Transcript of Dan Uetrecht, Director of Networks & Computing March 15, 2013 Infrastructure Update.
Dan Uetrecht, Director of Networks & Computing
March 15, 2013
Infrastructure Update
• S&T Campus Wireless Upgrade
• S&T VOIP Phone System Replacement
• S&T Network Access Control
• UMIT Microsoft Lync replaces OCS
• UMIT Office 365 replaces Outlook Live
• UMIT Data Center Consolidation
Change is in the wind
S&T Campus Wireless Upgrade
• Dell branded Aruba 802.11N 600Mb/s 2.5 and 5Ghz wireless solution selected
• Deployed to 25 buildings both on and off campus to date
• Will be proceeding with deployment on or before spring break
• Current status and FAQ at: http://it.mst.edu/services/wireless/aruba-n/
S&T VOIP Phone System
• Current Cisco VOIP system at end of life
• New Cisco replacement not cost effective
• Evaluated– UMC using CenturyLink hosted Broadsoft– Fidelity Communications hosted Broadsoft– Locally hosted Asterisk
• What features do you want to see in UC?
S&T Network Access Control
• NAC, what is it?– Easy wireless onboarding– Network access gatekeeper – Policy enforcer
• Selected Impulse Point SafeConnect• Deployment plan
– Audit mode– Protect wireless network– Upgrade and protect wired network
Microsoft Lync replaces OCS
• What is OCS? – MS first stab at UC– IM w/presence and video conferencing
• Lync is OCS on steroids.– Think of free Webex using IP based audio.– Outside federation to Office 365 coming– Public federation possible– SIP connectivity may integrate with local VOIP
• UMIT upgrading OCS to MS Lync on 4/1
Office 365 replaces Outlook Live
• Outlook Live transition to Office 365 over the summer
• Office 365 has more features– Exchange– Sharepoint– Lync– Office– 25G of SkyDrive
UMIT Data Center Consolidation
• Part of the UMIT reorganization strategic initiative
• Engaged World Wide Tech to assist us with right sizing the UMIT Data Center environment
• Statement of work is being finalized
• Basic process is assessment, analysis, recommendations, action plan.