Crossrail Line 1 Assessment of Lighting Impacts: Technical...
Transcript of Crossrail Line 1 Assessment of Lighting Impacts: Technical...
Crossrail Line 1Assessment of Lighting Impacts: Technical Report
Crossrail Line 1 Assessment of Lighting Impacts Technical Report Volume 2 of 2 1E0324-G0E00-00001
O
O
C
O
O
O
O
O
B
L
L
L
3
O
O
C
O
O
O OCB
5
O
O
O
O
O
C
O
O
B
L
L
4
O
O
B
L
L
L
2
O
O
O
O
O
C
O
O
B
L
L
M
1
Receptors Location
Other
B - Baseline C - Construction O - Operation Site Activity
Criteria + Magnitude
Workplace
ResidentialC - CriticalH - High M - ModerateL - Low
Receptor Group + Sensitivity
Other
Built Environment
Ecological
Dark Landscape
Astronomers
Pedestrian
Vehicular
Dim
Neutral
Security
Exterior Amenity
Exterior Vehicular/Pedestrian
Exterior Emergency
Exterior Workplace
BrightPerceived Brightness+ Impact
Interior WorkplaceN - Normal Working E - Extended Daytime A - Dusk Till 12.30am O - Dusk Till DawnI - Infrequent/TestingU - Unlit
Illumination Function+ Operational Hours
Site DescriptionAn extensive railway facility adjacent to the Grand Union Canal and Willesden Junction stations, comprising Diesel Electric Locomotive Depot, Maintenance and carriage sheds and turntable.Key Receptors:1. Residents of Old Oak Common Lane.2. Commercial Properties on Old Oak Common Lane.3. Commercial & Industrial Properties on Hythe Road &
Hogarth Industrial Estate.4. Traffic on Old Oak Common Lane.Lighting SchemeThe depot is illuminated with a mixture of high mast lighting, floodlights on located gantries and within carriage and maintenance sheds. Local street lighting comprises flat glass high-pressure sodium luminaire mounted on 10-12 metre high columns.
W3Route WindowOld Oak Common StablingSite
E3Environmental ZoneOld Oak Common DepotLocation
Baseline Scoping
Design Proposals and Scoping Assessment Pro-formaSite Location
N/AN/AEngineering Information provided by Crossrail
N/A
Revision
N/A
Date
Relevant Parliamentary Plan Sheets
Reference Documents
Proposals Assessment
CR - Rain M - Mist O - Overcast C - ClearClimatic Conditions
W3-1 to W3-30 inclusivePhotographic Record
07.10.04DateKeith Miller and Efren CartasPersonnel
Assessment
Site DescriptionWork comprises the provision of fourteen new stabling sidings within the depot, and also one further siding with a train washing facility. A staff accommodation building will be constructed.
Lighting SchemeThe Construction Planning Report states that:“…The works will continue during the winter months and general site lighting together with task specific lighting will be required from approximately November to February during the early morning and late afternoon periods. Temporary lighting will be required during all the possessions noted in the possession requirements. This will be directed towards the areas of work.”
Construction Design Proposals: Scheme description + Site Diagram
Site DescriptionFrom the lighting receptor’s point of view, outside the boundaries of the site, it is anticipated that the Depot will revert to the baseline condition.
Lighting SchemeThe Construction Planning Report states that:“…Additional permanent lighting may be required covering the access roads, pathways, accommodation, parking areas, stabling areas and ground frames for manual operation of entrance connections. This works will be identified by others.”
Baseline Installation Proposals: Scheme description + Site Diagram
Operation Design Proposals: Scheme description + Site Diagram
Old Oak Common Stabling
41
1
2
3
3
3
41
1
2
3
3
3
41
1
2
3
3
3
Site Boundary
Crossrail Line 1Assessment of Lighting Impacts: Technical Report
Crossrail Line 1 Assessment of Lighting Impacts Technical Report Volume 2 of 2 1E0324-G0E00-00001
Scoping and Proposals Analysis Pro-forma Site Location
L
L
L
3 5
L
L
4
L
L
L
2
L
L
M
1
Receptors LocationCriteria + Magnitude
Workplace
ResidentialC - CriticalH - High M - ModerateL - Low
Receptor Group + Sensitivity
Other
Built Environment
Ecological
Dark Landscape
Astronomers
Pedestrian
Vehicular
OCOCOCOCOCSite Activity Compared to Baseline C - Construction O - Operation
Construction Mitigation
IIIIIIIIIdentify Significance ( I ) of Impact or Proceed with Analysis ( A )
P+ PARTICULARLY SIGNIFICANT POSITIVES+ SIGNIFICANT POSITIVENS NOT SIGNIFICANTS- SIGNIFICANT NEGATIVEP- PARTICULARLY SIGNIFICANT NEGATIVE
Residual Impact
Secondary Mitigation
Primary Mitigation
CCCCCCCCConclude Assessment ( C ) orIdentify Mitigation ( M )
Action
Identify Significance ( I ) of Impact orProceed with Analysis ( A )
Action
NSNSNSNSNSNSNSNSP+ PARTICULARLY SIGNIFICANT POSITIVES+ SIGNIFICANT POSITIVENS NOT SIGNIFICANTS- SIGNIFICANT NEGATIVEP- PARTICULARLY SIGNIFICANT NEGATIVE
Significance of ImpactReceptor Sensitivity
N - NEGLIGIBLEM - MODERATE ADVERSES - SUBSTANTIAL ADVERSE
Potential ImpactDuration of Change
Action
N N N NNNNN
Conclude Assessment ( C ) orInstigate Detailed Assessment ( D)
Result
B - BENEFICIALN - NEGLIGIBLEM - MODERATE ADVERSES - SUBSTANTIAL ADVERSE
Magnitude of ChangeBrightness Comparison
AnalysisW3Route WindowOld Oak Common StablingSite
E3Environmental ZoneOld Oak Common DepotLocation
Crossrail Line 1Assessment of Lighting Impacts: Technical Report
Crossrail Line 1 Assessment of Lighting Impacts Technical Report Volume 2 of 2 1E0324-G0E00-00001
W3Route WindowOld Oak Common StablingSite
E3Environmental ZoneOld Oak Common DepotLocation
Design Proposals and Scoping Assessment Pro-formaSite Location
W3-1
W3-11
W3-6
W3-2 W3-3 W3-4 W3-5
W3-7 W3-8 W3-9 W3-10
W3-12 W3-13 W3-14 W3-15
Crossrail Line 1Assessment of Lighting Impacts: Technical Report
Crossrail Line 1 Assessment of Lighting Impacts Technical Report Volume 2 of 2 1E0324-G0E00-00001
W3Route WindowOld Oak Common StablingSite
E3Environmental ZoneOld Oak Common DepotLocation
Design Proposals and Scoping Assessment Pro-formaSite Location
W3-16
W3-26
W3-21
W3-17 W3-18 W3-19 W3-20
W3-22 W3-23 W3-24 W3-25
W3-27 W3-28 W3-29 W3-30