“Critical Chain” Project Management

27
“Critical Chain” Project Management Presentation for KCMPUG March 19, 2003 Dave Higgins Consulting, Inc. Website: www.davehigginsconsulting.com Email: [email protected]

description

“Critical Chain” Project Management. Presentation for KCMPUG March 19, 2003. Dave Higgins Consulting, Inc. Website: www.davehigginsconsulting.com Email: [email protected]. Dave Higgins. - PowerPoint PPT Presentation

Transcript of “Critical Chain” Project Management

Page 1: “Critical Chain” Project Management

“Critical Chain” Project Management

Presentation for KCMPUGMarch 19, 2003

Dave Higgins Consulting, Inc.Website: www.davehigginsconsulting.comEmail: [email protected]

Page 2: “Critical Chain” Project Management

Dave HigginsDave Higgins has been a student of systems development and improvement methods for nearly 30 years. Together with Ken Orr (of The Ken Orr Institute) and the late Jean-Dominique Warnier, Dave was one of the principal architects of the Warnier/Orr systems development methodology back in the 1980’s. During the course of his career he has performed hundreds of seminars on various topics from program design and modification, to systems and data base design, to requirements definition, to planning and project management. Dave has written five books on various aspects of software development and is the author of numerous articles and white papers. His first book, published in 1979, was one of the first on developing quality software for personal computers, and was translated into over a dozen languages. In recent years, Dave has focused on the strategic uses of technology to improve business processes, specializing in business process reengineering, strategic planning, data warehousing and knowledge management. Recent projects include the reengineering of document scanning and records retention systems for a big-three auto maker, and developing an electronic publication strategy for a national engineering standards organization.

Page 3: “Critical Chain” Project Management

CCPM Research… Article on CCPM for Cutter

Consortium

Page 4: “Critical Chain” Project Management

Origins of CCPM Eliyahu Goldratt, Israeli physicist &

PhD The Goal, 1984 Theory of Constraints, 1990 The Critical Chain, 1997

Website: www.goldratt.com

Page 5: “Critical Chain” Project Management

Theory of Constraints Identify the system’s constraints Decide how to exploit the system’s

constraints Subordinate and synchronize everything

else to the above decisions Elevate the performance of the

system’s constraints, If any of the above steps shift the

constraints, go back to step 1

Page 6: “Critical Chain” Project Management

CCPM Key Objectives Develop a realistic plan Develop a reliable plan Keep it simple Show the Critical Chain Minimize Schedule Change Optimize Globally, Minimize work-in-process and

multitasking

Page 7: “Critical Chain” Project Management

Developing the CCPM Schedule

Create the initial plan Level the resources Determine the Critical Chain, Add buffers to the schedule

Page 8: “Critical Chain” Project Management

What’s A Critical Chain?

Consider a “vanilla” project plan…

Page 9: “Critical Chain” Project Management

What’s A Critical Chain?

We all know about the critical path…

Page 10: “Critical Chain” Project Management

What’s A Critical Chain?

First, resource contention is ID’d…

R2 R1 R3 R4

R1 R2

R4 R1

Page 11: “Critical Chain” Project Management

What’s A Critical Chain?

Identify the critical chain…

R2 R1 R3 R4

R1 R2

R4 R1

Page 12: “Critical Chain” Project Management

What’s A Critical Chain?

Add buffers to the schedule…

R2 R1 R3 R4

R1 R2

R4 R1

Feeding Buffers

Project Buffer

Page 13: “Critical Chain” Project Management

What’s A Critical Chain?

The Critical Chain Project Schedule…

R2 R1 R3 R4

R1 R2

R4 R1

Customer Commitment Date

Project Start Date

Page 14: “Critical Chain” Project Management

What’s A Critical Chain?

The Critical Chain Project Schedule…

R2 R1 R3 R4

R1 R2

R4 R1

Customer Commitment Date

Project Start Date

Page 15: “Critical Chain” Project Management

And the advantage is?

R2 R1 R3 R4

R1 R2

R4 R1

R2 R1 R3 R4

R1 R2

R4 R1

Original Plan

CCPM Plan

Page 16: “Critical Chain” Project Management

And the advantage is?

R2 R1 R3 R4

R1 R2

R4 R1

R2 R1 R3 R4

R1 R2

R4 R1

Original Plan

CCPM Plan

Page 17: “Critical Chain” Project Management

The question becomes… If CCPM is better, why isn’t

everyone doing it? Projects will be shorter Projects will be easier to manage, Projects will be more successful

Page 18: “Critical Chain” Project Management

CCPM Assumptions Tasks are estimated at 50% vs.

90% Resource contention is eliminated Buffers are easier to manage Multitasking is minimized Projects are staggered, Time is money

Page 19: “Critical Chain” Project Management

Project facts of life

Time

Reso

urc

e

Scope

After Larry Putnam,www.qsm.com

Page 20: “Critical Chain” Project Management

Project facts of life

Time

Reso

urc

e

Scope

Smaller Project

Bigger Project

Page 21: “Critical Chain” Project Management

Project facts of life

Time

Reso

urc

e

Scope

When resource is fixed…

time can vary.

Page 22: “Critical Chain” Project Management

Project facts of life

Time

Reso

urc

e

Scope

When time is fixed…

resource can vary.

Page 23: “Critical Chain” Project Management

Project facts of life

Time

Reso

urc

e

Scope

When time & resource are fixed…

scope can vary.

Page 24: “Critical Chain” Project Management

Project facts of life

Time

Reso

urc

e

Scope

When time, resource and scope are fixed…

Oopsie!

Page 25: “Critical Chain” Project Management

Project facts of life and CCPM

Time

Reso

urc

e

Scope

If projects get shorter…don’t costs increase?

Page 26: “Critical Chain” Project Management

Self-fulfilling prophecy? Only progressive organizations

have generally tried it Requires a commitment from

management to change Scheduling Multitasking

Begging the question: How much is CCPM?

Page 27: “Critical Chain” Project Management

Conclusion Some good ideas Not a radical departure If you try it, you’ll probably have

some success… If you work at an organization that

will let you try it, you’ll probably have success even if you don’t.