Dead Run Stream Restoration Public Meeting May 19, 2015

42
A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Dead Run Segment 2/3 Stream Restoration Project Public Meeting McLean Community Center May 19, 2015

Transcript of Dead Run Stream Restoration Public Meeting May 19, 2015

Page 1: Dead Run Stream Restoration Public Meeting May 19, 2015

A Fairfax County, VA, publication

Department of Public Works and Environmental ServicesWorking for You!

Dead Run Segment 2/3 Stream Restoration Project

Public Meeting

McLean Community Center

May 19, 2015

Page 2: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Meeting Outline

2

• Project Scope and Status• Plan Summary and response to citizen comments• Concept Plan Overview

– Basis for design– Tree save options– Floodplain analysis and review of more frequent storm impacts– Buffer restoration measures– Examples

• Next Steps• Q and A• Walk to site

Page 3: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Project Limits

3

Segment 2 – McLean Central Park

• 800 Linear Feet

• Completely in Park

• Starts below previously restored section near library

Segment 3 – Dead Run Stream Valley Park

• 1,500 Linear Feet

• Extends to Churchill Road

• Residential lots along Elizabeth Drive and Carol Rayes Street

Page 4: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Project timeline

4

• Project initiated: Fall, 2013

• Surveys and assessment completed: Winter, 2013

• Pre-concepts submitted: April, 2014

• First public meeting – April 23, 2014

• Field walk with FCPA, MTA, Urban Forestry – August 15, 2014

• Pre-concept revisions to minimize tree loss completed: February, 2015

• Second public meeting – February 18, 2015

• Revised concept plan with alternative access options for Segment 3: completed May 12, 2015

• First field walk with community – May 19, 2015

• Second field walk with community – June 9, 2015

Page 5: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Overview of Plans

5

• _PG1-27.pdf: Existing and proposed conditions (plan, profile, and cross-sections)

- Plan: Bird’s eye view

- Profile: Change in elevations along the proposed stream channel centerline

- Cross-sections: View of a section taken perpendicular to the channel centerline at a particular location.

• _PG28-31a.pdf: Plan view of access with and without aerial photography background – two options for Segment 3

• _PG32-43.pdf: Hydrology (flows) summary, and hydraulics (water surface elevations) of existing and proposed conditions

• Excel files: Tree inventory – diameter, condition, removal status

Page 6: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of comments received

6

• Need to understand full scope of project:

• Access points, how they will be secured, personal liability if county seeks to access our property (_PG28-31a)

• Type/Size of equipment that will be used (Do not dictate means and methods, equipment proposed by contractor can be shared by contractor at Pardon Our Dust meeting)

• Consideration of alternative modes of accessing creek that could reduce impact on foliage (_PG28-31a – also discussed in detail later)

• Duration of project, hours of construction, how long neighborhood will be denied access to pathways (Estimated 6-9 months, Standard work hours are 7am – 5 pm. Loss of access to trails will be minimized to the extent possible)

Page 7: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of comments received

7

• Need to understand full scope of project:

• Any revision to path of creek (_PG1-27.pdf)

• Impact on topography and what type of approach will be used in what parts of creeks (terracing, widening) (_PG1-27.pdf)

• Commitment of funding for replacement of lost trees and maintenance by county to ensure trees survive (_PG28-31a)

• Aesthetic impact of sediment erosion techniques. (Erosion and Sediment controls are detailed as part of the final plans, all structures proposed to be installed are shown in the plan and profile).

Page 8: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of comments received

8

• How flooding concerns will be addressed:

• Creek jumps the bank a few times a year and threatens to flood homes

• Danger of flash floods in the park, property of nearby residences, and Churchill Road bridge

(_PG32-43.pdf, also discussed in detail later)

Recurrence

Interval Probability

100-year 1%

10-year 10%

2-year 50%

1-year approaches 100%

Page 9: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of comments received

9

• How flooding concerns will be addressed (continued):

Page 10: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Churchill Road Bridge Flooding

10

• VDOT inspection reports indicate no deficiencies with the bridge.• No current or future project planned for the bridge. • Not subject to frequent closures because of overtopping.

Page 11: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Summary of comments received

11

• Loss of tree canopy:

• Desire strong measures to maintain and preserve the existing canopy

• Anticipated tree impacts shown on plan sheets – 6-12” tree impacts for Segment 3 access options being updated

• Tree save efforts discussed in detail later

• Proposed buffer restoration measures discussed in detail later

Page 12: Dead Run Stream Restoration Public Meeting May 19, 2015

1 Basis for Design

• Stable Channel

• Understanding of

Floodplain

• Address Erosion

Page 13: Dead Run Stream Restoration Public Meeting May 19, 2015

1 Basis for Design • Natural Channel Design (NCD) Approach – reference reach, analytical,

regional relationships and hydraulic analysis

• Stream pattern, profile and section

• Range of values for stable stream pattern

• Tree loss is unavoidable but provides opportunity to improve riparian diversity

Page 14: Dead Run Stream Restoration Public Meeting May 19, 2015

1 Basis for Design

• Establish Goals:

• 1. Improve Flow Conditions in the Channel through Adjustments to Plan/Profile/Section

• 2. Create a Stable Channel by Reducing Bed/Bank Erosion that has Benefit of Reducing Contributions of Nitrogen and Phosphorus (i.e. Water Quality Improvement)

• 3. Improve Channel Geomorphology and Opportunities for Species Diversity (i.e. Use Structures to Stabilize Channel and Create Pool Habitats)

• 4. No-Rise / No-Impact of the Floodplain

Page 15: Dead Run Stream Restoration Public Meeting May 19, 2015

2 Tree Save Efforts

12” and Larger Trees:

• ~557 trees 12” and larger assessed

• ~43 trees 12” and larger are “at risk”

• Species: ~32% tulip tree, ~27% red maple, ~7% green ash

6-12” Trees:

• ~214 trees 6-12” assessed

• ~28 trees 6-12” are “at risk”

• Species: ~23% red maple, ~21% boxelder, ~18% slippery elm, ~11% green ash

Page 16: Dead Run Stream Restoration Public Meeting May 19, 2015

2 Tree Save Efforts

• Pre-Concept Plan (Feb. 2014) = ~137 trees 12” and larger removed. This was same plan walked in August 2014.

• Concept Plan (Feb. 2015) = ~110 trees 12” and larger removed. Initial alternative access options developed.

• Since Feb. 2015 meeting, we’ve modified the channel layout and access options, and located 6 to 12” size trees.

Page 17: Dead Run Stream Restoration Public Meeting May 19, 2015

2 Tree Save Efforts

Some of the saved trees

Page 18: Dead Run Stream Restoration Public Meeting May 19, 2015

2 Tree Save Efforts

Some of the saved trees

Page 19: Dead Run Stream Restoration Public Meeting May 19, 2015

2 Tree Save Efforts

Some of the saved trees

Page 20: Dead Run Stream Restoration Public Meeting May 19, 2015

2 Tree Save Efforts

Some of the saved trees

Page 21: Dead Run Stream Restoration Public Meeting May 19, 2015

3 Access Options

• Current Plan (May 2015) = ~88 trees 12” and larger proposed

for removal, of which ~23 are “at risk”. Up to 10 additional

trees could be removed due to access. ~133 trees 6-12”

proposed for removal, of which ~28 are “at risk”. Up to 20

additional trees could be removed due to access.

• 12” and Larger Trees species most affected:• ~24% tulip tree, ~20% red maple, ~17% green ash

• 6-12” Trees most affected:• ~20% red maple, ~27% boxelder, ~20% slippery elm, ~13% green ash

• Woody vegetation should not be in the sanitary easement and is subject to removal by Wastewater at any time.

Page 22: Dead Run Stream Restoration Public Meeting May 19, 2015

3 Access Options

Segment 2

Tree DEC474 has been removed

Page 23: Dead Run Stream Restoration Public Meeting May 19, 2015

3 Access Options

Segment 3 Alternative 1

Removals due to access are primarily on the left bank. ~9 trees (~2 >12” and ~7 6-12” size)

Trees DEC91 & DEC301 have been removed

Page 24: Dead Run Stream Restoration Public Meeting May 19, 2015

3 Access Options

Segment 3 Alternative 2

Removals due to access are primarily on the right bank. ~21 trees (~7 are >12” and ~14 are 6-12” size) – most are within the sanitary easement

Page 25: Dead Run Stream Restoration Public Meeting May 19, 2015

4 Floodplain Analysis• Studied more frequent storm events 1-, 2-, 10- year flows

• Studied less frequent storm events 50-, 100- year flows

• No-Rise / No-impact to the floodplain

• See pages 32-43 of plan

Page 26: Dead Run Stream Restoration Public Meeting May 19, 2015

4 Floodplain Analysis

Pre/Post Comparison – Existing Section 13552 year flow out of banks

• Existing Conditions Analysis

Page 27: Dead Run Stream Restoration Public Meeting May 19, 2015

4 Floodplain Analysis

Pre/Post Comparison – Existing Section 1355Proposed Channel and Nested Channel

Page 28: Dead Run Stream Restoration Public Meeting May 19, 2015

4 Floodplain Analysis

Pre/Post Comparison 100 and 10 yearTypical Channel Section

Page 29: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Stream Restoration Pictures

29

Government Center Stream Restoration - Before and After

Page 30: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Stream Restoration Pictures

30

Poplar Springs, Burke - Before and After

Page 31: Dead Run Stream Restoration Public Meeting May 19, 2015

Stream Restoration

Stormwater Management

Dead Run at Dolley Madison Library

31

Page 32: Dead Run Stream Restoration Public Meeting May 19, 2015

Stream Restoration

Stormwater Planning Division

Dead Run at Dolley Madison Library

32

August 2014 Right

January 2010 Below

Page 33: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Stream Buffer Restoration Potential

33

Page 34: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Chesapeake Bay Preservation Ordinance

Resource Protection Area (RPA)

34

http://www.fairfaxcounty.gov/dpwes/environmental/cbay/

Page 35: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Stream Buffer Existing Conditions

35

Page 36: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Stream Buffer Restoration Potential

36

Segment 3 Stream Buffer Concept

Page 37: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Stream Buffer Restoration - Example

37

Typical Planting Area

County Staff will coordinate with individual homeowners on plant selection and placement on their properties

Buffer Parameters

35’ Minimum from edge of stream bank

50’ Offset optional

Plant density determined by Chesapeake Bay PreservationOrdinance

Dense planting will provide privacy screening and help mitigate tree loss

Page 38: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Stream Buffer Restoration - Example

38

Shrub Layer

Typical ShrubSpecies

SpicebushAmerican ElderberryWitch HazelWinterberry HollySilky DogwoodButton Bush

Page 39: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Stream Buffer Restoration - Example

39

Understory Trees

Typical UnderstorySpecies

Sweetbay MagnoliaEastern RedbudAmerican HornbeamHazel AlderSlippery ElmSassafras

Page 40: Dead Run Stream Restoration Public Meeting May 19, 2015

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division

Stream Buffer Restoration

40

Canopy Layer

Canopy Tree

EvergreenUnderstory

Tree

DeciduousUnderstory

Tree

ShrubTypical CanopyTree Species

Sugar MapleRiver BirchAmerican BasswoodCommon PersimmonSwamp White OakPin OakWillow OakBlack Gum

Page 41: Dead Run Stream Restoration Public Meeting May 19, 2015

Stormwater Planning Division

Dead Run Segment 2/3 Stream Restoration Project

Next steps with target dates

41

• Receive concept design comments by June 19th, 2015

• Compile comments, finalize concept plans and publish to website by July 10th, 2015

• Develop 95% design plans, permitting by September, 2015

• Final design phase public meeting, October, 2015

• Final plan authorization and bidding phase – TBD based on funding and approved budget

• Target is late spring/early summer, 2016

• Sequence with Dead Run Segment 1 (Dominican Retreat)

• Pardon Our Dust meeting with residents and contractor before issuing construction notice to proceed.

Page 42: Dead Run Stream Restoration Public Meeting May 19, 2015

Additional Information

For additional information, please contact

www.fairfaxcounty.gov/dpwes

Dead Run Segment 2/3 Stream Restoration Project

Stormwater Planning Division 42

Dipmani Kumar

703-324-5500

[email protected]