CWA RESTROOM SANITARY PROJECT
Transcript of CWA RESTROOM SANITARY PROJECT
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
1/23
Sanitary Restroom Project:
College of West Africa
Monrovia, Liberia
RestroomsReconstruction/Renovation
College of West AfricaAlumni Association, USA
INC.
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
2/23
CWA Student RestroomInformation
The boys and girls restrooms at CWA aredeplorable. Students are leaving the main
campus to use alternative restrooms and returnto class.
As you will see from current photos attached, therestrooms are not conducive or safe for the
students or staff to use. More importantly, there
is no water source in the restrooms to flush thetoilets or for the students to wash their hands
after use unhygienic.
Unfortunately, the 2008 renovation of the school22
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
3/23
CWA RestroomInformation Cont
33
CWA-AA, USA Inc. (in collaboration withthe leadership of CWA), has retained a
local contractor in Monrovia to help withthis very special project.
A proposed draft of therenovation/reconstruction of the student
restrooms, the staff restroom, as well as acomprehensive estimate is attached.
CWA-AA, USA requires that this project be
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
4/23
Current photo of GirlsRestroom
44
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
5/23
Current Photos of BoysRestroom
55
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
6/23
Current Photo of BoysRestroom
66
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
7/23
Proposed Draft of GirlsRestroom
Click
toeditMast e
rtex
t styles
Secon
dlevel
Third
level
Four
th level
Fifthl e
vel
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
8/23
Restroom Water Solution
Click
toe
ditMast e
rtextstyles
Secon
dle
ve l
Third
level
Fourth
level
Fifthlevel
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
9/23
Proposed Draft of BoysRestroom
Click
toe
ditMast e
rtext sty
les
Secon
dle
vel
Third
level
Fourthlevel
Fifthlevel
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
10/23
Proposed Draft of StaffRestroom
Click
toeditMast e
rtext
styles
Secon
dlevel
Third
le
vel
Fourth
level
Fifth
l evel
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
11/23
Project Summary
1111
Description/Phases Total Costs
PH I Girls Restroom $5,192.50
PH III- Water Tower $1,899.50
PH III- Boys Restroom $4,142.00
PH IV- Staff Restroom $2,637.50
Total Project Cost $13,871.50
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
12/23
Girls Restroom Estimates
1212
Item QTY Unit Cost Total
PAINT BRUSHES 4 PCS $3.00 $12.00
PAINT ROLLERS 3 ROLLS $5.00 $15.00
THINNER 3 GALS $12.00 $36.00
WHITE OIL PAINT 66 GALS $14.50 $87.00
SAND LOAD 1 LD $200.00 $200.00
CEMENT 35 BAG $9.00 $315.00
2X2 FLOOR TILES 19 CTNS $20.00 $380.00
6X6 WALL TILES 86 CTNS $18.00 $1,548.00
ELECTRICAL TAPES 1 ROLL $5.00 $5.00
FLORACENT LAMPS 4 PCS $20.00 $80.00FACE BASIN 3 SETS $35.00 $105.00
1X2 TIMBER 35 PCS $1.50 $52.50
CABINET LOCKS 4 PCS $4.00 $16.00
Commode Set 6 SETS $65.00 $390.00
FAUCETS 3 SETS $5.00 $15.00
FORMICAL GLUE 1 GAL $15.00 $15.00
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
13/23
Girls Restroom EstimatesCont
1313
Item QTY Unit Cost Total
HINGIES 10 PKS $3.00 $30.00
LOCKS 1 PC $20.00 $20.00
MIRRORS 5 SHT $10.00 $50.00
PLYWOOD 1/2 2 SHT $22.50 $45.00
PLYWOOD 5/8 1 SHT $24.00 $24.00
PVC ELBOW 2" 4 PCS $3.50 $14.00
PVC GLUE 2 PKS $5.00 $10.00
PVC PIPES - 1" 3 PCS $5.00 $15.00
PVC PIPES - 2" 2 PCS $10.00 $20.00
PVC TEE - 2" 5 PCS $3.50 $17.50
SAND PAPER 25 PCS $0.50 $12.50
SCREEN WIRE 1 ROLL $18.00 $18.00
SCREWS 2 PKS $5.00 $10.00
STAPLE 6 PCS $3.00 $18.00
STEEL NAILS 4 PKS $3.50 $14.00
TISSUE HOLDER 6 SETS $5.00 $30.00
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
14/23
Final GirlsRestroomEstimate
1414
Item QTY Unit Cost Total
WHITE CEMENT 2 BAGS $15.00 $30.00
WIRE NAILS (ASSORTED) 1 CTNS $30.00 $30.00
WOOD GLUE 1 QRT $13.00 $13.00
MATERIAL TOTAL $3,692.50
TRANSPORTATION $100.00
LABOR COST $1,400.00
GRAND TOTAL $5, 192.50
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
15/23
Boys Restroom Estimates
1515
Item QTY Unit Cost TotalCOMODE 4 SETS $65.00 $260.00
FACE BASIN 2 SETS $35.00 $70.00
PVC PIPES - 2" 3 PCS $10.00 $30.00
PVC TEE - 2" 5 PCS $3.50 $17.50
PVC ELBOW - 2" 4 PCS $3.50 $14.00
PVC GLUE 1 QRT $5.00 $5.00
URINER BOLT 3 SETS $35.00 $105.00PVC PIPE - 1" 3 PCS $5.00 $15.00
PVC ELBOW - 1" 5 PCS $1.50 $7.50
PVC TEE - 1" 5 PCS $1.50 $7.50
CLAMPS 2 PKS $5.00 $10.00
PLYWOOD 5/8 4 PCS $24.00 $96.00
PLYWOOD 1/2 2 PCS $22.00 $44.00
PLYWOOD 1/4 - DOORS 15 PCS $13.00 $195.00
HANDLES 9 PCS $2.00 $18.00
HINGIES 12 PCS $2.00 $24.00
1X2X14 DRESSED 20 PCS $1.50 $30.00
WOOD GLUE
1 GAL $12.00 $12.00
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
16/23
Final Boys RestroomEstimates
1616
Item QTY Unit Cost Total
2X2X12 WALL TILES 20 CNTS $20.00 $400.00
6X6 FLOOR TILES 68 CNTS $18.00 $1,224.00
CEMENT 25 BAGS $9.00 $225.00
SAND 15 BAGS $3.00 $45.00
WHITE CEMENT 2 BAGS $15.00 $30.00
WHITE OIL PAINT 3 GALS $14.50 $43.50THINNER 2 GALS $12.00 $24.00
STAPLE 4 PCS $3.00 $12.00
LOCKS 1 PC $20.00 $20.00
CARBINET LOCK 8 PCS $3.00 $24.00
WHITE LATEX 2 GALS $7.00 $14.00
MIRRORS 3 SHTS $10.00 $30.00
FORMICAL GLUE 1 GAL $15.00 $15.00
MATERIAL TOTAL $3,067.00
TRANSPORTATION $75.00
LABOR COST $1,000.00
GRAND TOTAL $4,142.00
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
17/23
Staff Restroom Estimates
1717
Item QTY Unit Cost Total
COMMODE 3 SETS $65.00 $195.00
FACE SASIN 3 SETS $35.00 $105.00
PVC PIPE - 2" 1 PCS $10.00 $10.00
PVC ELBOW - 2" 3 PCS $3.50 $10.50
PVC TEE - 2" 3 PCS $3.50 $10.50
PVC GLUE 1 QRT $5.00 $5.00
PVC PIPE - 1" 1 PC $5.00 $5.00
PVC ELBOW - 1" 3 PCS $1.50 $4.50
PVC TEE - 1" 3 PCS $1.50 $4.50
2' X 2' FLOOR TILES 12 CNTS $20.00 $240.00
6" X 6" WALL TILES 48 CNTS $18.00 $864.00
CEMENT 20 BAGS $9.00 $180.00
WHITE CEMENT 1 BAG $15.00 $15.00
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
18/23
Final Staff RestroomEstimate
1818
Item QTY Unit Cost Total
SAND 15 BAGS $3.00 $45.00
FLOURACENT LAMP 4 SETS $20.00 $80.00
WIRE #10 1 ROLL $65.00 $65.00
WHITE OIL PAINT 2 GALS $14.50 $29.00
WHITE LATEX PAINT 2 GALS $7.00 $14.00
CLAMPS 1 PC $5.00 $5.00
PLYWOOD 5/8 2 SHTS $24.00 $48.00
PLYWOOD 1/2 1 SHTS $22.50 $22.50
MIRRORS 4 SHTS $10.00 $40.00
MATERIAL TOTAL $1,997.50
TRANSPORTATION $40.00
LABOR COST $600.00
GRAND TOTAL $2,637.50
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
19/23
Water Solution TowerEstimate
1919
Item QTY Unit Cost TotalPolytank 1 tank $600.00 $600.00
PVC PIPE 4" 1 PC $10.00 $10.00
PVC ELBOW 4'' 3 PC $3.50 $10.50
PVC VALE 1 PC $10.00 $10.00
PVC GLUE 1 QRT $5.00 $5.00
$635.50
WELDING
ANGLE BAR 3 PCS $65.00 $195.00
WELDING ROD 1 PK $8.00 $8.00
CUTTING DIS 2 PCS $6.00 $12.00
RUST PAINT 1 GAL $14.50 $14.50
CEMENT BAG 2 BAGS $9.00 $18.00
CRUSHED ROCKS 3 BAGS $10.00 $30.00
WAWA PLANKS 1 PC $5.00 $5.00
STEEL ROD 1/4 " 1 PC $13.00 $13.00
TILEWIRE 1 ROLL $5.00 $5.00
THINNER 1 GAL $11.00 $11.00
$311.50
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
20/23
Final Water SolutionEstimate
2020
Item QTY Unit Cost Total
WATER LINES
1" PVC PIPE 20 PCS $5.00 $100.00
1" PVC TEE 30 PCS $2.00 $60.00
1" PVC ELBOW 20 PCS $2.00 $40.00
1" PVC CONNECTOR 15 PCS $3.00 $45.00
1" VALVES 30 PCS $6.00 $180.00
1" CLAMPS 15 PKS $5.00 $75.00
1" STEEL NAILS 15 PKS $3.50 $52.50
PVC GLUE 5 QRTS $5.00 $25.00
$577.50
MATERIAL TOTAL $1,524.50
TRANSPORTATAION $25.00
LABOR COST $350.00
GRAND TOTAL $1,899.50
GRAND TOTAL OF PROJECT
$13,871.50
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
21/23
Class/Family/ IndividualContribution
It is often said, an educated child begins with a healthy child.
After many years of usage, this is what the restrooms at CWA looklike. A typical reaction from an American child would be, Yikes!
Id rather pee in my pants, before I use that restroom.
We have embarked on this restroom restoration project to provideCWA students a healthy/sanitary learning environment.
2121
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
22/23
-
8/8/2019 CWA RESTROOM SANITARY PROJECT
23/23
Thank You!
23
23
Please do not hesitate to inform us of your classactivities. Publicity is available via the Associations
website, Facebook page, and Public Affairs.
Remember: Before you reinvent the wheels in giving toCWA, the Association already works 24/7 to assess theneeds of CWA and find the best (specialized) ways to
meet those needs.
CWA-AA, USA thanks you for your support!