Dalhousie Parking Project Final Report
Transcript of Dalhousie Parking Project Final Report
Dalhousie University (Sexton Campus) Department of Civil & Resource Engineering
CIVL4802 Capstone Project FINAL REPORT
DALHOUSIE PARKING PROJECT
TEAM 13
Andrew Eagen - B00607513 Christopher Wallace - B00579178
Ian Milne - B00605397 Kenzie MacDonald - B00534747
Submitted to: Andrea Doncaster, P.Eng.
Faculty Advisor
Colin Dickson, MBA, FEC, P.Eng. Farid Taheri, P.Eng.
Client:
Nathan Rogers, Assistant Director, Capital Planning
April 4th, 2016
EXECTIVE SUMMARY
WEMM Engineering has completed a full analysis of the parking needs and supply at
Dalhousie University. The key goal of this study is to develop an understanding of parking
at Dal and to cultivate a solution to the parking deficit faced by the University. This project
can be broken down into three main components. The assessment of Dalhousie’s current
parking infrastructure, the development and optimisation of sustainable strategies to
reduce the number of individuals taking personal vehicles to campus, and finally, the
design of an on-campus parking structure to increase the number of parking stalls on
University property.
This report will quantify Dalhousie’s parking resources and requirements and it will
outline four strategies to lower the number of cars coming to campus. It will then outline
the need for a parking structure and evaluate four potential locations on-campus. The
report will take the reader through the analysis of these potential sites and make a
suggestion toward the optimal location. Proceeding site selection, the report will evaluate
different functional design considerations for parking structures and suggest the best
options for a Dalhousie parkade. The report will then explain detailed structural designs
and members for the structure, it will also outline the work to be done in relation to site
preparation. Finally, a comprehensive cost estimate and investment recovery plan for the
structure will be outlined. This report defines the parking problem at Dalhousie University
and provides a comprehensive, multi-faceted solution.
i
TABLE OF CONTENTS
LIST OF TABLES ............................................................................................................................................... iii
LIST OF FIGURES ............................................................................................................................................. iv
LIST OF SYMBOLS AND ABBREVIATIONS .............................................................................................. v
1. INTRODUCTION ............................................................................................................................................ 1
1.1. Scope of Work ....................................................................................................................................... 1
1.2. Site Location .......................................................................................................................................... 2
2. BACKGROUND ............................................................................................................................................... 4
2.1. Literature Review ................................................................................................................................ 4
2.2. Initial Conditions – Parking ............................................................................................................. 5
2.3. Initial Conditions – Possible Structure Sites ............................................................................. 7
2.4. Constraints ............................................................................................................................................. 9
3. DESIGN PROCESS ...................................................................................................................................... 11
3.1. Parking Structure Site Selection ................................................................................................. 12
3.2. Building Material Selection ........................................................................................................... 13
3.3. Design Loads ...................................................................................................................................... 14
4. DETAILS OF FINAL DESIGN .................................................................................................................. 16
4.1. Sustainable Solution Strategies ................................................................................................... 16
4.2. Parking Structure Functional Design ........................................................................................ 19
4.3. Parking Structure Structural Design ......................................................................................... 22
4.4. Preliminary Hydrological Considerations .............................................................................. 24
4.5. Foundation Considerations .......................................................................................................... 24
4.6. Cost Summary .................................................................................................................................... 26
5. CONCLUSIONS AND RECOMMENDATIONS .................................................................................... 29
ii
APPENDIX A – Division of Labour......................................................................................................... A-1
APPENDIX B – Supporting Calculations ............................................................................................. B-1
APPENDIX C – Gantt Chart of Project Progress ................................................................................ C-1
APPENDIX D – Potential Site Maps ....................................................................................................... D-1
APPENDIX E – TDM Significant Findings ............................................................................................ E-1
APPENDIX F– Detailed Site Selection Information.......................................................................... F-1
APPENDIX G – NBC of Nova Scotia as it Pertains to Parking Structures................................ G-1
APPENDIX H – Test Pit Logs .................................................................................................................... H-1
APPENDIX I – Functional Parking Structure Design ........................................................................ I-1
APPENDIX J – Site Preparation Cut and Fill Quantities .................................................................. J-1
APPENDIX K – Structure Drawings and Details .............................................................................. K-1
APPENDIX L – K-Wall S-Frame Analysis under Governing Earthquake Load ...................... L-1
iii
LIST OF TABLES
Table 2.2-1: Canadian University Parking Comparison ......................................................................... 6
Table 2.3-1: Initial Conditions of Potential Sites ...................................................................................... 9
Table 3.3-1: Dead Loads of Precast Members ......................................................................................... 14
Table 4.6-1: Cost Estimation Data ............................................................................................................... 27
iv
LIST OF FIGURES
Figure 1.2-1: Site Location, Halifax, NS ......................................................................................................... 2
Figure 1.2-2: Site Location, Dalhousie University Halifax Campus .................................................... 3
Figure 1.2-3: Site Location, LSC Parking Lot .............................................................................................. 3
Figure 2.2-1: Dalhousie Halifax Campuses Parking ................................................................................. 5
Figure 2.3-1: Site Location, Dunn Parking Lot ........................................................................................... 7
Figure 2.3-2: Site Location, Hancock Parking Lot..................................................................................... 8
Figure 2.3-3: Site Location, Wickwire Field ................................................................................................ 8
Figure 2.3-4: Site Location, LSC Parking Lot .............................................................................................. 8
Figure 2.4-1: Dalhousie Zoning ........................................................................................................................ 9
Figure 3-1: Design Process ............................................................................................................................. 11
Figure 3.1-1: Site Evaluation Results.......................................................................................................... 13
Figure 4.1-1: Transit Routes on Dalhousie Campus ............................................................................. 17
Figure 4.1-2: Bicycle Racks at Dalhousie .................................................................................................. 18
Figure 4.2-1: Isometric Floor Layout .......................................................................................................... 20
Figure 4.2-2: Structure Rendering............................................................................................................... 21
Figure 4.2-3: Structure within Campus Setting ...................................................................................... 22
v
LIST OF SYMBOLS AND ABBREVIATIONS
CIP = Cast in place
HOV = High occupancy vehicle
I.S. = Individual System
LSC = Life Sciences Centre
m = Metres
mm = Millimetres
PCI = Precast/Prestressed Concrete Institute
TDM = Transportation Demand Management
1 | P a g e
Final Report
1. INTRODUCTION
The client has requested that WEMM Engineering evaluate the parking situation at
Dalhousie University. As Dalhousie grows and expands its services, it is seeking to alleviate
parking congestion on-campus and to consolidate surface parking in a central location. This
parking plan needs to fit into the campus master plan of Dalhousie.
1.1. Scope of Work
Parking Analysis
The primary goals of this report are to take an inventory of all parking spots on
Dalhousie’s three campuses. A separate analysis must be completed to determine the
parking needs at Dalhousie. These two values will be compared to each other to establish a
quantifiable insufficiency of parking on Dalhousie campus. This report will also compare
parking at Dalhousie to other large Canadian Universities and determine what changes
need to be made to compete with them in terms of parking stalls per student/staff member.
Sustainable Strategy Optimisation and Development
To successfully combat the parking insufficiencies at Dalhousie University, a long
term, sustainable strategy must be implemented to reduce the number of personal vehicles
frequenting campus. Dalhousie already offers several programs that provide alternative
options for commuters. WEMM Engineering has evaluated the effectiveness of these
programs and will provide expansion and optimisation strategies that will enable students
and staff to benefit even further from these services.
Structure Design
Once parking insufficiencies have been established, and it has been determined that
a structure is necessary not only to supply the University with its immediate need for more
parking, but to consolidate parking in a central location for future campus optimisation.
The first step is to determine which location best serves the Dalhousie population as a
whole. All potential sites need to be established eliminating those that do not meet size or
zoning restrictions. Once a list of possible sites is established, they must be objectively
2 | P a g e
Final Report
scored and the optimum site must be chosen using a specified evaluation criteria. Upon
final decision of the optimal site, a site investigation needs to be completed to determine
the grade of the area as well as the soil information. Once all necessary data is obtained, a
structure must be designed. The material for said structure must be decided upon, and
functional parking structure design must be reviewed and tailored specifically to Dalhousie
University in every aspect. Once functional design criteria are chosen, detailed designs of
the parking structure must be developed taking into consideration calculated structural
loads. Once site preparation and structural designs have been established, a comprehensive
cost estimate must be developed.
1.2. Site Location
This Project is going to take place in Halifax Nova Scotia, shown in Figure 1.2-1.
Figure 1.2-1: Site Location, Halifax, NS
The parking investigation portion of this project will be performed on the three Halifax
Dalhousie campuses outlined in Figure 1.2-2.
3 | P a g e
Final Report
Figure 1.2-2: Site Location, Dalhousie University Halifax Campus
The building design portion of this project is going to be performed for the LSC parking lot
seen in Figure 1.2-3 located on the North-West end of Studley Campus between the
University of King’s College and the LSC.
Figure 1.2-3: Site Location, LSC Parking Lot
4 | P a g e
Final Report
2. BACKGROUND
2.1. Literature Review
Dalhousie Transportation Demand Management Plan – IBI Group (2011)
This document outlines a study into the transportation patterns of Dalhousie
students and staff and explores their commuting patterns in depth. It evaluates the
benefits of alternative methods of travel to driving and suggests sustainable
transportation programs that can be introduced at Dal. Some of its most relevant
findings can be found in Appendix E.
Dalhousie Campus Parking Study – Morrison Hershfield (2013)
This report is the product of a study done after the TDM plan was established. It
develops a parking inventory of Dal’s three campuses and suggests possible building
sites on Dal property and evaluates them for both parking and alternative uses.
Precast Concrete Design Manual – CPCI (2007)
This design manual gives member strengths and design procedures and examples
for precast, pre-stressed concrete structures. It was used to determine member
sizes for the parking structure design.
Mitigating the Campus Parking Problem: 5 Town-Grown Solutions - Spenser Havlick (2013)
This document presents multiple solutions to having a shortage of parking spaces
on-campus. It was used as a source for the section of the report on alleviating the
parking issue alternative to building a parking structure.
Precast/Prestressed Concrete Parking Structures: Recommended Practice for Design and
Construction – PCI (1997)
This is a summary of the general recommendations and processes involved in
designing and constructing parking structures using precast concrete. This was
useful during the early stages of design.
5 | P a g e
Final Report
Nova Scotia Building Code 2010
The Nova Scotia Building code provides technical requirements that need to be met
in order to ensure stability, safety, and efficiency of the structure. It contains
guidelines specific to parking structures that are included in Appendix G.
Dalhousie University Campus Master Plan Framework Plan
This document outlines the goals of Dalhousie for the future and is an important
resource to abide by when developing new infrastructure at Dalhousie.
2.2. Initial Conditions – Parking
Dalhousie currently has 2,228 parking spaces distributed among the 3 Halifax
Campuses as shown in Figure 2.2-1. The parking lots distributed around the campuses can
be seen as grey squares.
Figure 2.2-1: Dalhousie Halifax Campuses Parking
There are currently 18,564 students and 6,000 faculty and staff at Dalhousie.
According to The Transportation Demand Management (TDM) survey done by an external
consulting group, 11% of students and 39% of staff drive to campus each day. To
accommodate this many vehicles, Dalhousie would need to have a total of 4,257 parking
spaces, which is 2,029 more spaces than what’s currently available. However, this is not the
number of spaces that needs to be provided due to the fact that all these individuals do not
6 | P a g e
Final Report
frequent campus at the same time. These individuals are also spread over the three
campuses, two of which (Sexton and Carleton) rarely reach capacity. This is demonstrated
by TDM studies, results of which are found in Appendix E, which shows the capacity of lots
around campus at different times of day in September and April.
The TDM study in Appendix E indicates that there is clearly still a lack of spots as
demonstrated by the lots consistently at capacity on Studley Campus. WEMM Engineering
has come to the conclusion, based off how often it reaches capacity, that the center of the
parking issues at Dalhousie revolve around Studley campus, and therefore established that
that is where changes need to be made.
To establish the insufficiency of Studley campus’ parking, WEMM Engineering
compared Dalhousie to other large Canadian universities. As shown by Table 2.2-1,
Dalhousie has a high ratio of people per parking space in relation to comparable
universities.
University Undergraduate Graduate Staff Total Parking Spaces
People/Space
University of Guelph
18,000 2,500 3,000 23,500 5,281 4.45
University of Alberta
31,161 7,572 8200 46,933 7,393 6.35
Queen’s University
17,413 3,768 6000 27,181 2,604 10.44
UBC 41,365 10,820 14,212 66,397 8,000 8.30
Average 7.4
Dalhousie 14,650 3,914 6000 24,564 2,228 11.03
Table 2.2-1: Canadian University Parking Comparison
For Dalhousie to meet the average ratio of these other schools, 3319 parking spaces
need to be provided. That is an increase of 1091 parking spots. Therefore, Dalhousie either
needs to keep this many people from driving, or add this many spots to solve their parking
problem. WEMM Engineering proposes a combination of both which will be outlined later
in the report.
To increase the number of parking spaces at Dalhousie, it is important to consider
the Facilities Management Master Plan Framework Plan available through Dalhousie’s
7 | P a g e
Final Report
website. A key aspect of the goals Dalhousie has outlined includes achieving a higher level
of campus density so that an improved level of services can be offered to both students and
staff. This “build up rather than out” model will lead to easier accessibility to the services
and facilities being provided because they will be located geographically close to one
another.
The problem of lack of parking therefore takes on a broader definition than simply
accommodating current parking demand. The solution must be one which both alleviates
current parking strain and which contributes positively to the future growth of the school.
In order for Dalhousie to achieve higher campus density in the future, the land currently
used for surface parking needs to be freed up so that it can be developed into spaces or
facilities which better serve the community. Additionally it must be possible to
accommodate the increase in parking demand associated with higher density land use.
To achieve an adequate parking supply, WEMM proposes that stacked parking
facilities be utilized. These facilities serve as a solution to Dalhousie’s problem in that they
both increase the parking supply on-campus, and free up valuable land for future
development. It is therefore necessary that Dal build a large on-campus parking structure.
2.3. Initial Conditions – Possible Structure Sites
Dunn Parking Lot
The Dunn Lot is located on the North-West side of the Studley Campus. It is situated in
between the Dunn Building and Howe Hall. Access to the lot is provided through Castine
Way.
Figure 2.3-2: Site Location, Dunn Parking Lot
Hancock Parking Lot
The Hancock parking lot is located in the North-West corner of Dalhousie’s Studley Campus
on the backside of King’s Campus. This lot is accessed off of Coburg Road.
8 | P a g e
Final Report
Figure 2.3-3: Site Location, Hancock Parking Lot
Wickwire Field
Wickwire field is located on the south side of the Dal Campus. It is home to several varsity
teams as well as countless intramurals. It is potentially accessible from South Street or
Alumni Crescent. The proposed structure would be a single storey installed underneath the
field.
Figure 2.3-4: Site Location, Wickwire Field
LSC Parking Lot
The LSC parking lot, located at the North-West end of Studley Campus is adjacent to King’s
Campus and Dalhousie’s Life Science Center. This lot can be accessed through either Lord
Dalhousie Drive to the East, or Castine Way to the North.
Figure 2.3-5: Site Location, LSC Parking Lot
Table 2.3-1 on page 9 shows the specific details for each of the above potential sites.
9 | P a g e
Final Report
Site Dunn Hancock Wickwire LSC Number of
Spots 199 139 0 72
Footprint (m2)
3100 2100 13,000 2800
Zoning U-2 U-2 U-2 U-2
Height Restrictions
(m) 16.76 16.76 16.76 none
Setback Restrictions
(m)
15.24 on one side
15.24 on two sides
15.24 on one side
none
Slope (m)
3.05-0 from North to South
3.05-0 from East to West
1.52-0 from South to North
0.91-0 from East to West
none
2.13-0 from South to North
2.13-0 from East to West
Table 2.3-2: Initial Conditions of Potential Sites
2.4. Constraints
Zoning: All of Dalhousie is classified as either zone U-1 (low density university) or U-
2 (high density university) as seen in Figure 2.4-1. U-2 is the darker blue and U-1 is
the lighter blue. A parking structure can only be built on U-2 zoning.
Figure 2.4-6: Dalhousie Zoning
10 | P a g e
Final Report
Minimum size for structure: for design of a parking structure to function, a
minimum footprint size of 2000 m2 is required. All sites smaller than this must be
eliminated from consideration.
Traffic accommodation: The surrounding area needs to be able to absorb peak hour
traffic flows into and out of the parkade to avoid congestion of neighboring street.
Setback and height restrictions as outlined in Table 2.3-1.
11 | P a g e
Final Report
3. DESIGN PROCESS
Figure 3-1: Design Process
12 | P a g e
Final Report
3.1. Parking Structure Site Selection
Four potential parking structure sites were obtained by studying all available land
on Dalhousie’s Studley campus. The sites not zoned for a parking structure (U-1 zoning)
and the sites too small to house a functional parkade (less than 2000 m2) were eliminated,
and the sites deemed acceptable were the Dunn parking lot, The Hancock parking lot,
underneath Wickwire field, and the LSC parking lot. The initial conditions of these sites are
outlined in section 2.3 of this report and maps of each site with access streets and five
minute walking radius outlined can be seen in Appendix D.
The criteria used as site selection guidelines for this project came from a
combination of both quantitative transportation needs and qualitative future goals for the
university with regards to development and growth. In the short term it is the
transportation demand which needs to be addressed. To achieve this in a way that will
benefit the university in the future, more than just the immediate transportation needs had
to be considered. In order to fully evaluate the feasibility of a parking structure on-campus
the context of each site has been evaluated with regards to its surroundings to determine
which site fits best into the overall campus framework. This perspective is required to
address the current and future need of Dalhousie and to begin to arrive at a solution that
works for both the short and long term.
The criteria for each site was broken down and evaluated in terms of four key
aspects: relative gain of parking spaces available (potential number of future spots sample
calculation can be found in Appendix B), the distance to major buildings on-campus, the
accessibility for vehicle traffic, and the impact on existing infrastructure in the immediate
vicinity as well as potential implications for future development. These aspects of site
consideration were further broken down into related sub-categories that were weighted
based on perceived importance. The results of the evaluation are shown in Figure 3.1-1 and
the full breakdown can be found in Appendix F.
13 | P a g e
Final Report
Figure 3.1-2: Site Evaluation Results
The relative parking gain seen at the bottom of the legend in Figure 3.1-1 was
deemed the most important criteria, and the weightings decrease as you move up the list,
until the least important criteria: construction access. The criteria weightings were
assigned in line with the aspects deemed important in the Dalhousie master plan. Each site
was awarded a score out of 10 which was then weighted out of 100. A perfect score is a
score of 1000. Shown above, the LSC site was found to be the ideal choice to host an on-
campus parking structure, and therefore all the structure designs were based on this
location.
3.2. Building Material Selection
The choice of building material is an important factor to decide upon when
designing a structure. The primary building material should be cost effective, aesthetically
pleasing, durable, and have minimal maintenance costs throughout the life of the building.
The available building materials include steel and concrete, with concrete being sub
divided into pre cast and cast in place (CIP).
WEMM Engineering has eliminated steel as a viable building material for this
parking garage due mainly to its limitations with respect to corrosion resistance; which
makes it a more expensive option considering the increased maintenance costs throughout
the lifespan of the building. The industry standard for stand-alone parking garages is to
14 | P a g e
Final Report
build concrete structures, so WEMM Engineering evaluated the two concrete construction
methods: CIP and precast.
Precast concrete was deemed a better option for this project for several reasons, the
most notable of which is the increased speed of construction. The precast members are
fabricated off site, keeping the mess of concrete forming and pouring at the precast facility
and off Dalhousie property. The concrete members are then transported to the project
location and can be quickly assembled. Since Dal already has limited parking, and
throughout the construction of this structure even more will be inaccessible, it is crucial
that the construction process be as fast as possible. Precast concrete members can also be
sourced locally from Strescon Ltd. which has multiple years of experience designing
precast concrete parking structures. Precast concrete is the building material for the
majority of standalone parking garages in Halifax for good reason and this structure will
not be an exception.
3.3. Design Loads
All design load calculations can be found in Appendix B. Dead loads for the structure
were calculated using data obtained from Strescon Ltd. regarding their specific structural
members and from the Precast Concrete Design Manual – CPCI (2007) which lists unit
weights for various member sizes. Dead loads of structural elements that were not
explicitly listed in either of those sources were calculated using a density of concrete of
24kN/m3. The dead load forces attributed to each individual structural member is
summarised in Table 3.3-1 below.
Member Dead Load per Member (kN)
Pre-Topped Double Tee Beams 270
Spandrel 190
Column (per storey) 34
K-Wall (per storey) 175
Litewall (per storey) 803
Table 3.3-1: Dead Loads of Precast Members
15 | P a g e
Final Report
A live load of 2.4kPa was used and was obtained from the NBCC 2010 – Part 4. This
value is typical for garages built for vehicles not exceeding 4000kg.
Snow loads were calculated according to Commentary G of the NBCC 2010. In
calculating the snow load it was assumed that snow would not accumulate around the
litewall as much as it would around a solid wall of the same height due to the slots in the
litewall that would allow air to flow through. The snow load for the roof was found to be
1.94 kPa for the majority of the roof, and 2.76 kPa within 2.14 m of the parapet.
Wind loads were calculated according to Commentary I of the NBCC 2010. The loads
resulting from the factored wind pressure and wind suction were calculated by assuming
that approximately half of the structure is open in terms of square meter area of any of the
exterior walls. The largest wind load acting on the structure was found to be 0.98 kPa
Seismic loading was determined in accordance with the NBCC 2010 – Part 4. The
seismic lads for floors 4, 3, 2, and 1 were found to be 1790 kN, 1342 kN, 895 kN, and 224
kN respectively.
16 | P a g e
Final Report
4. DETAILS OF FINAL DESIGN
4.1. Sustainable Solution Strategies
When considering the problem of the current parking shortage on-campus, there
are two types of possible solutions that are necessary to consider. The first is decreasing
parking demand, and the second is increasing parking supply. This section discusses
several strategies related to decreasing parking demand.
If less people found it necessary to drive to school or work, the need for available
parking would decrease. Decreasing the demand for parking can be done multiple ways,
including relying on increased transit ridership, offering rideshare incentives to limit single
occupancy vehicle use, implementing strategies geared to growing the number of bicycle
commuters, and instituting walking promotion campaigns. This section of the report will
explain each of these four strategies and how they will lower the number of cars on-
campus.
1) Increase Transit Ridership:
Dalhousie currently offers a UPass to students at a cost of $150 for an eight month
semester (cost of $560 for non-students) and an EPass to employees at a 25% reduction off
cost. These passes allow for unlimited transit ridership during the school year from
September to April. Since a higher percentage of staff drive than students, it would
decrease the number of cars on-campus significantly if Dalhousie could offer the same sort
of price reduction on transit passes for staff as they do for students. By decreasing the price
even further than a 25% savings, it increases the appeal of taking the bus over personal
vehicles significantly.
Future trends indicate that transit ridership is likely to increase as transit services
offered by Halifax improve. Additionally, all three campuses are already served well by
numerous routes, with multiple stops around the perimeter of the campuses, as shown in
Figure 4.1-1. It’s becoming easier and easier to commute by bus and that will decrease the
number of people parking on-campus over time.
17 | P a g e
Final Report
Figure 4.1-1: Transit Routes on Dalhousie Campus
2) Increase Rideshare Participation
There is currently a rideshare program offered through Dalhousie, however only a
small percentage of students and employees know about and utilize the service. If
Dalhousie put more effort into marketing the program, participation would increase. Dal
could also add in more “car pool reserved” parking spaces to the 3 campuses to increase
the appeal.
A large portion of people opt out of rideshare programs because they like to have
their car available should an unexpected situation arise. For example if they need to pick up
a child, or they feel sick and want to go home early. Dalhousie currently offers a
“guaranteed ride home” program, which offers rideshare participants up to five free taxi
fares a year from the university in the case of an unexpected need to leave before or after
your rideshare’s scheduled time. This program encourages people who wouldn’t have
normally participated to take part in the program.
18 | P a g e
Final Report
Bicycle Commuter Promotion
The third sustainable approach to keep students and staff from driving to work is to
make it easy for people to commute by bicycle. You can see on the map in Figure 4.1-2 that
there are quite a few bike racks on-campus already, if Dalhousie increased the number of
racks even further and improved the end of trip facilities for cyclists (end of trip facilities
include sheltered bike storage, lockers, and showers) then more and more people would
start to bike.
Figure 4.1-2: Bicycle Racks at Dalhousie
Currently, none of the major surrounding campus streets have bike lanes, and the
campus is uninviting to bicycle traffic. In order for bike ridership to increase significantly, a
better campus-wide bicycle network should be implemented. This would encourage more
cautious bikers to start cycling.
A final strategy to increase the number of bicycle commuters is Dalhousie could
organize an event in partnership with a local bike shop and get them to come onto campus
and provide free demos of popular commuter bikes. This would give students and staff an
19 | P a g e
Final Report
opportunity to test bicycles for free and perhaps encourage them to purchase one and start
commuting by bike. Through the implementation of these pro-cycle strategies, more and
more people will begin cycling rather than driving.
4) Walking Promotion
A final method Dalhousie could use to get people out of their cars is by encouraging
them to start walking to work. The university could implement a program where they
partner with a company like Fitbit (a company that manufactures advanced pedometers)
and start holding weekly competitions. The competitions would involve distributing Fitbits
to individuals on a weekly basis and monitoring the number of steps they take. At the end
of the week, the winning contestant would receive a prize. Not only would this promote a
healthy, active lifestyle, but it would also make individuals realize that there are more
options than simply driving to campus.
While the four options above represent potential for decreasing the demand for
parking on-campus, they are long term, slow acting solutions which cannot necessarily be
counted on to work right away. Based on the nature of the issue and the fact that Dalhousie
cannot force anyone to opt for alternate modes of transportation, WEMM Engineering has
concluded that there is still a need for increased parking capacity that can only be met by a
parking structure. The sustainable solutions, and parking structure solution will work
together over time to provide an improved Dalhousie campus. In the future, as the
sustainable solution decreases the need for parking spots more and more, having
consolidated parking in a structure will allow for the removal of surface parking to be used
for more desirable facilities.
4.2. Parking Structure Functional Design
All design decisions for this parking structure were geared to making it as functional
as possible. WEMM Engineering determined which aspects of parking structures pertain to
their functionality and tailored the design of this structure specifically to the needs of
Dalhousie. The functional qualities of a parkade and how they pertain to Dal can be found
in Appendix I. All designs were completed in accordance with the National Building Code of
20 | P a g e
Final Report
Nova Scotia as it pertains to stand alone parking structures. All relevant clauses from this
code can be found in Appendix G.
The parking structure we have designed is 36.5 m wide by 73.2 m long with
alternating slopes in the middle section. This design was developed after a site visit to
Strescon Ltd. Their standard double tee beams are precast at 18 m long, 4 m wide. Four
double tee beams tied together make up one bay. The structure is composed of 10 bays (5
long and 2 wide). This can be seen in the plan view of the structure which can be found in
Appendix K. The two end bays are flat whereas the 3 middle bays make up the sloping,
single helix ramping system seen in Figure 4.2-1. The ramps climb a half storey per run
leading to a 4.4% grade. Our original design consisted of one ramp per floor which had a
slope of 8.8%. However, according to the PCI Recommended Practice for Design and
Construction handbook, the max allowable slope that allows parking spaces is 6%.
Figure 4.2-3: Isometric Floor Layout
In can be seen in Figure 4.2-1 that the stalls are oriented at 90° to the drive aisles,
each stall is 2.5 meters wide and 5.5 meters long. There are dead zones located in each
corner where no stalls can go, so to avoid wasting surface area, the staircases have been
placed in two of the corners, and the other two corners will be used for bicycle and
21 | P a g e
Final Report
motorcycle parking. The calculation to determine the total number of parking stalls per
storey can be found in Appendix B and yields that there are 104 parking stalls per storey,
leading to 416 new parking stalls within the entire structure. By allowing parking on the
ramps and by including exterior rooftop parking, this design efficiently maximises the
available space of the structure. A rendering of the building it its entirety can be seen in
Figure 4.2-2
Figure 4.2-4: Structure Rendering
It can also be seen in Figure 4.2-2 that the structure will be designed to have over
25% of the total exterior wall area open to the inside of the structure. This eliminates the
need for mechanical ventilation in accordance with the Nova Scotia Building Code 2010.
A rendering of the structure in the location that it will be built can be seen in Figure
4.2-3. This image shows how well the structure fits in with the context of the surrounding
campus. Since there are no height restrictions in the zone of the structure, the building
could have been designed with more stories, increasing its parking capacity, however, the
Kings College buildings located just across Castine Way are only three stories tall, and an
22 | P a g e
Final Report
overly large structure in this location would stand out and be aesthetically unappealing.
WEMM Engineering wanted to not only add parking spaces to the campus, but to add to the
campus appeal and atmosphere as well.
Figure 4.2-5: Structure within Campus Setting
4.3. Parking Structure Structural Design
The construction process will begin with site preparation work. While this step is
important with any project, it is imperative in precast construction to perform site
preparation accurately and according to intended design so that precast elements
connecting to foundation elements are erected in proper locations and at proper
elevations. Excavation to bedrock will be performed for all footing and foundation wall
locations so that CIP foundations can be poured on bedrock to provide adequate bearing
capacity. Additionally, due to the geologic conditions of the LSC site, available in Appendix
H, excavation to bedrock is also necessary to get below the frost line in most locations.
Having footings bearing on bedrock also eliminates concerns regarding settlement,
specifically differential settlement. Column footings and a retaining wall for backfill will be
poured once excavation has occurred, and fill will be placed for the slab on grade according
to the site elevations shown in Appendix J.
23 | P a g e
Final Report
Precast elements can be installed upon completion of site preparation. Column
connections to footing pilasters will be executed according to the detail shown in Appendix
K. The design of precast connections is done at the discretion of the precast manufacturer,
but connection types are shown in Appendix K for clarity. Columns will connect to CIP
elements through the use of NMB splice sleeves cast into the column base and Wilson
sleeves cast into the footing pilaster. Once proper alignment has been achieved, the sleeves
are grouted solid with high strength grout capable of developing the full capacity of each
bar, effectively making the bar between the CIP and precast elements continuous. Efficient
load transfer is therefore maintained between these members.
Litewall sections will be placed one storey at a time in conjunction with column
placement. Litewall connection to footings at the base of the wall will be similar to footing
connections for columns. Each successive storey will also be connected through the use of
NMB splice sleeves cast into the top and bottom of the members. K-wall sections will also
be placed and secured to foundations in the same manner, using NMB splice sleeves and
Wilson sleeves to achieve adequate load transfer. The S-Frame analysis under the
governing earthquake loading for these K-walls can be found in Appendix L.
Spandrel beams will be placed between columns once erection of columns has taken
place. The intended spandrel connection is a bearing connection to the column, with the
spandrel transferring load to the column along its axis of symmetry so as to avoid moment
due to eccentricity. The spandrel will bear on column corbels.
Placement of the double tee members can take place once columns, spandrels, and
litewall/K-wall sections have been placed. Representative double tee to spandrel and
double tee to litewall connections are shown in appendix K for clarity. Spandrels will be
notched out at double tee web locations, and the double tee will bear on the spandrels at
these locations. Load transfer will occur through bearing plates cast into the double tee and
spandrel beams. These plates can be site welded to provide a secure connection. Additional
shear and pullout capacity is obtained through the use of a PSA insert cast into the spandrel
that is site welded to a JVI spider plate cast into the flange of the double tee. This PSA
insert/spider plate connection is also used where double tee members connect to litewall
24 | P a g e
Final Report
sections, however in these connections bearing transfer is achieved through the use of
corbels on the litewall.
Proper connection between the individual double tee members is a major
consideration in order to achieve structural integrity. The spider plates cast into the flanges
of the double tees allow for continuity of reinforcing bars running transverse to the span.
These bars can be welded together on site at spider plate locations, and thus provide a
mechanism for the transfer of tensile forces in the transverse direction relative to double
tee span. Shear transfer between double tee members is achieved through the use of vector
connectors welded into the flanges of the members along their length. The combination of
transverse bar and shear transfer allows the double tees to work as a system rather than
independently. This load transfer mechanism creates a floor diaphragm.
This same process is repeated for every storey until completion of the structure.
Once the structure has been completed, finishing touches such as painting of parking stall
boundary lines can be carried out.
4.4. Preliminary Hydrological Considerations
The footprint of the proposed structure imposes upon an area of green space behind
the LSC. Currently the rainfall on that area is able to infiltrate into the ground, however
after the construction of the parking structure, the water that falls on that area will need to
be routed to the nearest storm water drain. WEMM Engineering has performed preliminary
calculations to determine the extra strain that will be placed on that drain. These
calculations can be found in Appendix B and showed that the removal of the permeable
green space results in an additional runoff volume of 48.96 m3/hr. The existing drainage in
the area must be evaluated to determine if it can handle this increased flow.
4.5. Foundation Considerations
This section will evaluate the geotechnical investigation performed by LVM
Maritime Testing in April 2014 (included in Appendix H) and will outline the preliminary
foundation considerations of a four storey parking structure located adjacent to the LSC
building on Dalhousie University Campus. The total footprint of the proposed structure is
25 | P a g e
Final Report
36.5 x 73.2 meters. The two borehole samples obtained are located in the Southeast corner
of the structure and it has been assumed, due to lack of available information, that the soil
conditions found apply to the whole building.
The results of the borehole testing revealed 10 centimeters of grass and topsoil, 0.5 -
1 meters of silty sand containing some cobbles and trace organics, then bedrock located
between 0.5 and 1.2 meters below the ground surface. Neither of the boreholes found
evidence of any water so it can be assumed that the groundwater table is located well
below the area of interest.
WEMM Engineering considered the use of Individual footings, strip footings, and
pile foundations. Pile foundations were deemed unnecessary due to the height of the
bedrock providing acceptable conditions for the use of shallow foundations. Due to the
difficulty involved in excavating the bedrock, strip footing were also eliminated. Since the
building gravity loads are carried by columns not walls, individual footings were chosen as
the optimal foundation design because they are the most effective and efficient method to
take the loads of the structure in the given soil conditions and they required less excavation
of the bedrock.
The individual footings should be founded on sound bedrock. The rock should be
level and clear of any dirt, large cracks, water, and other irregularities. The prepared
subgrade surfaces should be inspected prior to pouring of concrete. The design frost depth
for the area is 1.2 meters so all footings will have a minimum soil cover of 1.2 meters.
The shallow silty sand soil has maximum thickness of 1.2 meters, which according to
the Occupational Safety General Regulations of Nova Scotia is an acceptable depth of loose
soil for a person to enter without providing minimum slope requirements or sheet piling.
Drilling, and hoe ramming techniques will be required to excavate the bedrock. Where
bedrock is too damaged for acceptable footing placement, it shall be over excavated and
Grade A fill shall be placed to provide a level surface for the footing.
In accordance with Halifax Municipal Design Guidelines, backfilling within the
footprint of the building shall be done with Type 1 gravel and shall be placed at a maximum
thickness of 200 mm prior to compaction. The fill on the exterior of the building envelope
shall be placed in increments of 300 mm before compaction.
26 | P a g e
Final Report
More information on the initial site conditions and planned future grade can be
found in Appendix J.
4.6. Cost Summary
WEMM engineering has approached this project using a design/build methodology.
This concept involves bringing together all parties to design and construct the most cost
effective structure. By using a design/build project technique, our precast concrete
supplier will be involved early and able to contribute ideas for the most cost effective
solutions. This method will give a single source responsibility to expedite the time of
construction and keep the overall project costs as low as possible.
Our cost estimate detailed in Table 4.6-1 was formed using the 2016 RSMeans
reference guide. We developed a class “D” cost estimation on the design and construction of
our proposed parking structure.
LSC Parking Structure Cost Estimate
Description QTY Unit Unit Cost Total
Site Preparation:
Site Clearing 1 I.S. $10,000.00 $10,000.00
Excavation and Disposal 2828 C.Y. $12.00 $33,940.00
Environmental Site Assessment 1 I.S. $6,000.00 $6,000.00
Landscaping 1 I.S. $8,000.00 $8,000.00
Construction Costs:
Site Signage 1 I.S. $6,000.00 $6,000.00
Worker Facilities 1 I.S. $8,000.00 $8,000.00
Structural Members:
Column Footings 450 C.Y. $350.00 $157,500.00
Precast Columns 38.14 L.F. $355.00 $258,440.00
Precast Spandrels 112 E.A. $6,775.00 $758,800.00
Precast Stairs 36 Riser $1,675.00 $60,300.00
Staircase Walls 10 C.Y. $400.00 $4,000.00
Staircase Slab 15000 S.F. $4.00 $60,000.00
Elevated Slab 1100 C.Y. $700.00 $770,000.00
Elevated Sloped Slab 2200 C.Y. $750.00 $1,650,000.00
Double Tees 154 E.A. $6,350.00 $977,900.00
27 | P a g e
Final Report
K-wall 66.84 C.Y. $565.00 $37,764.00
Centre Wall 175 C.Y. $565.00 $98,875.00
Interior Finishing:
Expansion Joints 521 I.F. $30.00 $15,630.00
Staircase Roofing 538 S.F $5.00 $2,690.00
Fire rated Steel Frame and Door 10 E.A. $1,500.00 $15,000.00
Miscellaneous Painting 1 I.S. $5,000.00 $5,000.00
Seal Concrete Floors 86400 S.F. $0.50 $43,200.00
Interior Signage 1 I.S. $25,000.00 $25,000.00
Staircase Railings 1 I.S. $39,700.00 $39,700.00
Interior Facilities:
Drainage Receivers and Piping 1 I.S. $147,000.00 $147,000.00
Interior Lighting 1 I.S. $80,000.00 $80,000.00
Wiring 1 I.S. $20,000.00 $20,000.00
Total Construction and Installation Costs (USD): $5,298,739.00
Soft Costs:
Engineering, CM, and Legal (15%) 1 I.S. $1,052,131.00 $794,810.85
Contingency (10%) 1 I.S $645,307.00 $529,873.90
Administration 1 I.S. $50,000.00 $50,000.00
Total Cost (US Dollars) $6,673,423.75
Total Cost (Canadian Dollars) $8,666,784.09 Table 4.6-1: Cost Estimation Data
An important factor to Dalhousie University when considering any new construction
is revenue generation and investment payback. Because of Dalhousie’s collective
agreement, the cost of parking passes cannot be drastically increased even though a new
parking structure will improve the service. Since there is no way to develop further
revenue off of parking passes the return on the 8.7 million dollars that this structure will
cost must come from other sources.
By consolidating parking into a structure, it densifies parking at Dalhousie. As the
sustainable strategies outlined in Section 4.1 start to become more widely used, and fewer
people require on-campus parking, a parking surplus will start to develop. With the
construction of a parking structure, it allows for more parking spots in a smaller area,
28 | P a g e
Final Report
allowing the University to remove existing surface lots and reallocate that space for more
desirable, revenue generating facilities such as residences. It is through these facilities that
Dalhousie will generate the revenue to warrant the cost of this parking structure.
29 | P a g e
Final Report
5. CONCLUSIONS AND RECOMMENDATIONS
WEMM Engineering was assigned the task of studying the parking situation at
Dalhousie University. Upon completion of said study, WEMM engineering determined that
a problem does exist with the current system. The major causes and underlying issues
associated with the parking system in place have been identified and a solution to this
problem has been developed. The lack of parking spaces at Dalhousie needs to be
addressed using two methods: keeping people from driving (sustainable solution), and
increasing the parking supply (parking structure solution). As time passes, and the four
outlined sustainable strategies (increasing transit ridership, carshare participation, and
number of bicycle/walking commuters) decreases the need for on-campus parking, the
construction of the parking structure is still justifiable because The Master Plan of
Dalhousie outlines a desire for a high density campus. The structure not only alleviates the
immediate parking needs of Dalhousie University, but the future needs as well. If a parking
abundance is achieved, having consolidated parking in the form of an on-campus structure
will allow surface parking to be removed, freeing up space for facilities more in line with
the Master Plan.
The parking structure designed by WEMM Engineering provides Dalhousie with
over 400 new parking stalls and fits in nicely with the surrounding campus. The functional
design of the 8.7 million dollar structure has been tailored specifically for Dalhousie. A
functional, easily accessible parking structure at Dal will not only increase the campus’s
accessibility, but it will contribute toward the educational excellence of this prestigious
University.
A-1
Final Report
APPENDIX A – Division of Labour
For the most part, WEMM Engineering worked together as a team. Each person took lead
on certain elements, but by working on things together it allowed us to use our diverse set
of strengths to produce the best possible product. Each team member assisted with and
reviewed every aspect of the project to ensure it was done to the best of our ability as a
team rather than as individuals. Found below, are short descriptions of each team members
role through the two semesters of this project.
Andrew Eagen:
In the first semester Andrew was responsible for defining initial conditions for each
possible site location. He also was in charge of the preliminary geotechnical considerations.
In second semester, Andrew put together the final presentation and designed the design
expo poster. He also did the calculations for snow and earthquake loads and took lead in
the development of the sustainable solutions. For both semester’s Andrew was the main
contact for the advisors and was responsible for scheduling group meetings. He also
compiled, formatted, and edited both the progress report and final report.
Christopher Wallace:
During the first semester Chris worked on basic pricing, materials selection, and consulting
with Strescon Ltd. in order to research various options for the building layout. During the
second semester he was responsible for modelling the proposed structure in an
architectural software and developing renderings and mock ups of the final design.
Ian Milne:
In the first semester Ian worked on site assessment of the Dunn site, as well as a parking
needs assessment, comparing Dalhousie to other Canadian schools. Second semester he did
the cost estimation for the parking structure and calculated the wind pressure on the
exterior of the building. Ian also worked on the sustainable solutions to reduce Dalhousie’s
parking demand worked on the risk assessment. Ian was also responsible for developing
agendas prior to each meeting, and for generating and submitting the meeting minutes
throughout the year.
A-2
Final Report
Kenzie MacDonald:
In the first semester Kenzie created the campus maps that were used to show various
aspects of the considerations that went into site selection and sustainable approach
solutions. These were created using the PDF editing software BlueBeam. He also came up
with grading criteria for the site selection. In the second semester he produced of all
AutoCAD drawings and CIVIL3D cut and fill analysis, as well as the S-Frame model which
was used to assess the magnitude of forces that would result from our worst case lateral
load criteria.
B-1
Final Report
APPENDIX B – Supporting Calculations
Table of Contents:
Parking Stalls on Each Floor............................................................................................................................B-2
Member Weights...................................................................................................................................................B-3
Snow Load Calculation.......................................................................................................................................B-5
Specified Wind Calculation...............................................................................................................................B-7
Earthquake Load Calculation..........................................................................................................................B-8
Calculation of Service Load Moments.......................................................................................................B-10
Calculation of the Effect of a Structure on Current Drainage.........................................................B-11
M.ve*,tec t r
N"r""..k<- - e5* k:. h-s-,#,q {1r,"" p,sf- F / "'g"(:
tI
II
I
rclII
IIIIIII
\i,
Exler;o- v*-l I sLf ls ;
+S * l[: -c) a 6s'8 .-
J6- ;{-s,r,) ? 2q.,0,^.
1y".lL rn) Soull *ul| Sl*tIt/\lGt:?.,_\ *a * 5L sl*rrsf:;t-) "- <-----E
St*tl S,'** : )-5* c--ida5'S,..- J"*j
fr-e
4 kWe^ce "
Pre.*sL f Pr. sl,=s *J (
P"nl';"9 Sfnllvz.\e"o*;#ef Pr**t- g '?o' j
cnuf-e
f'*, l'it'*
Eosl o- )t et'l-g\t/lL "2._t )
fnhvr sLll5ial
1:{3'g \ *\ .r'f ]
VesF vu*ll' sLlfS
>L k lg sLllg
i)e6tgn F-. Cenlr- Pcr ( t<<?)
l,I
1Ar,/n<
To+-l 1," u-'-.l"e- o[
'[O lol vt u,*^be-- oF Sl--*lf S : ) oq x t4 Sh- ie f: t-llG sL*l)s
lerFun -uul' bf t A(, l?a';o*u) by t I )tA
I tr
Zt'\ Stua I l5ffi
u{*llt W" Flonr : 5> t fbe
: loq sl-,lt
3q
B-2
Pryteersq_D_:u\!iJSe@#lSQa Y Foo
|\[otr,o,\ benerly fsncd'Ls l?yn
:t&o
. qls l?to , qrs rr--F-
fit= I f,( .Soo tn*lf= t{ \\|?9 ^\ot on..r$
\= 3?5 h1l rna
v = t.? t<it 1"3V/s'S?*$
! -,'\cr
p:\L
fp*
LK\.lJr$
Jlnv.n'1 13 , tot6
Iqrr I't\ilnt
= t5 VIP*,
:l*o ,faP*
" q{o ti$q
ln,va
rso]
9e = $3)Da= E\\
f "t'"i
[-*u**,"
.,.) "c)
rro{
ropos!$ SBc.{ict t."a"} o ?.Q k$cornt6y ) t$nnrn
'irnpo*e* lae.{iCf i**} s \.\
[a'YotOf = $6tnfts'
6c.*s 66oltcn".l en\ = (t.tg*\ Lo.u: il - (".1$T,'\[',9) (" .-'l-59n^\te' ) tq? rr\
s.ots9rr, A* o's(3t'rrta
)qBErn f,1.<-*-.\ Jasi\ (e".rc**S = a$ r*lrrus
1-= (g.tt"Y\ - (o.Grn\ - t\,o\yn* *u\etr .kn-.$a&r\f LFvrFtr
, spansrrls
\^f = (o " Sttt ,,1\( fV.ognn) fas h.]t t"P) ( it \
= )o.984.s:Kil
5t'\
CdPvrco<* tcsl'ecrd 6"6q{Ptf Hon*b.oh
.slY3*
).)3'
.tsrbrns]*hl-.,Rr{ievF\ Lv;
Rtfs rrncq : FC I
B-3
J",nrlq$J \3) aolIqn f4.\nF
): 2$ l(tu/ro,i
\ - o .ctStq[t'! ( qt. 18 ? r*\--1 3- 1".5 tct
To|^\ \o\q*t '.
\ = (1.3 **\ (1 s'clisnf s 5\.\ nns
Tor_-.\ f orre of' K -v"\\ :
r : (xr,i..:\*KNlc,f) = {\ ?aq.q Krl
("olnr*
p : (*, 0 - 1 o. [ *\(: .1 qaf*,\(,i){ tQt<nl*r\
= l3L.\\ Y"\l
T.*J f6rEB of o..l\ 0-l'rmnst
F' i31 1?'l?k1"1
!:v{o\\_ tolcf
ece*-.{ C.osl SeC}ion:
h: 5o6o = ?S Aq61 m,.l
To|",\ Le.$h:
L : 3 (.t x",1") + e ( (o gt rorn) +
a 2$?-g\."1'-t
Yo lurnf ".
't
I t..*'
IIh
Tq.t?{ ^ |
T
2 haq?
3. tV5 n"'
t'ron)
Prnfqcrnbt bV I I[i\
Nev\eve} bv : CW
ffne.sl ft.gti'esged
t
MN
tlrPs$r.tb:, FCf Gncftf o \|6'vr$\oqOk
B-4
Sn""r L.q\ G\tghlidntu@ r
s = Lt L 5s ({bL,-C, t^)
Is . , mporlo,6., f*.ftrr t l. o f,r.- pur{n,*,l, J
es = /i.' So ye,"r S*wr-J -lr:scJlo*Js = l"q
LU: br^s,e ,""f snn-*.J*nj f*ehr o-8
C,- = C-iry) &xpct5",,< f*" {t = l-Q (rJ ooe,r\ ek)nS por rt,ft
C + ' ro"rl SloPe T*"lon
Ca, = 5h*P* E cl*rr r c-o.lc,* 3r.*,
* y y,a 5Q f&*" t**,s.^kJ r*'6 )o*r) ;' O'(e kPr
(*|"-l 9 {^. F"y 4J" {l'ot *} perc.,oef
5.1
(-)
FeL"uY 1rt*t
lu rra.j*-
l*y^ { il*l,Iax
rpa*."J ,:*dz]- .-*lJs )
\rej
:a*,* icr 1oY)':*o 6"r - ' .!-"t
P.#trryp
x (
r{) lH < 35sl/ ^tl l )
hil titttttltl{ ri {,J,'l'lrJ,i[,],+
xA#- ry* l-- 06{ IoJ,g
>35,/ X
lf
-;*lt
o c^ o)
o<r< XA (1 ,#uJ.<ry-< bl,,t t
o) loh' ,
Tlerre is ol5o s-h<'u.ev'er tl i5 rtolJ )^..r.r3\ r'v€+Trlfig ;+
.
iln = hegt"+ PrfLtty r
t, lhp= l-of- b?=
c.;a ,{ i f {r{7v.:fr 7Sczl;A tv.A l-v'S*u'o*) L b-ild'
. t_\
bp ' t'e-glh
73 "- av1 long
*.e$aee' l€.'nau'g\ g
VF
f*'-* pe"*
stlz =
3,..( Xd -< 't *^ Gto) o-,r I2)' . 21" ,/
I,
,tl[ [ . i,^ri,] u^*'ghl st\a,-^' j-co[
{ rs.l.r'p,
SnaJ
36"- e^ slo,trs'J<.
tvt
i l-.e
IlP 6]lo-.
) ilrt . ut*
,Y, ui.h- ;F5s
kN f ,*.2
zj'),
B-5
Feb. u"'$ } 2slL
Srre> vt [-e*, (o,\crr
X},
b.t :
,/ ^ /^ .4Lr ^ u'('2 +
pa'r"u'Pe-l *
a{t"*+} * j.lr.tr*
13* ),[-4'- S T=D -oo d*-. i,*-i43-
* O;C}
5 ,-,;litn z-l[ Fva oF WbPe*'o- {' f ,,--\ - -
J: l'o! )"4(o,Atr'Q x l*() u l't47) | o'' )- L
..'t "n
= /-75 hPo,,
S Fo- nesl o$ b*;l d:F:g { 6* ' t 'ct}
5'- r'o C t'41 ( o'v ' t'a * l'o x r"P)
'= l"(4L1 kqa'-. __*__ -. ;:;*;t:r5
Cel*-*!a'L i'" €g}"i CI$ "{n9* tt{\ gi.'-" {',*: f *J' :
A, t Q,,oo*g& + Ur, tn(l+
As,onlsrt*' )r;ll o' Prc* ff"1
, = >h l-lq J- 3L 'a)" 2"?4kP'u
= IZ4b l^^)
Q, ' ing'd.* pa.o * zb-,n l. [+r-,t-43tU .L l"N
Jfx*t)J ^i
[lk,,-t-73-tt^4* )-le_
t -qq7
b)s = 5W a ,p6L r-,j e*.{l,y*}^u {'urc € {,*t*uJohbn
Perf.e,nrS- S- \ Ai\':jt:r-4"-bl r rn-bfrS$q: (q${'\s^tor\ g - NBdC
B-6
Jq".2? r1"olI".o gilhe
SpeciP;e I vin* (e.\culqVisrl
[d.e""ot p\ess u rtcrt * \ri\\ino .l
\oo Srlclr;>ru d*e b qin d o\ gacf sr *il sF .r. srr
P -- l" 1, Cc Ctct
\v = t. ( qosn ".)\; " o.s8 (torlIy vird Pressuc ohP6 l/ro Ye"f)
c: F b. ? (h/ rzJ'? = o.?$t Gorrcnsg,g
Ct = a.S ( Svr.l;o'rs .'r! glfs-no\ Ct*\\\
Ce= €>.? (ftppnSrx Fl) L"pesinls .*f c\oseJ in Starrn)
".r9,..\t'+\= oQ9
P, = o^5?.6 KPa.
P"= O .91 KPqPa= Q'StE ltP*
FV = o.\'? t^Fo,
t nol- GevrrT{s'\
tselefeq4t'; Cscarreat".lf : Nts6L
MTvlB*n:*eA-bX : cbJ
B-7
L"*\ Cq\crr\".|ion
,r /2\ sb-z).Ttw\1ta (T)-Pa\vo
T€ = rrvtparir-r.a lo* t'-*r + l"O
5[r'7\ = ftigv-rc coef,F,.;*-'l F*1 |*o'B'fort ? o'&3
'W ' *v* {,l,Fy F,-:crg 4,' $irc* fr*e', $*.o }*r 3 t -S
g- ? o\,,ers{rt -'3l-f. }n*e- r'v-roclnrFf .o F ,,"* F*"g*-
W ' u,aghl o? S+**r' h,*&
= DL u /ST, S
, 5). 1?7 y o " Zs(43tV "Z)
=54, a g 2, n* l', f roorg = lj
DL=3suS;r"\'T-beiftt
. 57 ot72
,t5 tJ KN /p luar
l"> |,*lF ,ftS .5 t"Ja *aSo f/*.r.6 +5e kN
Febcvucy 3, 2o
4* 1"3
lo t4t l0 + l tllqtl
Sph&rl gsl,a*
k4
f;"st $ !oo.
$r*"J*| { gte leJ
r J.1oo4
i;Le'-h-*t
,, /r r (o-23)(t-o)(54osz';\/--l*l#v [3i (t-s)/r.:)
rr1_>
Ft\'-'----)ftl
--*
= t4 ;-5o kru
tJ- l"r '
*,eter$neFt :Faet \Fer*P.gneA.5 \ AtReuicsteA ty I Jf\
,rIt/hitt
l- _ lrr s3s
A fuao I
lJsqgl IV,t\y
l5 3tso
t-,x4
/r \(Fr'- o .1
- NBCC
B-8
*:
6?st
)3 sr3
)35 t,,
*35 rJ
ui r?25 r.4€t t
5; q s?'
7+ scr
Z u,l hl
0 rrzFZ
?-: !!
o'31 r"
11"r12 i
ts\ gT-t*h*
hi?.'J49
?" 6otr:
Utx h*
FFbr\,crY ? J
, f t--"i'-l- -- lVlt .')J)J-T
6atf "7
13 {/!v - |
t+V{{ " S
tr f,) j
11 , s35
/5"3SS jo3 cr!
5- = JSq 538
* {ku;r, j.rsJ; ..l..}w€r r', r.}'-{r- i"'"i 'vJ
- - | A,?P eeft>rrnFj _F!. I
^rS_*_qy q* \sy : I trt
t Lf- * N&tCttqfus:Eg.i Po,r
{'- t -o
B-9
Ftt.{*$l !,,1*n hi\ne
C* \Crr\*{G.f, .f _S llv.:jt_ \=$*\SI}ry$t $Go x8ao dslUtP Tae
SP0rn * ltn*$vper irnpog64 ohqJ b** 3EuFf.- imp*sg$ live l.od
*
lsnCcff I
f f 't$wiftufc;' : tS l4h
}{orrnq\ funsi*gfeslresseJ ver ndrcBrnon*,
Itr-- \l rnr"r 16(0
fte __ ( rq (19\ __
PPo = o'? f1u
Sec*ion Prtprlies :0o = S0(r6.so tn*^t.;': ?S rt}to yio6 hrnr
\u*- (32 n"r'r-5+_ llY*- 1 35b* \o.Eo"o tlo'Toyq
^S+' t93:fig3xrojtnqrvyr: t+S hSlq|*\^): \.i hpl". = lt'SVa V'N/rn
Preslrrss For63:P.= ( )?gG) [-.7) [rtto1 /r& . lgoo vtil
Pl = (to"r- i..itio,\ uss\ . (..q)(ttoo) = 15y'laUF" . (::rr- \ol'-\ \ors)= (".Y{) ttwo\ = 11?o k$
Srcrtiae )"g,.J Movntnls i*? oidsp*ct t
*.u, s ( rt.s\q FpJ",-) { ntf,t
luls.l = ( \.st l^pl *) ( tt-'fF
hr. (gge\*hlrJhil,(Snf8
Ft.$otnt\ EYt I\\
Rev ierprl bV t C.hJ.
F.e?e{'FaAS i Pc I Pcec*sl Fre<tcsse& C*t.c,.ate $.n&b-"[
c.S hbtlrrf € ).& Hillrnt,7S k$l/,ht' = e,*o\ l<Vln
l,th. sfnss rol;sd sfr"nJeItSU trnl
= _s,tq.:5*S:
= Yt| ,lt 5 \\N*
= 259'q, h$ '"'
B-10
B-11
C-1
Final Report
APPENDIX C – Gantt Chart of Project Progress
ID Task Name Duration Start Finish
1 I - Project Management/Organizational Tasks 131 days Mon 10/5/15 Mon 4/4/162 Weekly Team Meetings 131 days Mon 10/5/15 Mon 4/4/163 Log Books 131 days Mon 10/5/15 Mon 4/4/164 II - Preliminary Research and Design 30 days Mon 10/5/15 Fri 11/13/155 Campus Investigation and Site Selection 8 days Mon 10/5/15 Wed 10/14/156 Data Collection/Traffic analysis 10 days Mon 10/5/15 Fri 10/16/157 Zoning restrictions research 8 days Mon 10/5/15 Wed 10/14/158 Dalhousie parking requirements research 6 days Wed 10/7/15 Wed 10/14/159 Parking structure code requirements research 6 days Wed 10/7/15 Wed 10/14/1510 Geotechnical Analysis 6 days Wed 10/14/15 Wed 10/21/1511 Prelim. Technical Design Work 18 days Wed 10/14/15 Fri 11/6/1512 Conceptual Drawings 15 days Mon 10/26/15 Fri 11/13/1513 III - Design Selection and Analysis 79 days Fri 11/13/15 Wed 3/2/1614 Design Selection 4 days Fri 11/13/15 Wed 11/18/1515 Loads Analysis 14 days Mon 1/4/16 Thu 1/21/1616 Exam Period/New Years Break 20 days Tue 12/8/15 Mon 1/4/1617 Storm Water Routing 10 days Mon 1/4/16 Fri 1/15/1618 Building Renderings 10 days Mon 1/4/16 Fri 1/15/1619 Gravity Load Design 14 days Fri 1/22/16 Wed 2/10/1620 LLRS Design 14 days Fri 1/22/16 Wed 2/10/1621 Foundation Design 10 days Thu 2/11/16 Wed 2/24/1622 Cost Estimate 5 days Thu 2/25/16 Wed 3/2/1623 IV - Final Report/Drawing Package 37 days Fri 2/12/16 Mon 4/4/1624 Poster Board Design 5 days Wed 3/9/16 Tue 3/15/1625 Final Report 37 days Fri 2/12/16 Mon 4/4/1626 Final Presentation 24 days Mon 2/29/16 Thu 3/31/1627 CAD Drawings/Renderings 18 days Thu 2/25/16 Mon 3/21/1628 V - Deliverables 131 days Mon 10/5/15 Mon 4/4/1629 Work Plan Due 1 day Tue 10/6/15 Tue 10/6/1530 Project Team 40% Presentation 1 day Fri 12/4/15 Fri 12/4/1531 Project 40% Report Due 1 day Mon 12/7/15 Mon 12/7/1532 Submit Logbooks for Review 1 day Mon 12/7/15 Mon 12/7/1533 Poster Board File Due 1 day Tue 3/15/16 Tue 3/15/1634 Design Expo 1 day Tue 3/22/16 Tue 3/22/1635 Draft of Project Team Design Report Due 1 day Sun 3/27/16 Sun 3/27/1636 Project Team Final Presentation 1 day Fri 4/1/16 Fri 4/1/1637 Project Team Final Design Report Due 1 day Mon 4/4/16 Mon 4/4/1638 Logbooks Due 1 day Tue 4/5/16 Tue 4/5/16
25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 3 8 13 18 23 28 2 7 12
Sep 13, '15 Sep 27, '15 Oct 11, '15 Oct 25, '15 Nov 8, '15 Nov 22, '15 Dec 6, '15 Dec 20, '15 Jan 3, '16 Jan 17, '16 Jan 31, '16 Feb 14, '16 Feb 28, '16 Mar 13, '16 Mar 27, '16 Apr 10, '16
Task
Completed
Milestone
Summary
Break
Completed Milestone
Page 1
Project: Gantt TimelineDate: Sun 4/3/16
C-2
D-1
Final Report
APPENDIX D – Potential Site Maps
Dunn:
Hancock:
D-2
Final Report
Wickwire:
LSC:
E-1
Final Report
APPENDIX E – TDM Significant Findings
Details of Available Parking at Dalhousie University
E-2
Final Report
Peak Occupancy Observed During Parking Survey:
E-3
Final Report
Continued…
E-4
Final Report
Total Occupancy at each Campus by time of day:
F-1
Final Report
APPENDIX F– Detailed Site Selection Information
Crite
riaW
eight
ingDu
nn
Scor
e
Dunn
Weig
hted
Hanc
ock
Scor
e
Hanc
ock
Weig
hted
Wick
wire
Scor
e
Wick
wire
Weig
hted
LSC S
core
LSC
Weig
hted
Relat
ive pa
rking
gain
156
906
9010
150
812
0
Stree
t acce
ss12
1012
03
365
6010
120
Cost
125
606
721
127
84
Size (
capa
city)
128
963
366
729
108
Impa
ct on
surro
undin
g site
s12
112
1012
07
843
36
Strain
on pa
rking
durin
g con
struc
tion
91
92
1810
904
36
Camp
us ac
cessi
bility
11
888
444
555
999
Impa
ct on
curre
nt us
e9
1090
1090
00
872
Noise
durin
g con
struc
tion
53
158
405
253
15
Cons
tructi
on ac
cess
35
157
218
245
15
Total
100
595
567
572
705
G-1
Final Report
APPENDIX G – NBC of Nova Scotia as it Pertains to Parking Structures
1) The building would be classified as a Group F, Division 3, Low Hazard Industrial
Occupancy. (Storage Garage)
Whether it is sprinklered or not depends on the building area and building height
(assuming up to 5 storeys), as specified in Articles 3.2.2.78. to 3.2.2.80. Note that
3.2.2.88. would be of significant importance regarding an unsprinklered parking
garage.
It is assumed that there will be no storeys below grade, otherwise Sentence
3.3.5.4.(7) will require them to be sprinklered.
2) By definition, an open-air storey is one in which at least 25% of the total area of its
perimeter walls is open to the outdoors in a manner that will provide cross-
ventilation to the entire storey.
3) It must be noted that if the building is not sprinklered, several of the 3.2.2.
requirements state the number of streets that must be available for fire-fighting
purposes.
Remember that “2 streets” require 50% of the perimeter be available, and “3
streets” requires 75% of the perimeter be available for fire-fighting access.
4) If the building meets the requirements of Article 3.2.2.88., but is not more than 15 m
high, Sentence 3.2.5.9.(4) would not require a standpipe system to be provided.
This would be the only exception to providing a standpipe system regardless of a
sprinkler system or not.
5) Sentence 3.2.3.10.(1) would permit an exposing building face to have unlimited
unprotected openings if such building face has a limiting distance of not less than 3
m, and all storeys are constructed as open-air storeys. If the limiting distances are
less than 3 m, then the usual requirements for percentage of unprotected openings
and type of construction would apply. (Table 3.2.3.7.)
G-2
Final Report
6) Sentence 3.3.5.4.(5) would require a clear height of not less than 2 m throughout the
structure.
7) Clause 3.4.6.7.(1)(b) would permit a maximum ramp slope of 1 in 6 for this
industrial occupancy.
There does not appear to be any special provision for people in wheelchairs that
may have to contend with this gradient.
8) Exit stairs must be located so that the travel distance to at least one such stair from
any point on a floor area does not exceed 60m in an unsprinklered building. (Article
3.4.2.5.)
9) The width of exit stairs must be at least 1100 mm (Table 3.4.3.2.A.) which would
have a capacity for 137 people per exit, per storey.
10) If the building is designed under Article 3.2.2.88. the exit stair enclosures must have
a fire-resistance rating of at least 45 minutes.
If any other Article is used for design, the exit stair enclosures must be equal to that
specified for floor assemblies by the specified Article. (See Article 3.4.4.1.)
11) Whereas the floor areas exceed 600 m², the Barrier-Free requirements of the N.S.
Building Code Regulations would require the installation of an elevator. (Put
Barrier- Free parking stalls (7 at up to 500 stalls) outside parking structure if you
prefer to go without an elevator)
H-1
Final Report
APPENDIX H – Test Pit Logs
H-2
Grass / TopsoilFILL : silty sand, some cobbles, traceorganics, loose, moist, dark brown tobrown.
Elev: 0.98 feet
Inferred Bedrock Level
End of Test Pit at 3 feet in Bedrock.
Test Pit dry upon completion.
Note that the Bedrock surface acrossthe test pit varied from 1 foot on theeast side to 3 feet on the west side.
18661
SURFACE ELEVATION
SOIL SAMPLE
PROJECT
LOGGED/DWN. BAM CKD. TKM DATE OF INVEST. TP 1
WC % wp- w- wl-
10 20 30 40 50
DEPTH
ft m
MODIFIED
USCS
SOIL
SYMBOL
SOIL DESCRIPTION
DATUM BM : Top of Door Threshold,LSC Building, Assigned Elev:0.0 feet
JOB NO.4/25/14
COND.
TYPE Mini Excavator
WMCL Building, Dalhousie University, Halifax, NSGeotechnical Investigation -
3.98 feet POCKET
PENE.
BACKHOE TYPE
OTHER TESTS
PLATE 1
TEST PIT LOG
TEST PIT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5H-3
Grass / TopsoilFILL : silty sand, some cobbles, traceorganics, loose, moist, dark brown tobrown.
Elev: 1.56 feet
Inferred Bedrock Level
End of Test Pit at 2.08 feet inBedrock.
Test Pit dry upon completion.
18661
SURFACE ELEVATION
SOIL SAMPLE
PROJECT
LOGGED/DWN. BAM CKD. TKM DATE OF INVEST. TP 2
WC % wp- w- wl-
10 20 30 40 50
DEPTH
ft m
MODIFIED
USCS
SOIL
SYMBOL
SOIL DESCRIPTION
DATUM BM : Top of Door Threshold,LSC Building, Assigned Elev:0.0 feet
JOB NO.4/25/14
COND.
TYPE Mini Excavator
WMCL Building, Dalhousie University, Halifax, NSGeotechnical Investigation -
3.64 feet POCKET
PENE.
BACKHOE TYPE
OTHER TESTS
PLATE 2
TEST PIT LOG
TEST PIT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5H-4
Grass / TopsoilFILL : silty sand, some cobbles, traceorganics, loose, moist, dark brown tobrown.
Elev: -4.30 feetInferred Bedrock Level
End of Test Pit at 5.07 feet inBedrock.
Test Pit dry upon completion.
Note that the test pit was excavatedadjacent to the foundation wall of theChase Building and the depth tobedrock indicated on the Test Pit Logwas measured to the bottom of thefoundation wall. At approximately 4feet out from the wall, bedrock wasencountered at a depth of 1.2 feetbelow ground surface.
18661
SURFACE ELEVATION
SOIL SAMPLE
PROJECT
LOGGED/DWN. BAM CKD. TKM DATE OF INVEST. TP 3
WC % wp- w- wl-
10 20 30 40 50
DEPTH
ft m
MODIFIED
USCS
SOIL
SYMBOL
SOIL DESCRIPTION
DATUM BM : Top of Door Threshold,LSC Building, Assigned Elev:0.0 feet
JOB NO.4/25/14
COND.
TYPE Mini Excavator
WMCL Building, Dalhousie University, Halifax, NSGeotechnical Investigation -
0.77 feet POCKET
PENE.
BACKHOE TYPE
OTHER TESTS
PLATE 3
TEST PIT LOG
TEST PIT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5H-5
Grass / TopsoilFILL : mixture of site native till andgravel, some cobbles, slate boulders,loose, moist, brown to orange brown.
Elev: -4.30 feet
Inferred Bedrock Level
End of Test Pit at 7.68 feet inBedrock.
Test Pit dry upon completion.
Note that the bedrock surface variedacross the test pit.The test pit wasexcavated adjacent to a foundationwall and near an abandoned steamline pipe. The depth to bedrockindicated on the Test Pit Log wasmeasured to the bottom of thefooting. At approximately 4 feet outfrom the wall, bedrock wasencountered at a depth of 3 feetbelow ground surface.
18661
SURFACE ELEVATION
SOIL SAMPLE
PROJECT
LOGGED/DWN. BAM CKD. TKM DATE OF INVEST. TP 4
WC % wp- w- wl-
10 20 30 40 50
DEPTH
ft m
MODIFIED
USCS
SOIL
SYMBOL
SOIL DESCRIPTION
DATUM BM : Top of Door Threshold,LSC Building, Assigned Elev:0.0 feet
JOB NO.4/25/14
COND.
TYPE Mini Excavator
WMCL Building, Dalhousie University, Halifax, NSGeotechnical Investigation -
3.38 feet POCKET
PENE.
BACKHOE TYPE
OTHER TESTS
PLATE 4
TEST PIT LOG
TEST PIT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5H-6
Grass / TopsoilFILL : silty sand, traces of cobblesand slate, glass, loose, moist, brown.
Elev: 1.10 feet
Inferred Bedrock Level
End of Test Pit at 2.0 feet in Bedrock.
Test Pit dry upon completion.
18661
SURFACE ELEVATION
SOIL SAMPLE
PROJECT
LOGGED/DWN. BAM CKD. TKM DATE OF INVEST. TP 5
WC % wp- w- wl-
10 20 30 40 50
DEPTH
ft m
MODIFIED
USCS
SOIL
SYMBOL
SOIL DESCRIPTION
DATUM BM : Top of Door Threshold,LSC Building, Assigned Elev:0.0 feet
JOB NO.4/25/14
COND.
TYPE Mini Excavator
WMCL Building, Dalhousie University, Halifax, NSGeotechnical Investigation -
3.10 feet POCKET
PENE.
BACKHOE TYPE
OTHER TESTS
PLATE 5
TEST PIT LOG
TEST PIT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5H-7
Concrete StoneFILL : mixture of slate cobbles andboulders, some sand and gravel,slightly compact, moist, brown.
Elev: -5.54 feet
Inferred Bedrock Level
End of Test Pit at 3.44 feet inBedrock.
Test Pit dry upon completion.
Note that the bedrock surface variedacross the test pit.The test pit wasexcavated adjacent to a foundationwall and the depth to bedrockindicated on the Test Pit Log wasmeasured to the bottom of thefooting. At approximately 3.5 feet outfrom the wall, bedrock wasencountered at a depth of 2.5 feetbelow ground surface.
18661
SURFACE ELEVATION
SOIL SAMPLE
PROJECT
LOGGED/DWN. BAM CKD. TKM DATE OF INVEST. TP 6
WC % wp- w- wl-
10 20 30 40 50
DEPTH
ft m
MODIFIED
USCS
SOIL
SYMBOL
SOIL DESCRIPTION
DATUM BM : Top of Door Threshold,LSC Building, Assigned Elev:0.0 feet
JOB NO.4/25/14
COND.
TYPE Mini Excavator
WMCL Building, Dalhousie University, Halifax, NSGeotechnical Investigation -
-2.10 feet POCKET
PENE.
BACKHOE TYPE
OTHER TESTS
PLATE 6
TEST PIT LOG
TEST PIT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5H-8
I-1
Final Report
APPENDIX I – Functional Parking Structure Design
The functional design of a parking structure encompasses the fluidity of flow of pedestrians
and vehicles throughout the garage as well as into and out of the structure.
Operational Types
Two main types of parking structures exist: self-park and attendant park facilities.
In self-park facilities, drivers park their own vehicles and walk through the garage to an
exit. In attendant park facilities, the users leave their cars at the entrance and attendants
park their vehicles for them. Attendant park facilities maximize the capacity of the
structure through stacked parking, however they have a higher upkeep cost due to the
salary of the parking attendants. For the structure at Dalhousie, a self-park facility is a
better option because of the arrival patterns. 80% of the cars will arrive and leave at rush
hour times, which would overwhelm the attendants and lead to long wait times that can be
avoided by a self-park operational type.
Building Type
Two building types exist for parking structures: open parking structures and
parking garages. Open parking structures relies on facade openness (minimum of 25% of
total wall area) allowing for natural ventilation, but it means that the garage cannot be
effectively heated. Closed in parking garages and be heated but require mechanical
ventilation. The garage built for Dalhousie will be an open parking structure to keep costs
minimal and prevent the need for a fire sprinkler system.
Revenue Control
The proposed parking structure will be provided on Dalhousie Campus for students
and faculty, therefore, it will be included in amenities provided through the purchase of a
Dalhousie parking pass. This means that there is no need for pay stations at building
entrances and exits, instead an attendant will circulate the garage and verify that all parked
cars have a pass; the same technique used in all of Dalhousie’s parking lots. This provides
an easy flow into the garage without the buildup of ingress/egress lines.
I-2
Final Report
Stall Changeover Frequency
Stall Changeovers can be transient, or infrequent. The use of this garage will be
primarily for students and staff coming to campus for class, meaning that there will be
minimal parking stall turnover. Someone will pull into a stall in the morning, stay for the
day, and pull out at the end of the day. The minimal stall changeover allows for the design
of the parking spaces to meet, and not exceed, the minimum parking spot dimensions. If
cars were constantly entering and exiting, there would be benefit to providing oversized
stalls, limiting the total number of spots, however in this case there is no need.
Street Access
Ideally, parking garages should be accessed from the busiest street possible to allow
for the fastest path from the parker’s origin to their parking destination, and it should exit
onto the least busy street possible to reduce exit delays caused by street congestion. This
proposed parking structure is surrounded by internal Dalhousie streets that are all low
volume and easily accessible by main roads, giving it the ideal ingress/egress conditions.
This parking structure will provide two two-way entrances/exits providing an efficient
traffic flow as well as an extra entrance/exit in case one becomes unusable. A minimum
ceiling clearance of 2.1 meters is recommended by parking garage codes, so the Dalhousie
garage shall comply with that entrance/exit size.
Circulation System Level of Service
The level of service of a parking structure can be affected by several things: parking
space angle and width, drive aisle width, number and radii of turns, ceiling heights, lighting
levels, ramp slopes, pedestrian crossings, entry/exit location and design, vehicle travel
distances, and the traffic circulation system. WEMM Engineering will be designing a
detailed circulation plan next year taking into account all of these considerations
J-1
Final Report
APPENDIX J – Site Preparation Cut and Fill Quantities
J-2
J-3
J-4
K-1
Final Report
APPENDIX K – Structure Drawings and Details
1 2 3 4 5 6
A
B
C
1463014630 14630
18288
18288
1463014630DWG:
DRAWN BY:
DATE:
SCALE:
PLAN
KM
APRIL 4/2016
1:250
You
cre
ated
this
PD
F fr
om a
n ap
plic
atio
n th
at is
not
lice
nsed
to p
rint t
o no
vaP
DF
prin
ter
(http
://w
ww
.nov
apdf
.com
)
K-2
3845
3845
NORTH ELEVATION
5775
5768
3845
3845
1930
SOUTH ELEVATION
3845
DWG:
DRAWN BY:
DATE:
SCALE:
ELEVATIONS
KM
APRIL 4/2016
1:250
You
cre
ated
this
PD
F fr
om a
n ap
plic
atio
n th
at is
not
lice
nsed
to p
rint t
o no
vaP
DF
prin
ter
(http
://w
ww
.nov
apdf
.com
)
K-3
EAST ELEVATION
WEST ELEVATION
DWG:
DRAWN BY:
DATE:
SCALE:
ELEVATIONS
KM
APRIL 4/2016
1:250
You
cre
ated
this
PD
F fr
om a
n ap
plic
atio
n th
at is
not
lice
nsed
to p
rint t
o no
vaP
DF
prin
ter
(http
://w
ww
.nov
apdf
.com
)
K-4
EAST ELEVATION
36576
6096
DWG:
DRAWN BY:
DATE:
SCALE:
SECTION AT KWALL
KM
APRIL 4/2016
1:150
You
cre
ated
this
PD
F fr
om a
n ap
plic
atio
n th
at is
not
lice
nsed
to p
rint t
o no
vaP
DF
prin
ter
(http
://w
ww
.nov
apdf
.com
)
K-5
3845
NORTH ELEVATION
5775
3845
3845
DWG:
DRAWN BY:
DATE:
SCALE:
SECTION AT LITEWALL
KM
APRIL 4/2016
1:250
You
cre
ated
this
PD
F fr
om a
n ap
plic
atio
n th
at is
not
lice
nsed
to p
rint t
o no
vaP
DF
prin
ter
(http
://w
ww
.nov
apdf
.com
)
K-6
DW
G:
DR
AW
N B
Y:
DA
TE:
SC
ALE
:
CO
LUM
N C
ON
NEC
TIO
N
KM
APR
IL 4
/201
6
1:8
WIL
SO
N S
LEEV
E
NM
B SP
LIC
ES
LEEV
E
CO
LUM
N C
ON
NE
CTI
ON
TO
CIP
PIL
ASTE
R B
Y O
THER
S
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
K-7
DW
G:
DR
AW
N B
Y:
DA
TE:
SC
ALE
:
DT
BRG
ON
SPA
ND
REL
KM
APR
IL 4
/201
6
1:8
CO
NN
EC
TIO
N B
Y O
THER
S
BR
G. P
LATE
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
K-8
DW
G:
DR
AW
N B
Y:
DA
TE:
SC
ALE
:
DT
TIE
TO
SPA
ND
REL
KM
APR
IL 4
/201
6
1:8
CO
NN
EC
TIO
N B
Y O
THER
S
PSA
INS
ERT
SPI
DE
R P
LATE
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
K-9
DW
G:
DR
AW
N B
Y:
DA
TE:
SC
ALE
:
VC
IN D
T FL
ANG
E
KM
APR
IL 4
/201
6
1:8
CO
NN
EC
TIO
N B
Y O
THER
S
PLA
N
ELE
VATI
ON
VE
CTO
RC
ON
NE
CTO
R
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
K-10
DW
G:
DR
AW
N B
Y:
DA
TE:
SC
ALE
:
DT
TO L
ITEW
ALL
BRG
KM
APR
IL 4
/201
6
1:8
CO
NN
EC
TIO
N B
Y O
THER
S
BR
G. P
LATE
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
K-11
DW
G:
DR
AW
N B
Y:
DA
TE:
SC
ALE
:
DT
TO L
ITE
WAL
L TI
E
KM
APR
IL 4
/201
6
1:8
CO
NN
EC
TIO
N B
Y O
THER
S
PSA
INS
ERT
SPI
DE
R P
LATE
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
K-12
L-1
Final Report
APPENDIX L – K-Wall S-Frame Analysis under Governing Earthquake Load
Halifax, Nova Scotia
Dalhousie Parking Structure - K WallFilename: G:\WINTER 2015-2016\CIVL 4802\S-FRAME\KWALL WITH OFFSET.TELGRAPHICAL RESULTS - Ld Case 8 Seismic 2->Axial Force (kN)
Engineer: WEMM Engineering
Page: 1 of 1
ACADEMIC VERSION NOT FOR COMMERCIAL USE S-FRAMEAcademic Version 11.1.14
© Copyright 1995-2015, S-FRAME Software Inc.
X
Y
Axial Force (kN)
2497.5586
2023.8461
1550.1337
1076.4213
602.7087
128.9963
-344.7161
-818.4285
-1292.1410
-1765.8534
-2239.5659
-2713.2783
-3186.9907
Axial Force (kN)
2497.5586
2023.8461
1550.1337
1076.4213
602.7087
128.9963
-344.7161
-818.4285
-1292.1410
-1765.8534
-2239.5659
-2713.2783
-3186.9907
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
L-2
Halifax, Nova Scotia
Dalhousie Parking Structure - K WallFilename: G:\WINTER 2015-2016\CIVL 4802\S-FRAME\KWALL WITH OFFSET.TELGRAPHICAL RESULTS - Ld Case 8 Seismic 2->Moment (kN-m)
Engineer: WEMM Engineering
Page: 1 of 1
ACADEMIC VERSION NOT FOR COMMERCIAL USE S-FRAMEAcademic Version 11.1.14
© Copyright 1995-2015, S-FRAME Software Inc.
X
Y
Moment (kN-m)
75.5270
63.9133
52.2996
40.6859
29.0722
17.4585
5.8448
-5.7689
-17.3826
-28.9963
-40.6100
-52.2237
-63.8374
Moment (kN-m)
75.5270
63.9133
52.2996
40.6859
29.0722
17.4585
5.8448
-5.7689
-17.3826
-28.9963
-40.6100
-52.2237
-63.8374
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
L-3