1 DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTION District of Columbia Water and Sewer Authority May 24, 2018 Brandon Flora Greeley and Hansen CWEA Collection Systems Committee Spring Seminar

Transcript of DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown...

Page 1: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

1

DC CLEAN RIVERS PROJECT

CONSENT DECREE EVOLUTION

District of Columbia Water and Sewer Authority

May 24, 2018

Brandon FloraGreeley and Hansen

CWEA Collection Systems Committee

Spring Seminar

Page 2: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

2

▪ Background

▪ Project Evolution

▪ LTCP Base Plan

▪ Total Nitrogen/Wet Weather

Modifications

▪ Summer 2012 Bloomingdale

Flooding Response

▪ Green Infrastructure

▪ Wrap-up and Current Status

▪ Questions

Agenda

2

Page 3: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

BACKGROUND

3

Page 4: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

▪ Provides

▪ Drinking water distribution

▪ Wastewater collection and treatment

▪ Stormwater collection and conveyance

▪ Treats wastewater for a population of 2.1 million

▪ District of Columbia

▪ Montgomery & Prince George’s Counties, MD

▪ Fairfax & Loudoun Counties, VA

▪ Operates the world’s largest advancedwastewater treatment plant

▪ Serves a regional area of approximately 725 mi2

Background

DC Water Overview

4

Page 5: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

Background

DC Water Service Area

5

Page 6: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

▪ Control combined sewer overflows to the:

• Potomac River

• Anacostia River

• Rock Creek

▪ Relieve flooding in the Northeast Boundary Area

▪ Implemented under a Federal Consent Decree among:

• US Environmental Protection Agency (US EPA)

• US Department of Justice (US DOJ)

• District of Columbia

• DC Water

▪ Fully in operation by 2030

• Major intermediate milestones in 2018 and 2025

Background

DC Clean Rivers Project Background

6

Page 7: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

7

Controls Combined

Sewer Overflows

2142

1063

49

3254

1282

638

48

1968

391638

48

1077

54 79 5138

0

500

1000

1500

2000

2500

3000

3500

AnacostiaRiver

PotomacRiver

Rock Creek TotalSystem

CSO

Ove

rflo

w (

mg/

avg

year

)

1996 2017 2018 LTCP Completed

7

Background

Magnitude of the Challenge

7

Page 8: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

8

PROJECT EVOLUTION

8

Page 9: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

9

Public Participation Public Participation

Project Evolution

Program History

January 14, 2016 –Consent Decree

Modification Entered in Federal Court

9

1 2 3 4

Page 10: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

1010

Original LTCP

Green Infrastructure

12’ diaMining Site

for 23’ tunnel

Mining Site for 12’ tunnels

1 2 4TN/WW Plan 3 Bloomingdale Flooding

126 mg

9.5 mg

58 mg

Tunnel Dewatering PS

Tunnel Dewatering PS

157 mg

12’ dia

Blue Plains Tunnel

225 mgd Tunnel Dewatering PS

225 mgd Enhanced Clarification Facility

9.5 mg

58 mg

Tunnel Dewatering PS

20.5’

dia

Mining Site

157 mg

9.5 mg

58 mg

Tunnel Dewatering PS

157 mg

365 imp ac managed by GI

Base Plan Challenge:New effluent limit in NPDES permit for Blue Plains due to Chesapeake Bay TMDL

Challenge:Modify Consent Decree to

incorporate Green Infrastructure

133 imp ac managed by GI

• 30 mg with GI• 40 mg without GI

Challenge:Flooding demands urgent action for an

undersized sewer that’s existed for 135+ years

Project Evolution

Program History

10

Page 11: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

11

Anacostia Tunnel System

(126 mg)

Blue Plains WWTP

Anacostia TunnelDewatering

Pumping Station

▪ 126 MG Anacostia River Tunnel System▪ Dewatered to existing system via

deep pumping station near Poplar Point

▪ Smaller diameter branch tunnels for flood relief in Northeast Boundary

▪ 58 MG Potomac River Runnel▪ Dewatered to existing system via

deep pumping station near Lincoln Memorial

▪ 9.5 MG Piney Branch Tunnel▪ Dewatered to existing system via

gravity

1

Potomac River Tunnel(58 mg)

Potomac River TunnelDewatering Pumping

Station

Piney Branch Tunnel

(9.5 mg)

Project Evolution

Original LTCP (1999-2002)

11

Page 12: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

12

▪ Before 2007

▪ No permit limit - effluent goal of

8.4672 million lbs/yr or 7.5 mg/L

▪ 2007 NPDES Permit Modification

▪ Nitrogen limit of 4.689 million lbs or

4.2 mg/L (reduction of 44%)

12

Project Evolution

2007 – New Nitrogen Discharge Limit for Blue Plains

12

Page 13: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

13

Blue Plains370 mgd annual avg

Complete

Treatment ENR

Excess Flow Treatment,

Plain Settling, Add

4 Primary Tanks

Outfall 001Outfall 002

336 mgd

1076 mgd

Conventional Approach

Complete

Treatment ENR

Enhanced Clarification

(improved effluent to lower

pollutant loads)

Outfall 001Outfall 002

521 mgd

1076 mgd

Selected Approach

31 mg of storage

225 mgd

Blue Plains370 mgd annual avg

Total Cost to DC Water

Additional Cost to CSO Program $ 0 $ 239 M

$ 1,600 M $ 800 M

Significant Savings by Integrating Nitrogen Removal Goals into

CSO Program

Project Evolution

Nitrogen Removal Alternatives

740 mgd

Peak = 2.0

555 mgd

Peak = 1.5

13

Page 14: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

14

Anacostia Tunnel System

(157 mg)

Blue Plains WWTP• 225 mgd Wet Weather

Treatment Facility • Tunnel Pumping Station at

Blue Plains• Easily expandable to 500 mgd

Anacostia Tunnel System

(126 mg)

Blue Plains WWTP

Anacostia TunnelDewatering

Pumping Station

Before 2007 Nitrogen Permit Limits After 2007 Nitrogen Permit Limits

30 mg Blue Plains Tunnel

added

Anacostia TunnelDewatering

Pumping Station Eliminated

2Project Evolution

Project Changes for Blue Plains Nitrogen Control

14

Page 15: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

15

Date DurationRainfall

(inches)

NOAA Point

Precipitation

Frequency (Nearly)

7/10/2012 1-hour 1.96 10-year storm

7/18/2012 30-minute 1.35 5-year storm

7/19/2012 15-min 0.94 5-year storm

9/2/2012 2-hour 2.78 10-year storm

Storm Intensity Map Courtesy of:

Washington Post

Project Evolution

2012 Bloomingdale Flooding

15

Page 16: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

16

Rhode Island Metro

1st St NW

Flagler St NW

Rhode Island & T St NW

Rhode Island Between 1st & 2nd St NW

Rhode Island & T St NW

Rhode Island & 1st St NW

16 1st & V St NW

Photo courtesy of: Greg Roberts

Photo courtesy of

huffintonpost.comPhoto courtesy of myfox.com

Photo courtesy of myfox.com Photo source unknown

Photo source unknown

Photo source unknown

Photo source unknown

Photo source unknown

Project Evolution

2012 Bloomingdale Flooding

16

Page 17: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

17

▪ Over 200 property owners affected

▪ Flood clean-up costs ranged from

$3,000 to $18,000 per household

▪ Major concerns regarding public

health and safety

Hallway Flooding

Photo source unknown

Basement Cleanup

Photo source unknown

Basement Flooding

Photo source unknown

Map of Reported 2012 Flooding17

Project Evolution

2012 Bloomingdale Flooding

Page 18: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

18

4 storms caused major

flooding: July 10, 18, 19

and Sept 2, 2012

Mayor formed Task

Force in Aug 2012

Task Force report

delivered end of Dec

2012

Over 25 Recommendations:

Engineering Measures• McMillan Stormwater Storage

• First Street Tunnel

• Northeast Boundary Tunnel

Regulatory Code ChangesOperations &

MaintenancePublic

Outreach

Project Evolution

Response to Bloomingdale Flooding

18

Page 19: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

19

MCMILLAN STORMWATER STORAGE & IRVING ST GREEN INFRASTRUCTURE4 million gallons(Spring 2014)

FIRST STREET TUNNEL8 million gallons(Spring 2016)

NORTHEAST BOUNDARY TUNNELGravity System to Blue Plains2023

A

C

B

A

B

C

Irving St.

Fir

st

St.

North

Cap

. S

t.

Channing St.

N

Project EvolutionEngineering Measures to Mitigate Bloomingdale Flooding

19

Page 20: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

20

Before Bloomingdale Flooding

3

After Bloomingdale Flooding

Blue Plains WWTP

12’ dia

Mining Site for 23’ tunnel

Mining Site for 12’ tunnels

Complete by 2025

Blue Plains WWTP

20’ dia

Project Evolution

Project Changes for Bloomingdale Flood Mitigation

Realigned Single 23’ dia. Northeast Boundary Tunnel

First Street Tunnel Accelerated and Built

with Dewatering Pumping Station

(Complete by 2016)

Complete by 2023

20

Page 21: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

21

Project Evolution

Green Infrastructure

21

Page 22: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

22

▪ Added environmental, social

and economic benefits

▪ Heat island reduction

▪ Improved air quality

▪ Enhanced aesthetics

▪ Opportunity for local, green jobs

▪ Supports Sustainable DC Plan

22

Existing Plan

Recommended Plan

0

10

20

30

40

50

60

20

12

20

14

20

16

20

18

20

20

20

22

20

24

20

26

20

28

20

30

20

32

20

34

Millio

n G

allo

ns

/Av

era

ge

Ye

ar

Year

Rock Creek - Predicted CSO Overflow Volume

0

10

20

30

40

50

60

2012

2014

2016

2018

2020

2022

2024

2026

2028

2030

2032

2034

Millio

n G

allo

ns

/Av

era

ge

Ye

ar

Year

Rock Creek - Predicted CSO Overflow Volume

CSO reduction begins in 2017 and continues throughout program

CSO reduction occurs in 2025

Project Evolution

Benefits of Green Infrastructure

22

Page 23: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

23

4

Before GI Amendment After GI Amendment

Project EvolutionChanges due to GI Amendment and Potomac River Tunnel Gravity Extension

GI in lieu of 9.5 MG Piney Branch Tunnel

Potomac River Tunnel(58 mg)

Potomac River TunnelDewatering Pumping

Station

Piney Branch Tunnel

(9.5 mg)

365 impervious acres managed by GI

133 impervious acres managed by GI

Interconnected Potomac River Tunnel

(30-40 mg)

Sewer Separation for CSOs 025, 026

GI in lieu of Tunnel for CSOs 027, 028, 029

▪ Full GI build-out pending practicability determination

based on first project in each sewershed 23

Page 24: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

24

WRAP-UP AND CURRENT STATUS

24

Page 25: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

25

Wrap-Up and Current StatusOverview

• DC Clean Rivers Project: $2.7 Billion

• Nitrogen Removal: $950 Million

• Total > $ 3.5 Billion

• 25 yr implementation (2005 – 2030)

• 96% reduction in CSOs & flood relief in Northeast

Boundary

• Approx 1 million lbs/yr nitrogen reduction predicted

DC CLEAN RIVERS PROJECT AND

NITROGEN REMOVAL PROGRAMS

IN OPERATION

IN OPERATION

Tunnel

System

Status Operation

Date

First Street

Tunnel

In Operation 2016

Anacostia River

Tunnel

In Operation 2018

Northeast

Boundary Tunnel

Construction 2023

Potomac River

Tunnel

Planning 2030

25

Page 26: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

26

Controls Combined

Sewer Overflows

26

Wrap-Up and Current Status

Major Benefits of Project Changes

26

▪ Significantly more economical approach to

meeting Blue Plains nitrogen limits

▪ Accelerated flooding relief for Bloomingdale

▪ Triple-bottom line benefits of Green

Infrastructure

▪ Interconnected tunnel system operates

entirely by gravity

▪ Single dewatering pumping station at Blue

Plains

▪ Interconnection provides better control for

localized storms

▪ System provides operational redundancy

for existing pumping stations

▪ Allows for elimination of inflatable dams

Page 27: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

27

▪ Anacostia system was placed into

operation March 20, 2018

▪ April 16 rain event

▪ 2 inches of rain in 3 hours

(2- to 5-year storm)

▪ Tunnel filled to capacity

▪ Tunnel captured 180 MG of

combined sewage

▪ May 13-19 rain events

▪ ~6” of rain over 7 days

▪ Tunnel captured 650 MG of

combined sewage

▪ Tunnel did not overflow

▪ Smaller overflows from existing

CSOs (greatly reduced by tunnel)

Wrap-Up and Current Status

Anacostia River Tunnel in Operation

27

Page 28: DC CLEAN RIVERS PROJECT CONSENT DECREE EVOLUTIONPhoto courtesy of myfox.com Photo source unknown Photo source unknown Photo source unknown Photo source unknown Photo source unknown

28

Questions and Answers