Cost Irrigation
-
Upload
harishsandeep -
Category
Documents
-
view
214 -
download
1
description
Transcript of Cost Irrigation
Abstract of the Total Cost of the Project
(Rs. In Lakh) Sl. No.
Scheme Qnty Rate Unit *Amount Remarks
A DIRECT COST A.1 Main Pump Station :
1 30 hp Centrif Pumps 2 336,000.00 Units 672,000.00 2 Earthwork 57 24.00 Cum 1,368.00 3 Reinforced Concrete 14 1,900.00 Tons 26,600.00 4 Piping 1 20% of the capital cost Units 139,994.00 5 Electrical & Controls 1 12% of the capital cost Units 83,997.00 6 Yard Improvements 1 15% of the capital cost Units 104,996.00
Sub Total of A 1 1,028,955.00 1,028,955.00 A 2 Main Line to Pivots 0.00
1 Excavation / Backfill 3,398 24.00 cum 81,552.00 2 ” PVC Pressure Pipe 3,049 200.00 m 609,800.00
Sub Total of A 2 691,352.00 691,352.00 A 3 Manifold System for
Pivots 0.00
1 Pnumatic Valves 3 21,000.00 units 63,000.00 2 Earthwork 28 24.00 cum 672.00 3 Reinforced Concrete 7 1,900.00 tons 13,300.00 4 Piping 1 24,600.00 units 24,600.00 5 Electrical & Controls 1 18,900.00 units 18,900.00 6 Yard Improvements 1 24,600.00 units 24,600.00
Sub Total of A 3 145,072.00 145,072.00 A 4 Irrigation Distribution
System (Pipe Network, Pivot Base)
0.00
1 Excavation/Backfill 946 24.00 cum 22,704.00 2 6” PVC Pressure Pipe 955 200.00 m 191,000.00 3 Reinforced Concrete 4 1,900.00 tons 7,600.00
Sub Total of A 4 221,304.00 221,304.00 A 5 Pivot Irrigation System (3
1,044-ft Pivots) 0.00
1 Pivot Pads 3 4,200.00 units 12,600.00 2 Valley Tech Supervision 1 203,300.00 Units 203,300.00 3 Valley Pivots 3 1,979,500.00 Units 5,938,500.00
Sub Total of (A 5) 6,154,400.00 6,154,400.00 Total of Direct Cost (A) 8,241,083.00 8,241,083.000B Indirect Costs 0.00 B 1 Engineering Design 1 11% of Direct Cost units 379,200.00 B 2 Construction Management 1 10% of direct cost Unit 804,039.00 B 3 Administration 1 1 % of Direct Cost Unit 80,404.00 Total of Indirect Total
(B): 1,263,643.00 1,263,643.00 1,263,643.000
C Contingency 1 12% of Total Cost Unit 1,200,328.00 1,200,328.00 1,200,328.000 Grande Total 10,705,054.000
NOTES:
1 estimates based on conceptual designs and order of magnitude unit cost budgets. All costs assume Rs.4211JS$l .00.2 Valley equipment costs FOB - do not include tax, shipping, import duties, in-countiy fright, etc.
30 lip Centrif Pumps Rs 336,000 /unit 2 units Rs 672,000
Earthwork Rs 24 fin 57 m P.s 1,368
Reinforced Concrete Rs 1,900 /ton 14 tonsRs 26,600
Piping 20% of capital 1 unit Rs 139,994
Electrical & Controls 12% of capital 1 unit Rs 83,997
Yard Improvements 15% of capital I unit P.s 104,996
Subtotal:
Rs 1,028,955
t’Iain Line to Pivots
Excavation/Backfill 8” PVC Pressure Pipe
P.s 24.00 /m
Rs 200.00 /m
3,398 m
3,049 ni
Rs 81,552 P.s 609,800
Subtotal:
Rs 691,352
vfanifold System for Pivots Pnumatic Valves
Earthwork
Reinforced Concrete
Piping
Electrical & Controls
Yard Improvements
P.s 21,000.00 /unit 3 units
Rs 24.00 /m 28 m
Rs 1,900.00 /ton 7 tons
Rs 24,600.00 /urnt 1 unit
P.s 18,900.00 /imit I unit
Rs 24,600.00 limit 1 unit
Rs 63,000 Rs 672
P.s 13,300
P.s 24.600
Rs 18,900
P.s 24,600
Subtotal:
Rs 145,072
rrigation Distribution System (Pipe Network, Pivot Base)
Excavation/Backfill Rs 24.00 /m
6” PVC Pressure Pipe Rs 200.00 /m
Reinforced Concrete P.s 1,900.00 lton
946 rn
955 m
4 tons
Rs 22,704 P.s 191,000
P.s 7,600
.
Subtotal:
Rs 221,304
Divot Irrigation S (3 1,
Pivot Pads
Valley Tech Supervision
Valley Pivots
044-ft Pivots)
P.s 4,200 /unit
P.s 203,300 /urnt P.s 1,979,500 /umt
3 unit
1 unit
3 unit
Rs 12,600 Rs 203,300 P.s 5,938,500
Subtotal:]
Rs 6,154,400
Direct Tot
Rs 8,241,083
Indirect Costs
Engineering Design
Construction Management
Administration
11% of Direct
10% of Direct
1% of Direct
1 unit
1 unit
1 unit
Rs 379,200 P.s 804,039 P.s 80,404
Indirect Total:
Rs 1,263,643
Contingency 12% of Total 1 unit
—- Grande Total:
Rs 1,200,3281 Rs 10,705,0541
NOTES:
1 estimates based on conceptual designs and order of magnitude unit cost budgets. All costs assume Rs.4211JS$l .00.
2 Valley equipment costs FOB - do not include tax, shipping, import duties, in-countiy fright, etc.