Cx Sequence of Events ICE ActivitiesOAC Activities Cx RFP Response to RFPOwner issues Cx contract...

15
ICE ICE INTERNATIONAL COMMISSIONING ENGINEERS

Transcript of Cx Sequence of Events ICE ActivitiesOAC Activities Cx RFP Response to RFPOwner issues Cx contract...

ICEICEINTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities

Cx RFP

Response to RFP Owner issues Cx contract

Initialization Letter to Architect

Cx Sequence of Events

ICE Activities OAC Activities Issue "SD" documents

Review "SD" & issue comments

Response to Cx comments

Cx Sequence of Events

ICE Activities OAC Activities Issue “DD" documents including Cx comments

Review “DD" & issue comments

Response to Cx comments

Issue Preliminary Cx Plan

Cx Sequence of Events

ICE Activities OAC Activities Issue “CD" documents including Cx comments

Review “CD" & issue comments

Response to Cx comments

Issue construction documents

Cx Sequence of Events

ICE Activities OAC Activities Schedule Cx Kick-Off Meeting

Cx Kick-Off Meeting

Issue Meeting Minutes

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 30% MEP progress (2 weeks)

Perform 30% field inspection

Issue Action Items Response to Cx comments

Cx Sequence of Events

ICE Activities OAC Activities Preliminary O&M Manual w/ submittals

Issue Final Cx plan Response to Cx Plan

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 60% MEP progress (2 weeks)

Perform 60% field inspection

Issue Action Items Response to Cx comments

Cx Sequence of Events

ICE Activities OAC Activities

Equipment Start-up

Issue Equipment Start-up Verification

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 90% MEP progress (2 weeks)

Perform 90% field inspection

Issue Action Items Response to Cx comments

Cx Sequence of Events

ICE Activities OAC Activities

TAB Field Work

Controls Field Work

Issue TAB Deficiency List

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 100% MEP completion (2 weeks)

Begin FPT Support FPT effort

Issue Preliminary FPT Report

Response to FPT Report

Cx Sequence of Events

ICE Activities OAC Activities Finish FPT Support FPT effort

Issue FPT AIS Report Response to Cx AIS

Deficiencies remedied appropriately

Notify Cx of remedies

Cx Sequence of Events

ICE Activities OAC Activities Verify deficiency remediation

Issue Final Report Schedule 12 Month Warranty Inspection

Participate in 12 Month Warranty Inspection