Cost valuation reconciliation
![Page 2: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/2.jpg)
When
• Usually commences after the external valuation
• Time dependent upon the complexity and size of project
• Usually takes two weeks to complete• Discussed at Monthly CVR meeting
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
2
![Page 3: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/3.jpg)
Fundamental principle
• Prudence• Match expenditure with income• Uses the application for payment and the
architects certificate to substantiate the valuation/Net sales value of the works
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
3
![Page 4: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/4.jpg)
Documentation used
• External valuation– Identification of:• Overmeasure• Undermeasure• Variations in dispute• Claims in dispute• Materials on site• Undercertification
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
4
![Page 5: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/5.jpg)
Information flows
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
5
![Page 6: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/6.jpg)
Documentation (contd.)
• Overmeasure schedule• Undermeasure schedule• Subcontractor liability build-up• Architects/Engineers certificates• Contra charge invoices
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
6
![Page 7: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/7.jpg)
Definitions• Overmeasure
– Claimed-Unpaid– Claimed-Paid
• Definition-“Application for monies in advance of their eligibility”• Undermeasure• Definition-“Work completed that costs have been incurred for but
haven’t been included in the application for payment”– Measured works– Variations
• Work in Progress• Definition-“Work that has been carried out in the period between
the cost cut-off date and the valuation date”
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
7
![Page 8: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/8.jpg)
Basic principle
• Net sales value uses the application for payment as the baseline
• Application adjusted as follows:– Overmeasure – Deducted– Undermeasure - Added–Materials on site - Deleted
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
8
![Page 9: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/9.jpg)
Basic principle
• Net sales value uses the application for payment as the baseline
• Application adjusted as follows:–Overmeasure – Deducted–Undermeasure - Added–Materials on site - Deleted
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
9
![Page 10: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/10.jpg)
Documentation supporting the CVR
• Internal valuation broken down into a set of allowances• Overmeasure schedule• Undermeasure schedule• Cost statement• Subcontractor liabilities• Buying reconciliation• Materials reconciliation• Cost to complete exercise• Estimated final account/profit margin• Architects/Engineers certificate• Narrative explaining variances
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
10
![Page 11: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/11.jpg)
Cost statement
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
11
![Page 12: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/12.jpg)
Adjustments for work in progress
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
12
![Page 13: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/13.jpg)
When to report a loss?
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
13
![Page 14: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/14.jpg)
Internal and external bills
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
14
![Page 15: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/15.jpg)
Adjustments
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 15
![Page 16: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/16.jpg)
Simplified CVR pro forma
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.16
![Page 17: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/17.jpg)
A more complex example
17
![Page 18: Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.](https://reader030.fdocuments.net/reader030/viewer/2022032415/56649f015503460f94c16d5f/html5/thumbnails/18.jpg)
Discussions at CVR meeting
• Profit release• Cash flow• Turnover• Items in dispute– Variations– Claims
• Items for management action