DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB...

30

Transcript of DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB...

Page 1: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

RoadName

From

To

Total

Section

Project

Replacement

Length

Implementation

Cost

Developer

DC

andBenefit

Jurisdiction

(KM)

Type

(COB)

Contribution

Contribution

toExisting

2017

Roads

BiscayneCreek

/

WestcreekBtvd

connection

BramaleaRoad

ClarkwayDrive

ClarkwayDrive

CountrysideDrive

CountrysideDrive

HeritageRoad

HeritageRoad

Intersection

Improvements

MississaugaRoad

Noisewall

retrofit

Properlyacquisition

Sidewalks

TrafficSignallzation

Urbanizationof

Highway10

WanlessDrive

BiscayneCrescent

BovairdDrive

MayfieldRoad

CastlemoreRoad

DixieRoad

TheGoreRoad

FinancialDrive

SteelesAvenue

Variouslocations

BovairdDrive

Variouslocations

Variouslocations

Variouslocations

Variouslocations

BovairdDrive

CreditviewRoad

Sub-Total

-Roadsfor2017

GradeSeparations

Highway410overpass

Biscayne

Creek/Westcreek

WestcreekBlvd

SteelesAvenue

CountrysideDrive

CountrysideDrive

AirportRoad

Hwy50

NewRoadA

FinancialDrive

COB

COB

COB

COB

COB

COB

COB

COB

COB

SouthernCi

tySoundaryROP

COB

COB

COB

COB

Northern

CityboundaryCOB

MississaugaRoad

COB

COB

0.550

6.100

1.250

3.700

4.100

3.600

3.300

0.700

7.500

0.608

1.500

5.000

1.400

4UC-NC

INTBRT

2-4UMA-WS

2-4UMA-WR

INTPrimCor

2-4UMA-WR

2-4UMA-WS

2-*UMA-WS

INT

INTBRT

NoiseWall

Property

Sidewalks

Signals

4RUA-RR

2-4UMA-WS

OverPass

2.347.700

4,473,100

7,815,700

14.857,300

4.424,300

21.425,800

8.202.400

11.192.100

1,348.900

1,557,500

920.700

13.500.000

126.300

5.203.200

23,576.700

3,761.500

$124,735,200

11.250.000

1.173.800

1.173.800

4,249,400

7,424,900

14.114,400

4,203,100

20.354,600

7.792,300

10.632.500

1,261,500

1,479,600

690,500

13.500.000

128.300

4.943.100

22.397.900

3,573.400

$1,173,800

$117,939,300

10,687,500

223,700

390,800

742,900

221,200

1.071.300

410.100

559.600

67,400

77.900

230,200

260,200

1.178.800

188.100

$5,622,200

562,500

o

> CD

Q.

x'

Page 2: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

RoadName

From

To

Jurisdiction

Total

Section

Project

Replacement

Length

Implementation

Cost

Developer

DC

andBenefit

(KM)

Type

(COB)

Contribution

Contribution

toExisting

Sub-Total

-GradeSeparationsfor2017

Gateways

Queen

Street&

Airport

Road

QueenStreet&

MississaugaRoad

Sub-Total

-Gatewaysfor2017

Totalfor2017

2018

Roads

BiscayneCreek

/

WestcreekBlvd

connection

BiscayneCreek

/

WestcreekBlvd

connection

BramwestParkway

/

NSTC

ConservationDrive

HeritageRoad

Intersection

Improvements

John

Street

KennedyRoad

Noisewaitretrofit

Propertyacquisition

SandalwoodParkway

Sidewalks

BiscayneCreek

WestcreekBoulevard

NorthofHighway407

Highway10

NewRoadA

Variouslocations

TrumanSt

SandalwoodParkway

Variouslocations

Variouslocations

BramaleaRoad

Variouslocations

Firs

tGulfBlvd

TomkenRd

COB

COB

COB

COB

Southof

SteelesAve

COB

KennedyRoad

BovatrdDrive

CentreStreet

COB

COB

CO8

COB

SouthernCityBoundaryROP

TorbramRoad

COB

COB

COB

COB

0.500

0.700

1.460

1.300

2.500

0.500

10.300

0.608

0.900

1.500

Gateways

Gateways

i

2-4UC-WS

2-4UC-WS

6-6UAI-WS

2-4UMA-WR

2-4UMA-WS

INT

2RUMA-RR

INTPrimCor

NoiseWall

Property

4-6UAI-WS

Sidewalks

$11,250,000

312,500

312.500

$625,000

1136,610,200

2,255,700

1.583,000

3.375.000

6.557.400

23,709.300

1,348.900

1.923.100

13,364,600

920,700

4.000,000

2,835.900

128.300

$0

$10,687,500

296.900

296.900

$0

$593,800

$1,173,800

$129,220,600

2,143,000

1.503.900

3.375,000

6.229,500

22,523,600

1,281,500

1,827,000

12,696,400

690,500

4.000,000

2,694,100

128.300

$562,500

15,600

15,600

$31,200

$6,215,900

112,800

79,200

327,900

1,185,500

67.400

96,200

668,200

230,200

141.800

CDZJg.

x'

>

Page 3: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

RoadName

From

To

Total

Section

Project

Replacement

Length

Implementation

Cost

Developer

DC

andBenefit

Jurisdiction

(KM)

Type

(COB)

Contribution

Contribution

toExisting

TrafficSignalization

TTMPandDCUpdate

Study

Variouslocations

Citywide

Sub-Total

-Roadsfor2018

Gateways

Eldorado

LormelGate

Sub-Total

-Gatewaysfor2018

Totalfor2018

2019

Roads

BramwestParkway

/

NSTC

HeritageRoad

Intersec

tion

Improvements

JohnStreetExtension

Noisewa

llre

trof

it

Propertyacquisition

SandalwoodParkway

Sidewalks

Traf

ficSignalization

WilliamsParkway

SteelesAvenue

WanlessDrive

Variouslocations

CentreStreet

Variouslocations

Variouslocations

DixieRoad

Variouslocations

Variouslocations

TorbramRoad

Sub-Total

-Roadsfor2019

COB

COB

COB

COB

EmbletonRoad

COB

MayfieldRoad

COB

COB

JamesStreet

COB

COB

COB

BramaleaRoad

COB

COB

COB

Humbeiwest

COB

3.100

1.260

0.200

0.60B

1.300

1.500

2.600

Signals

Study

Gateways

Gateways

6-8UAI-WS

2RUC-RR

INT

2UC-NC

NoiseWall

Property

4-6UAI-WS

Sidewalks

Signals

4-6UA-WS

5.203,200

500,000

$67,705,100

75,000

62,500

$137,500

$67,842,600

6,375,000

3,176,800

1,348,900

5,851,700

920,700

4,000,000

2,073,700

128,300

5,203,200

8,826,600

$37,904,900

$0

$0

2,925,800

$2,925,800

4,943,100

475,000

$64,511,100

71,200

59,400

$130,600

$64,641,700

6,375,000

3,018,000

1,281,500

2,925,800

690,500

4,000,000

1,970,000

128,300

4,943.100

8.385,300

$33,717,500

260,200

25.000

$3,194,400

3,700

3,100

$6,800

$3,201,200

158,800

67,400

230,200

103,700

260,200

441.300

$1,261,600

CD

Page 4: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

RoadName

From

To

Total

Section

Project

Replacement

Length

Implementation

Cost

Developer

DC

andBenefit

Jurisdiction

(KM)

Type

(COB)

Contribution

Contribution

toExisting

Totalfor2019

2020

Roads

East-WestSpineRd

HeritageRoad

Intersec

tion

Improvements

Noisewall

retrofit

Propertyacquisition

Sidewalks

TrafficSignalization

North-SouthSpineRd

Hwy.#7/BovairdRd

Variouslocations

Variouslocations

Variouslocations

Variouslocations

Variouslocations

Sub-Total

-Roadsfor2020

Totalfor2020

2021

Roads

CreditviawRoad

Intersection

Improvements

McLaughlinRoad

Noisewall

retr

ofit

Propertyacquisition

SandalwoodParkway

Sidewalks

TrafficSignalization

WanlessDrive

Variouslocations

WanlessDrive

Variouslocations

Variouslocations

MississaugaRoad

Variouslocations

Variouslocations

McLaughlinRd

Wanless

Drive

MayfieldRoad

MayfieldRoad

HeritageRd

COB

COB

COB

COB

COB

COB

COB

COB

COB

COB

COB

COB

COB

COB

COB

3.500

3.000

0.608

1.500

1.300

1.200

0.608

1.400

1.500

4UC-NC

2-4UMA-WS

INT

NoiseWall

Property

Sidewalks

Signals

2-4UMA-WR

INT

2-4UMA-WR

NoiseWall

Property

4UA-NC

Sidewalks

Signals

$37,904,900

12.343.900

7.496.500

1.151.200

920.700

4.000.000

128,300

5,203,200

$31,243,800

$31,243,800

7.092,300

1.348,900

4,830,100

920,700

4.000,000

5,228,700

128,300

5,203,200

$2,925,800

6.172.000

$6,172,000

$6,172,000

2,614,400

$33,717,500

6.172.000

7.121.700

1.093,600

690,500

4.000.000

128,300

4.943,100

$24,149,200

$24,149,200

6,737,700

1,281.500

4,588,600

690,500

4,000,000

2,614.400

128,300

4,943,100

$1,261,600

374,800

57,600

230,200

260.200

$922,800

$922,800

354,600

67,400

241,500

230,200

260,200

Page 5: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

RoadName

From

To

Total

Section

Project

Replacement

Length

Implementation

Cost

Developer

DC

andBenefit

Jurisdiction

(KM)

Type

(COB)

Contribution

Contribution

toExisting

WanlessDrive

MississaugaRoad

Sub-Total

-Roadsfor2021

Interchanges

Highway410&

Highway10

Highway410&Mayfield

Road

Sub-Total

-Interchangesfor2021

Totalfor2021

By2031

Roads

BramwestParkway

/

NSTC

BramwestParkway

/

NSTC

ChinguacousyRoad

CreditviewRoad

HeritageRoad

Intersection

Improvements(10

years)

Noisewall

retr

ofit

(10

years}

Propertyacquisition(10

years)

SandalwoodParkway

(new

project)

Sidewalks(10years)

SandalwoodParkway

EmbletonRoad

BovairdDrive

BovairdDrive

WanlessDrive

Variouslocations

Variouslocations

Variouslocationsat

$4.35M/year

HeritageRd

Variouslocations

WinstonChurchillBlvd.COB

MayfieldRoad

BovairdDrive

WanlessDrive

Ml.PleasantTransit

Spine

MayfieldRoad

WinstonChurchillBlvc

COB

COB

COB

COB

COB

COB

COB

COB

I.COB

COB

3.800

1.900

3.400

3.100

1.000

1.200

6.077

1.400

15.000

2-4UMA-WS

IC

IC

6UA-NC

6-8UAI-WS

4-6UA-WS

4-6UA-WS

2-4UMA-WS

INT

NoiseWall

Property

4UMA-NC

Sidewalks

10,367,200

$39,119,400

4,375,000

4,375,000

$8,750,000

$47,869,400

8,750,000

5,500,000

11,123,900

2,940,500

4,299,600

1,348,900

9,206,700

40,000,000

6,604.700

1,283,000

$2,614,400

$0

$2,614,400

3,302.300

9,848,900

$34,833,000

4,375.000

4,375,000

$8,750,000

$43,583,000

8,750,000

5,500.000

10,567,700

2,793.500

4,084,600

1,281,500

6,905,000

40,000,000

3,302,300

1,283,000

516,400

$1,672,300

$0

$1,672,300

556,200

147,000

215,000

67,400

2,301,700

Q.

Page 6: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

RoadName

From

To

Total

Section

Project

Replacement

Length

Implementation

Cost

Developer

DC

andBenefit

Jurisdiction

(KM)

Type

(COB)

Contribution

Contribution

toExisting

Traf

ficSignalization(10

Variouslocations

years)

TTMPandDCUpdate

Citywide

Study

Sub-Total

-RoadsforBy2031

GradeSeparations

HeritageRd&CN

HattonLine

SandalwoodRd&CN

HaltonLine

Sub-Total

-GradeSeparationsforBy2031

TotalforBy2031

GrandTotal

COB

COB

COB

COB

Signals

Study

GS-Rail

GS-Rail

52.032,400

1.000,000

$144,089,700

6.244.700

6,244,700

$12,489,400

$156,579,100

$1,790,233,400

$3,302,300

$0

$3,302,300

49,430,700

1.000,000

$134,898,300

5,932,500

5,932,500

$11,865,000

$146,763,300

$104,164,100$1,624,091,300

2,601.600

$5,888,900

312,200

312.200

$624,400

$6,513,300

$61,978,600

as

> ■Q CD

Q.

X*

Page 7: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix B

CITY OF BRAMPTON 2009 DEVELOPMENT CHARGES

Outstanding Issues Raised In June 25, 2009 Memo from Altus Group on behalf of BILD

July 21, 2009

1. The use of "gross" population in new units to calculate the 10 year historic average

service level cap

2. Treatment of Negative Reserve Fund Balances

• BILD's position is that any negative reserve fund balances funded by the

development charge must be included in the 10 year historic average service level

cap, as described in the June 25, 2009 Altus Group memo. City staff have advised

that an adjustment will be made to the development charge calculation to address

this issue. BILD cannot comment further until the City's revised calculations are

provided.

3. Reserve Fund Balance Adjustments

• Following the Altus/IBI/Brampton meeting on July 7, Brampton staff provided a

spreadsheet with some information respecting the adjustments to reserve fund

balances. BILD has requested additional detail regarding how the specific

adjustments were calculated (how was each calculated, and how much development

(total units or square footage) is represented by each category of adjustment).

• BILD is also requesting clarification in respect of how the City will permanently adjust

its Reserve Fund Account to account for the above adjustments.

4. Central Area DC Incentive Program

• BILD has requested a description from the City in respect of how the Central Area

DC Incentive Program is accounted for in the current reserve fund balances, and

some detail respecting the amounts reflected in the reserve fund balances for the

incentive program (i.e., what are the total amounts accounted for in the reserve funds

for the incentive programs and how many units of each type do the amounts

represent).

5. Transit Congestion Factor

• This issue is also raised in the June 25, 2009 memo from BA Group. BILD has

requested an analysis that demonstrates how the 20% "congestion factor" was

justified and calculated in relation to the 10 year historic service level for transit and

and future road system congestion attributable to development.

6. Interest Rate Differential

• This issue described in detail in the June 25, 2009 Altus Group memo is outstanding.

Page 8: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix B

-2-

7. Industrial Growth

• Following the Altus/IBI/Brampton meeting on July 7, Brampton staff provided

spreadsheets with a breakdown of floorspace and employment forecasts and GFA

per employee factors as requested. BILD is reviewing the detailed City assumptions

that have been provided.

8. General Government - Parking

• BILD has requested additional information requested regarding how the need for the

parking service was established for growth specifically over the study period, and

how the capital cost was estimated.

• BILD also requested confirmation that existing parking facilities included in the

historic service level calculations are not used to accommodate municipal employee

parking. The City has confirmed that parking facilities used to accommodate

municipal employee parking is not included in the historic service level calculations.

9. General Government - Studies

• BILD has requested additional information from the City regarding the scope of the

planning studies included in the estimated capital costs, and the criteria for studies

to be funded by the City versus developers. BILD is awaiting receipt of this

information.

10. General Government - Courthouse

• BILD has requested additional information from the City regarding the breakdown

of Courthouse funding, including original costs and grant amounts, the amount of

the courthouse funded to date.

• BILD is also requesting calculations respecting the manner in which the need for

the courthouse is allocated to previous and future development (i.e., what is the

capacity of the courthouse facility in relation to the population at the time of

construction, population since the courthouse was included in the development

charge, population during the study period and population after the study period)?

11. Library Board

• Given the temporary library facilities identified in the existing inventory, BILD is not

satisfied that there isn't additional benefit to existing development that should be

accounted for in proposed facilities that will replace temporary facilities. BILD has

requested details pertaining to the City's Library program. The City has advised

that information in that regard is contained in the draft Library Master Plan. BILD

has requested the draft Library Master Plan.

12. Transit Facilities - Land

• The City has advised that it is making an adjustment to its development charge

calculation to reduce certain land values that have been used for the replacement

value of existing transit stations. BILD cannot comment further until the City's

revised calculations are provided.

Page 9: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

A Appendix B

-3-

13. Transit Facilities - Grants

• BILD disagrees with the manner in which the City applied grants in calculating the

capital cost amounts included in the development charge calculation for transit.

BILD's detailed position was provided to the City by letter dated July 20,2009.

14. Growth Projections for TTMP Update

• This issue is described in the June 25 Altus memo. City staff advised in a meeting

that the higher population used in TTMP would not impact road requirements, and

that the issue may be addressed through the TTMP. BILD is awaiting further

explanation through the TTMP.

15. Housing Mix

• The housing mix information provided by City following the Altus/IBI/Brampton

meeting on July 7 appears inconsistent with the Background Study. The City has

advised that an adjustment is being made to the Background Study.

16. Level of Service - Quality - Libraries

• The June 25 Altus memo raised the issue of increased replacement values for library

facilities that have not been justified. Brampton staff have advised that the costs are

based on generic costs found in the City's draft Library Master Plan. BILD has

requested the relevant excerpts from the Library Master Plan that justify the

increase.

17. Valleyland Development

• Following the Altus/IBI/Brampton meeting on July 7, Brampton staff provided a

information respecting the calculation of costs for Valleyland Development and the

Pathway Implementation Plan. BILD is currently reviewing this information.

18. Housing Projections

• The attached questions were previous provided to the City by Altus Group, but to

date no response has been received.

\574I956.2

Page 10: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix Bi

-4-

Question Regarding Housing Projections

The new housing forecast to be used to calculate the 2009 development charges projects

approximately 12,400 fewer dwelling units for 2031 than had been projected for 2031 in the Peel

Region Official Plan and Brampton's 2006 Development Outlook. We understand the new

forecast reflects a new GTAH-wide forecasting model undertaken by Hemson Consulting which

projects significantly fewer dwelling units for Peel Region than Hemson's Growth Outlook for the

Greater Golden Horseshoe (the basis of Schedule 3 in the Growth Plan for the Greater Golden

Horseshoe).

In order to assess the reasonableness of the new household forecast, we need to review of the

update of the GTAH-wide forecasting model including changes in key assumptions. In

particular, we require:

> The changes in the 2011, 2021 and 2031 population forecast by age cohort for the

GTAH;

> The new assumptions regarding fertility, mortality and net migration behind the new

forecast by age cohort;

> Projected household headship rates by age cohort and an explanation of changes from

the reference compact scenario in the Growth Outlook for the Greater Golden

Horseshoe;

> The new GTAH household forecast for 2011, 2021 and 2031;

> Unit type projections for the GTAH;

> The allocation of units by type to upper and single tier municipalities within the GTAH;

and

> The allocation of units by type within Peel Region.

Page 11: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix B

CITY OF BRAMPTON 2009 DEVELOPMENT CHARGES

Outstanding Issues Raised In June 25, 2009 Memo from Altus Group on behalf of BILD

July 21, 2009

1. The use of "gross" population in new units to calculate the 10 year historic average

service level cap

2. Treatment of Negative Reserve Fund Balances

• BILD's position is that any negative reserve fund balances funded by the

development charge must be included in the 10 year historic average service level

cap, as described in the June 25, 2009 Altus Group memo. City staff have advised

that an adjustment will be made to the development charge calculation to address

this issue. BILD cannot comment further until the City's revised calculations are

provided.

3. Reserve Fund Balance Adjustments

• Following the Altus/IBI/Brampton meeting on July 7, Brampton staff provided a

spreadsheet with some information respecting the adjustments to reserve fund

balances. BILD has requested additional detail regarding how the specific

adjustments were calculated (how was each calculated, and how much development

(total units or square footage) is represented by each category of adjustment).

• BILD is also requesting clarification in respect of how the City will permanently adjust

its Reserve Fund Account to account for the above adjustments.

4. Central Area DC Incentive Program

• BILD has requested a description from the City in respect of how the Central Area

DC Incentive Program is accounted for in the current reserve fund balances, and

some detail respecting the amounts reflected in the reserve fund balances for the

incentive program (i.e., what are the total amounts accounted for in the reserve funds

for the incentive programs and how many units of each type do the amountsrepresent).

5. Transit Congestion Factor

• This issue is also raised in the June 25, 2009 memo from BA Group. BILD has

requested an analysis that demonstrates how the 20% "congestion factor" was

justified and calculated in relation to the 10 year historic service level for transit and

and future road system congestion attributable to development.

6. Interest Rate Differential

• This issue described in detail in the June 25,2009 Altus Group memo is outstanding.

Page 12: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix B

7. Industrial Growth

• Following the Altus/IBI/Brampton meeting on July 7, Brampton staff providedspreadsheets with a breakdown of floorspace and employment forecasts and GFAper employee factors as requested. BILD is reviewing the detailed City assumptionsthat have been provided.

8. General Government - Parking

• BILD has requested additional information requested regarding how the need for theparking service was established for growth specifically over the study period andhow the capital cost was estimated.

• BILD also requested confirmation that existing parking facilities included in thehistoric service level calculations are not used to accommodate municipal employeeparking. The City has confirmed that parking facilities used to accommodatemunicipal employee parking is not included in the historic service level calculations.

9. General Government - Studies

• BILD has requested additional information from the City regarding the scope of theplanning studies included in the estimated capital costs, and the criteria for studiesto be funded by the City versus developers. BILD is awaiting receipt of thisinformation.

10. General Government - Courthouse

• BILD has requested additional information from the City regarding the breakdownof Courthouse funding, including original costs and grant amounts the amount ofthe courthouse funded to date.

• BILD is also requesting calculations respecting the manner in which the need forthe courthouse is allocated to previous and future development (i.e what is thecapacity of the courthouse facility in relation to the population at' the time ofconstruction, population since the courthouse was included in the developmentcharge, population during the study period and population after the study period)?

11. Library Board

• Given the temporary library facilities identified in the existing inventory, BILD is notsatisfied that there isn't additional benefit to existing development that should beaccounted for in proposed facilities that will replace temporary facilities BILD hasrequested details pertaining to the City's Library program. The City has advisedthat information in that regard is contained in the draft Library Master Plan BILDhas requested the draft Library Master Plan.

12. Transit Facilities - Land

• The City has advised that it is making an adjustment to its development chargecalculation to reduce certain land values that have been used for the replacementvalue of existing transit stations. BILD cannot comment further until the City'srevised calculations are provided.

Page 13: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix B

13. Transit Facilities - Grants

• BILD disagrees with the manner in which the City applied grants in calculating thecapital cost amounts included in the development charge calculation for transit.BILD's detailed position was provided to the City by letter dated July 20,2009.

14. Growth Projections for TTMP Update

• This issue is described in the June 25 Altus memo. City staff advised in a meetingthat the higher population used in TTMP would not impact road requirements, andthat the issue may be addressed through the TTMP. BILD is awaiting furtherexplanation through the TTMP.

15. Housing Mix

• The housing mix information provided by City following the Altus/IBI/Bramptonmeeting on July 7 appears inconsistent with the Background Study. The City hasadvised that an adjustment is being made to the Background Study.

16. Level of Service - Quality - Libraries

• The June 25 Altus memo raised the issue of increased replacement values for libraryfacilities that have not been justified. Brampton staff have advised that the costs arebased on generic costs found in the City's draft Library Master Plan. BILD hasrequested the relevant excerpts from the Library Master Plan that justify theincrease.

17. Valleyland Development

• Following the Altus/IBI/Brampton meeting on July 7, Brampton staff provided ainformation respecting the calculation of costs for Valleyland Development and thePathway Implementation Plan. BILD is currently reviewing this information.

18. Housing Projections

• The attached questions were previous provided to the City by Altus Group but todate no response has been received.

\574l95ft.2

Page 14: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix B

61-53

Question Regarding Housing Projections

The new housing forecast to be used to calculate the 2009 development charges projects

approximately 12,400 fewer dwelling units for 2031 than had been projected for 2031 in the Peel

Region Official Plan and Brampton's 2006 Development Outlook. We understand the new

forecast reflects a new GTAH-wide forecasting model undertaken by Hemson Consulting which

projects significantly fewer dwelling units for Peel Region than Hemson's Growth Outlook for the

Greater Golden Horseshoe (the basis of Schedule 3 in the Growth Plan for the Greater Golden

Horseshoe).

In order to assess the reasonableness of the new household forecast, we need to review of the

update of the GTAH-wide forecasting model including changes in key assumptions. In

particular, we require:

> The changes in the 2011, 2021 and 2031 population forecast by age cohort for the

GTAH;

> The new assumptions regarding fertility, mortality and net migration behind the new

forecast by age cohort;

> Projected household headship rates by age cohort and an explanation of changes from

the reference compact scenario in the Growth Outlook for the Greater Golden

Horseshoe;

> The new GTAH household forecast for 2011, 2021 and 2031;

> Unit type projections for the GTAH;

> The allocation of units by type to upper and single tier municipalities within the GTAH;

and

> The allocation of units by type within Peel Region.

Page 15: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix C

CITY OF BRAMPTON 2009 DEVELOPMENT CHARGE REVIEW

Response to: Communication from Robert Howe (Goodmans) entitled, "Outstanding Issues Raised in

June 25,2009 Memo from Altus Group on behalf of BILD", dated July 21,2009.

1. The position of the City on the "gross" population in new units methodology is addressed in the

staff report to Committee of Council on July 27, 2009.

2. Adjustments have been made to the development charge calculation in respect to the

treatment of negative reserve fund balances. The full amount of negative reserve fund balances

has been included as a part of the capital program that is funded under the service level cap.

Details as follows:

Service

Category

Reserve

Fund

Fire

Public

Works

Transit

Most Recent

Calculation of

Maximum

Allowable

$21,159,704

$27,068,049

$68,056,056

Negative Balance

of Reserve Fund

to be included in

Capital program

$11,921,828

$1,854,022

$7,436,849

Total of

Other Capital

Projects

within the

Maximum

Allowable

$9,237,876

$25,214,027

$60,619,207

3. Adjustments were made to the DC Reserve Fund balances in recognition of 2004 by-law

Transition Measures, Industrial Discounts and Places of Worship exemption that cannot be

recovered through future DCs. Details of each calculation follows this paragraph. For the

purposes of calculating the DC rates in this by-law review, the City has adjusted the reserve

funds in accordance with the Development Charges Act. The City will review its accounting

practices in this regard after completion of the DC review.

2004 By-Law Transition Measures

The adjustment due to transition measures was calculated based on the activities (for

residential) or revenues (for non-residential) during the transition period. The details of each

development type are as follows:

July 23,2009 Pagel

Page 16: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix C

a. Residential Transition Measure Calculation

Month UnitsForegone Collections per

Unit

Foregone

Collections for

Month

September 2004 248 $4,490.08 $1,113,539.84

October 2004 1,281 $4,490.08 $5,751,792.48

November 2004 91 $3,221.55 $293,161.05

December 2004 2,006 $3,221.55 $6,462,429.30

Totals 3,626 $13,620,922.67

b. Non-Residential Transition Measure Calculation

Month

September 2004

October 2004

November 2004

December 2004

January 2005

February 2005

March 2005

Totals

Transitional Discount

Additional Collection Without Transition

Foregone Collections With Transition

Non-Industrial /

Non - Office Actual

Revenue

$207.59

$179,734.74

$177,859.94

$47,547.83

$55,887.04

$4,239.66

$138,055.29

$603,532.09

47.25%

$1,144,051.94

$540,519.85

Industrial / Office

Actual Revenue

$1,061,411.63

$771,272.68

$953,382.12

$497,209.60

$86,421.13

$0.00

$5,604,846.08

$8,974,543.24

34.19%

$13,637,866.58

$4,663,323.34

c. Total Transition Measure Reductions

Development Type

Residential

Non Industrial / Non-Office

Industrial / Office

Total

Revenue Forgone

$13, 620,922.67

$540,519.85

$4,663,323.34

$18,824,765.86

July 23, 2009 Page 2

Page 17: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix C

Industrial Discount

Industrial discount adjustment was based on percentage discount to total actual revenue of $25

million over the past five years. The calculation is as follows:

September 2004- April 2008: $23,859,662 x 11% = $2,624,563

May 2008-Dec 2008: $1,214,127 x 32.5% = $394,591

Total: $3,019,154

Places of Worship Exemption

The Places of Worship exemption adjustment was calculated on each individual site plan. The

total of the exempted area was 7,718.13 m2 for all Places of Worship who paid DCs during the

by-law period. The total foregone revenue was calculated by multiplying the exempted area for

each site plan by the DC rate in effect at the time of permit issuance for the respective site plan.

The sum total of the foregone revenue equaled $586,849.30.

4. Although the City of Brampton covers the City's portion of development charges that a company

would pay in order to develop in the downtown incentive program defined area (subject to an

evaluation process), the revenue is fully recognized in the DC reserve accounts as if they had

been paid at building permit issuance. This is accomplished by including a "receivable" at the

full cost of DCs owing in the DC Reserve Fund and a "payable" from one of the City's non-DC

reserve funds. In total, $15.1 million is accounted for in the DC reserve funds for the downtown

incentive program, including 430 residential units and 239.64 m2 of commercial developments.

5. The position of the City on the "Transit Congestion Factor" is addressed in the staff report to

Committee of Council on July 27, 2009.

6. The interest rate difference between positive and negative balance (3.5% positive, 5.5%

negative) reflects the City's investment yield and financing cost. While it is recommended in the

draft DC Background Study that funding for growth related capital programs be financed

internally, it is not certain whether or not this can be achieved in the next by-law period given

the many growth and non-growth related financial pressures placed on the City. At its own

discretion, Council may elect at any time to obtain external financing for any of its capital

programs.

7. This information was provided to BILD on July 7, 2009.

8. The position of the City on the "General Government - Parking" is addressed in the staff report

to Committee of Council on July 27, 2009.

July 23,2009 Page 3

Page 18: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix C

9. Growth Studies and Other represent those capital projects that are growth related but

attributable to soft services within the City including studies related to planning for growth

within the City. The studies identified in the DC background study include those studies funded

by the City in its ongoing program to plan for and manage growth. On a continuous basis, the

City maintains a multi year program of preparing and updating studies, master plans and

planning policy documents in order to administer its planning program. Such studies include:

TTMP updates, DC Background Studies, Growth Management Studies, Master Plans on topics

such as recreation and environment, Official Plan Policy Updates, Secondary Plan Policy

Updates, localized transportation reviews, area planning/zoning studies, peer reviews etc. The

amounts included reflect estimates based on past funding required for similar studies of similar

scope since the specific terms of reference have generally not yet been developed for future

studies. The studies identified and included in the DC Background Study do not include those

studies which are funded by individual landowners or landowner groups through the City's

development approval and planning process. For example, only Secondary Planning studies to

be carried out to update existing Secondary Plans are included and Secondary Planning Studies

for new Secondary Plans are not included even if those studies may be managed by the City

since those are typically funded by landowner groups. Other landowner funded studies such as

Block Plan background studies and studies done in support of development applications are also

not included.

10. The total funding requirement of the POA Courthouse facility was $10.8 million, of which $4.1

million was provided through provincial funding and $6.7 million from internal City borrowing.

As of December 31,2008, $0.4 million has been paid on the principal and $1.5 million on the

interest.

Adjustments have been made to the historical service level inventories to take into

consideration the over sizing of the courthouse facility during the 2004-2008 period. As a result,

the maximum allowable of General Government - Growth Studies and Other has been reduced

from $3,229 million to $1,034 million. Detailed calculations and related inventory changes are as

follows:

Period Growth

Growth 2003-08

(Adjustment for last 10 yrs.)

Growth 2009-18

(Addition to inventory in 2009)

Growth 2019-31

(Addition to inventory in 2019)

Total and Previously Included

in Draft Background Study

Growth

(Pop&

Employment)

136,549

196,400

185,590

518,539

%

Allocation

26%

38%

36%

100%

Building

sq.ft.

15,402

22,153

20,933

58,488

Land (AC)

0.507

0.730

0.690

1.927

July 23, 2009 Page 4

Page 19: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix C

11. BILD has requested details pertaining to Library facilities and information related to planned

development. Please find attached the Board approved Brampton Library Facilities Master Plan

Update November 2007.

12. The land unit cost of transit service centres has been adjusted to $1,147 million per hectare, as a

result, the adjusted transit maximum allowable is $68,056 million.

13. The position of the City on the "Transit Facilities - Grants" is addressed in the staff report to

Committee of Council on July 27, 2009.

14. Initial re-runs of the TTMP model has shown that any discrepancy due to population forecasts

for the year 2031 have minimal to no effect on the requisite road network to serve a population

of 707,000 or 738,000 (758,000 with undercount). The TTMP update is scheduled to be

completed in the fall of 2009 and further verification can be found within that report.

15. An adjustment based on a discrepancy in the Housing Mix data has been rectified in calculating

currently proposed rates. The growth in new units for the period 2009 - 2018 has been changed

from 143,940 to 144,430.

16. The draft DC Background Study currently values the replacement of the permanent library

structures at $332/sqft. This has been extracted from the approved Library Facility Master Plan

Update November 2007. The City believes these costs are in line with an expected replacement

value of these facilities under current market costs. Benchmarks from surrounding

municipalities also support the position that $332/sqft is a justified replacement cost for existing

library facilities.

17. This information was provided to BILD on July 7, 2009.

18. This information was provided to BILD and Altus Group Consulting on May 15, 2009 and the City

heard no further comment on these issues.

July 23,2009 Page 5

Page 20: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

rAGROUPI / j \ TransportationV—S \ Consultants

Appendix D

BA Consulting Group Lid.

45 ST. Clair Avenue Wast. Suite 300

Toronto. Ontario M4V1K3

416.961.7110(plvine) 416.961.980711a*)

mm.bagioup.com

[email protected]

Memorandum

To:

BILD Brampton DC Review

Team

From:

Paul Sarjeant, MASc, P.Eng

Senior Transportation Engineer

Date:

June 25, 2009

Project:

7162-03

2009 Brampton DC ReviewC:\Documents and SeWngs\PmsBACTOR\My

Documonts'PrcjectsW16203 BILD Brampton DC

Review\Coirespondence\2009 06 24 File Memo,doc

Page 1 of 5

Subject: City of Brampton 2009 Development

Charge: Issues Identified to Date per

Proposed Road Charge

The following concerns and requirements for additional

information have been identified to date with respect to the

calculation of the City of Brampton's 2009 Development

Charge for Roads:

1/ Level of Service Analysis

The level of service analysis presented in the Background Study

is problematic:

• The baseline measurement used for the qualitative level

of service measure is "Simulated 2006" V/C ratios. As

indicated in the Background Study text on page 1 of the

Roads Summary, in paragraph 5: "the need for

service... must not include an increase that would result

in the level of service exceeding the average level

provided in the City over the 10 year period preceding

the preparation of the background study."

The level ofservice numbers, as presented:

• do not represent a 10 year average, and

• reflect a simulated level of service derived from

a forecast model, as opposed to a real, measured

level of service.

The quantitative level of service (lane km / population

and employment) is insensitive to improvements that do

not add lane-kilometres ofroadway. This would

include:

Intersection and signal improvements

Railway Grade Separations

Gateways

Urbanization ofHwy 10

Noise Walls

Page 21: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix D

2/ Noise Walls

We are concerned that the introduction ofnoise walls on road widening projects is being charged

largely to the DC. Our understanding is that City Council endorsed introduction ofNoise Walls as a

required element on arterial road widening projects in built up areas. As such, the benefit of the walls is

largely to the existing population.

The proposed program includes about $34 million worth of noise walls. Ofthese:

• about $16 million is for "Noise Wall retrofits" at unidentified locations which are allocated

75% to growth.

• the remainder is for noise walls on specific road widening projects in built up areas, which are

generally allocated 95% to growth.

Please provide the rationale for these growth allocations.

3/ Gateways and Urbanization

In addition to the $23 million proposed for the "Urbanization" of Highway 10, there are about $6.5

million worth of "Gateway" improvements in the proposed program. All of these projects are allocated

95% to growth.

Please provide the rationale for this growth allocation.

4/ Property Acquisition Costs

About $278 million ofthe proposed roads program is earmarked for property acquisition, and is

allocated 100% to growth. This comprises 18% of the entire roads DC cost.

Ofthis total, $106 million is identified specifically as property acquisition related to the NSTC.

For which project has this money been set aside: is it related to the NSTC (north of Embleton) or

to the Bramwest Parkway (south of Embleton)?

If it is related to the City's proposed additional items to the NSTC, does it take into account the

property acquisition already built into the Region of Peel's DC?

What is the basis for the calculation of this cost?

• How was the area of land required determined?

• What unit cost was assumed?

The remaining property costs have been allocated on an annual basis: $13.5 million per year to 2017,

and then $4.0 million per year thereafter.

What is the basis for the determination of these annual costs?

Page 22: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix D

5/ Bramwest Parkway and North South Transportation Corridor (NSTC)

The costs for this facility include extending the NSTC as reflected in the Region ofPeel's DC north of

Sandalwood, and widening the section between Embleton and Bovaird to 8 lanes. The need for these

particular road network elements are arguably not related to growth within Brampton.

As such, the landowner's position has been that that the two projects, namely Bramwest Parkway and

the NSTC, service inter-regional travel demand, and should ultimately be uploaded to either the Region

of Peel or the Province. Furthermore, identification of the specific functional requirements (alignment,

connectivity, and number of lanes) of these projects can only be properly determined through an inter

regional study such as the ongoing HPBATS, or a Provincial freeway study such as the GTA West

Corridor study.

The landowners, through BILD, will continue working with the City to ensure that the uploading

of these projects can be achieved in an appropriate manner.

6/ Bramwest Parkway Interchange

In the road projects identified as being related to Bramwest Parkway, there are two high cost items that

relate to road works in the same area.

The first is identified in 2012 as Bramwest Parkway from Highway 407 (Meadowvale Road) to Steeles

Ave, with the jurisdiction identified as Region of Peel. The total cost of this project is $34.88 million.

The second item is identified in 2013 as the Bramwest Parkway and Highway 407 Interchange. The

cost of this project is $25.76 million.

Please provide a more detailed description of these two projects, and the basis for costing them.

7/ Benchmark Cost Anomalies

The construction prices for road work are being reviewed in detail. There is a general sense that the

construction prices that are being used in the DC calculation are high relative to the experience of

members ofthe developer's group and their consultants. Furthermore BILD believes that developer

built infrastructure (such as green field collector roads) can generally be delivered at a lower cost than is

reflected herein, and may warrant special costing consideration insofar as the DC roads cost estimates

are concerned.

To this end, a review of the unit costs, and ofthe benchmark road costing in comparison to City of

Brampton standard road sections has been undertaken. To date, this exercise has revealed a number of

discrepancies:

• In addition to Storm sewers, Sanitary sewers have been include in all of the costed sections.

Are these not a Region of Peel responsibility?

• Manholes appear to have been spaced as closely as catchbasins, which has not been typical in

the past in Brampton.

Page 23: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix D

The estimated length of catchbasin lead installation appears to be low (83m is included in the

calculation, our estimated length is 192m)

For new roads: a line item for the adjustment of existing manholes has been included in the

estimates.

For existing roads: line items for both adjustment and removal of manholes and catchbasins

have been included. Only one or the other should be applied to any given section ofroad as

appropriate.

The pavement markings estimate is based on the number oflanes +1, rather than the number of

lanes- 1.

The granular B width estimate does not include the curb widths.

Subdrains do not appear to have been accounted for.

More clarity as to the presence of, location of and number ofbike lanes is required.

A 20% adjustment for the cut and fill estimates has been included for new construction. What

is the basis for this adjustment.

Stormceptors have been assumed to occur at a frequency of one per kilometre, which is a closer

spacing then would generally be used (particularly over the entire roads program). The unit

price for these items appears to have almost doubled relative to the pricing used in the 2008 DC

Roads Cost Update.

Asphalt splash pads have been included for collector roads, but do not appear in the current City

standards.

8/ Region of Peel Projects

There have been past discussions regarding the City of Brampton's obligation with respect to funding

works related to Region ofPeel roads.

Please confirm that the identified Region of Peel road works have been coordinated with the

Region's works program, and that an understanding of which jurisdiction is responsible for

which works (sidewalks for example) is shared by both the City and the Region.

Please provide the basis for assessing the number of, and costing assumptions for, the

intersection tie ins related to Region of Peel projects.

9/ MTO Projects

Subsidy ofprovincial projects has been identified in the past as a problem, with the industry taking the

position that these works are not eligible for DC funding. This position remains unchanged.

4

Page 24: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix D

10/ Transit Congestion Factor

This adjustment appears to be unrelated to the 10 year level of service measure for transit vehicles. Nor

is it clear as to whether it reflects the benefit of the numerous transit specific improvements included in

the program (for example transit signal priority and queuejump lanes).

Please provide the details of the calculation of this factor, and the rationale for it's support under

the DC Act

11/ Criteria for including Collector Roads

We note that a number ofnew collector roads have now been included in the DC Roads Program.

Has the City developed a criteria for making a determination as to whether a collector road

qualifies for inclusion in the DC or not? If so, please provide this criteria.

12/ Change in Growth Allocation of Road Widening Projects

In the past, these projects had been allocated 90% to Growth, hi this DC program they are allocated

95%.

Please provide the rationale and calculated basis for determining this allocation.

13/ Intersection Improvements

Programmed Intersection Improvements on both City and Regional roads have been allocated 100% to

growth.

Please provided the rationale for this allocation.

14/ Intersections and Stuctures

A key issue raised by the building industry in previous DC negotiations was the need to identify the

intersections and structure that have been included in the DC cost estimates. This provides clarity when

negotiating sole source agreements and determining DC credits for road works built by developers.

Will the City be documenting and making available the specific locations of the intersections and

structures that have been assumed to be required through this costing exercise?

Page 25: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

engineering consultants

Appendix EiTRANS Consulting Inc.

100 York Blvd. Suite 300

Richmond Hill, ON L4B 1J8

Tel: (905) 882-4100

Fax:(905)882-1557

www.itransconsultinq.coiTi

File: 2.0

Project* 4587

Memorandum

To: Klaus Stolch - City of Brampton

Chris Duyvestin - City of Brampton

Cc: Henrik Zbogar - City of Brampton

Tyrone Gan - iTRANS Consulting

From: Elizabeth Szymanski - iTRANS Consulting

Date: July 20, 2009

Re: 2009 City of Brampton Development Charge Update

Reply to BA Group Memorandum June 25,2009

The Memorandum from BA Group to BILD Brampton DC Review Team dated June 25,

provided to iTRANS on June 31,2009 documents the results of the review of the 2009-2031

roads cost and background documentation completed by BA Group for BILD. The meeting

and discussion between BA Group, City staffand iTRANS on July 2,2009 helped clarify the

issues and questions raised by BA Group, provided opportunity to discuss and clarify inputs

and methods applied to cost calculation as well as cost allocation (Growth vs. BTE) ofa

number ofDC items. Following July 2 meeting, City staff has directed iTRANS to revisit

some sections of DC calculation inputs, methods and items and revise them accordingly. This

Memorandum summarises the response to BA Group Memorandum and documents changes

and modifications made to DC tables and calculations as a result ofBA Group's concerns.

1. LEVEL OF SERVICE ANALYSIS

The Level ofService methodology used in the 2009 DC Update is replicating the method used

in the 2004 update. The method has two components - qualitative measure relies on observed

traffic volume information extracted from cordon count database and simulated in demand

forecasting model and quantitative measure uses the lane km/capita population and

employment. The 2006 quality level ofservice is the volume to capacity ratio simulated for

the peak directions during the pm peak hour of traffic in 2006. The 2006 V/C is considered to

reasonably represent average conditions during the 1999-2008 period. The 2006 simulated v/c

on all arterial roads within Brampton is at 0.75 whereas the comparable observed v/c is at

0.73.

The quantitative measure of lane km/capita is consistent with the previous DC study. While

the infrastructure identified is not specifically addressed individually, the infrastructure is part

ofthe road infrastructure, and represents a standard level of service measure successfully

applied in the past DC by-law updates.

1of6

Page 26: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix E

2. NOISE WALLS

Noise walls for road widening projects are allocated at 95% to growth. These noise walls

(there are five ofthem at the cost of$18,34M) are the result of Environmental Assessment

recommendations and are considered as integral to the road widening project as the

installation ofsidewalks or drainage. These road widening projects require noise walls as

mitigation due to increased noise levels from traffic growth and the road being widened closer

to the adjacent properties. The noise walls are a part of the road widening projects, and

therefore, have a DC allocation identical to the project ofwhich they are a part.

The noise wall retrofits contain both new and replacement noise walls. The new noise walls

are required due to an increase in noise levels from traffic growth. The noise walls are also

designed to mitigate future traffic volumes. Similar to new noise walls, the replacement of

noise walls are designed to mitigate future traffic volumes. This is analogous to the

replacement and upsizing ofwater pipes, where benefits to both growth and existing

development are apparent.

3. GATEWAYS AND URBANIZATION

The Highway 10 Urbanization project has been carried over from the previous rounds ofDC

spreadsheets. The urbanization of Highway 10 will include full reconstruction and "change of

character" ofthe 5 km stretch ofroad built to MTO's standards for rural provincial highway.

The urbanization is envisioned to modify the roadway cross-section to an urban standard,

upgrade intersections and signals, and provide transit, cycling and pedestrian facilities. At

present, the $23M amount is driven largely by the length of the segment in question and the

need to upgrade the intersection, including the undertaking ofan EA and utility relocation.

The cost ofHwy 10 Urbanization is treated as an infrastructure cost allowance until more

detailed information and cost estimates become available.

Hwy 10 Urbanization is a part of the overall effort to accommodate new development and

growth within the City and as such has been allocated at 95% to growth.

Gateway improvements reflect the urban design and streetscaping standards that arc an

integral part of infrastructure investment in "gateway" corridors, and were always included in

previous City ofBrampton Capital Programs supported by Development Charges. The

Gateway improvement program is directly linked and triggered by the need to allocate and

manage growth within the City and as such has been allocated at 95% ofcost recovery from

DC.

2of6 iTRANSProject n 4587

Page 27: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix E

4. PROPERTY ACQUISITION COSTS

Bramwest Pkwv/ NSTC Property Costs

Property costs estimates for Bramwest Pkwy/NSTC tabled in May 2009 Draft DC

Background Study Report were based on the following assumptions:

■ NSTC at 45m and 50m ROW

■ 8-lane facility from Hwy 407 to Embleton Rd

■ 6-lane facility form Sandalwood Rd to Mayfield Rd

■ 2 additional lanes (to widen from 6 to 8) from Embleton Rd to Bovaird Rd

■ Existing intersection space at major intersections (Stceles, Bovaird, Sandalwood and

Mayfield) has been excluded

■ Total land required: 79.8 acres

■ Real Property Land Sales for commercial, industrial, residential and retail uses; for

Southwest Quadrant, Sep '07 to Aug '08 as provided by the City of Brampton.

■ Current characteristic of land ownership in Bram West (68.3% of employment

(industrial/ commercial) land, 25.8% residential, 5.9% other, no retail). BramWest

characteristic applied to NWB.

■ Estimated cost of land acquisition in Bram West at S90.8M, Estimated cost of land

acquisition in NWB at S15.8M.

To account for the TTMP recommendations for Bramwest Pkwy/ NSTC ROW to be

constructed (subject HP BATS results) at 54 m. ROW and to include property costs for the

construction of36m ROW (plus 2 m buffer) section ofBramwest Pkwy/ NSTC south ofHwy

407 to Heritage Rd the property costs were revised. The resulting total land requirement is at

91.17 acres. The estimated cost of land acquisition in Bram West (Heritage to Embleton Rd) is

at S95.6M and North West Brampton at S20.9M.

Other property costs

The $13.5 M annual property costs are based on City's average annual land acquisition

expenditures quoted in the City Budget (S10M) and additional $3.5M required for transit road

related projects such as bus bays, queuejump lanes etc. Following the information extracted

from Budget spreadsheets, the $13.5 will be required until 2017, after that the land acquisition

costs are expected to decrease to $4M per annum.

5. BRAMWEST PKWY AND NORTH SOUTH

TRANSPORTATION CORRIDOR (NSTC)

This issue will be addressed in the staffreport to Committee ofCouncil on July 27th, 2009.

3of6 iTRANSProject U 4587

Page 28: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix E

6. BRAMWEST/NSTC PKWY INTERCHANGE

The Bramwcst Pkwy/NSTC interchange has been double counted. The cost of the

interchange, estimated at $22M will be removed from the cost of the Bramwest

Parkway/NSTC segment from Highway 407 (Meadowvale Rd) to Steeles Ave. The resulting

cost ofthe construction ofthe 6-lane segment is S3.48M. The Bramwest Pkwy/ NSTC/Hwy

407 interchange costing is based on unit price and structure benchmarks developed for this DC

update.

The NSTC railway grade separation south of Sandalwood Rd will be removed from the DC

spreadsheet as this item is already in the Regional DC table.

7. BENCHMARK COST ANOMALIES

Ql: In additional to Storm sewers, Sanitary sewers have been included in all of the costed

sections. Are these not a Region ofPeel responsibility?

A: Yes. The cost ofsanitary sewers is a Regional responsibility. Cost ofsanitary sewers has

been removed from calculations.

Q2: Manholes appear to have been spaced as closely as catchbasins, which has not been

typical in the past Brampton.

A: Manhole spacing has been adjusted to match City's road design standards at 100 m apart.

Q3: The estimated length ofcatchbasin lead installation appears to be low (83m is included in

the calculation; our estimated length is 192m).

A: We agree with the revision. Catchbasin lead formula has been modified to reflect no. of

catchbasins x Vi the width ofroadway.

Q4: For new roads: a line item for the adjustment ofexisting manholes has been included in

the estimates.

A: We agree with the revision. Adjustment has been removed from the "new construction"

projects.

Q5: For existing roads: line items for both adjustment and removal ofmanholes and

catchbasins have been included. Only one or the other should be applied to any given section

of road as appropriate.

A: We agree with the revision. Double count for adjustment and removal has been removed.

Q6: The pavement markings estimate is based on the number of lanes +1, rather than the

number of lanes-I

A: Agreed, calculation has been modified to match City standards (number oflanes -1).

Q7: The granular B width estimate does not include the curb widths.

4of6 iTRANSProject # 4587

Page 29: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix E

A: Unit price for curbs and gutters includes costs ofgranular B and subdrains.

Q8: Subdrains do not appear to have been accounted for.

A: Unit price for curbs and gutters includes costs ofgranular B and subdrains.

Q9: More clarity as to the presence of, location ofa number ofbike lanes is required

A: Calculations are based on the provision of 1.5 m sidewalk on one side and a 3 m multi-use

path on the other side for artcrials and collectors;

Q10: A 20% adjustment for the cut and fill estimates has been included for new construction.

What is the basis for the adjustment?

A: A rough estimate of20% adjustment is based on profile adjustments required for new

constructions only.

Ql 1: Stormceptors have been assumed to occur at a frequency ofone per kilometre, which is a

closer spacing than would generally be used (particularly over the entire roads program). The

unit price for these items appears to have almost doubled relative to pricing used in the 2008

DC Road Cost Update.

A: 1 km spacing ofstormceptors is the current City practice. iTRANS used average price for

maintenance holes stormceptor (4000) & 401.010 which at a mid-price level between

maintenance holes stormceptor (750) & 401.010 (average price at $30,700) and maintenance

holes stormceptor (6000) & 401.010 (average price at $62,900). It is possible that the 2008

DC Update was based on the average price for maintenance holes stormceptor (750).

However application of the low end stormceptor will underestimate the costs since in a

number ofcases maintenance holes stormceptors 4000 and 6000 were used. We cannot

confirm what stormceptor type was costed in 2007 pricing.

Q12: Asphalt splash pads have been included for collector roads, but do not appear in the

current City Standards.

A: Asphalt splash pads have been removed from the benchmark cost calculations

Other comments:

BA has provided iTRANS with the results ofdetailed review ofroad work benchmarks by

treatment type. All comments and suggestions have been taken into consideration and

incorporated where necessary.

8. REGION OF PEEL PROJECTS

We confirm that Region of Peel road work projects have been coordinated with the Region of

Peel. Based on the previous agreements between the Region and the City, Brampton will

continue to collect charges on selected projects (as specified by Peel DC) until 2015. After

2015 the City is not collecting charges for any component ofregional projects. This agreement

and the selected projects are reflected in the current DC update.

iTRANSProject # 4587

Page 30: DC Contribution to Developer Existing Cost Benefit Total of Cou… · COB COB COB COB COB COB COB COB COB Southern City SoundaryROP COB COB COB COB Northern City boundary COB Mississauga

Appendix E

Special effort was put into eliminating double counts ofregional and other intersection

improvements linked to road widening or new construction projects. As a general rule,

widening of intersections under regional jurisdictions was assumed to be handled by the

Region.

9. MTO PROJECTS

A City component ofMTO projects is solely triggered by the need to accommodate growth. It

is therefore allocated to growth component ofthe DC.

10. TRANSIT CONGESTION FACTOR

This issue will be addressed in the staffreport to Committee ofCouncil on July 27*, 2009.

11. CRITERIA FOR INCLUDING COLLECTOR

ROADS

Four-lane new collector roads were included in the DC.

12. CHANGE IN ALLOCATION OF ROAD WIDENING

PROJECTS

The 5% ofthe costs allocated to BTE reflects the costs ofresurfacing the existing lanes. On

average, costs of asphalt removal, repaying and re-application of pavement markings (that is

ofbenefit to existing users) accounts for 4% to 5% ofthe cost ofthe entire widening project.

Previous 10% allocation to BTE has been identified by City staffas an overestimation of cost

in need of rectification.

13. INTERSECTION IMPROVEMENTS

All intersection improvement projects have been revised to a 95% growth and 5% BTE

allocation.

14. INTERSECTIONS AND STRUCTURES

The City will be providing full documentation of intersections and structures (bridges, culverts

and grade separations) included in the DC road work program at a later date as approved by

the Commissioner ofWorks & Transportation and the City Treasurer.

End ofMemorandum

6of6 iTRANSProject #4587