D&B Overview (V2)

download D&B Overview (V2)

of 11

Transcript of D&B Overview (V2)

  • 8/3/2019 D&B Overview (V2)

    1/11

    Click to edit Master subtitle

    style

    D&B FocusJune 2011

  • 8/3/2019 D&B Overview (V2)

    2/11

    Blast Design

    Costs

    Drills

    Field Controls

    QA/QC Planning / Scheduling

    Storage

    Contracts

    CIP _ Continuous Improvement Program

    Focus

  • 8/3/2019 D&B Overview (V2)

    3/11

    Blast Design

    PREVIO

    US

    BLAS

    T

    P

    REVIOU

    S

    BLAST

    PRECONDITIONING

    EFFECT

    UN-BLASTE

    D

    Issue:

    Shots terminating along the zigzagof the rows tends to precondition theun-blasted area, resulting in oversize.

    If the un-blasted area has been drilledout, the adjacent holds have atendency to suffer from dislocation.In the event the un-blasted area hasnot been drilled drilling is difficult.

    Remedy:(We now)Terminate shots alongechelons.

    Fac

    e

    Fac

    eUN-BLASTE

    D

  • 8/3/2019 D&B Overview (V2)

    4/11

    Blast Design

    Blast Block Geometry Areasof Focus:

    Terminate along echelonsUniform Faces (unlike Fig 1.)

    In addition bring into thedesign proposal/checking Blast Length to Pit WidthRatioBlast Length should be no

    less than 3 times the width.Our blasts are commonly 70mts wide therefore ourminimum length should be210 mts. This rule is basedon Burden Relief & preventing

    Preconditioning.

    H Pit

    Fig 1.)

  • 8/3/2019 D&B Overview (V2)

    5/11

    Blast Design

    Note, Holes vary from 4 metres to 70 metresBurden & Spacing (Diameter) as the parameters relate to BenchHeight requires closer attention Blast design checker:

    Blast Design Checker (Hole by Hole V1).xlsx

    Design parameters influenced by

    Bench Height

    http://opt/scribd/conversion/tmp/scratch6130/Blast%20Design%20Checker%20(Hole%20by%20Hole%20V1).xlsxhttp://opt/scribd/conversion/tmp/scratch6130/Blast%20Design%20Checker%20(Hole%20by%20Hole%20V1).xlsx
  • 8/3/2019 D&B Overview (V2)

    6/11

    Stemming

    Stem higherpercentage of holeswith importedproduct, particularlythose withinSandstone bands.

    Drill Cuttings VsGravelEstablish site specificminimum stemheights for each

    medium.

    Loading stem material to be delivered to

    the bench

    Gaspressure

    Stemming ejection time ms

    20 30%No stemming ejec

    Stemming ejectio

    5 10ms

    Blast Design

  • 8/3/2019 D&B Overview (V2)

    7/11

    Costs

    Costs Design Vs Actual:

    Design costs generated at the design stage, then overlaid to budget.Later to be overlaid to actual.

  • 8/3/2019 D&B Overview (V2)

    8/11

    Field ControlsWater

    Control:

    Planning fora rain event.

    Broken

    Stock

    Bunds preventing waterflow

    Blast holes covered by

    water

    H Pit May 2011

  • 8/3/2019 D&B Overview (V2)

    9/11

    25Mts.

    Field ControlsClean ups:

    Performed once,eliminate rework.

    T Pit May 2011

  • 8/3/2019 D&B Overview (V2)

    10/11

    Field ControlsClean ups Summary:

    Thiess & Golding's depart mining location not leaving bench in a drillablestate

    Timely manner cleans up not performed in sync with drill rigsfinishing/starting new pattern

    Allocation of resources weekly meeting does not identify equipmentrequired

    Responsible Supervisor - weekly meeting does not identify equipmentrequired

    Due date - weekly meeting does not identify equipment required

  • 8/3/2019 D&B Overview (V2)

    11/11

    Drills

    5degrees

    Angle Drilling:Vertical holes are not drilledvertical they are drilled at 5degrees from vertical. Theorientation of this angle is dictatedby the driller.

    This would mean the toe of a 45metre blast hole would be 3.9 mtsfrom design location, etc..

    Drill monitoring systems installedbut not in use on two rigs.

    Action Plan:Test units (are they working)Train (2) operators (at first)Engage HPGPSCollect data with focus on rockrecognition