Cost valuation reconciliation

Transcript of Cost valuation reconciliation. When Usually commences after the external valuation Time dependent...

Page 1: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Cost valuation reconciliation

Page 2: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

When

• Usually commences after the external valuation

• Time dependent upon the complexity and size of project

• Usually takes two weeks to complete• Discussed at Monthly CVR meeting

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

2

Page 3: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Fundamental principle

• Prudence• Match expenditure with income• Uses the application for payment and the

architects certificate to substantiate the valuation/Net sales value of the works

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

3

Page 4: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Documentation used

• External valuation– Identification of:• Overmeasure• Undermeasure• Variations in dispute• Claims in dispute• Materials on site• Undercertification

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

4

Page 5: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Information flows

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

5

Page 6: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Documentation (contd.)

• Overmeasure schedule• Undermeasure schedule• Subcontractor liability build-up• Architects/Engineers certificates• Contra charge invoices

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

6

Page 7: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Definitions• Overmeasure

– Claimed-Unpaid– Claimed-Paid

• Definition-“Application for monies in advance of their eligibility”• Undermeasure• Definition-“Work completed that costs have been incurred for but

haven’t been included in the application for payment”– Measured works– Variations

• Work in Progress• Definition-“Work that has been carried out in the period between

the cost cut-off date and the valuation date”

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

7

Page 8: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Basic principle

• Net sales value uses the application for payment as the baseline

• Application adjusted as follows:– Overmeasure – Deducted– Undermeasure - Added–Materials on site - Deleted

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

8

Page 9: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Basic principle

• Net sales value uses the application for payment as the baseline

• Application adjusted as follows:–Overmeasure – Deducted–Undermeasure - Added–Materials on site - Deleted

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

9

Page 10: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Documentation supporting the CVR

• Internal valuation broken down into a set of allowances• Overmeasure schedule• Undermeasure schedule• Cost statement• Subcontractor liabilities• Buying reconciliation• Materials reconciliation• Cost to complete exercise• Estimated final account/profit margin• Architects/Engineers certificate• Narrative explaining variances

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

10

Page 11: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Cost statement

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

11

Page 12: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Adjustments for work in progress

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

12

Page 13: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

When to report a loss?

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

13

Page 14: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Internal and external bills

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

14

Page 15: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Adjustments

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 15

To production: Please change “cummulative and cut off” to “cumulative and cutoff”.
Page 16: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Simplified CVR pro forma

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.16

Page 17: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

A more complex example

17

Page 18: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.

Discussions at CVR meeting

• Profit release• Cash flow• Turnover• Items in dispute– Variations– Claims

• Items for management action