COSTING OF SMALL HYDRO 2017/Documents/Small Hydro Workshop/10...Build-up of Investment Costs •Step...
Transcript of COSTING OF SMALL HYDRO 2017/Documents/Small Hydro Workshop/10...Build-up of Investment Costs •Step...
COSTING OF SMALL HYDRO
Medellin, November 2017
Dr. Brian Glover
CEO Bærekraftig Investering AS
• Principles and costing methods1
• Investment costs: Small hydro data 2
• Life-cycle analysis3
Costing of small hydro - Overview
PRINCIPLES AND COSTING METHODS1
Before starting cost estimating
• What are the cost figures to be used for?
• How are they to be derived? Data sources
• Investment or capital costs depend on quality
of equipment and competence of contractor.
Great variations (+/- 100%!!)
• First consider recurrent costs (O & M)
• If cheap low tech investment –high O&M !
Cost estimating principles
• What is the purpose of the estimate to be provided? All the alternatives below will have different ”total cost figures” for the same project
– Macro-economic analysis (e.g feasibility for thenation)
– Micro- economic analysis (company investmentdecisions, including taxation effects)
– Financial analysis (loans and their conditions – seenfrom government or from lending banks)
– Budgetting and access to capital
Cost estimates vary with time
– Often the main source of public confusion and
misunderstandings when accurate figures are used
out of context or imprecisely quoted.
– All cost figures relate to a particular month in time,
either past (feasibility period) or future (for financing
and future supplier payments).
– The final cost figures will often be larger when
payments are finally made due to the effect of
inflation or variations in exchange rates
Investment Cost Estimating –alternative approaches
• Alternative Methods for Civil Works
– Contractors method (plant, labour, materials)
– Engineering method (quantities and unit rates)
• E&M Supplies
– past experience, cost curves
– budget pricing from suppliers (minus 10%)
Build-up of Investment Costs
• Step 1 Civil and E&M from previous projects,
cost curves, historic prices. Adjust all to a
common year
• Step 2 Add general items (see next slides)
• Step 3 Add physical contingencies
• Step 4 Inflate all costs to expected construction
date – use a hard currency not expected to
devalue (Euros, USD, CHF)
• Now you have an economic investment cost
estimate for use in macro-economic analysis
General items (in addition to main contracts in civil and E&M)
• HV equipment and transmission to enable
operation with existing grid
• Access roads and camps, site preparation
• Engineering and construction supervision
(consultancies)
• Own project administration (internal)
• Environmental mitigation and monitoring
• Resettlement, compensation, legal costs
Add Physical Contingencies
• Equipment and transmission 10%
• Civil Works 15-20%
• Access roads and camps 15-20%
• Engineering and administration 20-25%
• Environmental mitigation and monitoring 30-
50%
Investment Costs.NVE database from 2010
2
Investment Costs. NVE database from 2010
• http://webby.nve.no/publikasjoner/veileder/2012/veileder2012_02.pdf
http://webby.nve.no/publikasjoner/veileder/2012/veileder2012_03.pdf
• Database Costs generally do not include:
– Project preparation and investigations
– Site infrastructure and access roads
– Legal and administration costs
– Engineering and supervision
– Environmental mitigation and monitoring
– Resettlement and compensation
Only for first estimates and fair comparison of alternatives
Small diversion damsConcrete overflow Rockfill
Waterways (2010)Channels Unlined tunnels
Blasted tunnels
Note that these prices
are normally lower
than in remote
countries with little
hydro experience and
inexperienced
contractors
Recommend adding
30% for remote
projects where
contractor is from
abroad
16
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
0 10 20 30 40 50 60 70 80 90
Contractor costs [NOK/ m]
Tunnel cross-section [m2]
TOTAL PRICECost = 219.99A + 13658
BASIC PRICECost = 91.39A + 7905
Drilled shafts
17
4
5
6
7
8
9
10
11
12
13
14
15
16
0 0.5 1 1.5 2 2.5 3 3.5
Co
ntr
ac
tor
co
sts
[1
00
0 N
OK
]
Diameter [m]
Poor drillability (DRI = 37): Cost = 0.64D2 + 0.64A + 7.5Medium drillability (DRI = 49): Cost = 0.55D2 +
0.56A + 6.5Good drillability (DRI = 65): Cost = 0.47D2 + 0.47A + 5.5
0.9
1
1.1
1.2
1.3
0 100 200 300 400 500
Co
rrecti
on
facto
r
Drilled length [m]
Example of penstock laying costWe use a lot of GRP pipes in Norway up to 2m diameter
E & M unit packages (2010)Pelton Francis
Many items not included by NVE
Investment and annual O & M costsPeriod Economic costs Financial costs
Construction/
investment Surveys and investigations
Contractor’s general costsand site infrastructure
Civil works ( often in separatelots e.g dam,tunnels etc.)
Equipment (manufacture,transport and erection)
Engineering fees andsupervision
Admin., insurance and legalcosts
Land acquisition, rights ofway, resettlement
Environmental mitigation
Taxes and importduties
Interest duringconstruction
Financial fees
Guarantee premiums
Operation Operating staff
Repair and maintenance costs
Annual debt service
Water user fees
License fees
Environmental andsocial funds
Life Cycle Cost Components
• Project preparation costs (often sunk cost)
• Construction costs (capital investment)
• Operation and Maintenance (O&M)
• Rehabilitation costs (intermittent)
• (De-commissioning costs!)
But we don’t have not all costs yet!
• Financial costs come on top.
• They are real and substantial, even wheninterest rates are low as now.
• The financial costs must be included in all financial analyses and micro-economicinvestment decisions.
• The cost of private sector capital can increaseproject costs substantially (typically 30-50%)
Financial Costs Include:
• Interest During Construction (in or out depending on
what year the cost estimate is generated for)
• Taxes and Duties, incl. VAT for some Financial
Commitment and Management Fees
• Guarantee Premiums
• Private sector investors require a high return
on equity capital at risk (typically 15-20%)
Internalise Environmental & Social Costs and contingencies• Economic Analysis includes TOTAL cost to
society
• Financial Analysis includes ALL costs to owner
• Do not off-load costs onto government or others
• The project must bear the full E&S cost
Risk avoidance and costs
• Off loading risk is the same as increasing cost. Who takes the risk?
• Risk og unforeseen ground conditions
• Risk of river diversions being inadequate for surprise floods
• Risk of early or proponged monsoon
• Risk of strikes, import delays, security failure etc
Costs internalisedPROJECT Construction
Cost
( MUSD )
Enviro costs % of
( MUSD ) Costs
COMMENTS
Theun Hinboun,
Laos ( 210 MW)
260.0 1.0 planned!! 0,4 % + 1.6 MUSD in
re-regulating pond
Pak Mun, Thailand 39.0 Whereof 34 MUSD
compensation
Kali Gandaki A,
Nepal (144 MW)
397.0 17.6 4.0% Whereof 2 MUSD
compensation
Lower Kihansi,
Tanzania ( 180 MW)
270 9% 3.3 % Health & Socio =
6 MUSD
Theun Hinboun Ext 720 48,0 6,7% 70% is social
(280 MW )
Life Cycle Analysis (LCA)3
What is LCA/LCC ?
• LCC includes all the costs throughout a constructions life cycle
– Investment costs (capital)
– Management costs
– Operation costs
– Maintenance costs
– Development and upgrading costs
– Decommissioning costs
Management
Investment (capital cost)
Development/ upgrading
Maintenance &
replacement
Operations, energy &
cleaning
Why LCC ??
• Visualizes total costs per MW or GWh
• Visualizes the consequences of investment
• Makes sense from a macro economical point of view
• Compares costs of alternatives fairly
• Improves maintenance planning
• Basis for benchmarking projects
Annual MOM
Functional Lifetime
NP
V –
Lif
eti
me C
ost
Ca
pit
al
Co
st
An
nu
al
Co
st
• Material with high quality
• Detailed design for durability
• Skilled workmanship
• Knowledge of environmental impact
• Preventive maintenance
The old church
Important to remember
• To end up with the lowest possible LCC is not an aim in itself, but the calculations should demonstrate the consequences of the choices made
• It should be a duty of the design / construction teams to set up LCC of the choices made, but it is the privilege of the owner to choose alternative.
• Owners choice may often be: investing more capital or not in a project with better durability, reliability, lower running cost and longer operational life?
LCC or Annual Costs analysis is used:
• to prepare budgets for investment and MOM-costs (Management, Operating, Maintenance) throughout the planning and construction process
• to evaluate alternatives• to estimate consequence cost of rebuilding,
improvements, upgrades or changes in operationor in other words
• to choose among alternatives, provide arguments, check profitability, provide
budgets etc
Example of alternative calculation
• Wood window
• Invest: 3.500 NOK
• Service life: 30 years
• Maintenance: 500 NOK/10y
• Net present value: 4.930 NOK
( 60 years, interest: 5 %)
• Aluminium window
• Invest: 4.600 NOK
• Service life: > 60 Y
• Maintenance: 500 NOK/30Y
• Net present value 4.715 NOK
3500 3800 4600500 500 500
Why is Life Cycle Analysis vital for hydropower?
• Hydro has the longest lifetime of all generation projects
• High equipment efficiency and reliability is extremely valuable over such long lifetimes
• True value of investment is not reflected in economic analyses of only 30 year duration or financial analysis with short loan periods
• Discount rates should be low at present
Life Cycle AnalysisBenefit Reduction Factors
• Increased upstream water usage (e.g. for
irrigation) reducing inflow to the plant
• Increased deforestation causing increasing
spillage and reduced low-flows
• Reservoir sedimentation
• Reduced unit efficiency
• Reduced plant availability due to more
frequent outages as the equipment ages
Factors Reducing Investment Costs
• Good Construction Planning
• Comfortable Time Schedules
• International Competitive Bidding
• Prequalification of Contractors/Supplies
• Risk-Sharing Contracts
• Incentive-Based Contracts
• “Partnerships” Contract Models