DECISION TREE ANALYSIS - PMI

22
© 2013 Dr. Kenneth F. Smith, PMP Project Management Fundamentals Slide 1 DECISION TREE ANALYSIS Dr. Kenneth F. Smith, PMP PMI (Honolulu Chapter) [email protected] June 2013

Transcript of DECISION TREE ANALYSIS - PMI

Page 1: DECISION TREE ANALYSIS - PMI

© 2013 Dr. Kenneth F. Smith, PMP Project Management Fundamentals Slide 1

DECISION TREE ANALYSIS

Dr. Kenneth F. Smith, PMP PMI (Honolulu Chapter)

[email protected]

June 2013

Page 2: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 2

Consider Alternative Solutions

Page 3: DECISION TREE ANALYSIS - PMI

Slide 3

Page 4: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 4

Which of the several possible courses of

action could be pursued?

Bias in solutions?

Consultants;

Others in

Community

Are there alternative

ways to achieve them ?

Higher / lower technology?

Less risk?

Faster / slower

implementation?

Less / more cost?

Greater / lesser chance of

sustainability?

Change in behavior?

Page 5: DECISION TREE ANALYSIS - PMI

© 2013 Dr. Kenneth F. Smith, PMP Project Management Fundamentals Slide 5

The Decision Tree Technique

for weighing & considering

PROJECT SCOPE

Alternatives

Page 6: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 6

Identify the BASELINE Situation & Any

ALTERNATIVES (With Additive Costs),

and arrange them as separate Branches

of the “Tree”

Baseline

Alt “A” $

Alt “B” $$

Page 7: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 7

Identify the EXPECTED RESULTS anticipated

from the Baseline, and the Alternatives

Baseline

Alt “A”

Alt “B”

Expected

Results

Page 8: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 8

IDENTIFY THE RISK SITUATION

Baseline

Alt “A”

Alt “B”

Risk

Situation

Expected

Results

Page 9: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 9

IDENTIFY PROBABILITY OF OCCURRENCE

Baseline

Alt “A”

Alt “B”

Risk Situation &

Probability Expected

Results % Probability of

Happening

% Probability of NOT

Happening

Page 10: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 10

REPEAT FOR ALL ALTERNATIVES

Baseline

Alt “A”

Alt “B”

Risk Situation &

Probability Expected

Results % Probability

% NOT

% Probability

% Probability

% NOT

% NOT

Page 11: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 11

IDENTIFY IMPACT -- EXPECTED OUTCOME

Baseline

Alt “A”

Alt “B”

Risk Situation &

Probability Expected

Results %

% Not

Page 12: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 12

IDENTIFY ANTICIPATED PAYOFF FOR

EACH POSSIBLE OUTCOME

Baseline

Alt “A”

Alt “B”

Risk Situation &

Probability Expected

Results %

% Not

1 TOTAL COST

2 TOTAL

BENEFIT &

3 NET BENEFIT

For Each Possible

Outcome

Page 13: DECISION TREE ANALYSIS - PMI

© 2013 Dr. Kenneth F. Smith, PMP Project Management Fundamentals Slide 13

DECISION TREES

Options

Options

&

Probabilities

&

Probabilities

Page 14: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 14

CALCULATE EXPECTED MONETARY VALUE (EMV)

for EACH OPTION -- Baseline & Alternatives

Baseline

Alt “A”

Alt “B”

Risk Situation &

Probability Expected

Results %

% Not

WORK

BACKWARDS:

1 Multiply the NET

BENEFIT of the

Outcome by its

Probability

2 Add the Results for

each ALTERNATIVE

EMV $ + $

EMV $ + $

EMV $ + $

Page 15: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 15

CALCULATE BENEFIT-COST RATIO (BCR)

BCR = EMV of Alternative - EMV of Baseline

Cost of Alternative

Page 16: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 16

Repeat for All Alternatives

BCR = EMV of Alternative - EMV of Baseline

Cost of Alternative

SELECT THE BEST OPTION

Page 17: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP

MAPPING & COMPUTING “EMV”

Slide 17

PMBOK

Example

NOTE: Alternatives

Only; No Baseline

Page 18: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 18

PMBOK EXAMPLE 2 Risk Probabilities: Build or

Upgrade Plant for Increased Customer Demands?

1

Build a New &

More Efficient

Plant

2

Upgrade

Existing Plant

SITUATION:

Anticipate

Increased

Demand for

Electricity by

Customers in a

New Area*

Estimated

Cost $120 m

Estimated

Cost $50 m

ALTERNATIVES RISK SCENARIO

PROBABILITY

Peak Service

Demand

Max Service

Demand

Low

Demand

Low

Demand

60 %

60 %

40 %

40 %

ESTIMATED

NET REVENUE*

NET

VALUE

(ER – EC)

$200 m

$90 m

$120 m

$60 m $10 m

$70 m

-$30 m

$80 m

*After Operating Costs --

based on relative efficiencies

of the respective plants *NOTE: Existing Plant incapable of meeting any Increased

Demand for Electricity by Customers in the New Area

Page 19: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 19

PMBOK EXAMPLE: Computation of Expected

Monetary Value (EMV)

1

Build a New &

More Efficient

Plant

2

Upgrade

Existing Plant

SITUATION:

Anticipate

Increased

Demand for

Electricity by

Customers in a

New Area

Estimated

Cost $120 m

Estimated

Cost $50 m

ALTERNATIVES RISK SCENARIO

PROBABILITY

Peak Service

Demand

Max Service

Demand

Low

Demand

Low

Demand

60 %

60 %

40 %

40 %

NET

VALUE

$10 m

$70 m

-$30 m

$80 m

(P x NV)

$48 m

-$12 m

$4 m

$42 m

EMV =

$46 m

EMV =

$36 m

Page 20: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 20

DECISION TREE 3 Risk Probabilities : Build /

Upgrade to meet Increased Customer Demands?

1

Build a New &

More Efficient

Plant

2

Upgrade

Existing Plant

SITUATION:

Anticipate

Increased

Demand for

Electricity by

Customers in a

New Area*

Estimated

Cost $120 m

Estimated

Cost $50 m

ALTERNATIVES RISK SCENARIO

PROBABILITY

Peak Service

Demand

Max Service

Demand

Medium

Demand

Medium

Demand

Low

Demand

Low

Demand

30 %

30 %

10 %

10 %

60 %

60 %

ESTIMATED

NET REVENUE*

NET

VALUE

(ER – EC)

$600 m

$400 m

$200 m

$350 m

$100 m

$250 m

$50 m

$200 m

$300 m

$80 m

$280 m

$480 m

*After Operating Costs --

based on relative efficiencies

of the respective plants *NOTE: Existing Plant incapable of meeting any Increased

Demand for Electricity by Customers in the New Area

Page 21: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP Slide 21

DECISION TREE 3 Risk Options: Computation

of Expected Monetary Value (EMV)

1

Build a New &

More Efficient

Plant

2

Upgrade

Existing Plant

SITUATION:

Anticipate

Increased

Demand for

Electricity by

Customers in a

New Area

Estimated

Cost $120 m

Estimated

Cost $50 m

ALTERNATIVES RISK SCENARIO

PROBABILITY

Peak Service

Demand

Max Service

Demand

Medium

Demand

Medium

Demand

Low

Demand

Low

Demand

30 %

30 %

10 %

10 %

60 %

60 %

NET

VALUE

$50 m

$200 m

$300 m

$80 m

$280 m

$480 m

(P x NV)

$144 m

$168 m

$8 m

$5 m

$120 m

$90 m

EMV =

$215 m

EMV =

$320 m

Page 22: DECISION TREE ANALYSIS - PMI

Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP

Risk IMPACT Planning

Slide 22

Later we will look again at

Major Overall Risks

in terms of their impact on

the Project

Schedule & Budget

and use the Decision Tree Analysis

to estimate the size of a

Management Reserve “Buffer”