Critical Analysis Project
-
Upload
zachary-hicks -
Category
Documents
-
view
99 -
download
1
Transcript of Critical Analysis Project
MEMORANDUM TO: Matthew O’Malley
DATE: March 31, 2015
FROM: Zachary Hicks
SUBJECT: Critical Analysis Project
Project Information
Developer Thomas Kaufman of United Therapeutics Corporation is renovating a historic
townhouse rezoned as an office building located at 1733-1735 Connecticut Avenue NW in
Washington, DC for Owner United Therapeutics Corporation. The site visit and interview were
both conducted on March 26, 2015. The General Contractor is Project Manager Jerry Cripps,
and the Architect is Dan Gulbins of Philadelphia-based Ewing Cole. Ewing Cole has their own
mechanical, electrical, and plumbing design teams that worked on this project. Ewing Cole’s
credentials include being the Architect for MetLife Stadium in East Rutherford, NJ and Lincoln
Financial Field in Philadelphia.
Base Building Improvements
Both buildings will be getting a new roof, new access control and security, and a new
building HVAC system. 1733 Connecticut Avenue NW will be getting a rear façade demolition
and reconstruction.
Basement Improvements
1733 Connecticut Avenue NW’s basement will be getting a new high density filing
system, as well as a new HVAC, new drywall and ceiling, new lights, new carpet, and net paint.
1735 Connecticut Avenue NW’s basement will be getting a new rear emergency egress door,
and all abandoned equipment will be removed.
First Floor Improvements
1
1733 will be getting a new conference room on the first floor. The new conference room
will have AV/VTC, lights, furniture, and paint and carpet. 1735 will have new tile put in, as well
as a built-in walk-off matt.
Second Floor Improvements
The second floor at 1733 will have a larger rear office with new furniture, as well as a
lounge area. It will get new carpet, new paint, a new HVAC unit, and new access control. 1735
will get new AV/VTC in the conference room, along with new appliances in the kitchen, a new
washer/dryer, new intercom and access control units, new paint, and seal exposed brick.
Third Floor Improvements
The front office in 1733 will get new lights, new carpet and paint, a new coat closet, and
new furniture. The rear area in 1733 will receive new office furniture, a new work area, new
carpet and paint, and new lights. The third floor in 1735 will get new access control, a chase to
accommodate 4th floor plumbing, and new appliances.
Fourth Floor Improvements
On the fourth floor, the front office of 1733 will get new paint, a new walkstation, and a
new coat closet. The rear area will receive a new galley kitchen, a new work area, new carpet
and paint, and new lights. The fourth floor at 1735 will get a new suite entrance, a new
hardwood floor, a new coat closet, new appliances, a new galley kitchen, and a new copy area.
Fifth Floor Improvements
The fifth floor at 1733 will have another front office. The front office will be expanded,
and will have new lights, new paint, and new countertop, new furniture, a new coat closet, and
the skylight will be replaced. The rear area at 1733 will have a new bathroom with a shower, a
2
new washer/dryer, new carpet and paint, new lights, and a new coat closet. Meanwhile, the
fifth floor at 1735 will get new paint and new carpet.
How Successful Has the Project Been?
While there were significant problems in the preconstruction phase of the project, the
project has been successful. There have been no complaints from any of the parties involved
about the difficulty of the job or working with the other parties. The project is a smaller
renovation that has to deal with tenants who are currently occupying the space, and the
General Contractor and the Owner have done an excellent job accommodating the needs of the
tenants and catering to their schedules.
Major Issues on the Project
There were multiple major issues that had to be addressed. Both roofs had serious
water problems and are being replaced. The rear existing brick façade was removed and
replaced with steel stud construction. The Owner wanted to occupy parts of the property
during construction, but they had to move some employees their office in Silver Spring to allow
for easier access by the General Contractor during construction. Furthermore, the second and
third floors are still partially occupied, and the Owner inherited a first floor retail tenant which
is operating during construction.
The property has no rear alley access, so all materials had to enter the building through
the Connecticut Avenue NW basement access stairs. This posed a problem for the General
Contractor. Noise from demolition was also being produced on the back façade and roofs. To
further compound the issue, the Executive only gave the Contractor a narrow two-week
3
window when she would not occupy her office, making the Contractor work around this
window.
The Developer’s goal was to keep the lawyer tenants happy. The Developer went
through an extended design process with the Architect, which included two General
Contractors before the current GC. The design was changed several times, and eventually
elements of the design scope were omitted from the final construction documents, including a
roof deck and gym.
Overview of the Contractual Structure and Procurement of the Project
The project was originally a Guaranteed Maximum Price (GMP) project, but changed the
current budget to a stipulated sum. The owner decided on this structure because owner-driven
changes in the design process halved the budget. The owner plans on using this method in the
future.
Project Cost/Budget
The project has a budget of about $2 million. The GC also has a fixed fee of 10% of the
construction cost. The GC also marks up any change order by 10%.
Project Schedule
Spring 2014 – Design with Architect
Summer 2014 – Pricing with GC
Fall 2014 – Value Engineering Exercise
Fall 2014 – Current GC hired
January 2015 – 2 building permits acquired
February 2015 – Construction started
4
July 2015 – Move-in
Change Orders
The PM said that no change orders have been processed so far. There are some change
orders in the works, and those will affect the contract sum. The change orders resulted from
owner-driven requests.
Quality of Work
The Developer has been pleased with the quality of work performed by the Contractor.
Overall Management of the Project by the Contractor
The PM stated that the work is not challenging, but the logistics were hard. There is no
rear alley access or outdoor staging area. Workers had to work late afternoon and evenings at
times. The PM said there is usually about a dozen people working on the site per day, including
a laborer to do constant clean-up of debris.
Will the Owner and the Contractor Work Together in the Future?
The GC said he has a good working relationship with the Owner, and the Architect has
been more lenient about submittal processes than expected. The parties plan on working
together for future projects.
5