Copyright © 2009 Accenture All Rights Reserved.

Deployment Timeline and Key Activities Deployment Roles and Responsibilities Questions

Agenda

DBSi 5.0 Deployment Overview

Page 3: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Deployment Process Timeline

DBSi 5.0 Deployment Overview

Page 4: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Deployment – Key Activities

DBSi 5.0 Deployment Overview

Pre-Planning:Entry Criteria:• Finance decision madeTasks:• Develop Project Timeline• DBSi 5.0 Environment Hardware Allocated – iSeries HW &

Coda Servers 5.0• Schedule Launch • Request Coda XL/Word Licenses

Milestone / Exit Criteria: • Deployment Agreements Signed• CODA eAssets/eProcurement decision made• Dealer Implementation Team Created

Page 5: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Launch Meeting

DBSi 5.0 Deployment Overview

Launch:Entry Criteria:• Deployment Agreements Signed• CODA Software Package Delivered• DBSi 5.0 Conversion Package Delivered• DBSi 5.0 Release Package Delivered Tasks:• Project Kickoff - Deployment Overview • Review Deployment Launch presentations• Coda eFinance Overview• DBSi 5.0 Integration w/Coda• DBSi 5.0 Conversion Process• Deliver BPW • Review CODA Client softwareMilestone / Exit Criteria: • Coda Client Software Reviewed• Coda Training Scheduled• DBS 2.3.4 Data Cleansing Strategy Planned• DBSi 5.0 Delta Training Planning Started

Additional Dealer PlanningTasks:• Document changes to Chart of Account (COA) structure• Coda e-Finance servers in place and loaded with Coda

application, base company & training company• DBSi 5.0 test environment built• Complete initial pass at all conversion cross reference

spreadsheets• Complete BPW prep pack• Complete CODA Client Installs• Review Dealer Task ListMilestone/Exit Criteria:• Initial draft COA completed• Initial draft conversion cross reference spreadsheets completed• Coda V4 Retirement Planning Completed

Page 6: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

CODA Training/Configuration

DBSi 5.0 Deployment Overview

Coda Training/ConfigEntry Criteria• BPW Customer Preparation Pack completed• Coda servers built (TRN, FDC, PRD Instances)• CODA Client Installs completed Tasks:• Key users workshops (Coda): Functional Enablement/Design, Reporting, & Coda security• Key users workshops: Finance interfaces, cutover planning• Key user training: Coda Application overview & maintenance, e-Customiser, Cash Mgmt, Credit Desktop, &

Multi-Company• Coda XL Training• Training on data conversion processes• Training on DBSi 5.0 core changes (Parts, Service, EMS updates, database & program changes) Milestone / Exit Criteria: • Key Users trained & have attended all workshops• Dealer Finance Lead (Process Owner) Approved all Coda E-Finance workshop decisions

Page 7: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Dealer Configuration

DBSi 5.0 Deployment Overview

Dealer Configuration:Tasks:• Finance Config:- Create master data for migration - companies, documents, elements, balance,

year, currency, groups, tax, hierarchies, pay masters, presenters, selectors, input templates, and users.

• Review Dealer Task ListFDC/DDC:• Update/test Critical path FDC/DDC’sMilestone / Exit Crtieria: • Finance functional configuration complete and approved by Dealer Finance Lead (Process Owner)

Page 8: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Conversion Test

DBSi 5.0 Deployment Overview

Conversion TestEntry Criteria:• Test/FDC Coda Configured & Ready for Conversion TestTasks:• Cleanse, Convert & validate, GL Account, Elements, Hierarchies, 6 periods of Coda V4 detail & summary

data. Include a month-end & year-end close out.• Configure the conversion menu (define the required companies)• Perform the initial backup• Develop Production Data Conversion ScheduleMilestones\Exit Criteria:• FDC/DDC Conversions complete

Page 9: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Production Conversion

DBSi 5.0 Deployment Overview

Production Conversion:Entry Criteria:• Production Data Conversion Schedule completedTasks:• Cleanse, Convert & Validate all Coda V4 Data into Coda V11Checkpoint 1: • GL Accounts, Elements, Customers and Vendors converted • Coda V4 Summary Conversions • Early Go-Live Decision PointCheckpoint 2: • 20% to 30% of Coda V4 Detail historyCheckpoint 3:• 80% to 90% of Coda V4 Detail historyMilestone/Exit Criteria: • All data converted except final period(s)

Page 10: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Business Testing / Train End Users

DBSi 5.0 Deployment Overview

Business Testing:Entry Criteria:• Prepare Mock environment & Coda Servers• Business Test Environment Data Date Set (prd database backup date)• Business Testing User Security, PC's & Room(s) Identified• Business Testing Plan completed• FDC/DDC Work Plan completed• FDC Entry Code Cross Reference Completed• FDC Customer Cross Reference Completed• FDC Document Source Input Spreadsheet UploadedBusiness Testing:• Complete Business testing (Business scenario testing) in dealer

integrated environment• DDC/FDC testingTraining:• Complete End-User training (Finance/DBS Parts, Service, EMS)Milestones/Exit Criteria: • DBSi 5.0 Business Testing complete & all severity 1 & 2 issues resolved• Batch Testing Completed• Mock Cutover Completed• All FDC/DDC’s updated/tested• End users trained • Production Cutover Planning Completed• Delta Training Completed• CODA Input forms completed and tested• CODA security set up and tested

Page 11: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Go-Live

DBSi 5.0 Deployment Overview

Go-Live:Entry Criteria:• Hot / High issues completed• All Data Converted Except Final Period(s)• Production LPAR Full System Save• DBS Customer Adds/Updates Frozen• Coda V4 Vendor Adds/Updates Frozen• Pre Conversion DBS Batch Scheduled• GL Posting Extract• Go-Live Go/No Go MeetingTasks:• Complete DBS Batch Activities• Convert master data & final period(s)• 5.0 Upgrade• Migrate DDC changes from test environment to production • Dealer validation test• Business Catch up

Milestone / Exit Criteria: • Final finance data converted• Final system validated

Page 12: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Roll-Out Support

DBSi 5.0 Deployment Overview

Roll-Out Support:Tasks:• Remote Support through 1st month end• Coda V4 & Conversion tools removed 6 weeks following go-liveMilestones / Exit Criteria:• Final Executive Update

Page 13: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Pre-Planning – Prepare for deployment - hardware ordered; contracts signed; Identify & form teams

Launch – Kick off – Coda v11 overview; review data cleansing and extracts, element and external reference helpers, schedule deployment work plan and training dates

Dealer Planning – Initial draft of COA completed; Coda servers in place and pre-loaded; initial draft of conversion cross reference spreadsheet completed

Training and Configuration – Key users trained and work shops completed; Dealer Finance Lead approved all Coda e-Finance workshop decisions

Dealer Configuration – Finance functional configuration complete and approved by Dealer Finance Lead

Conversion Test – Data Upload and UAT complete

Production Conversion - Convert finance data and CODA input forms completed and tested

Business Testing – All testing complete and End users trained

Go-Live – Cut Over from DBS 2.3.4 to DBSi 5.0

Roll-Out Support – Post implementation support

Deliverables

DBSi 5.0 Deployment Overview

Page 14: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Accenture/CODA

1. Co-manage deployment project plan with dealer counterpart

2. Conduct key user training and workshops

3. Support dealer during data conversion

4. Conduct status calls

Dealer

1. Manage 5.0 implementation plan

2. Qualified and available Finance key users

3. Attend workshops and key user training

4. Configure Coda e-Finance

5. Approve e-Finance Designs

6. Execute and validate Finance Data Conversions per schedule

7. Train all end-users

8. Update and test all FDC/DDC’s/Third Party Software integration

9. Test/validate Mock & Final Cut-Over

10. Manage Deployment Environments Activities

Responsibilities Overview

DBSi 5.0 Deployment Overview

Page 15: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Dealer – GeneralDBSi Champion/Executive - (1 Person)

– Charter & Sponsor DBSi 5.0 Project

Deployment Project Manager - (1 Person)

– Coordinate Deployment Activities – Manage deployment project, coordinate supporting resources/activities, manage risks,

& escalate as needed.– Manage Local Issues Log– Report timeline status updates– Plan & Coordinate Mock, Business Test, Business Transition & Final cut-over activities

– Schedule & coordinate CODA Training– Coordinate deployment scheduling/timeline updates– Provide support for FDC and Production Conversions– Provide support for Post Go Live– Coordinate environment activities

Deployment Roles & Responsibilities

DBSi 5.0 Deployment Overview

Page 16: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Dealer – FinanceFinance Process Owner

– Approves Coda E-Finance designsFinance Key Users (2 persons, minimum.. 4 persons recommended)

– Attend all key user training and finance workshops– Document finance processes and complete configuration of Coda– Convert and validate finance data– Define reporting requirements & develop desired reports– Deliver Coda E-Finance end user training– Complete mock cut-over testing/validation– Execute finance cut-over tasks (final periods)

Finance SME's (Varies) – Assist with areas of finance expertise as needed during Coda E-Finance

workshops & configuration (Ex. Credit Manager)

Finance End-Users (Varies)– Attend end user training for Coda finance– Assist as needed for mock testing validation & cut-over validation

Deployment Roles & Responsibilities

DBSi 5.0 Deployment Overview

Page 17: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Dealer – ITDealer IT Manager (1 person)

– Manage & coordinate IT activities (Data conversion/DDC testing and data cleansing)– Assist with DBSi environment coordination activities/resources

Dealer IT Analyst (1-2 persons) – Assist with finance data conversion – Test & update FDC/DDC’s with DBSi 5.0– Assist with Coda security

Dealer – Other DepartmentsDealer DBS Core Key Users (1 person/department)

– Participate in DBSi 5.0 testing– Attend Key User training on Parts/Service program changes– Provide training to end-users on Parts/Service program changes– Evaluate new 5.0 functionality– Validate mock & cut-over testing as required

Deployment Roles & Responsibilities

DBSi 5.0 Deployment Overview

Page 18: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Accenture/CODA Deployment Roles - Primary Dealer EngagementDeployment Coordinator (1 person)

– Manage deployment project & budget, escalate issues as needed– Assist with SRs (escalate as needed or assist with specific issues (i.e. bug/fix, environment issues

for hosted dealers))– Conduct Project Launch meeting at Dealership to mobilize dealer for deployment– Provide off-site support for FDC and Production Conversions– Assist dealer with Mock & Production Cutover planning– Coordinate Delta training sessions– Provide off-site support for Business Testing– Provide off-site support during Go Live (production cutover)– Provide off-site support for Post Go Live

CODA Implementer (1 person) – Conduct key user training for all Coda finance modules– Conduct Business Process Workshop: Finance process mapping to functional design, finance

reporting, and finance security.– Support/Assist deployment during Coda configuration & validate final configuration prior to data

conversion– Support dealer business testing, finance transition planning, final cut-over activities, & support 1st

month end.

Deployment Roles & Responsibilities

DBSi 5.0 Deployment Overview

Page 19: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Accenture/CODA Deployment Roles - Primary Dealer EngagementFinance Implementer (1 person)

– Conduct Coda/conversion overview in Launch meeting at Dealership– Provide off-site support for CODA Training, FDC and Production Conversions– Assist dealer with DBSi 5.0 integration questions and setup– Provide off-site support for Mock Cutover and Business testing with dealer– Provide off-site support for Business Testing– Provide off-site support during Go Live (production cutover) – Provide off-site support for Post Go Live

Tech Support (1 person)– Assist with technical system and integration questions– Provide off-site support during Test/Production conversions, Mock, and Go Live

(production cutover)

Accenture/CODA Deployment Roles - SupportingDBSi Functional Support SME’s (1 person per functional area)

– Provide off-site support on new or changed DBSi 5.0 functionality from DBS 2.3.4 during the identified deployment project timeline (via conference calls and/or e-mail as needed)

Deployment Roles & Responsibilities

DBSi 5.0 Deployment Overview

Page 20: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.

Suggested on-site time shaded above. Actual on-site time to be determined by Dealer, Accenture, and CODA

On-Site Time

DBSi 5.0 Deployment Overview

Page 21: DBSi 5.0 Deployment Overview Quinn March 22, 2011.

Copyright © 2009 Accenture All Rights Reserved.