Croda DC Power Plants for Telecom and Data 0910056a805a0b...¾Charger sizing CSI Telecommunications...
Transcript of Croda DC Power Plants for Telecom and Data 0910056a805a0b...¾Charger sizing CSI Telecommunications...
1
DC Power Plants for Telecommunications and Data
Thomas G. CrodaPrincipal Engineer
Presented toPresented to
INFOBATT INFOBATT 20052005
CSI Telecommunication
Engineers
CSI Telecommunications Engineers 2
IntroductionEngineering RequirementsApplicable Standards
CSI Telecommunications Engineers 3
Engineering Considerations
Equipment to be PoweredRequired Reserve TimeMinimum Operating VoltageSize of the Facility
CSI Telecommunications Engineers 4
Plant Size and Design
Load current
Voltage operating range
Required reserve time
Recharge time
Battery sizing
Rundown problems
Allowable plant voltage drop
Grounded (+) conductor
CSI Telecommunications Engineers 5
2000 - 25,000 Amp DC Power PlantDual Level Distribution
BatteryString #11300 AH
1
2
11 12
23
24
BatteryString #N1300 AH
1
2
11 12
23
24
800 AmpBatteryCharger
#1
+ +
Shunt-48 VDC
Return
480 VAC3 Phase
480 VAC3 Phase
PrimaryPower Bay
600 AFuses
12
14
800 AmpBatteryCharger
#N
SecondaryPower Bay
“A” Power
“B” Power
Return
To EquipmentBays
CSI Telecommunications Engineers 6
Load Current
At float voltage
At end of discharge
CSI Telecommunications Engineers 7
Voltage Operating Range
See T1.315 for new equipment (40-57 VDC)
Check specific equipment for its operating range
Float voltage
End of discharge voltage
Equalize voltage
CSI Telecommunications Engineers 8
Required Reserve Time
Regulatory requirementsReliability requirementsEconomic issues
CSI Telecommunications Engineers 9
Recharge Time
Reliability RequirementsRundown ProblemCharger sizing
CSI Telecommunications Engineers 10
Rundown Problem
The problem of more load than the chargers will supportWhat happens with a 1000 Amp load at 54 VDC?Since the entire load is "constant power" the load at 40 VDC is: 54 * 1000 / 40 = 1350 AmpsThe MINIMUM amount of chargers must exceed 1350A.
CSI Telecommunications Engineers 11
Plant Type
Single or Dual Level Distribution ArchitectureSmall plants use single level distributionLarge plants use dual level distribution
CSI Telecommunications Engineers 12
DC Power – Single Point Ground
Minimal current in frameworkBalanced distribution to cancel fields
CSI Telecommunications Engineers 13
Applicable Standards
T1.311 DC Power Systems –Telecommunications Environment Protection T1.315 Voltage Levels for DC-Powered Equipment in the Telecommunications EnvironmentNFPA 70 National Electrical CodeApplicable Local Standards
CSI Telecommunications Engineers 14
Allowable Plant Voltage Drop
2 volts - battery to load0.25 volts - between battery and primary distribution1.0 volt - between primary and secondary distribution0.5 volts - between secondary distribution and load bay0.25 volts - allocated for fuse, circuit breaker, and shunt loss Other allocations are possible
CSI Telecommunications Engineers 15
Battery Sizing Considerations
Average Discharge CurrentAverage Discharge Voltage used for calculating Average Discharge Current45 VDC is a good value (42-48)/2=45VDCIf the load is 1000 ADC at Float (54 VDC), the load at 45 VDC is 1000*54/45 = 1200 ADCUSE THIS VALUE TO SIZE YOUR BATTERY
CSI Telecommunications Engineers 16
Battery DisconnectNot generally used in the telecom industry.If used, it should be 2-pole to completely isolate the battery.Each string should have a separate disconnect so one failure will not fail the plant.
CSI Telecommunications Engineers 17
CSI Telecommunications Engineers 18
CSI Telecommunications Engineers 19
CSI Telecommunications Engineers 20
CSI Telecommunications Engineers 21
CSI Telecommunications Engineers 22
CSI Telecommunications Engineers 23
CSI Telecommunications Engineers 24
CSI Telecommunications Engineers 25
Questions?