PM Tools for Success —A Project Manager’s Guide for More Effective Management, Planning and CommunicationJohn Bondeson, Principal, RTKL Associates Inc.PS-208
![Page 2: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/2.jpg)
2 ©2012 Deltek, Inc. All Rights Reserved
Project Management Activities Elements
Vision tools Identifying them Using them
Agenda
![Page 3: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/3.jpg)
3 ©2012 Deltek, Inc. All Rights Reserved
Managing is: Identifying requirements Establishing clear and achievable objectives Balancing the competing demands for quality, scope, time and cost Adapting the specifications, plans and approach to the different
concerns and expectations of the various stakeholders
PM Tools for Success
![Page 4: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/4.jpg)
4 ©2012 Deltek, Inc. All Rights Reserved
Time (Schedule)
Cost (Budget)
Human Resources
Communication
Risk
Quality (Scope)
Elements of Project Management
![Page 5: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/5.jpg)
©2012 Deltek, Inc. All Rights Reserved5
Time and Vision
. . . is of the essence
![Page 6: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/6.jpg)
6 ©2012 Deltek, Inc. All Rights Reserved
Estimate labor accurately
Incorporate project changes
Work to the plan and keep it updated
Time Schedule
![Page 7: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/7.jpg)
©2012 Deltek, Inc. All Rights Reserved7
Time and Vision
How can project managers use Vision to estimate and control time?
![Page 8: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/8.jpg)
8 ©2012 Deltek, Inc. All Rights Reserved
Methods for estimating time Top down Analogous (similar project) Parametric Estimating (i.e., Cost/SF) Three-Point Estimating (Optimistic, Pessimistic, Most Likely) Rolling wave planning (plan as you go) Team proportion Expert judgment Bottom up
Time Schedule
![Page 9: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/9.jpg)
9 ©2012 Deltek, Inc. All Rights Reserved
Top Down
Start with the project feeThis is sometimes based the floor area of the project ($ / SF or SM) or a percentage of construction cost ($ x %)
Divide the fee into the phases or labor codesThe percentage of the total fee for each phase is typically documented in the contract or proposal. (Example 5% Predesign (Concept), 20% SD, 25% DD, 35% CD and 15% CCA)
Estimate the time based on the expected feeThis may not match the time actually needed to complete each phase. It may be greater or less. Plans need to be updated and adjusted during the project to reflect reality as it unfolds.
Time — Top Down
![Page 10: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/10.jpg)
10 ©2012 Deltek, Inc. All Rights Reserved
Time — Top Down
![Page 11: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/11.jpg)
04/12/202311 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Top Down
132
![Page 12: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/12.jpg)
04/12/202312 ©2012 Deltek, Inc. All Rights Reserved
Time — Top Down
![Page 13: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/13.jpg)
13 ©2012 Deltek, Inc. All Rights Reserved
Time — Top Down
![Page 14: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/14.jpg)
14 ©2012 Deltek, Inc. All Rights Reserved
Time — Analogous
![Page 15: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/15.jpg)
15 ©2012 Deltek, Inc. All Rights Reserved
Proportion percentage determined by discipline
Architecture 38%
Interiors 23%
Structural 19%
MEP 16%
Direct expenses 3%
100%
Time — Team Proportion
![Page 16: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/16.jpg)
16 ©2012 Deltek, Inc. All Rights Reserved
Phase percentage determined by scope of work
Scope A Scope B Scope C
Schematic Design 15% 20% 25%
Design Develop 20% 20% 25%
Contract Docs 40% 30% 20%
Bidding 5% 5% 5%
Contract Admin 20% 25% 25%
TOTAL 100% 100% 100%
Time — Proportion
![Page 17: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/17.jpg)
04/12/202317 ©2012 Deltek, Inc. All Rights Reserved
Time — Proportion
![Page 18: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/18.jpg)
18 ©2012 Deltek, Inc. All Rights Reserved
Bottom up
Start with the work required to complete each phaseIdeally, these correspond to the labor codes in the Vision plan (SD, DD, CD, CA, etc.)
Break into smaller milestones ( e.g. 50% progress set)Divide into smaller chunks of work to create work packages (the smallest level a PM can monitor). Create the list in the order that the activities occur.
PMBOK 8/80 Rule*No work package should be less the 8 hours or greater than 80 hours. Find the right work package scale for the project.
*Project Management Body Of Knowledge – a general project management standard
Time — Bottom Up
![Page 19: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/19.jpg)
04/12/202319 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Bottom Up
![Page 20: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/20.jpg)
04/12/202320 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Bottom Up
![Page 21: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/21.jpg)
04/12/202321 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Bottom Up
![Page 22: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/22.jpg)
22 ©2012 Deltek, Inc. All Rights Reserved
Time — Bottom Up
![Page 23: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/23.jpg)
04/12/202323 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Bottom Up
![Page 24: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/24.jpg)
04/12/202324 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Bottom Up
![Page 25: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/25.jpg)
25 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Schedule
![Page 26: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/26.jpg)
26 ©2012 Deltek, Inc. All Rights Reserved
Time — Schedule
![Page 27: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/27.jpg)
27 ©2012 Deltek, Inc. All Rights Reserved
Time — Labor Summary
![Page 28: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/28.jpg)
28 ©2012 Deltek, Inc. All Rights Reserved
Time — Labor Detail Report
![Page 29: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/29.jpg)
29 ©2012 Deltek, Inc. All Rights Reserved
Time — Resource Utilization Module
![Page 30: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/30.jpg)
30 ©2012 Deltek, Inc. All Rights Reserved
Time — Resource Utilization Module
![Page 31: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/31.jpg)
31 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Time — Resource Utilization Module
![Page 32: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/32.jpg)
04/12/202332 ©2012 Deltek, Inc. All Rights Reserved
Time — Planned
![Page 33: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/33.jpg)
©2012 Deltek, Inc. All Rights Reserved33
Cost and Vision
Budgets: Internal and External
![Page 34: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/34.jpg)
34 ©2012 Deltek, Inc. All Rights Reserved
Internal Costs Labor Overhead Direct Project Expenses Reimbursable Project Expenses
Cost — Budget
![Page 35: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/35.jpg)
©2012 Deltek, Inc. All Rights Reserved35
Cost and Vision
How can project managers use Vision to help understand and control costs?
![Page 36: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/36.jpg)
36 ©2012 Deltek, Inc. All Rights Reserved
Cost — Fees and Billing
![Page 37: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/37.jpg)
37 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
Cost — Tracking
![Page 38: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/38.jpg)
38 ©2012 Deltek, Inc. All Rights Reserved
Cost — Tracking
![Page 39: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/39.jpg)
39 ©2012 Deltek, Inc. All Rights Reserved
Cost — Tracking
![Page 40: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/40.jpg)
40
Vision screenshots
Cost — Tracking
![Page 41: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/41.jpg)
41 ©2012 Deltek, Inc. All Rights Reserved
Cost — Analysis Tab
![Page 42: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/42.jpg)
42 ©2012 Deltek, Inc. All Rights Reserved
Cost — Summary Tab
![Page 43: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/43.jpg)
43 ©2012 Deltek, Inc. All Rights Reserved
Cost — Consultant Tracking
![Page 44: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/44.jpg)
44 ©2012 Deltek, Inc. All Rights Reserved
Using the grid to plan anticipated invoices
Cost — Consultant Tracking
![Page 45: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/45.jpg)
45 ©2012 Deltek, Inc. All Rights Reserved
Use the grid to plan when expenses will be incurred
Cost — Expense Tracking
![Page 46: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/46.jpg)
Human Resources and Vision
People Power
©2012 Deltek, Inc. All Rights Reserved46
![Page 47: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/47.jpg)
47 ©2012 Deltek, Inc. All Rights Reserved
Human Resource Planning
Assembling a Project TeamFinding the right people
Developing a Project Team
Managing a Project Team
Human Resources
![Page 48: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/48.jpg)
Human Resources and Vision
How can project managers use Vision to manage human resources
©2012 Deltek, Inc. All Rights Reserved48
![Page 49: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/49.jpg)
04/12/202349 ©2012 Deltek, Inc. All Rights Reserved
Human Resources — Resource Search
Right Click
![Page 50: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/50.jpg)
50 ©2012 Deltek, Inc. All Rights Reserved
Human Resources — Resource Search
![Page 51: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/51.jpg)
51
Human Resources — Resource Search
1
2
3
4
5
![Page 52: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/52.jpg)
04/12/202352 ©2012 Deltek, Inc. All Rights Reserved
Human Resources — Utilization
![Page 53: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/53.jpg)
©2012 Deltek, Inc. All Rights Reserved53
Communication and Vision
Can you hear me now?
Vision can help internal and external communication
![Page 54: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/54.jpg)
54 ©2012 Deltek, Inc. All Rights Reserved
Communication
![Page 55: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/55.jpg)
55 ©2012 Deltek, Inc. All Rights Reserved
Communication
![Page 56: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/56.jpg)
56 ©2012 Deltek, Inc. All Rights Reserved
Communication
![Page 57: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/57.jpg)
04/12/202357 ©2012 Deltek, Inc. All Rights Reserved
Vision Screenshots
Communication — E-Mail
![Page 58: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/58.jpg)
©2012 Deltek, Inc. All Rights Reserved58
Risk and Vision
Nothing ventured, nothing gained
![Page 59: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/59.jpg)
59 ©2012 Deltek, Inc. All Rights Reserved
Areas of risk Proposals and Contracts Lack of communication during design Client payment Drawing errors and omissions Construction defects
Risk
![Page 60: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/60.jpg)
©2012 Deltek, Inc. All Rights Reserved60
Risk and Vision
Track proposals and contracts
Track payments and invoices
Enhance communication
![Page 61: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/61.jpg)
61 ©2012 Deltek, Inc. All Rights Reserved
RiskCustomization – Go / No Go
![Page 62: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/62.jpg)
62 ©2012 Deltek, Inc. All Rights Reserved
Vision Screenshots
RiskSigned Agreement Tracking
![Page 63: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/63.jpg)
63 ©2012 Deltek, Inc. All Rights Reserved
RiskSigned Contract Tracking
![Page 64: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/64.jpg)
64 ©2012 Deltek, Inc. All Rights Reserved
Risk — Signed Proposal Tracking
![Page 65: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/65.jpg)
65 ©2012 Deltek, Inc. All Rights Reserved
Risk — Signed Consultant Agreement Tracking
![Page 66: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/66.jpg)
04/12/202366 ©2012 Deltek, Inc. All Rights Reserved
Vision screenshots
RiskARs
Right Click
![Page 67: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/67.jpg)
67 ©2012 Deltek, Inc. All Rights Reserved
RiskARs
1
2
![Page 68: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/68.jpg)
68 ©2012 Deltek, Inc. All Rights Reserved
RiskARs
![Page 69: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/69.jpg)
Quality and Vision
What is Quality?
©2012 Deltek, Inc. All Rights Reserved69
![Page 70: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/70.jpg)
70 ©2012 Deltek, Inc. All Rights Reserved
The word comes from Latin through Anglo-French and Middle English originating from “of what kind”
Degree of Excellence Descriptive of nature, caliber, class, grade, rate Implies superiority of kind For PMs it can relate to delivering Scope of Work or Service
Quality
![Page 71: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/71.jpg)
©2012 Deltek, Inc. All Rights Reserved71
Quality and Vision
How can project managers use Vision to help enhance Quality?
![Page 72: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/72.jpg)
72 ©2012 Deltek, Inc. All Rights Reserved
Quality
![Page 73: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/73.jpg)
73 ©2012 Deltek, Inc. All Rights Reserved
Quality
![Page 74: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/74.jpg)
74 ©2012 Deltek, Inc. All Rights Reserved
Vision offers: A database Tools to help keep things in balance Different ways to look at (the same) data
Quality
![Page 75: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/75.jpg)
75 ©2012 Deltek, Inc. All Rights Reserved
Vision Tools for Effective Project Management Time (Schedule) Cost (Budgets) Human Resources Communication Risk Quality (Scope)
Summary
![Page 76: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/76.jpg)
©2012 Deltek, Inc. All Rights Reserved76
Questions?
![Page 77: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/77.jpg)
©2012 Deltek, Inc. All Rights Reserved77
Thank You!
![Page 78: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/78.jpg)
PM Tools for SuccessA Project Manager’s Guide for More Effective Management, Planning and CommunicationJohn Bondeson, Principal, RTKL Associates Inc.PS-208
![Page 79: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/79.jpg)
79 ©2012 Deltek, Inc. All Rights Reserved
RiskCustomization – Go / No Go
![Page 80: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/80.jpg)
80 ©2012 Deltek, Inc. All Rights Reserved
RiskCustomization – Go / No Go
![Page 81: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/81.jpg)
04/12/202381 ©2012 Deltek, Inc. All Rights Reserved
RiskCustomization – Go / No Go
![Page 82: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/82.jpg)
82 ©2012 Deltek, Inc. All Rights Reserved
RiskCustomization – Go / No Go
![Page 83: Deltek Insight 2012: PM Tools for Success. A Project Manager's Guide for Effective Management, Planning and Communication](https://reader037.fdocuments.net/reader037/viewer/2022110307/5555eaf2d8b42ad3548b4bb5/html5/thumbnails/83.jpg)
83 ©2012 Deltek, Inc. All Rights Reserved
Consistency
Professionalism
Clarity
Concise
Positivity
Diligence
Understanding
Communication