Demand Side Investment Planning
description
Transcript of Demand Side Investment Planning
Demand Side Investment Planning
Transmission Planning Code Workshop 2
1st May 2008
Introduction
Supply assumptions for planning were discussed in Workshop 1 (3rd April)
Aim of this presentation to describe how demand forecasts and Offtake Capacity Statement (OCS) information are used for investment planning
Basis for Investment Planning
Gas Act 1986 (as Amended by the Gas Act 1995) Economic and efficient
Standard Special Condition A9. Pipe-Line system Security Standards
Firm demand is likely to be exceeded (whether on one or more days) only in 1 year out of 20 years.
Special Condition C2 Long Term Development Statement Identify likely developments over a 10-year period
Special Condition C8E. NTS gas exit incentives, costs and revenues
Respond to requests for incremental capacity
Gas Safety (Management) Regulations 1996 (GS(M)R). Deliver appropriate pressure at offtake
Demand Information
Provided by Customers Contracted quantities
Direct connects Offtake Capacity Statements
From DNs Firm commitment for 4-years (to
2011/12) Indicative for 1- year (2012/13)
Section H - OAD Indicative load duration
information from DNs Pressures
ANOPs for direct connects Within OCS for DNs
Provided by National Grid Internal forecasts
At least 10-years Annuals, Peaks, Load duration
curves Sectoral analysis Econometric modelling
Demand Forecasting Methodology
Describes National Grid’s approach to developing demand forecasts
Peak Day forecasts Load Duration Curves e.g. 1 in 50
(severe), average
Published on National Grid’s website
Gas Demand Forecast
0
200
400
600
800
1000
1200
1400
1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016
Th
rou
gh
pu
t (T
Wh
)
-6%
-4%
-2%
0%
2%
4%
6%
8%
10%
12%
14%
DN Firm DN Interruptible NTS Industrials NTS Pow er
Irish Exports Continental Exports Grow th DN Grow th
Gas Demand Forecast
2007 saw another fall in DN demand Higher prices Energy efficiency Demand destruction
2008 Forecasts significantly lower Continued high prices Loss of demand in large firm / interruptible sectors in
early part of forecast Demand slightly higher in early part of 2008 Uskmouth Power station – LDZ connection
Offtake Capacity Statement data
OCS process runs in parallel to TBE process Initiated 1 June each year OCS agreed by 30 September for the approaching gas year (Y) to
year Y+3 DNs may revise bookings in future years
UNC TPD Section B: Offtake Capacity Statement process Signals DN 1 in 20 peak day requirements for Offtake Capacity and
Agreed Operating Pressures
UNC OAD Section H: Long term demand forecast data DN off-peak forecast data Used to inform TBE demand forecasts Split of offtake flows used as input to network analysis for off-peak
analysis
Timeline for Investment Planning - Exit
May June July Aug Sept Oct Nov Dec
June-July
OCS requests and
DN offtake forecasts
Aug-Sept
Analysis of requests and
discussions with DNOs end Sept
DNOs notified of Offtake Capacity
holdings and AOPs
Exit analysis confirmation of annual Plan
May-June
initial TBE Base Case available
Dec
investment proposals
published in TYS
Transporting Britain’s Energy (TBE) process
Annual consultation process with industry
Consensus on likely supply and demand patterns over the ten year planning horizon
Conclusions published in Ten Year Statement each December
Base Case scenario Range of potential supplies Range of potential demands
Interaction between OCS and NG Forecasts
OCS info limited to 5-years But requirement is for a 10-year plan
For the first 5-years OCS provides the definitive measure of DN 1 in 20
requirements NG forecasts analysed as a sensitivity
For the last 5-years NG forecast is the only source of information
Demand Scenarios – Balancing Assumptions
Investment planning analysis must start from a balanced supply/demand position for any demand day being studied
If available supply exceeds total demand Supplies are reduced using balancing/rank/range assumptions
If total demand exceeds available supply After taking into account potential new supplies
Power station load is reduced Where OCS data is used, DN loads will be reduced for Plan Years 5+
before power station load is reduced* Exceptions are power station loads at extremities of network
*This corresponds to the indicative (5th) year onwards in the OCS
Hierarchy of analysis
1. Flat (10-year horizon) NG forecast
2. Flat (OCS)
3. Flex (OCS)
4. Pressure (OCS)
5. Off peak analysis (10-year horizon)
Flat Capacity Uncertainties
Demand patterns are generally better understood than potential supply patterns
Population centres and CCGT demands and locations are reasonably stable
Supply distribution has a major impact on ability to deliver demand side requirements
Sensitivities What if Grain does not flow into the South East? Milford – South West? Storage – South West? Other stress tests as required
Off peak analysis required to refine investment options and predict plant usage
Flex Capacity Uncertainties
Modelled Transiently (hour by hour)
Sensitivities Similar supply uncertainties to flat Include wider supply variations Supply profiling considered
Allocation within existing and planned capability No specific investment
Pressure
Pressure capability is output of flat and flex capacity analysis.
Sensitivities Need to consider long run requirements for flat and flex Seasonal variations Operational configurations
Comparison between Entry and Exit analysis
Entry Capacity Exit (Flat) Capacity
Supply scenarios
TBE Base Case and
supply sensitivities
TBE Base Case and
localised supply sensitivities
Demand scenarios
TBE Base Case
TBE Base Case and OCS Demands and
sensitivities for new loads
Load Conditions
1 in 20 peak day and off-peak (selected days on average load duration curve)
Development of optimal investment plan
Optimal investment plan considers range of supply and demand cases and other available options e.g. constrained LNG, buyback
Existing investment projects are kept under review Sanctioning of new entry investment projects
undertaken on strength of long-term auction signals Sanctioning of new exit investment projects undertaken
after user commitment received (currently through ARCAs)
S6
S5
S7
S4
S3
S1S2
Identification of Scenarios
S6
S5
S7
S4
S3
S1S2
Capability Analysis
Optimal Investment Plan
S6
S5
S7
S4
S3
S1S2
Investment Planning Analysis
Summary
Base Case view of supply and demand outlook for the planning horizon developed after industry consultation through the TBE process
Further supply cases are required for planning due to the diversity and uncertainty surrounding future supplies to the UK and to test localised adverse supply patterns for exit
Further demand cases are required to ensure NTS meets 1 in 20 peak day requirement
TBE and OCS Demand data is analysed Analysis conducted for peak and off-peak conditions
Investment projects are determined by considering Reinforcement across supply scenarios for different demand conditions Other options not requiring capital investment Long-term signals from users