    Sanitary Restroom Project:

    College of West Africa

    Monrovia, Liberia

    RestroomsReconstruction/Renovation

    College of West AfricaAlumni Association, USA

    INC.

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    2/23

    CWA Student RestroomInformation

    The boys and girls restrooms at CWA aredeplorable. Students are leaving the main

    campus to use alternative restrooms and returnto class.

    As you will see from current photos attached, therestrooms are not conducive or safe for the

    students or staff to use. More importantly, there

    is no water source in the restrooms to flush thetoilets or for the students to wash their hands

    after use unhygienic.

    Unfortunately, the 2008 renovation of the school22

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    3/23

    CWA RestroomInformation Cont

    33

    CWA-AA, USA Inc. (in collaboration withthe leadership of CWA), has retained a

    local contractor in Monrovia to help withthis very special project.

    A proposed draft of therenovation/reconstruction of the student

    restrooms, the staff restroom, as well as acomprehensive estimate is attached.

    CWA-AA, USA requires that this project be

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    4/23

    Current photo of GirlsRestroom

    44

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    5/23

    Current Photos of BoysRestroom

    55

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    6/23

    Current Photo of BoysRestroom

    66

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    7/23

    Proposed Draft of GirlsRestroom

    Click

    toeditMast e

    rtex

    t styles

    Secon

    dlevel

    Third

    level

    Four

    th level

    Fifthl e

    vel

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    8/23

    Restroom Water Solution

    Click

    toe

    ditMast e

    rtextstyles

    Secon

    dle

    ve l

    Third

    level

    Fourth

    level

    Fifthlevel

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    9/23

    Proposed Draft of BoysRestroom

    Click

    toe

    ditMast e

    rtext sty

    les

    Secon

    dle

    vel

    Third

    level

    Fourthlevel

    Fifthlevel

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    10/23

    Proposed Draft of StaffRestroom

    Click

    toeditMast e

    rtext

    styles

    Secon

    dlevel

    Third

    le

    vel

    Fourth

    level

    Fifth

    l evel

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    11/23

    Project Summary

    1111

    Description/Phases Total Costs

    PH I Girls Restroom $5,192.50

    PH III- Water Tower $1,899.50

    PH III- Boys Restroom $4,142.00

    PH IV- Staff Restroom $2,637.50

    Total Project Cost $13,871.50

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    12/23

    Girls Restroom Estimates

    1212

    Item QTY Unit Cost Total

    PAINT BRUSHES 4 PCS $3.00 $12.00

    PAINT ROLLERS 3 ROLLS $5.00 $15.00

    THINNER 3 GALS $12.00 $36.00

    WHITE OIL PAINT 66 GALS $14.50 $87.00

    SAND LOAD 1 LD $200.00 $200.00

    CEMENT 35 BAG $9.00 $315.00

    2X2 FLOOR TILES 19 CTNS $20.00 $380.00

    6X6 WALL TILES 86 CTNS $18.00 $1,548.00

    ELECTRICAL TAPES 1 ROLL $5.00 $5.00

    FLORACENT LAMPS 4 PCS $20.00 $80.00FACE BASIN 3 SETS $35.00 $105.00

    1X2 TIMBER 35 PCS $1.50 $52.50

    CABINET LOCKS 4 PCS $4.00 $16.00

    Commode Set 6 SETS $65.00 $390.00

    FAUCETS 3 SETS $5.00 $15.00

    FORMICAL GLUE 1 GAL $15.00 $15.00

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    13/23

    Girls Restroom EstimatesCont

    1313

    Item QTY Unit Cost Total

    HINGIES 10 PKS $3.00 $30.00

    LOCKS 1 PC $20.00 $20.00

    MIRRORS 5 SHT $10.00 $50.00

    PLYWOOD 1/2 2 SHT $22.50 $45.00

    PLYWOOD 5/8 1 SHT $24.00 $24.00

    PVC ELBOW 2" 4 PCS $3.50 $14.00

    PVC GLUE 2 PKS $5.00 $10.00

    PVC PIPES - 1" 3 PCS $5.00 $15.00

    PVC PIPES - 2" 2 PCS $10.00 $20.00

    PVC TEE - 2" 5 PCS $3.50 $17.50

    SAND PAPER 25 PCS $0.50 $12.50

    SCREEN WIRE 1 ROLL $18.00 $18.00

    SCREWS 2 PKS $5.00 $10.00

    STAPLE 6 PCS $3.00 $18.00

    STEEL NAILS 4 PKS $3.50 $14.00

    TISSUE HOLDER 6 SETS $5.00 $30.00

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    14/23

    Final GirlsRestroomEstimate

    1414

    Item QTY Unit Cost Total

    WHITE CEMENT 2 BAGS $15.00 $30.00

    WIRE NAILS (ASSORTED) 1 CTNS $30.00 $30.00

    WOOD GLUE 1 QRT $13.00 $13.00

    MATERIAL TOTAL $3,692.50

    TRANSPORTATION $100.00

    LABOR COST $1,400.00

    GRAND TOTAL $5, 192.50

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    15/23

    Boys Restroom Estimates

    1515

    Item QTY Unit Cost TotalCOMODE 4 SETS $65.00 $260.00

    FACE BASIN 2 SETS $35.00 $70.00

    PVC PIPES - 2" 3 PCS $10.00 $30.00

    PVC TEE - 2" 5 PCS $3.50 $17.50

    PVC ELBOW - 2" 4 PCS $3.50 $14.00

    PVC GLUE 1 QRT $5.00 $5.00

    URINER BOLT 3 SETS $35.00 $105.00PVC PIPE - 1" 3 PCS $5.00 $15.00

    PVC ELBOW - 1" 5 PCS $1.50 $7.50

    PVC TEE - 1" 5 PCS $1.50 $7.50

    CLAMPS 2 PKS $5.00 $10.00

    PLYWOOD 5/8 4 PCS $24.00 $96.00

    PLYWOOD 1/2 2 PCS $22.00 $44.00

    PLYWOOD 1/4 - DOORS 15 PCS $13.00 $195.00

    HANDLES 9 PCS $2.00 $18.00

    HINGIES 12 PCS $2.00 $24.00

    1X2X14 DRESSED 20 PCS $1.50 $30.00

    WOOD GLUE

    1 GAL $12.00 $12.00

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    16/23

    Final Boys RestroomEstimates

    1616

    Item QTY Unit Cost Total

    2X2X12 WALL TILES 20 CNTS $20.00 $400.00

    6X6 FLOOR TILES 68 CNTS $18.00 $1,224.00

    CEMENT 25 BAGS $9.00 $225.00

    SAND 15 BAGS $3.00 $45.00

    WHITE CEMENT 2 BAGS $15.00 $30.00

    WHITE OIL PAINT 3 GALS $14.50 $43.50THINNER 2 GALS $12.00 $24.00

    STAPLE 4 PCS $3.00 $12.00

    LOCKS 1 PC $20.00 $20.00

    CARBINET LOCK 8 PCS $3.00 $24.00

    WHITE LATEX 2 GALS $7.00 $14.00

    MIRRORS 3 SHTS $10.00 $30.00

    FORMICAL GLUE 1 GAL $15.00 $15.00

    MATERIAL TOTAL $3,067.00

    TRANSPORTATION $75.00

    LABOR COST $1,000.00

    GRAND TOTAL $4,142.00

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    17/23

    Staff Restroom Estimates

    1717

    Item QTY Unit Cost Total

    COMMODE 3 SETS $65.00 $195.00

    FACE SASIN 3 SETS $35.00 $105.00

    PVC PIPE - 2" 1 PCS $10.00 $10.00

    PVC ELBOW - 2" 3 PCS $3.50 $10.50

    PVC TEE - 2" 3 PCS $3.50 $10.50

    PVC GLUE 1 QRT $5.00 $5.00

    PVC PIPE - 1" 1 PC $5.00 $5.00

    PVC ELBOW - 1" 3 PCS $1.50 $4.50

    PVC TEE - 1" 3 PCS $1.50 $4.50

    2' X 2' FLOOR TILES 12 CNTS $20.00 $240.00

    6" X 6" WALL TILES 48 CNTS $18.00 $864.00

    CEMENT 20 BAGS $9.00 $180.00

    WHITE CEMENT 1 BAG $15.00 $15.00

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    18/23

    Final Staff RestroomEstimate

    1818

    Item QTY Unit Cost Total

    SAND 15 BAGS $3.00 $45.00

    FLOURACENT LAMP 4 SETS $20.00 $80.00

    WIRE #10 1 ROLL $65.00 $65.00

    WHITE OIL PAINT 2 GALS $14.50 $29.00

    WHITE LATEX PAINT 2 GALS $7.00 $14.00

    CLAMPS 1 PC $5.00 $5.00

    PLYWOOD 5/8 2 SHTS $24.00 $48.00

    PLYWOOD 1/2 1 SHTS $22.50 $22.50

    MIRRORS 4 SHTS $10.00 $40.00

    MATERIAL TOTAL $1,997.50

    TRANSPORTATION $40.00

    LABOR COST $600.00

    GRAND TOTAL $2,637.50

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    19/23

    Water Solution TowerEstimate

    1919

    Item QTY Unit Cost TotalPolytank 1 tank $600.00 $600.00

    PVC PIPE 4" 1 PC $10.00 $10.00

    PVC ELBOW 4'' 3 PC $3.50 $10.50

    PVC VALE 1 PC $10.00 $10.00

    PVC GLUE 1 QRT $5.00 $5.00

    $635.50

    WELDING

    ANGLE BAR 3 PCS $65.00 $195.00

    WELDING ROD 1 PK $8.00 $8.00

    CUTTING DIS 2 PCS $6.00 $12.00

    RUST PAINT 1 GAL $14.50 $14.50

    CEMENT BAG 2 BAGS $9.00 $18.00

    CRUSHED ROCKS 3 BAGS $10.00 $30.00

    WAWA PLANKS 1 PC $5.00 $5.00

    STEEL ROD 1/4 " 1 PC $13.00 $13.00

    TILEWIRE 1 ROLL $5.00 $5.00

    THINNER 1 GAL $11.00 $11.00

    $311.50

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    20/23

    Final Water SolutionEstimate

    2020

    Item QTY Unit Cost Total

    WATER LINES

    1" PVC PIPE 20 PCS $5.00 $100.00

    1" PVC TEE 30 PCS $2.00 $60.00

    1" PVC ELBOW 20 PCS $2.00 $40.00

    1" PVC CONNECTOR 15 PCS $3.00 $45.00

    1" VALVES 30 PCS $6.00 $180.00

    1" CLAMPS 15 PKS $5.00 $75.00

    1" STEEL NAILS 15 PKS $3.50 $52.50

    PVC GLUE 5 QRTS $5.00 $25.00

    $577.50

    MATERIAL TOTAL $1,524.50

    TRANSPORTATAION $25.00

    LABOR COST $350.00

    GRAND TOTAL $1,899.50

    GRAND TOTAL OF PROJECT

    $13,871.50

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    21/23

    Class/Family/ IndividualContribution

    It is often said, an educated child begins with a healthy child.

    After many years of usage, this is what the restrooms at CWA looklike. A typical reaction from an American child would be, Yikes!

    Id rather pee in my pants, before I use that restroom.

    We have embarked on this restroom restoration project to provideCWA students a healthy/sanitary learning environment.

    2121

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    22/23

  • 8/8/2019 CWA RESTROOM SANITARY PROJECT

    23/23

    Thank You!

    23

    23

    Please do not hesitate to inform us of your classactivities. Publicity is available via the Associations

    website, Facebook page, and Public Affairs.

    Remember: Before you reinvent the wheels in giving toCWA, the Association already works 24/7 to assess theneeds of CWA and find the best (specialized) ways to

    meet those needs.

    CWA-AA, USA thanks you for your support!