Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

22
Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs CCWA Board of Directors February 25, 2010

description

Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs. CCWA Board of Directors February 25 , 2010. Delta Conveyance Status. Significant progress has been made on Delta Conveyance planning Significant additional steps are needed - PowerPoint PPT Presentation

Transcript of Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Page 1: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance:Update on the Planning Process and Analysis of Water Supply and Costs

CCWA Board of DirectorsFebruary 25, 2010

Page 2: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance: Analysis of Water Supply and Costs

Delta Conveyance Status

• Significant progress has been made on Delta Conveyance planning

• Significant additional steps are needed

• The planning process will run out of money by the end of 2010

• SWP Contractors need to decide on continuing the planning process

Page 3: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance: Analysis of Water Supply and Costs

All of the information and data are preliminary and subject to revision.

About this Presentation…

DRAFT!

Preliminary Subject to Revision

Page 4: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance: Analysis of Water Supply and Costs

Going from Plan to Permits

Preliminary Subject to Revision

The Delta Habitat Conservation and Conveyance Program Process

BDCP Develops HCP Proposed Project(Includes habitat projects and conveyance)

DHCCP Team Creates the EIR/EIS

Record of Decision /Notice of Determination

Page 5: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance: Analysis of Water Supply and Costs

Going from Plan to Permits

Preliminary Subject to Revision

BDCP/DHCCP Processes

• Bay Delta Conservation Plan (BDCP)• Initiated 2006• Focus on conveyance and restoring habitat for

fisheries within the Sacramento-San Joaquin Delta• Products

Habitat Conservation Plan Natural Communities Conservation Plan

• Delta Habitat Conservation and Conveyance Program (DHCCP)• Initiated 2008• Funding Agreements – $140 Million (50% SWP Share)• Develops EIR/EIS Documents and Record of Decision

(ROD)/Notice of Determination (NOD)

Page 6: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance: Analysis of Water Supply and Costs

Going from Plan to Permits

Preliminary Subject to Revision

DHCCP Program Status

• Original Final EIR/EIS Completion – December 2010• Current Status:

Conceptual Engineering Design Completed Tunnels Identified as New Alternative Require Additional

Engineering Analysis BDCP Preferred Program Delayed – December 2008 Target

Delayed until 2010, Causing Delays in DHCCP• Project Delayed and Tunnels Added Costs

Increased• Original Budget – $150 Million (Including BDCP)• Actual Costs to Date – $58 Million• Additional Planning Costs – $98 Million Starting 2011

Page 7: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance: Analysis of Water Supply and Costs

DHCCP/BDCP – Going from Plan to Permits

Preliminary Subject to Revision

Page 8: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Delta Conveyance: Analysis of Water Supply and Costs

Going from Plan to Permits

Preliminary Subject to Revision

Funding Next Steps

• May Need to amend existing Funding Agreement• No increase in expenditures for 2010; Additional

revenue collected in 2011, Commitments needed in 2010

• Financing for planning costs being considered• Schedule (if amendment required):

February 2010 – DHCCP Executive Committee reviews cost share proposal

March 2010 – Funding Amendment provided to SWP Contractors

April 2010 – SWP Contractors sign amendments

Page 9: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

• What will the project look like?o Where is the project?o How will it operate?

Can we afford a new Delta Conveyance Facility?

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

The three questions that everyone wants answers to:

• What are the benefits?o What can be delivered with new

conveyance?o How does this compare with what supplies

we currently receive?

• What will it cost?o How do we finance the costs?o How do we split the costs?

Page 10: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What will the Project look like?

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

Three alignment options:

For more information:

All Tunnel Alignment & Option Comparisions

Presented to:

BDCP Steering Committee

December 3, 2009

Page 11: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What will the Project look like?

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

Page 12: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What will the Project look like?

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

M-30 By-Pass Sur Túnel Norte, Madrid EPB Shield – 15.200 m diameter

Page 13: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What will it cost?Construction costs:

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

Eastern Alignment All Tunnel Western Alignment

Construction $7.9 to $8.5 billion $9.7 to $10.5 billion $8.2 to $9.0 billion

Footprint Land Acquisition $186.4 million $51.5 million $169.5 million

Mitigation Land Acquisition $247 million $87 million $241 million

Total Cost $8.33 to $8.93 billion $9.84 to $10.64 billion $8.61 to $9.41 billion

WARNING: ACTUAL C

OSTS ARE SUBJECT TO CHANGE

Page 14: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Long-term Bondo 40 yearso 5%

Cost Assumptiono $10 Billion – Current Tunnel Cost Estimateo Costs being updated – likely +/- 15%

Annual Debt Service (SWP & CVP Combined)o $583 Million

What will it cost?

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

Financing the construction costs:

Page 15: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What will it cost?Annual O&M and Power costs:

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

1 – Estimated Average Year Power Costs

Eastern Alignment

All Tunnel Western Alignment

O&M $17.6 Million $13.7 Million $16.0 Million

Power1 $33 Million $21.7 Million $26.9 Million

Total Cost $50.6 Million $35.4 Million $42.9 Million

Page 16: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What will it cost?

Delta Conveyance: Analysis of Water Supply and Costs

Possible Aproaches to Split costs between the Projects

Using conveyance capacity:o CVP: 39%o SWP: 61%

Preliminary Subject to Revision

Using contract amounts:o CVP: 45%o SWP: 55%

Total Water Supplyo CVP: 40.6%o SWP: 59.4%

Firm Deliveries (other some other method)

Page 17: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Project Cost Estimateo $10 Billion

Annual Capital Repayment o $583 Million

Estimated SWP Share – 60%

Annual Costs (including Capital & O&M)o SWP – $346 Million o CVP – $237 Million

What will it cost?

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

Financing the construction costs:

Page 18: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

To San Francisco

Sacr

amen

to R

iver

l Stockton

San Joaquin River

Clifton Court Forebay

The Delta

What are the benefits?

Delta Conveyance: Analysis of Water Supply and Costs

Compare With and Without new Delta conveyance

2005 SWP Reliability Report (Pre-Wanger):o Average Table A: 77%

Without Conveyance2009 SWP Reliability Report (Post BOs):

o Average Table A: 60%o Subject to Reductions due to

Regulatory Actions, Earthquakes, etc.

With ConveyanceBDCP Proposed Operation:

o Average Table A: 79%

Preliminary Subject to Revision

Page 19: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What will we get and what will it cost?Annual Cost & Supply Impacts of Delta Conveyance

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision

Without Delta

Conveyance Condition

With Delta

ConveyanceDifference

Supply1 2.15 MAF2 3.20 MAF3 1.05 MAF

Annual Cost $1,022 Million

$1,449 Million $427 Million

Melded Cost $408/AF $439/AF $31/AF

Incremental Cost $538/AF

1 – Supply Estimates do not Include Article 21 Water Availability2 – Assumes 60% SWP Reliability (2009 SWP Reliability Report)3 – Assumes 79% SWP Reliability (with BDCP Proposed Operations)

Page 20: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Water Quality:o Major reduction in salinity, chlorides, TOCs,

bromideso Reduced Treatment Costso Reduced Service Area Costs (e.g., reduced

homeowner costs for water heaters)

Improved Reliability:o Existing Supply Through Delta Potentially

Unusable in Future due to Significant Probability of Delta Levee Failure from Earthquakes, etc.

o Short term loss of supply (Table A and Article 21 Water) without Delta Conveyance

o Long term reduction without Delta Conveyanceo Delta Conveyance avoids potential future Delta

Regulatory restrictions

Delta Conveyance: Analysis of Water Supply and Costs

What are the benefits for me?Other benefits of a new Delta Conveyance

Preliminary Subject to Revision

Page 21: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

What are the Next Steps?

Delta Conveyance: Analysis of Water Supply and Costs

If DWR Financing of Planning Costs is Not Successful

• Key SWP Contractors Personnel Get Ready Access to DHCCP Documents including Environmental Material

• DHCCP developing a Funding Amendment with additional $49 Million ($98 Million total SWP & CVP) in costs to be billed in 2011

• Funding Amendments to be provided to SWP Contractors in March 2010

• Additional Costs for SWP Contractors Collectively -- $49 million

• Signed Funding Agreement Amendments needed by April 2010

• SWP Contractors working with DWR to finance planning costs – if successful, would eliminate need for Funding Agreements

Preliminary Subject to Revision

Page 22: Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs

Questions?

Delta Conveyance: Analysis of Water Supply and Costs Preliminary Subject to Revision