Cycle at 4 TeV and 7 TeV
-
Upload
maris-bauer -
Category
Documents
-
view
62 -
download
1
description
Transcript of Cycle at 4 TeV and 7 TeV
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Cycle at 4 TeV and 7 TeV
Many thanks to: the OP team (S.Redaelli and W.Venturini included!), the optic team and the FIDEL
team
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
outline
Commissioning
Cycle – operation
Cycle @~7 TeV
Conclusions
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (milestones)
Date Time Milestone Increment (days)
Wed 7.03 PM Powering test completed
Fri 9.03 21:32 BIC loop closed and LBDS armed
Sat 10.03 15:00 Both beams down the TLs
Wed 14.03 15:00 LHC ready for injection 0
23:40 Beam 1 injected
Thu 15.03 01:00 Both beams captured 1
Fri 16.03 22:44 4 TeV 2
Sat 17.03 16:30 Beam 1 at 0.6 m beta* 3
Sun 18.03 11:15 Both beams at 0.6 m beta* 4
Wed 21.03 24:00 Collimators set up @injection 7
Thurs 22.03 20:58 Squeeze with nominal Xing and sep 8
Sun 25.03 15:00 Inj protection setup 11
Tue 27.03 06:40 Pilot through all cycle 13
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (milestones)
Date Time Milestone Increment (days)
Thurs 29.03 15:00 Collimators aligned @4 Tev 15
Fri 30.03 23:00 Collimators aligned @collisions 16
Sat 31.03 22:00 Collimators aligned @END of squeeze 17
Sun 01.04 16.15 Collisions found in IP5 18
Thurs 05.04 00:38 First Stable Beams @4 TeV (3x3 b)Initial lumi 7.8x1030 cm-2s-1 22
Thurs 05.04 05:39 Stable Beams @4 TeV (47x47) 22
Thurs 05.04 19:54 Stable Beams @4 TeV (84x84) 22
Sat 07.04 02:07 Stable Beams @4 TeV (264x264) 24
Sun 08.04 10:16 Stable Beams @4 TeV (624x624) 25
Thurs 12.04 16:02 Stable Beams @4 TeV (840x840) 29
Fri 13.04 17:52 Stable Beams @4 TeV (1092) 30
Wed 18.04 06:34 Stable Beams @4 TeV (1380) 35
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (planning)
We are very good at planning!!!J.Wenninger @LBOC on 21st Feb
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
2012 changes
Ramp at 4 TeVB3 decay compensation at flatop
separated from the rampSqueeze to 0.6m β*Further optimization of optics
distribution in the squeeze
Tilted LHCb collisions
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (ramp)
First ramp @4TeV after 2 days (beam 2 dumped after a few minutes at flat top due to a glitch in the safe beam flag)
More ramps for tune, orbit and chroma measurements for feed-forward
Most changes around 1 TeV, as in 2011 ORBIT: RT corrections applied (in few steps)
TUNES: RT corrections applied in few steps (FF removed a tune bump between 100 and 200 s)
Snapback correction still not perfect (there are still tune correction spikes), to be analysed during LS1
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (squeeze)
In 2012, 2 major changes on the squeeze strategy: K function smoothing to reduce orbit spikes of 0.1 mm r.m.s, localized
near the matched points and reproducible from fill to fill The matched point distribution was improved by eliminating some points
above 1.5 m and by allowing different β* values in the IPs
J.Wenninger S. Redaelli
~120 mm
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (optics)
Optics measurements and corrections @4 TeV Around 20% peak beta-beating at flatop (very similar to 3.5 TeV machine)
Beta beat at 0.6 m reduced from 90/100% to 7% in both beams
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
40s 100s220s
40s100s 220s
Xing bump IR8: from H to V Xing
H plane
V plane
Separation bumps
Commissioning (collisions)
Before FF
100 mm 100 mm
100 mm100 mm
After FF After FF
Before FF
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
outline
Commissioning
Cycle – operation
Cycle @~7 TeV
Conclusions
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
RB.A12RQ6.L1
Cycle @4 TeVCu
rren
t (A)
Time
RAM
PDO
WN
INJE
CTIO
N P
ROBE
INJE
CTIO
N P
HYS
ICS
PREP
ARE
RAM
PRA
MP
FLAT
OP
SQU
EEZE
ADJU
ST
STABLE BEAMS…SETU
P
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Analysis method
Homogeneous set of fills (only physics fills with 1092/1380 bunches, 0.6m β* in IP1/5)
‘Rampdown’ & ‘setup’ not taken into account Time calculation for beam modes (tools: logging DB, PM, logbook)
This analysis is not meant to evaluate the efficiency of the machine but rather the performance of operation in the hypothetical case of 100% availability
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
INJECTIONWHAT WE DO
Inject the pilots and set up the beams Fill the machine
Remove the inj protection COLL Close the injection handshake
Min Mean Mean cut Theoretic
21 min 67 min 52 min n.a.
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
PREPARE RAMP
WHAT WE DO Set up and switch ON the fbs
Settings incorporation FGC+COLL functions load
Min Mean Mean cut Theoretic
140 s 287 s 259 s n.a.
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
RAMP
WHAT WE DO Ramp
Incorporation (in the shade)Min Mean Mean cut Theoretic
775 s 811 s 791 s 770 s
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
FLATOP
Min Mean Mean cut Theoretic
142 s 409 s 377 s n.a.
WHAT WE DO Tunes check (RQTD/F currents)
Settings incorporation FGC+COLL functions load
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
SQUEEZE
Min Mean Mean cut Theoretic
952 s 1020 s 996 s 925 s
WHAT WE DO Squeeze
Orbit fb OFF
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
ADJUST
Min Mean Mean cut Theoretic
260 s 542 s 513 s 220 s
WHAT WE DO Bring the beams into collisions
(LHCb tilting) IPs optimization (sometimes)
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
2010 2011 2012
Beam mode Theor Mean Compa
rison* Theor Mean Comparison* Theor Mean Compari
son*
INJPRO n.a.3 h 3 h
n.a. 2205~1.4 h
n.a.52 min ~0.86 h
INJPHYS n.a. n.a. 3034 n.a.
PRERAMP n.a. 504 504 n.a. 270 270 n.a. 259 259
RAMP 1400 1548 148 1020 1088 68 770 791 21
FLATTOP n.a. 468 468 n.a. 130 130 n.a. 377 377
SQUEEZE 1041(3.5 m) 2016 975 548
(1 m) 846 298 925 996 76
ADJUST 108 792 684 60 654 594 220 513 293
RAMPDOWN 4000 2100 2100
TOT 4h29m 2h17 1h41TOT (with
rampdown) 5h36m 2h52m 2h16m
Cycle @4 TeV
Unless differently specified, values are in seconds* length of the BP removed
36 min
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
outline
Commissioning
Cycle – operation
Cycle @~7 TeV
Conclusions
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Cycle @(~)7 TeV
Operational cycle at 6.5 TeV Injection at 11 m Ramp to 6.5 TeV (1250 s) Squeeze to 40/45 cm β* (1473 s –calculated for 55 cm) Collisions (270 s tilting LHCb)
it should be possible to go without the tilting if we have vertical crossing all along
Rampdown (~4200 s)
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
2010 2011 2012 2015
Beam mode Theor Mean Theor Mean Theor Mean Theor Mean*
INJPRO n.a.3 h
n.a. 2205 n.a.52 min
n.a.~3000
INJPHYS n.a. n.a. 3034 n.a. n.a.
PRERAMP n.a. 504 n.a. 270 n.a. 259 n.a. ~260
RAMP 1400 1548 1020 1088 770 791 1250 1271
FLATTOP n.a. 468 n.a. 130 n.a. 377 n.a. ~375
SQUEEZE 1041 (3.5 m) 2016 548
(1 m) 846 925 996 1473 1544
ADJUST 108 792 56 654 220 513 270 563
RAMPDOWN 4000 2100 2100 4200
TOT 4h29m 2h17m 1h41m 1h57mTOT (with
rampdown) 5h36m 2h52m 2h16m 3h07m
Cycle @(~)7 TeV
Unless differently specified, values are in seconds*calculated by adding replacing the estimated 2015 BP length to the 2012 values
51 min
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Cycle @(~)7 TeV
We have many possibility:
some of them would make the cycle shorter: Ramp & Squeeze Beta* levelling Low beta (5/7 m) injection (90 m for highbeta)
Some would have no effect on time Colliding & squeezing ATS vs standard optic Flat beams 25 ns
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Cycle @(~)7 TeV
Injection at 5 m (with collision tunes) Ramp & Squeeze to 6.5 TeV / 1 m (1250 s) Collisions without LHCb tilting (~100 s) Beta* levelling from 1 m
MOST AGGRESSIVE SCENARIO:
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
2010 2011 2012 2015 Most aggressive
Beam mode Theor Mean Theor Mean Theor Mean Theor Mean
INJPRO n.a.3 h
n.a. 2205 n.a.52 min
n.a.~3000 ~3000
INJPHYS n.a. n.a. 3034 n.a. n.a.
PRERAMP n.a. 504 n.a. 270 n.a. 259 n.a. ~250 ~250
RAMP 1400 1548 1020 1088 770 791 1250 1271 1250 1271
FLATTOP n.a. 468 n.a. 130 n.a. 377 n.a. ~375 ~375
SQUEEZE 1041 (3.5 m) 2016 548
(1 m) 846 925 996 1473 1544
ADJUST 108 792 56 654 220 513 270 563 100 393
RAMPDOWN 4000 2100 2100 4200 4200
TOT 4h29m 2h17m 1h41m 1h57m 1h28mTOT (with
rampdown) 5h36m 2h52m 2h16m 3h07m 2h38m
Cycle @(~)7 TeV
Unless differently specified, values are in seconds
29 min
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Cycle @(~)7 TeV
Thanks to FIDEL team
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Cycle @(~)7 TeV
Thanks to FIDEL team
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Conclusions 2012 commissioning was successful (first SB in 22 days!) – the
machine was very similar to 2011 On OP point of view we are approaching the limit time given by the
settings, but we still can improve (flatop, rampdown,…) Operation in 2012 was efficient and reproducible - despite the
longer settings, the cycle was in average 36 min faster than in 2011 (big gain at injection)
The OP cycle at 6.5 TeV would take ~51 min (37%) more time than at 4 TeV
This can be reduced (up to ~29 min - 15%) In order to properly prepare the 2015 operation we should converge
on a possible scenario by mid 2013 As baseline we propose to start with the same (type of) cycle as 4
TeV (well known!), then have a stop point around mid 2015 to steer the strategy
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
SPARE SLIDES
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (450 GeV)
0.47 mm
0.33 mm 0.36 mm
0.39 mm
Orbit of the flat machine was re-corrected, first against 2011 reference, then some absolute corrections were applied:
Orbit was found to be very similar to 2011 ref (0.2 - 0.3 mm rms difference)
Optics measurements and corrections @450 GeV Beta-beating down to 5-10% from 30-40%
Normalized H dispersion beat reduced from 0.04m1/2 to 0.01m1/2
B1 B2
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (optics)
Optics measurements and corrections @450 GeV Beta-beating down to 5-10% from 30-40%
Normalized H dispersion beat reduced from 0.04m1/2 to 0.01m1/2
B1 B2
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
SB & turnaround
MEAN = 6 h 34 min
MINIMUM = 2 h 8 min 24 s
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (squeeze)
Fill 2306 (Nov 2011) - r.m.s wrt first orbit (arc)
50 mm Ex: B1
After feed-forward
With parabolic round-off
The optimization can be further improved during LS1 to get less transient orbit spikes
100 mm
~120 mm
50 mm
Fill 2534
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Cycle at 4 TeV
Thanks to FIDEL team
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Commissioning (problems)
Glitch on the safe beam flag (noise on BCT2B giving values above the safe beam limit)
Intermittent interlock on BMPSA.4R6.B2 Vacuum gauge outgassing between Q6 and Q5.L5 Issue with generation of the functions for trim
quadrupoles (some points were too close after incorporation)
Problem with the bunch placement on the MKI waveform
FGC: A bug was found in the FCG software that ignored the real-
time correction Tweak on the current reference that was following the
measured current
LHC Beam Operation WS – Evian December 18th 2012 Matteo Solfaroli
Rampdown
W.Venturini
RQD.A56RQ4.R2
RQX.R5
4min max