Teagasc External Service Delivery Plan
Overall strategy
What is the objective? Deliver current (or new) service with reduced headcount and to acquire specific skills.
Proposed governance and resourcing
How does it fit with the shared services governance, (existing) larger reform governance ? Teagasc as a Non-commercial State Sponsored body
is not in a position to benefit to benefit from current shared services initiatives which are available only to central government bodies.
How will projects be resourced and managed? Projects will be resourced and managed internally.
Prioritisation process
How are your potential projects prioritised for action (headcount reduction opportunity, expected saving, readiness, etc) ? Prioritised by
readiness. Where a situation arises where a gap is created due to retirement etc. this will also be prioritised.
Human resources
What is the strategy to deal with excess human resources? (Redeployment, VR/VER, offer TUPE transfer, etc). Teagasc do not have excess
resources. We are however over our ECF number and to date Teagasc have lost 30% of staff. Redeployment and VRS are being used to achieve
compliance with the ECF. 12 staff have been externally redeployed to date.
Functions currently delivered externally No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
Cross-Departmental Function – Facilities Management 1 Catering 7 Sites National Yes € 216,000 Head of
Corporate
Services
2 Cleaning 44 sites (some with multiple
buildings)
Local Yes
€485,000 None – locally
managed
3 Security 6 sites have outsourced
some aspect of security
either camera monitoring or
onsite visits.
Local Yes € 185,000 None – locally
managed
4 Maintenance /Grounds 3 sites have outsourced
grounds maintenance
Local Yes
€70,000 None – locally
managed
Cross-Departmental Function - Human Resource 1 Recruitment Advertising, short-listing
and interview co-ordination
primarily for contract
research recruitment.
Sanction process, interview
and offer stages continued
to be handled by internal
resources.
National Yes
PAS delivered
this service in
2011 but were
unable to
continue to
deliver this
service.
€1000 per competition
€60,000 apx
Head of Human
Resources
Cross-Departmental Function – Information and Communication Technology
1 Help Desk & Deskside Support 25k calls per annum.
Approx. 9 headcount
equivalent
National Might suit the
development
of a standard
850,000 Head of ICT
2 System support (servers) 2-4 headcount approx.
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
4 Network Administration 1 headcount approx contract
/ framework
6 Application Development Development and support of
a suite of applications which
use .net web technologies;
Headcount varies from 1 up
to around 8
National No –
applications
are bespoke
and specific to
the
organisation
Fixed component 36,000
Variable component
depends on how much
development is to be done;
has been 0 some years, this
year budget is around
250,00
Head of ICT
7 Application Testing
8 Application Management
2 System support ( web applications)
9 Hosting 9 Racks (120 servers +
allied equipment) hosted by
Department of Agriculture,
Food and the Marine.
National Yes €0 Head of ICT
10 Cyber Security Reviews of application
developments
National yes Variable, but typically
around 20,000
Head of ICT
Departmental Specific Function – Advisory Services
1 REPS 2,229 REPS Record
Reviews subcontracted to
private planners
Regional No - Unique € 216,784 Head of
Regional Units
Departmental Specific Function – Education Services
1 Education Approx 6,250 hours of
education delivery
(lectures).
National No – Unique €400,000 Head of
Education
2 Education Eligibility of applicants for
grants.
National Engaging with
SUSI who
have not yet
been in a
position to do
this for us.
€15,000 Head of
Education
Departmental Specific Function – Advisory Services / Research
No. Action/Deliverable Detailed Description
(define scope,
volumes, headcount)
Level at which
contract administered
(eg. Local, Regional,
National)
Suitability
for multi-
department
contracts
Annual value of
contract(s) (€)
Senior
Responsible
Owner
1 Soil Sampling Analysis of 40,000 soil
samples annually.
National No - Unique € 1.1 M Head of Crops,
Environment &
Land Use.
Areas currently being tested for External Service Delivery or in the process of being moved to external delivery* No. Action/Deliverable Detailed Description (define
scope, headcount, volumes,
current data quality)
Key Steps for
Implementation and
Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsi
ble
Owner
Cross-Departmental Function - Facilities Management Corporate Services strategy
being prepared which will
identify areas which could
be outsourced.
Headcount unknown at this stage Strategy to be complete
by end 2013
Likely Likely Unknown Head of
Corporate
Services
Cross-Departmental Function - Procurement/logistics
Included in Corporate
Services strategy above
Headcount unknown at this stage
Cross-Departmental Function - Human Resource 1 Payroll Being considered for outsourcing
Headcount: 2.3
However headcount freed up would
be somewhat less as the outsourcer
would still have to be managed.
Freed up headcount expected to be of
the order of 1.8.
Function being
streamlined and the
possibility will be
examined bearing in mind
the Government Shared
Services centre.
Yes Yes Unknown Head of
Finance
3 Recruitment – see above This is expected to continue.
Headcount:1.5
Yes
HR Shared Services (people
point) is expected to be
relevant in the future for
Teagasc
Headcount unknown at this point –
depends on scope of services to be
offered by the HR Shared services.
Cross-Departmental Function - Finance/Business Processes
1 Accounts Payable Headcount: 8
However headcount freed up would
be somewhat less as the outsourcer
Currently the function is
being streamlined to
prepare it for possible
Yes Yes Unknown
Head of
Finance
No. Action/Deliverable Detailed Description (define
scope, headcount, volumes,
current data quality)
Key Steps for
Implementation and
Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsi
ble
Owner
would still have to be managed, not
all parts of the process can be
outsourced and there is a need to
deploy some staff to other work. Our
estimate on headcount that would be
freed up would be of the order of 3.
outsourcing. Business
Process Review to
conclude this year.
2 Debt collection It is currently very distributed. Our
estimate of freed up headcount is 0.3
Currently the function is
being streamlined to
prepare it for possible
outsourcing. Business
Process Review to
conclude this year.
Yes Yes Unknown
Head of
Finance
3 Billing of clients Headcount: 2.4
Freed up headcount would be of the
order of 2.
Currently the function is
being streamlined to
prepare it for possible
outsourcing. Business
Process Review to
conclude this year.
Invoices, receipts and
other notifications will be
printed and issued by
Revenue Printing Services
commencing Sept 2013.
Possibly Possibly Unknown
Head of
Finance
Departmental Specific Function – Education
1 Editing of Teagasc
educational workbooks
Three to Five workbooks annually
with print runs of 500 – 2,000 per
workbook.
Headcount: 0.5
Engaged with
Government Print Centre
(Revenue) but they cannot
produce these books.
RFT currently being
prepared to be complete
by year end.
No – Unique
No. Action/Deliverable Detailed Description (define
scope, headcount, volumes,
current data quality)
Key Steps for
Implementation and
Associated
Timelines
(Start/End Dates)
Suitability
for Shared-
Service
Suitability
for multi-
department
contracts
Expected
€ Saving
(inc.
asmptns)
Senior
Responsi
ble
Owner
2 External authentication of
Teagasc courses
Not yet scoped Currently headcount
involved is about 1.5.
Freed up headcount will not be
known until scoped but is unlikely to
be the full 1.5.
No – Unique
*Teagasc is currently preparing Change Programme III which is likely to identify a number of other possibilities for External Service Delivery.
Teagasc is also committed, where possible, to making use of contracts put in place by the NPS / OGP which may also offer opportunities in this