Daglig borerapportProject meeting March 23 2006
www.olf.no
Agenda
1. Status terminologi-definisjon- Presentere terminologi etter møter med BP, ConocoPhillips, Statoil, Hydro og programvareleverandører- Avklare behov for videreutvikling av terminologien
2. Planer for det videre arbeidet- Generering av XML-skjema- Tilrettelegging av LicenseWeb for daglig borerapportering- Produksjonssetting
3. Eventuelt
www.olf.no
Current PlanDate Task
26.01 Project meeting (1-06)
24.02 Daily Drilling Report Terminology based on CDRS suggested.
06.03 Meeting Hydro
07.03 Meeting Statoil
08.03 Meeting ConocoPhillips
09.03 Meeting BP
10.03 Start updating according to feedback from meetings and review
23.03 Project meeting (2-06)
31.03 Terminology work complete
xx.04 2-3 days XML kick off, POSC, Capgemini, project participants
25.04 Project meeting (3-06) ?
23.05 Project meeting (4-06) ?
31.07 XML schemas complete
01.08 Start Pilot, and adjust
31.08 Project meeting (5-06) – decision to recommends implementation?
www.olf.no
Summary
1. Met and reviewed terminology with drilling experts and it-professionals from operators and vendors.
• Statoil • Hydro• Conocophillips• Total• BP• Peloton• Landmark
2. Approximately 140 issues and comments from meetings.
• To be resolved by PSA/OD, Operators and DNV
www.olf.no
Open tasks in project1. Issue resolution
• Phase 1:CDRS including minor changes from NPD/PSA and other project participants.
• Phase 2:Major gaps?
2. Create XML schemas• Kick off meeting mid April with Capgemini, POSC and DBR
participants
3. Pilots – how, where and when?• Valhall one possible case• + one other case
Review detailsProject meeting March 23 2006
www.olf.no
Review details 1
1. The information in CDRS will cover partner reporting
2. Clarification of terms and definitions• GEOGRAPHICAL POSITION – relative to what?• FORMATION PORE PRESSURE – is this measured or
predicted?
3. Time codes/activities/operations• SUPERIOR
• Not logical with BOP TEST • MAIN OPERATION & SUB OPERATION
• Done differently from company to company• DOWN TIME/INTERUPTION not linked to interrupted
operation in CDRS• Seems to be a need for more downtime details than
CDRS provides• Hydro has suggested new coding • Complex job....
www.olf.no
4. Suggested additional information• Cement• Period of operation• “Drilling like” units of measure
• Hours in stead of minutes • Inches in stead of meters• Etc...
• Formation name – selection list• Use Survey tools not “Single shot measurement
indicator”• Datum (reference points)
• Mean sea level• Wellhead
• Casing type• Tapered string• Expandable
• Pressurized coring• Indicator
Review details 2
www.olf.no
4. Suggested additional information (cont.)• Well stimulation (At well testing) indicator• “Shallow water kick” is a kick type• Perforation - Shot density• RIG ID • RIGTYPE• Bit data• Side track
• Technical side track (BP)• Geological side track (BP)
• Tight wells
Review details 3
www.olf.no
Phase 1 vs. Phase 2 - suggestion
Phase 1• CDRS information• Clarification of terms and
definitions• Use Survey tools not “Single
shot measurement indicator”• RIG ID
Phase 2• Operation codes• Cement• Period of operation• “Drilling like units of measure• Formation name – selection
list• Datum (reference points) • Casing type• Pressurized coring• Well stimulation (At well
testing) indicator• Perforation - Shot density• RIGTYPE• Bit data• Side track• Tight wells• ++
www.olf.no
Daily Drilling Report – suggested sections
1. Basic information2. Status3. Mud data 4. Pore pressure5. Present operation 6. Survey7. Operation/mode8. Log9. Core10.Well production test11.Well Formation Test (WFT)12.Weather13.Remarks – Removed from CDRS14.Lithology15.Equipment failure16.Well Control Incident17.Preliminary zonation18.Perforation intervals