DC5 Shell Plate Leak

download DC5 Shell Plate Leak

of 7

Transcript of DC5 Shell Plate Leak

  • 8/3/2019 DC5 Shell Plate Leak

    1/7

    PRELIMINARY INVESTIGATION REPORT

    DC #5 SHELL PLATE LEAK

    1.0 Event

    Date : 05th November 2011

    Time : 10:20 am

    Heat No. : 5055443

    A. DC# 5 shell plate below KT3 leak; happen during

    tapping. The root cause of leakage was the bricks bad

    condition consequence from water leaking of panel WCP 1-9

    at 15 October 2011 and loose of coupler supply water WCP

    1-11 on 05 November 2011. Tap temperature high due to

    over arching worse the bricks condition.

    B. History of Incident

    Date Heat No. Event

    04.10.2011 5054917Slag penetrate below KT3Patching with castable and gunning

    15.10.2011 5055097 Panel WCP 1-9 leak

    27.10.2011 5055204 F/hose cooling block KT8 leak

    29.10.2011 5055338 Panel ECJ and RCP leak

    01.11.2011 5055377 Tap temp 1651 C,O2 ppm 288 ppm

    03.11.2011 5055405 Tap temp 1628 C,O2 ppm 556 ppm

    03.11.2011 5055413 Tap temp 1630 C O2 ppm 745 ppm

    03.11.2011 5055422 After hot repair Tap temp 1628 C O2 ppm 577 ppm

    04.11.2011 5055432 Over shoot tap temp 1647C ladle preheater

    04.11.2011 5055433 Gunning 1698kg

    04.11.2011 5055438 Gunning 1528kg

    05.11.2011 5055443Coupler W/return WCP 1-11 looseShell plate leak during tap

  • 8/3/2019 DC5 Shell Plate Leak

    2/7

  • 8/3/2019 DC5 Shell Plate Leak

    3/7

    2.0 Preliminary Causes

    Based on our investigation, the leakage happens due to :-

    1. The bricks area under KT 3 was very bad condition. The bricks

    heavy erosion due to effect of water leaking from WCP 1-9 at

    15 October 2011 and water leaking from loose coupler WCP 1-

    11 at 05 November 2011.

    2. Temperature high up to 1651oC due to overarching. Furnace

    operation increases the temperature for ladle parking, ladle

    preheater and after hot repair. The S.O.P required normal tap

    temperature only 1610oC and 1630 oC for ladle preheated.

    3. DRI was very low quality with high silica content 3 % required

    furnace to use high amount of CaO 3500 per heat.

    3.0 Equipment Damages

    i) Shell Plate under KT 3

    ii) Bricks area KT 3

    iii) Bottom furnace Sensor and Cable

    iv) Limit switch Tapping lock post

    v) Hose cooling busbar

    vi) Bottom electrode

    4.0 Preventive Measure

    1. To focus gunning at the high erosion bricks consistently.

    2. Detail Check furnace condition once stoppage/onpeak schedule.

    3. Dont delay the gunning activity schedule for safe mode.

    4. Change the high erosion bricks or collapse bricks as quick as

    possible.

    5. DR plant must plan for high quality DRI on the future consistently.

  • 8/3/2019 DC5 Shell Plate Leak

    4/7

    5.0 Cost Of Damages

    Shell Plate repair RM x

    New Bricks RM xBottom electrode RM x

    Bottom furnace Sensor and Cable RM x

    Busbar cooling hose RM x

    Tapping lockpost limit switch RM x

    Man Power RM x

    Total Cost RM xxxx

    Prepared by, Checked by,

    Mohd Zakaria Khamis Mr. Abd Rahman Che Min

    Mohd Nasuha Abd Halim

  • 8/3/2019 DC5 Shell Plate Leak

    5/7

    ATTACHMENT

    Picture 1: Shell plate leak below KT3

    KT3 KT8

    Leak area

  • 8/3/2019 DC5 Shell Plate Leak

    6/7

    Picture 2: Brick condition below KT3 after incident

    KT3

  • 8/3/2019 DC5 Shell Plate Leak

    7/7

    Picture 3: Below furnace