Project : Vinh Phuc Province Investment Climate Improvement Package CP-1: Main road though new urban zone of Me Linh METHOD STATEMENT FOR GEOTECHNICAL MONITORING OF EMBANKMENT ON SOFT SOIL QUY TRÌNH KỸ THUẬT QUAN TRẮC ĐỊA KỸ THUẬT NỀN ĐƯỜNG ĐẮP TRÊN ĐẤT YẾU --- --- PROJECT: VINH PHUC PROVINCE INVESTMENT CLIMATE IMPROVEMENT DỰ ÁN: CẢI THIỆN MÔI TRƯỜNG ĐẦU TƯ TỈNH VĨNH PHÚC PACKAGE CP-1: MAIN ROAD THROUGH NEW URBAN ZONE OF ME LINH GÓI THẦU SỐ 1: ĐƯỜNG TRỤC TRUNG TÂM KHU ĐÔ THỊ MỚI MÊ LINH OWNER: VINH PHUC PROVINCE PEOPLE’S COMMITTEE CHỦ ĐẦU TƯ: ỦY BAN NHÂN DÂN TỈNH VĨNH PHUC OWNER REPRESENTATION: VINH PHUC PROVINCE INVESTMENT CLIMATE IMPROVEMENT PROJECT MANAGEMENT UNIT (VPICI-PMU) ĐẠI DIỆN CHỦ ĐẦU TƯ: BAN QUẢN LÝ DỰ ÁN CẢI THIỆN MÔI TRƯỜNG ĐẦU TƯ TỈNH VĨNH PHÚC (VPICI-PMU) I. CÁC CĂN CỨ PHÁP LÝ VÀ TIÊU CHUẨN ÁP DỤNG – FOUNDATION ON PRINCIPAL OF LAW AND APPLICATION STANDARD - Bidding documents Volume IV – Drawings part 3.2.4 – Foundation treatment Hồ sơ mời thầu Tập IV – Các bản vẽ mục 3.2.4 - Xử lý nền. - Technical documents of the project; Hồ sơ kỹ thuật của dự án - Drawings for soft soil treatment for each line in the approved construction design drawings (setting by POSCO E & C Vietnam); Các bản vẽ xử lý nền trong cho từng đoạn tuyến trong hồ sơ thiết kế bản vẽ thi công đã được phê duyệt (do POSCO E&C Vietnam lập) - Construction methods for soft soil treatment (for the whole project) - established by POSCO E & C Vietnam, has been approved; Method statement for geotechnical monitoring of embankment on soft soil

Transcript of De Cuong Quan Trac (COGECO)

Page 1: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

METHOD STATEMENT FOR GEOTECHNICAL MONITORING OF EMBANKMENT ON SOFT SOIL

QUY TRÌNH KỸ THUẬT QUAN TRẮC ĐỊA KỸ THUẬT NỀN ĐƯỜNG ĐẮP TRÊN ĐẤT YẾU

--- ---

PROJECT: VINH PHUC PROVINCE INVESTMENT CLIMATE IMPROVEMENT

DỰ ÁN: CẢI THIỆN MÔI TRƯỜNG ĐẦU TƯ TỈNH VĨNH PHÚC

PACKAGE CP-1: MAIN ROAD THROUGH NEW URBAN ZONE OF ME LINH

GÓI THẦU SỐ 1: ĐƯỜNG TRỤC TRUNG TÂM KHU ĐÔ THỊ MỚI MÊ LINH

OWNER: VINH PHUC PROVINCE PEOPLE’S COMMITTEE

CHỦ ĐẦU TƯ: ỦY BAN NHÂN DÂN TỈNH VĨNH PHUC

OWNER REPRESENTATION: VINH PHUC PROVINCE INVESTMENT CLIMATE IMPROVEMENT PROJECT MANAGEMENT UNIT (VPICI-PMU)

ĐẠI DIỆN CHỦ ĐẦU TƯ: BAN QUẢN LÝ DỰ ÁN CẢI THIỆN MÔI TRƯỜNG ĐẦU TƯ TỈNH VĨNH PHÚC (VPICI-PMU)

I. CÁC CĂN CỨ PHÁP LÝ VÀ TIÊU CHUẨN ÁP DỤNG – FOUNDATION ON PRINCIPAL OF LAW AND APPLICATION STANDARD

- Bidding documents Volume IV – Drawings part 3.2.4 – Foundation treatment

Hồ sơ mời thầu Tập IV – Các bản vẽ mục 3.2.4 - Xử lý nền.

- Technical documents of the project;

Hồ sơ kỹ thuật của dự án

- Drawings for soft soil treatment for each line in the approved construction design drawings (setting by POSCO E & C Vietnam);

Các bản vẽ xử lý nền trong cho từng đoạn tuyến trong hồ sơ thiết kế bản vẽ thi công đã được phê duyệt (do POSCO E&C Vietnam lập)

- Construction methods for soft soil treatment (for the whole project) - established by POSCO E & C Vietnam, has been approved;

Hồ sơ biện pháp thi công xử lý nền (chung cho toàn dự án) – Do POSCO E&C Vietnam lập, đã được phê duyệt.

- TCVN 3972:1985 “Survey Work in Construction”;

TCVN 3972:1985 “Công tác trắc đạc trong xây dựng”.

- TCXD 271:2002 “Technical Requirements for Determining Settlement of Civil and Industrial Projects by Geometric Levelling”;

TCXDVN 271:2002 “Yêu cầu kỹ thuật cho việc xác định độ lún công trình dân dụng và công nghiệp bằng phương pháp đo cao hình học”.

Method statement for geotechnical monitoring of embankment on soft soil

Page 2: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

- TCXDVN 309:2004 “Survey Work in Project - Technical Requirements”;

TCXDVN 309:2004 “Công tác trắc đạc trong xây dựng – Các yêu cầu kỹ thuật”.

II. NỘI DUNG VÀ MỤC ĐÍCH CÔNG TÁC QUAN TRẮC ĐỊA KỸ THUẬT – CONTENT AND PURPOSES OF GEOTECHNICAL MONITORING

II.1. Content of monitoring / Nội dung công tác quan trắc

1. Surface settlement Plates (SSP)Quan trắc lún nông bằng bàn lún (SSP).

2. Deep Settlement Extensometer (DSE)Quan trắc lún sâu (DSE).

3. Electric Piezometer (EP)Đo áp lực nước lỗ rỗng (EP).

4. Lateral displacement observing stake (WP)Đo chuyển vị ngang bằng cọc gỗ (WP).

5. Observation Well (OW)Quan trắc cao độ mực nước tĩnh (OW).

II.2. Purposes of monitoring / Mục đích công tác quan trắc

- Monitoring of settlement at sand layer, monitoring of pore water pressure and elevation of ground water, monitoring of horizontal displacement

- Analyse datas (settlement and stability of embankment) acoording to monitoring datas. Calculate volume of settlment compensate for embankment.

- Base on data analysis for assessment:

Avaluate the efficiency of the soft soil treatment.

Adjust execution schedule.

Forecast unexpected risks which can emerge during execution and work out prevention and recovery (if any).

- Quan trắc độ lún tại lớp đệm cát, quan trắc áp lực nước lỗ rỗng và cao độ mực nước tĩnh, quan trắc sự dịch chuyển ngang của nền đất.

- Phân tích các số liệu (độ lún, độ ổn định) theo các số liệu quan trắc. Xác định khối lượng bù lún nền đường đắp.

- Trên cơ sở phân tích để đánh giá:

Đánh giá hiệu quả của các biện pháp xử lý nền đất yếu.

Điều chỉnh tiến độ thi công.

Dự báo các sự cố có thể xảy ra trong quá trình thi công, đưa ra các biện pháp ngăn ngừa và cách khắc phục nếu xảy ra.

Method statement for geotechnical monitoring of embankment on soft soil

Page 3: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

III. THIẾT BỊ QUAN TRẮC – MONITORING EQUIPMENT

The technical characteristics of equipment to be used for the embankment monitoring works are described as follows:

Các thiết bị sử dụng trong công tác quan trắc có các đặc tính kỹ thuật như sau:

III.1. Monitoring equipment for Surface settlement plates & Deep settlement extensometer

Thiết bị quan trắc lún cho công tác quan trắc lún nông bằng bàn lún và quan trắc lún sâu

a. Mục đích - Purpose:

Settlement monitoring for Surface settlement Plates & Deep Settlement Extensometer is to calculate the settlement rate and degree of consolidation during the execution and when works is taken into exploitation. Base on the settlement monitoring data, the Engineer cosultant and Contractor can:

- Adjust the backfill schedule considering the settlement rate and the total settlement of the foundation soil.

- Timely detect and treat the slope instability of the embankment.

- Evaluate the efficiency of soft soil treatment.

- Caculate the expected final settlement of the embankment.

- Determine the time to remove the surcharge for construction of road surface structure and the other works.

- Caculate volume of settlement compensate during construction.

Công tác quan trắc lún nông bằng bàn lún và quan trắc lún sâu nhằm xác định tốc độ lún và độ lún của đất nền trong quá trình thi công và khi đưa công trình vào khai thác. Trên cơ sở số liệu đo lún giúp Tư vấn và Nhà thầu:

- Điều chỉnh tiến độ đắp thông qua tốc độ lún và độ lún nền đường.

- Phát hiện và xử lý kịp thời nguy cơ trượt nền đường đắp.

- Đánh giá hiệu quả xử lý nền đất yếu.

- Làm cơ sở tính độ lún cuối cùng của nền đường.

- Xác định thời điểm dỡ tải và thi công kết cấu mặt đường và các công trình khác trên tuyến.

- Xác định khối lượng bù lún do nền đường bị lún trong quá trình thi công.

b. Thiết bị - Equipment:

Base on requirements of the project, at Section block 1, block 5 and block 9 the settlement plate will be installed as like as design data on construction drawings.

Theo yêu cầu của dự án, tại các gói số 1, số 5 và số 9 bàn đo lún bề mặt sẽ được lắp đặt tại các vị trí theo quy định của thiết kế trong trong bản vẽ thi công.

Method statement for geotechnical monitoring of embankment on soft soil

Page 4: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

The equipment will be used included:

Thiết bị sử dụng bao gồm:

- Surface settlment plate: steel plate 0.50 x 0.50 m with thickness 1.0 cm.

- Bàn đo lún bề mặt: tấm thép kích thước 0.50 x 0.50 m, dày 1.0 cm

Method statement for geotechnical monitoring of embankment on soft soil

SURFACE SETTLEMENT PLATE (ssp)

BÀN ÐO LÚN BỀ MẶT

Page 5: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

- Deep settlment extensometr: 10cm In diameter steel spiral foot.

- Thiết bị quan trắc lún sâu: thép xoắn lò so đường kính 10cm.

- Leveling machine used to measure the surface settlement is PENTAX - JAPAN

- Máy thủy chuẩn dùng để đo độ lún là máy PENTAX - JAPAN

-

Method statement for geotechnical monitoring of embankment on soft soil

DEEP SETTLEMENT PLATE (DSP)

Leveling machine PENTAX (Máy thủy chuẩn PENTAX)

Page 6: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

Table 1. The main technical features of the machine PENTAX AP281

Bảng 1. Các tính năng kỹ thuật chủ yếu của máy PENTAX AP281

Tính năng kỹ thuật / Technical Features Trị số / Value

Độ phóng đại của ống kính / Magnification of the lens 30x

Trường nhìn / field of view 1 30’

Độ chính xác / Accuracy 2mm

Khoảng cách ngắn nhất / The shortest distance 0.4m

III.2. Equipment for Lateral displacement observing stake (Wood pile)

Đo chuyển vị ngang bằng cọc gỗ

a. Purpose - Purpose:

The purpose of horizontal displacement monitoring at the ground surface adjacent to the roadway embankment is to be performed by observing the displacement of the alignment wood stake. The alignment stake will be placed into the ground surface along the embankment. Observing the displacement of the alignment stake helps the Engineer cosultant and the Contractor in checking the movement of the ground on either side of the embankment, from which slope instability of the embankment can be evaluated for the timely treatment. Position information is determined on the construction drawings.

The purpose of horizontal displacement monitoring at the ground surface adjacent to the roadway embankment is to be performed by observing the displacement of the alignment wood stake. The alignment stake will be placed into the ground surface along the embankment. Observing the displacement of the alignment stake helps the Engineer cosultant and the Contractor in checking the movement of the ground on either side of the embankment, from which slope instability of the embankment can be evaluated for the timely treatment. Position information is determined on the construction drawings.

b. Thiết bị / Equipment:

- The alignment stake is made of wood with the dimension 10 x 10cm, length of 170cm, 120cm deep install into the soil. At the top of wood bar is staked nail 5 (5cm long) which is the foundation for locating the pile.

- Cọc đo chuyển vị ngang được làm bằng thanh gỗ kích thước 10 x 10cm, dài 170cm, đóng sâu vào đất 120cm. Trên đỉnh thanh gỗ được đóng đinh 5 (dài 5cm) làm cơ sở định vị cọc.

Method statement for geotechnical monitoring of embankment on soft soil

Page 7: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

- Equipment is used to horizontal displacement monitoring is electronic Total Station with high precision TOPCON -235N manufactured by Japan or the machine with precision equivalent. In addition, the device comes as a tripod, concentration of optical, mini mirror, round mirror ...

- Thiết bị sử dụng để quan trắc là máy toàn đạc điện tử độ chính xác cao TOPCON-235N do Nhật chế tạo hoặc các máy có độ chính xác tương đương. Ngoài ra còn các thiết bị đi kèm như chân máy, bộ định tâm quang học, gương mini, gương tròn…

Method statement for geotechnical monitoring of embankment on soft soil

FRENCH NAIL

GROUND LEVEL

LATERAL DISPLACEMENT OBSERVING STAKE (OW)

WOODEN STAKE

Ðinh sắt

Cao độ tự nhiên

Cọc gỗ

Page 8: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

Table 2. The main technical features of the Total Station TOPCON 235N

Bảng 2. Các tính năng kỹ thuật chủ yếu của máy toàn đạc điện tử TOPCON 235N

Tính năng kỹ thuật / Technical Features Trị số / value

Hệ thống quang học / Optical system

Độ mở của ống kính / Aperture of the lens 45mm

Độ phóng đại của ống kính / Magnification of the lens

30x

Trường nhìn / field of view 1 30’

Hệ thống đo góc / angle measuring system

Độ chính xác đo góc ngang /

Horizontal angle measurement accuracy5” (1.5 mgon)

Độ chính xác đo góc đứng /

Vertical angle measurement accuracy5” (1.5 mgon)

Đo khoảng cách / distance measurement

Độ chính xác đo khoảng cách /

Distance measurement accuracy

a. Chương trình đo tiêu chuẩn /

Standard measuring program(3mm +5ppmD)

b. Chương trình đo chính xác /

Accurately measuring program(3mm +3ppmD)

Khoảng cách đo lớn nhất / Largest measurement distance

Tầm nhìn kém / poor vision 2000m

Tầm nhìn trung bình / Average vision 2700m

Tầm nhìn kém / Good vision 2700m

III.3. Monitoring equipment for Electric Piezometer

Thiết bị đo áp lực nước lỗ rỗng bằng điện

a. Purpose - Mục đích:

The purpose of electric piezometer is to observe the variation of the pore pressure in the

Method statement for geotechnical monitoring of embankment on soft soil

Total station TOPCON 235N and mini mirror(Máy toàn đạc TOPCON 235N và gương Mini)

Page 9: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

soft soil layer to gather the information necessary in evaluating the efficiency off the soft soil treatment. Based on the pore pressure measurement, the Contractor may adjust the execution schedule and forecast the ground behavior which can emerge during construction of the embankment.

Thiết bị đo áp lực nước lỗ rỗng bằng điện cho phép đo áp lực nước lỗ rỗng trong tầng đất yếu để cung cấp số liệu cho Nhà thầu, Tư vấn nhằm đánh giá hiệu quả xử lý nền đất yếu, điều chỉnh tiến độ thi công và dự báo các hiện tượng địa chất công trình bất lợi phát sinh trong quá trình thi công.

b. Thiết bị - Equipment:

- The equipment for measuring pore water pressure(vibrating wire style) will be placed in the boring hole in the designed depth. Using the standard monitoring head of GTC Vibrating Wire Piezometer – Korea.

- A cable connecting between the piezometer head and data logging equipment will be on the surface.

- The data recorder GEOKON 403 will be connected to the monitoring head by a leading cable.

- Đầu đo áp lực nước lỗ rỗng kiểu dây rung được lắp đặt trong lỗ khoan ở các độ sâu thiết kế. sử dụng đầu đo áp kế tiêu chuẩn loại GTC Vibrating Wire Piezometer – Hàn Quốc.

- Dây nối giữa đầu đo và máy đo trên mặt đất.

- Máy đo (hộp thu tín hiệu) Geokon 403: Được nối với đầu đo qua dây dẫn.

Method statement for geotechnical monitoring of embankment on soft soil

Page 10: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

Method statement for geotechnical monitoring of embankment on soft soil

GROUT

BORE HOLE

SAND BLANKET

EMBANKMENT

BENTONITE PELLET SEAL

SIGNAL CABLE

ELECTRICAL TRANSDUCER

CLEAN SAND (SATURATION)

Page 11: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

III.4. Giếng quan trắc mực nước tĩnh - Observation well

Ground water monitoring work determines level of undergruond water in embankment area. The monitoring data combined with piezometer measurement the foundation soil under embankment is to evaluate the efficiency of the soft soil treatment; and to detect and timely treat the slop instabilyty of the road embankment during the execution period.

Nhằm xác định cao độ nước ngầm trong phạm vi nền đường và khu vực xung quanh, kết hợp với tài liệu quan trắc áp lực nước lỗ rỗng của đất nền để đánh giá quá trình sử lý đất nền đất yếu. Phát hiện và sử lý các sự cố trong quá trình thi công tuyến đường.

The level of underground water is observed near the piezometer monitorig area. The location and depth of observation well are showed in observation plan.

Nước ngầm được quan trắc trong các giếng bố trí gần các vị trí quan trắc áp lực nước lỗ rỗng. Vị trí và độ sâu giếng được thể hiện tại bảng bố trí thiết bị quan trắc.

Surface settlement Plates (SSP)Quan trắc lún nông bằng bàn lún (SSP).

Deep Settlement Extensometer (DSE)Quan trắc lún sâu (DSE).

Electric Piezometer (EP)Đo áp lực nước lỗ rỗng (EP).

Lateral displacement observing stake (WP)Đo chuyển vị ngang bằng cọc gỗ (WP).

Observation Well (OW)Quan trắc cao độ mực nước tĩnh (OW).

Method statement for geotechnical monitoring of embankment on soft soil

Đầu đo áp lực nước lỗ rỗng GTC (GTC Vibrating Wire Piezometer)

Máy đo Geokon 403 (Data recorder GEOKON 403)

Page 12: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

IV. QUANTITY OF MONITORING - KHỐI LƯỢNG QUAN TRẮC

The quantity of monitoring works at block 1, block 5, block 9 are listed below:

Khối lượng quan trắc cho các gói 1, 5, 9 được liệt kê theo bảng sau:

III.1. Block 1 – Gói số 1:

STT

ID

Nội dung công việc

- Description

Đơn vị

Unit

Khối lượng

Quantity

1 Surface settlement Plates (SSP)Quan trắc lún nông bằng bàn lún (SSP)

SetBộ

9

2 Deep Settlement Extensometer (DSE)Quan trắc lún sâu (DSE)

SetBộ

3

3 Electric Piezometer (EP)Đo áp lực nước lỗ rỗng (EP)

SetBộ

9

4 Lateral displacement observing stake (WP)Đo chuyển vị ngang bằng cọc gỗ (WP)

Set

Bộ18

5 Observation Well (OW)Quan trắc cao độ mực nước tĩnh (OW)

Set

Bộ3

Method statement for geotechnical monitoring of embankment on soft soil

Page 13: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

III.2. Block 5 – Gói số 5:

STT

ID

Nội dung công việc

- Description

Đơn vị

Unit

Khối lượng

Quantity

1 Surface settlement Plates (SSP)Quan trắc lún nông bằng bàn lún (SSP)

SetBộ

39

2 Deep Settlement Extensometer (DSE)Quan trắc lún sâu (DSE)

SetBộ

13

3 Electric Piezometer (EP)Đo áp lực nước lỗ rỗng (EP)

SetBộ

39

4 Lateral displacement observing stake (WP)Đo chuyển vị ngang bằng cọc gỗ (WP)

Set

Bộ78

5 Observation Well (OW)Quan trắc cao độ mực nước tĩnh (OW)

Set

Bộ

13

III.3. Block 9 – Gói số 9:

STT

ID

Nội dung công việc

- Description

Đơn vị

Unit

Khối lượng

Quantity

1 Surface settlement Plates (SSP)Quan trắc lún nông bằng bàn lún (SSP)

SetBộ

6

2 Deep Settlement Extensometer (DSE)Quan trắc lún sâu (DSE)

SetBộ

2

3 Electric Piezometer (EP)Đo áp lực nước lỗ rỗng (EP)

SetBộ

6

4 Lateral displacement observing stake (WP)Đo chuyển vị ngang bằng cọc gỗ (WP)

Set

Bộ12

5 Observation Well (OW)Quan trắc cao độ mực nước tĩnh (OW)

Set

Bộ

2

V. EQUIPMENT INSTALLATION & MONITORING

LẮP ĐẶT THIẾT BỊ VÀ QUAN TRẮC

Installation and monitoring works shall meet the demand of project specifications and requirements of each equiment.

Công tác lắp đặt và quan trắc được thực hiện theo chỉ dẫn kỹ thuật của dự án và các quy định của từng loại thiết bị.

V.1. Equipment Installation and monitoring for Surface settlement Plates

Lắp đặt thiết bị và quan trắc lún nông bằng bàn lún

Method statement for geotechnical monitoring of embankment on soft soil

Page 14: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

a. Installation / Lắp đặt:

The settlement plates will be installed by technical notice in specification of project.

Base on the embankment schedule and elevation of embankment filling, the Contrator connects the monitoring piles together, ensuring that the head of stakes for settlement an the measurement is always higher the embankment height.

Các bàn đo lún được lắp đặt mới theo chỉ dẫn trong tiêu chuẩn kỹ thuật của dự án.

Căn cứ vào tiến độ đắp và chiều cao đắp, Nhà thầu tiến hành nối các đoạn ống quan trắc, đảm bảo cao độ đỉnh cần đo lún luôn cao hơn hoặc bằng cao độ nền đắp.

b. Quan trắc/ Monitoring:

Measure the elevation top of the surface setttlement plate, the caculating the settlement of foundation soil between each monitoring cycle and total settlement of foundation soil.

Đo cao độ đỉnh của các điểm cần đo lún bề mặt, từ đó xác định độ lún giữa các chu kỳ đo và tổng độ lún của đất nền.

V.2. Equipment Installation and monitoring for Deep Settlement Extensometer

Lắp đặt thiết bị và quan trắc lún sâu

a. Installation / Lắp đặt:

The Deep Settlement Extensometer will be installed by technical notice in specification of project.

Base on the embankment schedule and elevation of embankment filling, the Contrator connects the monitoring piles together, ensuring that the head of stakes for settlement an the measurement is always higher the embankment height.

Các thiết bị đo lún sâu được lắp đặt mới theo chỉ dẫn trong tiêu chuẩn kỹ thuật của dự án.

Căn cứ vào tiến độ đắp và chiều cao đắp, Nhà thầu tiến hành nối các đoạn ống quan trắc, đảm bảo cao độ đỉnh cần đo lún luôn cao hơn hoặc bằng cao độ nền đắp.

b. Quan trắc/ Monitoring:

Measure the elevation top of the surface setttlement plate, the caculating the settlement of foundation soil between each monitoring cycle and total settlement of soil layer at monitoring area.

Đo cao độ đỉnh của các điểm cần đo lún bề mặt, từ đó xác định độ lún giữa các chu kỳ đo và tổng độ lún của lớp đất tại khu vực quan trắc.

V.3. Equipment Installation and monitoring for Electric Piezometer

Lắp đặt thiết bị và quan trắc áp lực nước lỗ rỗng

a. Remarks for maintenace and installation - Những chú ý khi bảo quản và lắp đặt:

- Monitoring head: before installation, the equipment must be carefully preserved. particularly the measuring head which should be prevented from being dropped as well as filled with water, the filter set should not be saturated.

Method statement for geotechnical monitoring of embankment on soft soil

Page 15: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

- The signal cables and pipes system: The signal cables system must be carefully preserved without being cut or scratched, the signal cables and system should not be placed across the traffic road or rolled into ring.

- Pile system should be carefully marked for the convenience of distingguishing afterwards.

- Bore hole: before installation, it is necessary to measure the boring hole depth by a heavy surveying ruler. Using the ruler to mark the depth degree onto the pile.

- Betonite clay must be placed in the monitoring head, it is necessary to provide enogh water and time for clay to expand in accodance with the manufacture’s directions.

- Đầu đo: Các thiết bị trước khi lắp đặt cần được bảo quản cẩn thận, đặc biệt là đầu đo tránh đánh rơi chúng, đầu đo không được chứa đầy nước hoặc bộ lọc đã bão hòa đóng băng.

- Hệ thống cáp tín hiệu, ống: Hệ thống cáp tín hiệu phải được bảo quản cẩn thận, tránh bị cắt hay xước, không để hệ thống ống hay cáp nằm ngang đường giao thông, không cuộn thành các cuộn nhỏ, hoặc cố gắng kéo ống, cáp khi đã bị mắc kẹt.

- Hệ thống ống cần được đánh dấu cẩn thận để tiện nhận dạng sau này.

- Lỗ khoan: Trước khi lắp đặt cần kiểm tra độ sâu lỗ khoan bằng thước đo nặng. Dùng thước để đánh dấu các độ sâu trên ống và cáp.

- Sét bentonite phải được để bên trên đầu đo, phải đảm bảo cấp đủ nước và thời gian để sét trương nở theo các chỉ dẫn của Nhà sản xuất.

b. Installation equiment in the bore hole - Lắp đặt thiết bị trong lỗ khoan

- Bore the the design depth (1.0m deeper than the installation position). Pump and clean the boring hole.

- Install the equipment to the final depth.

- Saturate the filter head and the pore pressure measuring head. Check the accuracy of the monitoring heads and parameter displayed. “None” of the porous water pressure measuring head. Put the monitoring heads to the required depth.

- Use the directing tube to pour sand and around monitoring head (the sand must be wet) and check the performance of monitoring head.

- Pour one layer of benonite by pouring bentonite grains gradually into the boring hole to prevent the hole from being clogged horizontally, and wait for the bentonite to expand.

- Fill the rest of the hole with bentonite or betonite-cement grout to the depth of the upper monitoring equipment (betonite grout must be filled the place 1.0m deeper than the installation depth of monitoring equipment).

Method statement for geotechnical monitoring of embankment on soft soil

Page 16: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

- Continue to install the remaining pore pressure measuring equipment as the above order.

- Cover the pile or the cable to prevent water from penetrating. Build the mouth of boring hole to place a protection box. Record the beginning parameters.

- Khoan đến độ sâu thiết kế (sâu hơn vị trí lắp đặt 1.0m). Bơm rửa sạch lỗ khoan.

- Lắp đặt thiết bị ở độ sâu cuối cùng.

- Bão hòa đầu lọc và đầu đo áp lực nước lỗ rỗng. Kiểm tra sự hoạt động chính xác của các đầu đo và ghi các số đọc "Không" của đầu đo áp lực nước lỗ rỗng. Thả đầu đo vào lỗ khoan đến độ sâu yêu cầu.

- Dùng một ống dẫn đổ cát xung quanh đầu đo, cát phải ướt, kiểm tra sự hoạt động của đầu đo.

- Đổ một lớp bentonite bằng cách thả các hạt bentonite từ từ xuống lỗ khoan để tránh bị bịt ngang, bổ sung nước nếu cần để hydro hóa Bentonite, đợi cho bentonite trương nở.

- Lấp phần còn tại của lỗ khoan bằng bentonite hay vữa bentonite xi măng đến độ sâu của phần thiết bị đo bên trên (bentonite được lấp đến độ sâu sâu hơn độ sâu lắp đặt thiết bị bên trên 1.0m.

- Tiếp tục lắp đặt thiết bị đo áp lực nước lỗ rỗng bên trên theo trình tự nêu trên.

- Bịt đường ống hoặc cáp để ngăn nước vào, xây miệng hố khoan đặt hộp bảo vệ. Ghi các số đọc ban đầu.

c. Quan trắc – Monitoring:

Đo áp lực nước lỗ rỗng trong đất nền tại thời điểm đo theo chỉ dẫn trong tiêu chuẩn kỹ thuật của dự án.

Measuring porous water pressure in soft soil at monitoring time follow technical notice in specification of project.

V.4. Installation and monitoring content for Lateral displacement observing stake:

Lắp đặt thiết bị và quan trắc chuyển vị ngang trên bề mặt

a. Installation / Lắp đặt:

The installation will be carried out when the Contractor starts the embankment works.

The installation is implemented by staking the wooden stakes into the soil at design locations. The pile will be 1.20m into the ground, and the stake’s head will be 0.50m higher than the ground surface.

Công tác lắp đặt được thực hiện khi Nhà thầu tiến hành đắp nền đường.

Việc lắp đặt được thực hiện bằng cách đóng cọc chuyển vị xuống đất nền tại các vị trí thiết kế, cọc được đóng sâu 1.20m, cao độ đỉnh cọc cao hơn mặt đất 0.50m.

b. Quan trắc/ Monitoring:

Method statement for geotechnical monitoring of embankment on soft soil

Page 17: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

Measure the coodinates of the alignment stake, the caculating the distances after each monitoring and the displacement from its original position

Đo tọa độ đỉnh cọc đo chuyển vị, từ đó các định cự ly dịch chuyển giữa các lần đo và dịch chuyển so với vị trí ban đầu.

V.5. Observation well / Giếng quan trắc nước ngầm

Ground water monitoring work determines level of undergruond water in embankment area. The monitoring data combined with piezometer measurement the foundation soil under embankment is to evaluate the efficiency of the soft soil treatment; and to detect and timely treat the slop instabilyty of the road embankment during the execution period.

Nhằm xác định cao độ nước ngầm trong phạm vi nền đường và khu vực xung quanh, kết hợp với tài liệu quan trắc áp lực nước lỗ rỗng của đất nền để đánh giá quá trình sử lý đất nền đất yếu. Phát hiện và sử lý các sự cố trong quá trình thi công tuyến đường.

The level of underground water is observed at observation in embankment area. The location and depth of observation well are showed in observation plan.

Nước ngầm được quan trắc trong các giếng đặt trong phạm vi nền đường. Vị trí và độ sâu giếng được thể hiện tại bảng bố trí thiết bị quan trắc.

VI. MONITORING CYCLE / CHU KỲ QUAN TRẮC

STT

ID

Nội dung công việc

- Description

Đơn vị

Unit

Khối lượng

Quantity

1

Surface settlement Plates (SSP)

Quan trắc lún nông bằng bàn lún

CycleChu kỳ

- Before and after each change in loading- daily during filling operations- twice-weekly intervals for a period of two (2)

months- Thereafter, until the end of the settlement

period, each instrument or observation point shall be read at intervals not greater than once a week

- Monthly readings shall then be made through the end of the Contract period

2

Deep Settlement Extensometer

Quan trắc lún sâu

CycleChu kỳ

- Before and after each change in loading- daily during filling operations- twice-weekly intervals for a period of two (2)

months- Thereafter, until the end of the settlement

period, each instrument or observation point shall be read at intervals not greater than once a week

- Monthly readings shall then be made through the end of the Contract period

Method statement for geotechnical monitoring of embankment on soft soil

Page 18: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

3Electric Piezometer

Đo áp lực nước lỗ rỗng

CycleChu kỳ

- Once daily for the first seven (7) days after the installation, and during the reference section construction.

- Twice weekly for a period of two (2) months- Weekly intervals until the end of the settlement

period, or as directed by the Engineer. - Monthly readings shall then be made through

the end of the Contract period. - During periods of continuous rainfall, water

levels shall be monitored daily for duration to be directed by the Engineer

4

Lateral displacement observing stake

Đo chuyển vị ngang bằng cọc gỗ

Cycle

Chu kỳ

- Before and after each change in loading- daily during filling operations- twice-weekly intervals for a period of two (2)

months- Thereafter, until the end of the settlement

period, each instrument or observation point shall be read at intervals not greater than once a week

- Monthly readings shall then be made through the end of the Contract period

5Observation Well

Quan trắc cao độ mực nước tĩnh

Cycle

Chu kỳ

- Once daily for the first seven (7) days after the installation, and during the reference section construction.

- Twice weekly for a period of two (2) months- Weekly intervals until the end of the settlement

period, or as directed by the Engineer. - Monthly readings shall then be made through

the end of the Contract period. - During periods of continuous rainfall, water

levels shall be monitored daily for duration to be directed by the Engineer

VII. MONITORING REPORT - BÁO CÁO QUAN TRẮC

The Contractor shall submit a graphical plot of all monitoring instrumentation readings to the Engineer on a daily basis.

The Contractor shall submit to the Engineer a formal monitoring report at the end of each calendar month, in written, electronic digital and graphical format. A sample monitoring report shall be submitted to the Engineer (including all graphical presentations) for approval at least two weeks before the submission of the first monthly report.

Each monthly report shall include:

- A description of monitoring works performed during the previous month;

Method statement for geotechnical monitoring of embankment on soft soil

Page 19: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

- Information on reading anomalies or corrections, and factors which may have influenced the measured data;

- Observations and remarks;

- Drawings showing installed locations of instruments (taken from installation report);

- Data tabulations or plots of instrument readings as described hereafter;

- Computer disk file copies of all records.

Nhà thầu phải nộp một bản vẽ của tất cả các thiết bị quan trắc cho kỹ sư phụ trách hàng ngày.Nhà thầu phải trình Kỹ sư báo cáo quan trắc chính thức vào cuối mỗi tháng, bao gồm bản in, file mềm được sao in vào đĩa. Một mẫu báo cáo quan trắc sẽ được trình Kỹ sư (bao gồm tất cả các bản vẽ đi kèm) để kiểm tra ít nhất hai tuần trước khi nộp báo cáo hàng tháng đầu tiên.

Báo cáo tháng gồm có:

- Mô tả công việc quan trắc thực hiện trong tháng trước đó;

- Các yếu tố bất thường trong quá trình đọc hoặc có chỉnh sửa, và các yếu tố có thể ảnh hưởng đến dữ liệu đo;

- Quan trắc và nhận xét.

- Các bản vẽ thể hiện vị trí các điểm quan trắc( được lấy từ báo cáo lắp đặt);

- Các dữ liệu hoặc kết quả được phân tích, đánh giá;

- Ghi tất cả các kết quả báo cáo vào đĩa CD.

Data tabulation or plots of instrument readings:

- The Contractor shall have suitable software for generation of the required plots and tabulations. The zero time to be used in all the plots and tabulations shall be agreed with the Engineer. The time axis shall be agreed with the Engineer. The time axis shall be marked in days from "day zero" and an indication of date or month shall be included in the axis. The plots and tabulations, thereby giving a complete record starting from the time of installation.

Instrument Plots and Summaries Required

Settlement Plate

Alignment Stakes

Settlement Vs Time (Tabulation and plot)

Horizontal and vertical movement of each stake with reference

to a baseline survey. Position shall be plotted versus time and

date from beginning of embankment filling operations.

Piezometer pressure showing excess piezometric pressure versus

time for each piezometer and versus depth for latest set of

Method statement for geotechnical monitoring of embankment on soft soil

Page 20: De Cuong Quan Trac (COGECO)

Project : Vinh Phuc Province Investment Climate Improvement

Package CP-1: Main road though new urban zone of Me Linh

Piezometer readings (plots).

- All plots, where time forms the horizontal axis shall have same scale for the time axis. Where fill thickness, settlement and excess water head are all available at the same location, the plots shall be combined on the same sheet where possible. Final layouts, scales and details shall be agreed with the Engineer at the time of submitting the format.

VIII. MONITORING ORGANIZATION - SƠ ĐỒ TỔ CHỨC QUAN TRẮC

MONITORING ORGANIZATION

SƠ ĐỒ TỔ CHỨC QUAN TRẮC

Method statement for geotechnical monitoring of embankment on soft soil

Eng. NGHIÊM TUẤN HÀMonitoring Manager

Eng. TRẦN HỮU HẢI Director

COGECO CN MIỀN BẮCCOGECO NORTH

SITE MONITORING TEAMLeader: Eng. Vũ Anh SơnTechnician: Vũ Mạnh LinhTechnician: Nguyễn Văn ViếtTechnician: Nguyễn Hữu Lợi

ANALYSIS & REPORTLeader: Eng. Nghiêm Tuấn HàLeader: Eng. Nguyễn Xuân PhươngTechnician: Eng. Trần Văn CôngTechnician: Eng. Đỗ Văn Hướng