Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs
description
Transcript of Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs
Delta Conveyance:Update on the Planning Process and Analysis of Water Supply and Costs
CCWA Board of DirectorsFebruary 25, 2010
Delta Conveyance: Analysis of Water Supply and Costs
Delta Conveyance Status
• Significant progress has been made on Delta Conveyance planning
• Significant additional steps are needed
• The planning process will run out of money by the end of 2010
• SWP Contractors need to decide on continuing the planning process
Delta Conveyance: Analysis of Water Supply and Costs
All of the information and data are preliminary and subject to revision.
About this Presentation…
DRAFT!
Preliminary Subject to Revision
Delta Conveyance: Analysis of Water Supply and Costs
Going from Plan to Permits
Preliminary Subject to Revision
The Delta Habitat Conservation and Conveyance Program Process
BDCP Develops HCP Proposed Project(Includes habitat projects and conveyance)
DHCCP Team Creates the EIR/EIS
Record of Decision /Notice of Determination
Delta Conveyance: Analysis of Water Supply and Costs
Going from Plan to Permits
Preliminary Subject to Revision
BDCP/DHCCP Processes
• Bay Delta Conservation Plan (BDCP)• Initiated 2006• Focus on conveyance and restoring habitat for
fisheries within the Sacramento-San Joaquin Delta• Products
Habitat Conservation Plan Natural Communities Conservation Plan
• Delta Habitat Conservation and Conveyance Program (DHCCP)• Initiated 2008• Funding Agreements – $140 Million (50% SWP Share)• Develops EIR/EIS Documents and Record of Decision
(ROD)/Notice of Determination (NOD)
Delta Conveyance: Analysis of Water Supply and Costs
Going from Plan to Permits
Preliminary Subject to Revision
DHCCP Program Status
• Original Final EIR/EIS Completion – December 2010• Current Status:
Conceptual Engineering Design Completed Tunnels Identified as New Alternative Require Additional
Engineering Analysis BDCP Preferred Program Delayed – December 2008 Target
Delayed until 2010, Causing Delays in DHCCP• Project Delayed and Tunnels Added Costs
Increased• Original Budget – $150 Million (Including BDCP)• Actual Costs to Date – $58 Million• Additional Planning Costs – $98 Million Starting 2011
Delta Conveyance: Analysis of Water Supply and Costs
DHCCP/BDCP – Going from Plan to Permits
Preliminary Subject to Revision
Delta Conveyance: Analysis of Water Supply and Costs
Going from Plan to Permits
Preliminary Subject to Revision
Funding Next Steps
• May Need to amend existing Funding Agreement• No increase in expenditures for 2010; Additional
revenue collected in 2011, Commitments needed in 2010
• Financing for planning costs being considered• Schedule (if amendment required):
February 2010 – DHCCP Executive Committee reviews cost share proposal
March 2010 – Funding Amendment provided to SWP Contractors
April 2010 – SWP Contractors sign amendments
• What will the project look like?o Where is the project?o How will it operate?
Can we afford a new Delta Conveyance Facility?
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
The three questions that everyone wants answers to:
• What are the benefits?o What can be delivered with new
conveyance?o How does this compare with what supplies
we currently receive?
• What will it cost?o How do we finance the costs?o How do we split the costs?
What will the Project look like?
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
Three alignment options:
For more information:
All Tunnel Alignment & Option Comparisions
Presented to:
BDCP Steering Committee
December 3, 2009
What will the Project look like?
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
What will the Project look like?
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
M-30 By-Pass Sur Túnel Norte, Madrid EPB Shield – 15.200 m diameter
What will it cost?Construction costs:
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
Eastern Alignment All Tunnel Western Alignment
Construction $7.9 to $8.5 billion $9.7 to $10.5 billion $8.2 to $9.0 billion
Footprint Land Acquisition $186.4 million $51.5 million $169.5 million
Mitigation Land Acquisition $247 million $87 million $241 million
Total Cost $8.33 to $8.93 billion $9.84 to $10.64 billion $8.61 to $9.41 billion
WARNING: ACTUAL C
OSTS ARE SUBJECT TO CHANGE
Long-term Bondo 40 yearso 5%
Cost Assumptiono $10 Billion – Current Tunnel Cost Estimateo Costs being updated – likely +/- 15%
Annual Debt Service (SWP & CVP Combined)o $583 Million
What will it cost?
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
Financing the construction costs:
What will it cost?Annual O&M and Power costs:
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
1 – Estimated Average Year Power Costs
Eastern Alignment
All Tunnel Western Alignment
O&M $17.6 Million $13.7 Million $16.0 Million
Power1 $33 Million $21.7 Million $26.9 Million
Total Cost $50.6 Million $35.4 Million $42.9 Million
What will it cost?
Delta Conveyance: Analysis of Water Supply and Costs
Possible Aproaches to Split costs between the Projects
Using conveyance capacity:o CVP: 39%o SWP: 61%
Preliminary Subject to Revision
Using contract amounts:o CVP: 45%o SWP: 55%
Total Water Supplyo CVP: 40.6%o SWP: 59.4%
Firm Deliveries (other some other method)
Project Cost Estimateo $10 Billion
Annual Capital Repayment o $583 Million
Estimated SWP Share – 60%
Annual Costs (including Capital & O&M)o SWP – $346 Million o CVP – $237 Million
What will it cost?
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
Financing the construction costs:
To San Francisco
Sacr
amen
to R
iver
l Stockton
San Joaquin River
Clifton Court Forebay
The Delta
What are the benefits?
Delta Conveyance: Analysis of Water Supply and Costs
Compare With and Without new Delta conveyance
2005 SWP Reliability Report (Pre-Wanger):o Average Table A: 77%
Without Conveyance2009 SWP Reliability Report (Post BOs):
o Average Table A: 60%o Subject to Reductions due to
Regulatory Actions, Earthquakes, etc.
With ConveyanceBDCP Proposed Operation:
o Average Table A: 79%
Preliminary Subject to Revision
What will we get and what will it cost?Annual Cost & Supply Impacts of Delta Conveyance
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision
Without Delta
Conveyance Condition
With Delta
ConveyanceDifference
Supply1 2.15 MAF2 3.20 MAF3 1.05 MAF
Annual Cost $1,022 Million
$1,449 Million $427 Million
Melded Cost $408/AF $439/AF $31/AF
Incremental Cost $538/AF
1 – Supply Estimates do not Include Article 21 Water Availability2 – Assumes 60% SWP Reliability (2009 SWP Reliability Report)3 – Assumes 79% SWP Reliability (with BDCP Proposed Operations)
Water Quality:o Major reduction in salinity, chlorides, TOCs,
bromideso Reduced Treatment Costso Reduced Service Area Costs (e.g., reduced
homeowner costs for water heaters)
Improved Reliability:o Existing Supply Through Delta Potentially
Unusable in Future due to Significant Probability of Delta Levee Failure from Earthquakes, etc.
o Short term loss of supply (Table A and Article 21 Water) without Delta Conveyance
o Long term reduction without Delta Conveyanceo Delta Conveyance avoids potential future Delta
Regulatory restrictions
Delta Conveyance: Analysis of Water Supply and Costs
What are the benefits for me?Other benefits of a new Delta Conveyance
Preliminary Subject to Revision
What are the Next Steps?
Delta Conveyance: Analysis of Water Supply and Costs
If DWR Financing of Planning Costs is Not Successful
• Key SWP Contractors Personnel Get Ready Access to DHCCP Documents including Environmental Material
• DHCCP developing a Funding Amendment with additional $49 Million ($98 Million total SWP & CVP) in costs to be billed in 2011
• Funding Amendments to be provided to SWP Contractors in March 2010
• Additional Costs for SWP Contractors Collectively -- $49 million
• Signed Funding Agreement Amendments needed by April 2010
• SWP Contractors working with DWR to finance planning costs – if successful, would eliminate need for Funding Agreements
Preliminary Subject to Revision
Questions?
Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision