Costing case study pp
-
Upload
hajar-hafizah -
Category
Presentations & Public Speaking
-
view
140 -
download
3
Transcript of Costing case study pp
QUESTIONS
a) Calculate the following variances for product SLIM and SMART :
i. Material Price Variance
ii. Material Usage Variance
iii. Total Material Variance
iv. Labour Rate Variance
v. Labour Efficiency Variance
vi. Total Labour Variance
SLIM
Material Price Variance
MPV = ( AP - SP ) x AQ
= ( RM 4.90 – RM 5.00 ) X 8,200 kg
= RM 820 (F)
Material Usage Variance
MUV = ( AQ - SQ ) X SP
= ( 7,380 kg – 7,800 kg) X RM 5.00
= RM 2,100 (F)
Total Material Variance
MCV = MPV + MUV
= RM 820 ( F ) + RM 2,100 ( F )
= RM 2,920 (F)
SLIM
Labour Rate Variance
LRV = ( AR – SR ) X AH
= ( RM 7.20 – RM7.00 ) X 12,300 hours
= RM 2,460 (UF)
Labour Efficiency Variance
LEV = ( AH – SH ) x SR
= ( 12,300 hours - 11,700 hours) X RM 7
= RM 4,200 (UF)
Total Labour Variance
LCV = LRV + LEV
= RM 2,460 (UF) + RM 4,200 (UF)
= RM 6,660 (UF)
SMART
• Material Price Variance
MPV = ( AP - SP ) X AQ
= ( RM 6.50 – RM 6.00 ) X 10,000 kg
= RM 5,000 (UF)
• Material Usage Variance
MUV = ( AQ - SQ ) X SP
= ( 9,000 kg – 16,650 kg ) X RM 6.00
= RM 45,900 (F)
• Total Material Variance
MCV = MPV + MUV
= RM 5,000 (UF) + RM 45,900 (F)
= RM 40,900 (F)
SMART
• Labour Rate Variance
LRV = ( AR – SR ) X AH
= ( RM 8.00 – RM7.50 ) X 13,500 hours
= RM 6,750 (UF)
• Labour Efficiency Variance
LEV = ( AH – SH ) X SR
= ( 13,500 hours - 19,425 hours ) X RM 7.50
= RM 44,437.50 (F)
• Total Labour Variance
LCV = LRV + LEV
= RM 6,750 (UF) + RM 44,437.50 (F)
= RM 37,687.50 (F)
QUESTIONS
b) State TWO (2) possible reasons for each of the
Favourable (F) or Unfavourable (UF) variances above.
SLIM
Material Price Variance (MPV) : Favourable (F)
1. Decrease in price
2. Inefficient buying
Material Usage Variance (MUV) : Favourable (F)
1. Method of production
2. Handling in material
Total Material Variance (MCV) : Favourable (F)
1. Decrease in price
2. Method of production
SLIM
Labour Rate Variance (LRV) : Unfavourable (UF)
1. Paying workers at a lower rate (in standard rate)
2. Working overtime
Labour Efficiency Variance (LEV) : Unfavourable (UF)
1. Standard sets too loose
2. Inefficient equipments
Total Labour Variance (LCV) : Unfavourable (UF)
1. Working overtime
2. Standard sets too loose
SMART
Material Price Variance (MPV) : Unfavourable (UF)
1) Standard price set was too low
2) Increase in price
Material Usage Variance (MUV) : Favourable (F)
1) Condition of machinery
2) Nature of material
Total Material Variance (MCV) : Favourable (F)
1) Condition of machinery
2) Nature of material
SMART
Labour Rate Variance (LRV) : Unfavourable (UF)
1. Time taken for the work
2. Change in rate
Labour Efficiency Variance (LEV) : Favourable (F)
1. Standard sets too tight
2. Lost time due to machine brokedown
Total Labour Variance (LCV) : Favourable (F)
1. Standard sets too tight
2. Lost time due to machine brokedown
Thank you