DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ... ... using a trailing suction hopper dredger. The area...
date post
03-Nov-2020Category
Documents
view
0download
0
Embed Size (px)
Transcript of DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ... ... using a trailing suction hopper dredger. The area...
DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA
MINISTRY OF TRANSPORT AND HIGHWAYS
OFFSHORE SAND MINING FOR THE
COLOMBO 7
OFFSHORE SAND MINING FOR THE
COLOMBO KAiUNAYAKE EXPRESSWAY PROJECT
m^^^ IKONi iftiTjaii /j»ö.miöaßi?Fr-miMß»
ROAD DEVELOPIVIENT AUTHORITY
"Sethsiripaya", Battaramulla
SRI LANKA
DECEMBER 2000
OFTMIOHE I)U[JX;IN(; RIR C()U)MR() KATUNAVAKE EXPRESSWAY PROJECT
Eiiviromiiciilal lnip;)Ct Asscssiiicnl Ucpoil
TABLE OF CONTENTS
1.0 Introduction 1
1.1 Background 1
1.2 Extent and Scope of the Study 2
1.3 Brief Outline of the Conlentsand Methods Used 2
2.0 Description of the Project 4
2.1 Nature, Aims and Scope of the Project 4
2.2 Justification of the Project 4
2.3 Methodology of Operation 5
2.4 Evakialion of Alternatives 7
2.5 Workforce 10
2.6 Programme 10
3.0 Borrow Area and Dredging 11
3.1 Location and Size of Proposed Borrow Area 11
3.2 Volume and Type of Material 11
3.3 Method of Dredging 11
3.4 Timing, Rate and Zoning of Production 12
3.5 Vessel Numbers and Movements 12
3.6 Control of Dredging 12
3.7 Notification and Liaison 12
3.8 Onshore Destination 12
3.9 Alternative Sources of Material 12
4.0 Borrow Area and its Environment 13
4.1 Physical Environment 13
4.2 Biological Environment 13
4.3 Human Environment 15
4.3.1 Fishing Activities 15
4.3.2 Other Activities 17
5.0 Sand Storage Sites and Their Environment 18
6.0 Anticipated Environmental Impacts 19
Ün>iHORKDRi:D(;iN(; R)RCnU>MH() ICVTIINAVAKE EXPRIiSSWAY I * R 0 J E C T
Eiivironmciilal Impacl Assessment Rcjwrt
6.1 Physical Effects 19
6.2 Biological Effects : 20
6 3 Effects on the Human Environment 21
7.0 Proposed Mitigatory Measures 22
7.1 Royulaiiüii/'Müiiitoiiny ufDicdging Activity 22
7.2 Protection of Borrow Areas 22
7.3 Coastal Stability 22
7.4 Navigational Hazards and Interference with Fishing Activities 22
7. 5 Pipeline on Land and Crossing Hamilton Canal 23
7.6 Sea Water Impacts on Surface Water and Groundwater 23
8.0 Monitoring Programme 24
8.1 Dredging Activities 24
8.2 Pumping/Drainage Activities 24
8.3 Long Term Monitoring of Dredge Site 24
9.0 Conclusions and Recommendations 25
ANNEXES ANNEX 1
ANNEX 2
ANNEX 3
ANNEX 4
ANNEX 5
ANNEX 6
ANNEX 7
ANNEX 8
Terms of Kcfcrciice
Bathyntctric Survey Plan
Construction Programme
Mincralogical Analysis
Seismic SuiTcy Report
NARA Report on Fisheries and Marine Habitat
Boreholes Investigation Report
Section 5,4.1.1 Dredging and Transport of Sand to
Stockpiling Area (ElA Report of Colombo-Katunayake
Expressway RDA 1997)
IÄFSIIOREDREDGINC FOR COLOMBO KATUNAYAKE EXPRESSWAY PRO.TECT ^T
Fnviroiimciilal Impact Assessment Report
LIST OF HGURES
Figure 1 - Location Map fui Dreilging
Figure 2 - Location of Stockpiling Areas
Figure 3 - Proposed Trace of tlie Express Highway
Figure 4 - Typical Cross Section of the proposed Highway
Figure 5 - layout of the Submerged Pipeline
Figure 6 - Layout of Boreholes
Figure 7 - Resource Map (Isopatch Chart)
OFFSHORE DRF.IK;IN
OFFSHORE DREDGING FOR COLOMBO KATUNAYAKE EXPRESSWAY rROjECr Environmental Impact Assessment Report
1.2 Extent and Scope of the Study
Tlie EIA is to evaluate the impacts of removing a volume of approximately five million cubic
metres of well graded medium to coarse sea sand from the grid units designated 093203,
093204, 094203, 094204, 095203 and 095204 (see Figure No. 1). The area is located
approximately 3 km offshore of Kerawalapitiya. just north of Colombo. The average sea
depth at the location is 16m below LWOST. The area of dredging is 6 sq. km. and the
average depth of excavation will be approximately 1 .Om.
The scope of the study is to evaluate the aviulability of the required material and the effect of
removal on the wave climate, ajid Impacts on fisheries, shoreline stability and natural resources
of the area.
The methodology for pumping sand to a stockpiling area (also shown in Figure No. 2) and the
arrangements made for the return of saline water to the sea was to follow the practices adopted
for the Kerawalapitiya sand fill {see EIA Report, SLLRDC 1993). Originally the stockpile
was to be made within the Kerawalapitiya sand fill (see EIA Report - RDA 1997, and Relevant
Section in Annex 8). This methodology had already received clearance from the CEA.
However, the an alternative site , adjacent to the Kerawalapitiya and fill has now been reserved
for the stockpile. The methodology for sand fill and evacuation of drainage water remains
/ neariy the same. However, the impacts of filling this area and the return of saline water from
this area have also to be included in the study.
1.3 Brief Outline of (he Contents and Methods Used
The EIA Is formatted to follow the Terms of Reference (TOR) provided by the CEA. It
provides a description of the project, a site description and a description of the existing site
environment, a description of the anticipated environmental impacts, proposed mitigatory
measures and the monitoring programme to be followed.
TTiere have been two dredging projects implemented in the area immediately adjacent to the
site. These were for the purpose of obtaining approximately one million eubJc metres of sea
sand for filling purposes for the JA YE Container Terminal Project In the Colombo Harbour,
and for obtaining approximately 4.8 Million cubic metres of sea sand for the Kerawalapitiya
Reclamation Project. The Queen Elizabeth Quay Expansion Project has recently received
environmental clearance to obtain 1.69 million cubic metres of sea sand from an adjacent area.
An EIA and an lEE (Initial Environmental Examination) were carried out respectively for the
On->"HORF. T)RFDf;iN(; FOR COLOMBO KATIINAYAKF, EXPRESSWAY PROJECT 3 Enviroimiciilal Impact Assessment Report
the purpose of this EIA. The additional field investigations carried out for the present study are
described later in this report. All available information on the fishery and the reefs in the area
were studied.
The results of these investigations, studies and assessments are presented in tliis EIA.
OiTsiiORE DREDGING FOR COLOMBO KATUNAYAKE EXPRESSWAY PROJECT 4 Environmental Impact Assessment Report
2.0 DESCRIPTION OF TlIE PROJECT
2.1 Nature, Aims and Scoi>e of tlie Project
The need for a high speed link between Colombo and the International Airport and Export
Processing Zone in Kalunayake has been recognised from the I980's. The consirnction of the
Colombo-Kafunayake Hxpnsssway (CKE) along a final trace (see Figure No 3) was finally
approved by the C^inet of Ministers on 26* June 1998, after a prolonged planning process
which included extensive public consultations. The Environmental Impact Assessment Report
on this project was approved by the Central Environmental Authority on 28 January 1998.
The final design of the expressway (as shown in Figure No 3) has the following main
jiaramelers:
Lengtii (km)
Width of reservation (m)
Width of eadi carriageway (m)
Number of Inter changes
Southern Terminus
Northern Terminus
25.10
30-100
27.20 (Four Lanes)
02 (Peliyagoda and Ja-Ela)
New Keiani Bridge Intersection
Airport Intersection
Figure 4 shows the typical cross section of Ihe road.
The CKE trace runs through significant extents of marshy land witli peaty under-layers. The
proposed methodology for pre-loading and draining these layers has been considered in the
previous EIA. The metliodology requires the use of 5 million cubic metres of sand obtained
from offshore as fill material. The original CKE proposal was to mimic the procedure adopted
for the Muthurajawcia sand fill and environmental clearance was therefore granted. The new
proposals suggest the use of a storage area (see Figure No. 2) on the eastern side of the Dutch
Canal (Old Negombo Canal). This proposal has thus been included in this present EIA,
TTie originally proposed borrow areas are no longer available to this project. Thus it has been /
necessary to explore tlic availability of sand in new, adjacent areas and carry out a full
environmental impact asst̂ ssment of dredging and tmnsporting Ihe sand from these new areas
and to satisfy the Geological Survey and Mines Bureau (GSMB) licensing procedure for
exploration and mining.
2.2 Justification of the Project
The justification for the CKE Project has been deaJt with exhaustively in the main EIA Report
(RDA, 1997). The need for the expressway has been established and the choice of a road link,
OFI^IIÜRE DREDGING POR COLOM