DEEPAK-02
-
Upload
abdullahaneefa -
Category
Documents
-
view
219 -
download
0
Transcript of DEEPAK-02
-
8/11/2019 DEEPAK-02
1/3
PROJECT
LANCO ANPARA C 2X 600 MW THERMAL POWER PROJECTANPARASONEBHDRA DISTRICTUTTAR PRADESHINDIA
OWNER
LANCO ANPARA POWER PRIVATE LIMITEDHARYNANA--INDIA
Owner Consultant
L&T S&LFARIDABAD, HARYANA, INDIA
EPC Contractor
LANCO INFRATECH LTD, EPC DIVISIONGURGAON--INDIA
BTG SUPPLIER
DONGFANG ELECTRIC CORPORATIONCHENGDU CHINA
ORIGINATOR
DONGFANG BOILER Group Co., Ltd
ZIGONG CHINA
Document No.: Rev.:
Document Title :
LIST OF WELDING JOINTS AT SITE
Date Revision Prepared by Reviewed by Released by
-
8/11/2019 DEEPAK-02
2/3
DONGFANG ELECTRIC CORPORATION Lanco Anpara C 2 x600 MW Thermal Power Project, Anpara, Sonebhdr a Distr ict .
Uttar Pradesh - IndiaDocument No.: Document Title:List of welding joints at site Rev.: A
System/Equipment Name Originator: Manufacturer Sheet No.
LIST OF WELDING JOINTS AT SITE
SL.NO DESCRIPTIONSIZE (ODxT)
mmMATERIAL
SPECIFICATION
NUMBER OFJOINTS/BOILER
1 Water wall66.78
66.77SA-210C
5684368
2 Water Wall Suspension 82.511 15CrMoG 88
3Connection pipe from Down comer tolow header of W.W
14116 SA-106C 124
4 Rising pipe 16818 SA-106C 298
5 Economizer 516 SA-210C 2136
6 Economizer Suspension5110
5711.5SA-210C
534534
7Connection pipes from Economizer to
drum
12715 SA-106C 44
8Economizer Internal Connectionpipes
323.932
406.440SA-106C
208
9 Down comer609.660
609.665SA-106C
348
10 Front roof 516 15CrMoG 880
11 secondary pass44.55.5
44.56.5SA-210C
1262181
12 convection pass 63.58SA-210C
SA-210C+15CrMoG
1210179
13 Headers of SH Rearwall 406.460 SA-106C 12
14 SH internal pipes 16818 SA-106C 146
15 LT SH 577
15CrMoG+20G
20G +SA-210CSA-210C +15CrMoG
15CrMoG+12Cr1MoVG12Cr1MoVG
356712712712712
16 SH Vertical Panel 44.5712Cr1MoVG
SA-213T23
SA-213T91
1024640384
17 SH Vertical Platen NO
18 SH finish 518
12Cr1MoVG
SA-213T91
595
595
19 RH platen 63.55SA-210C
SA-210C+15CrMoG15CrMoG+12Cr1MoVG
890890890
20 RH finish 574.512Cr1MoVG
SA-213T911780890
21 Main Steam Pipe
45047
77533
76230
SA-335P91
12Cr1MoVG
SA-106C
81414
22 Header of water wall27355
27350SA-106C
41
23 Header of roof21935
27350SA-106C
11
Boiler Dongfang Bolier Group Co., Ltd 2 of 3
-
8/11/2019 DEEPAK-02
3/3
DONGFANG ELECTRIC CORPORATION Lanco Anpara C 2 x600 MW Thermal Power Project, Anpara, Sonebhdr a Distr ict .
Uttar Pradesh - IndiaDocument No.: Document Title:List of welding joints at site Rev.: A
System/Equipment Name Originator: Manufacturer Sheet No.
24 Header of economizer
406.460
21930
323.940
SA-106C
244
25 Header of LT SH27345
609.665
12Cr1MoVG 1
126 Header of SH finish
609.675
609.685
12Cr1MoVG
SA-335P91
11
27 Header of RH76245
863.656
SA-106C
SA-335P91
11
28 SH internal pipes
609.655
323.930
36835
609.665
12Cr1MoVG
1481612
Note: The number of weld joint is tentative. The final total number of weld joints shall be confirmed to the contractor after the completion ofthe detailed engineering. Apart from the above mentioned welding joints, there will be some more joints related to drain piping, vents,
tapping etc. and interfacing piping.
Boiler Dongfang Bolier Group Co., Ltd 3 of 3