Dead Run Stream Restoration Public Meeting May 19, 2015
-
Upload
fairfax-county -
Category
News & Politics
-
view
1.468 -
download
0
Transcript of Dead Run Stream Restoration Public Meeting May 19, 2015
A Fairfax County, VA, publication
Department of Public Works and Environmental ServicesWorking for You!
Dead Run Segment 2/3 Stream Restoration Project
Public Meeting
McLean Community Center
May 19, 2015
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Meeting Outline
2
• Project Scope and Status• Plan Summary and response to citizen comments• Concept Plan Overview
– Basis for design– Tree save options– Floodplain analysis and review of more frequent storm impacts– Buffer restoration measures– Examples
• Next Steps• Q and A• Walk to site
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Project Limits
3
Segment 2 – McLean Central Park
• 800 Linear Feet
• Completely in Park
• Starts below previously restored section near library
Segment 3 – Dead Run Stream Valley Park
• 1,500 Linear Feet
• Extends to Churchill Road
• Residential lots along Elizabeth Drive and Carol Rayes Street
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Project timeline
4
• Project initiated: Fall, 2013
• Surveys and assessment completed: Winter, 2013
• Pre-concepts submitted: April, 2014
• First public meeting – April 23, 2014
• Field walk with FCPA, MTA, Urban Forestry – August 15, 2014
• Pre-concept revisions to minimize tree loss completed: February, 2015
• Second public meeting – February 18, 2015
• Revised concept plan with alternative access options for Segment 3: completed May 12, 2015
• First field walk with community – May 19, 2015
• Second field walk with community – June 9, 2015
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Overview of Plans
5
• _PG1-27.pdf: Existing and proposed conditions (plan, profile, and cross-sections)
- Plan: Bird’s eye view
- Profile: Change in elevations along the proposed stream channel centerline
- Cross-sections: View of a section taken perpendicular to the channel centerline at a particular location.
• _PG28-31a.pdf: Plan view of access with and without aerial photography background – two options for Segment 3
• _PG32-43.pdf: Hydrology (flows) summary, and hydraulics (water surface elevations) of existing and proposed conditions
• Excel files: Tree inventory – diameter, condition, removal status
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Summary of comments received
6
• Need to understand full scope of project:
• Access points, how they will be secured, personal liability if county seeks to access our property (_PG28-31a)
• Type/Size of equipment that will be used (Do not dictate means and methods, equipment proposed by contractor can be shared by contractor at Pardon Our Dust meeting)
• Consideration of alternative modes of accessing creek that could reduce impact on foliage (_PG28-31a – also discussed in detail later)
• Duration of project, hours of construction, how long neighborhood will be denied access to pathways (Estimated 6-9 months, Standard work hours are 7am – 5 pm. Loss of access to trails will be minimized to the extent possible)
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Summary of comments received
7
• Need to understand full scope of project:
• Any revision to path of creek (_PG1-27.pdf)
• Impact on topography and what type of approach will be used in what parts of creeks (terracing, widening) (_PG1-27.pdf)
• Commitment of funding for replacement of lost trees and maintenance by county to ensure trees survive (_PG28-31a)
• Aesthetic impact of sediment erosion techniques. (Erosion and Sediment controls are detailed as part of the final plans, all structures proposed to be installed are shown in the plan and profile).
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Summary of comments received
8
• How flooding concerns will be addressed:
• Creek jumps the bank a few times a year and threatens to flood homes
• Danger of flash floods in the park, property of nearby residences, and Churchill Road bridge
(_PG32-43.pdf, also discussed in detail later)
Recurrence
Interval Probability
100-year 1%
10-year 10%
2-year 50%
1-year approaches 100%
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Summary of comments received
9
• How flooding concerns will be addressed (continued):
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Churchill Road Bridge Flooding
10
• VDOT inspection reports indicate no deficiencies with the bridge.• No current or future project planned for the bridge. • Not subject to frequent closures because of overtopping.
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Summary of comments received
11
• Loss of tree canopy:
• Desire strong measures to maintain and preserve the existing canopy
• Anticipated tree impacts shown on plan sheets – 6-12” tree impacts for Segment 3 access options being updated
• Tree save efforts discussed in detail later
• Proposed buffer restoration measures discussed in detail later
1 Basis for Design
• Stable Channel
• Understanding of
Floodplain
• Address Erosion
1 Basis for Design • Natural Channel Design (NCD) Approach – reference reach, analytical,
regional relationships and hydraulic analysis
• Stream pattern, profile and section
• Range of values for stable stream pattern
• Tree loss is unavoidable but provides opportunity to improve riparian diversity
1 Basis for Design
• Establish Goals:
• 1. Improve Flow Conditions in the Channel through Adjustments to Plan/Profile/Section
• 2. Create a Stable Channel by Reducing Bed/Bank Erosion that has Benefit of Reducing Contributions of Nitrogen and Phosphorus (i.e. Water Quality Improvement)
• 3. Improve Channel Geomorphology and Opportunities for Species Diversity (i.e. Use Structures to Stabilize Channel and Create Pool Habitats)
• 4. No-Rise / No-Impact of the Floodplain
2 Tree Save Efforts
12” and Larger Trees:
• ~557 trees 12” and larger assessed
• ~43 trees 12” and larger are “at risk”
• Species: ~32% tulip tree, ~27% red maple, ~7% green ash
6-12” Trees:
• ~214 trees 6-12” assessed
• ~28 trees 6-12” are “at risk”
• Species: ~23% red maple, ~21% boxelder, ~18% slippery elm, ~11% green ash
2 Tree Save Efforts
• Pre-Concept Plan (Feb. 2014) = ~137 trees 12” and larger removed. This was same plan walked in August 2014.
• Concept Plan (Feb. 2015) = ~110 trees 12” and larger removed. Initial alternative access options developed.
• Since Feb. 2015 meeting, we’ve modified the channel layout and access options, and located 6 to 12” size trees.
2 Tree Save Efforts
Some of the saved trees
2 Tree Save Efforts
Some of the saved trees
2 Tree Save Efforts
Some of the saved trees
2 Tree Save Efforts
Some of the saved trees
3 Access Options
• Current Plan (May 2015) = ~88 trees 12” and larger proposed
for removal, of which ~23 are “at risk”. Up to 10 additional
trees could be removed due to access. ~133 trees 6-12”
proposed for removal, of which ~28 are “at risk”. Up to 20
additional trees could be removed due to access.
• 12” and Larger Trees species most affected:• ~24% tulip tree, ~20% red maple, ~17% green ash
• 6-12” Trees most affected:• ~20% red maple, ~27% boxelder, ~20% slippery elm, ~13% green ash
• Woody vegetation should not be in the sanitary easement and is subject to removal by Wastewater at any time.
3 Access Options
Segment 2
Tree DEC474 has been removed
3 Access Options
Segment 3 Alternative 1
Removals due to access are primarily on the left bank. ~9 trees (~2 >12” and ~7 6-12” size)
Trees DEC91 & DEC301 have been removed
3 Access Options
Segment 3 Alternative 2
Removals due to access are primarily on the right bank. ~21 trees (~7 are >12” and ~14 are 6-12” size) – most are within the sanitary easement
4 Floodplain Analysis• Studied more frequent storm events 1-, 2-, 10- year flows
• Studied less frequent storm events 50-, 100- year flows
• No-Rise / No-impact to the floodplain
• See pages 32-43 of plan
4 Floodplain Analysis
Pre/Post Comparison – Existing Section 13552 year flow out of banks
• Existing Conditions Analysis
4 Floodplain Analysis
Pre/Post Comparison – Existing Section 1355Proposed Channel and Nested Channel
4 Floodplain Analysis
Pre/Post Comparison 100 and 10 yearTypical Channel Section
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Stream Restoration Pictures
29
Government Center Stream Restoration - Before and After
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Stream Restoration Pictures
30
Poplar Springs, Burke - Before and After
Stream Restoration
Stormwater Management
Dead Run at Dolley Madison Library
31
Stream Restoration
Stormwater Planning Division
Dead Run at Dolley Madison Library
32
August 2014 Right
January 2010 Below
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Stream Buffer Restoration Potential
33
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Chesapeake Bay Preservation Ordinance
Resource Protection Area (RPA)
34
http://www.fairfaxcounty.gov/dpwes/environmental/cbay/
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Stream Buffer Existing Conditions
35
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Stream Buffer Restoration Potential
36
Segment 3 Stream Buffer Concept
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Stream Buffer Restoration - Example
37
Typical Planting Area
County Staff will coordinate with individual homeowners on plant selection and placement on their properties
Buffer Parameters
35’ Minimum from edge of stream bank
50’ Offset optional
Plant density determined by Chesapeake Bay PreservationOrdinance
Dense planting will provide privacy screening and help mitigate tree loss
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Stream Buffer Restoration - Example
38
Shrub Layer
Typical ShrubSpecies
SpicebushAmerican ElderberryWitch HazelWinterberry HollySilky DogwoodButton Bush
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Stream Buffer Restoration - Example
39
Understory Trees
Typical UnderstorySpecies
Sweetbay MagnoliaEastern RedbudAmerican HornbeamHazel AlderSlippery ElmSassafras
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division
Stream Buffer Restoration
40
Canopy Layer
Canopy Tree
EvergreenUnderstory
Tree
DeciduousUnderstory
Tree
ShrubTypical CanopyTree Species
Sugar MapleRiver BirchAmerican BasswoodCommon PersimmonSwamp White OakPin OakWillow OakBlack Gum
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration Project
Next steps with target dates
41
• Receive concept design comments by June 19th, 2015
• Compile comments, finalize concept plans and publish to website by July 10th, 2015
• Develop 95% design plans, permitting by September, 2015
• Final design phase public meeting, October, 2015
• Final plan authorization and bidding phase – TBD based on funding and approved budget
• Target is late spring/early summer, 2016
• Sequence with Dead Run Segment 1 (Dominican Retreat)
• Pardon Our Dust meeting with residents and contractor before issuing construction notice to proceed.
Additional Information
For additional information, please contact
www.fairfaxcounty.gov/dpwes
Dead Run Segment 2/3 Stream Restoration Project
Stormwater Planning Division 42
Dipmani Kumar
703-324-5500