1 Cost Estimating & Decommissioning Funding ANL Decommissioning Training Course Joseph E. Carignan [email protected] 423-488-3393 Cell

Transcript of Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding –...

Page 1: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

1

Cost Estimating&

Decommissioning Funding

ANL Decommissioning Training Course

Joseph E. [email protected]

423-488-3393 Cell

Page 2: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

2

Cost Estimating &Decommissioning Funding

– Understand Purpose And Types Of Estimates Advantages/Disadvantages

– Understand And Describe The Approaches Used For Cost Estimating

– Obtain A Basic Understanding Of The Cost Estimating Elements/Terminology

– Identify Key Factors Affecting The Cost Estimate Results

Page 3: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

3

Introduction:Purpose

• Assures Adequate Funds Identified• Establishes Bases For:

– Evaluating Contractor Bids– Comparison of Approaches– Risk Management– Management Communication Tool

• Satisfies Regulatory Requirements • Establishes Oversight Confidence

Page 4: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

4

Introduction:Accuracy

• Association for the Advancement of Cost Engineering (AACE) Definitions:– Order of Magnitude CE -30% to +50%

• W/O Detailed Engineering Data (Scaling factors/ratios)• Scope not well defined

– Budgetary CE -15% to +30 • Scope defined – Have Site Plans/Drawings/Equipment

– Definitive CE - 5 % to +15%• Accurate Site Drawings/Records Available

(Examples - Plot Plans/Elevations, P&IDs, Equipment Data Sheets)

• Scope Well Defined/Characterization/Approach

Page 5: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

5

Introduction:Quality

• Poorly Prepared or No CE May Result In:– Insufficient Funds – Re-planning / Base lining– Poor Public Relations/Loss of Confidence– Non-compliance– Risk exposure– Poor Stewardship

• “Black Box” Cost Estimates Not Sufficient.

Page 6: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

6

Background:Funding Requirements

U.S. Power Reactors(10 CFR 50.75)

- NRC Minimum PWR – $105MM, BWR $135MM - Minimums

Adjusted Over Time

- Funds Collected From Rate Payers- Financial Assurance - Update Report Every Other Year

U.S. Non-Power Reactors(10 CFR 50.33 & 50.75)- No NRC Minimum- Decommissioning Report (10 CFR 50.33)- Financial Assurance Required

Other Facilities - Fed Government Sites Funds Collected From Taxpayers

• No Generic Minimum Required • Congressional Funding Allocated (Yearly)• > 5 Million Additional Oversight

Page 7: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

7

Background:Basis

• 1986 Guidelines Report (AIF/NESP-036)– “Guidelines for Producing Commercial Nuclear

Power Plant Decommissioning Cost Estimates”• Approach –

– Unit Cost Factors and Detailed Plant Inventory• Widely Accepted by Regulatory Authorities

– PUC– Federal Funding Agencies – NRC /DOE

Page 8: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

8

Background:Tools and Applications

• Commercial Estimating Applications Available• Customized Estimating Tools Available, Designed

By D&D Professionals– RACER– POWERtool– Others

• Maintains A ‘Library’ Of Activity Estimates/Rates, Based On Actual Data From Other D&D Projects, To Use On Future D&D Projects

Page 9: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

9

Preparing A Cost Estimate:Key Cost Elements

Activity-dependent Costs

Period-dependent Costs

Collateral Costs/Special Items Costs

Contingency

Page 10: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

10

Preparing A Cost Estimate:Activity-Dependent Costs

“Hands –On” Activities Clearly Defined Tasks/Normally Repetitive Removal, Decontamination, Packaging, Shipping and

BurialUsed to Develop Site-specific Unit Cost

Factors Site/regional Cost For Labor And Materials Work Adjustment Factors For Site Conditions

Page 11: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

11

Preparing A Cost Estimate:Period-Dependent Costs

• Directly Related To Project Duration• Necessary Functions For Program Management

– Engineering, Administration, Quality Assurance, Licensing, Operations, Maintenance, Security and Radiation Protection, Planning/Scheduling, Field Supervision

• Staff Composition/Level – Synchronized With Decommissioning Phases And Support Requirements

• Costs – Direct (Base Salaries)– Indirect Overhead (Fixed And Variable Components)– Transition, Severance, Training And Retention

Page 12: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

12

Preparing A Cost Estimate:Collateral / Special Item Cost

• Insurance, Taxes, Permits, Fees• Engineering

– Contracted or Off Site Support.

• Other Costs– Material/Supplies– Identified As a Cost Not Captured Elsewhere

• Scrap• Salvage

Page 13: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

13

Preparing A Cost Estimate:Other Cost Definitions/Elements

• Other Elements of the Cost Estimate– Scrap Costs

• Clean Material – may be recycled

– Salvage Costs• Material for Resale or Reuse – Must Evaluate Cost Benefit

Page 14: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

14

Preparing A Cost Estimate:Other Cost Definitions/Elements

• Work Breakdown Structure (WB)– Originally developed by the military ((MIL-STD 881B

(25 Mar 93))– A deliverable oriented hierarchical description of the

work to be performed – Organizes/defines the total scope of the project– Each descending level provides form detailed

definition of the work to be performed and eventually work packages.

Page 15: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

15

Preparing A Cost Estimate:Work Breakdown Structure

• Work Breakdown Structure (WBS)– A deliverable oriented hierarchical work activity description – Organizes/defines the total scope of the project– Each descending level provides detailed description of the work

to be performed

– Should correlate to final work packages .– Typically related to the accounting system used for budgeting– Track major elements against decommissioning costs

Page 16: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

16

Preparing A Cost Estimate:Other Cost Definitions/Elements

Page 17: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

17

Preparing A Cost Estimate:Work Breakdown Structure - Level 5 Example

X ResearchReactor1

Pre-planning1.1

DecommissioningPlanning1.3

DecommissioningActivities1.4

TransitionActivities1.2

Etc.1.x

DecontaminationPrimary Systems1.4.1

DecontaminationSecondary Systems1.4.2

Dismantleequipment in Room 1A1.4.3

Dismantleequipment in Room 1B1.4.3

Etc.1.4.x

General deconof room1.4.3.1

Remove allpiping1.4.3.2

Remove tank1A-21.4.3.3

Remove tank1A-21.4.3.4

Etc.1.4.3.x

Ensure pipingIs drained1.4.3.2.1

Disconnect Pipingfrom tank 1A-11.4.3.2.2

Disconnect Pipingfrom tank 1A-21.4.3.2.3

Etc.1.4.3.2.x

From IAEA Presentation

Page 18: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

18

Preparing A Cost Estimate:Work Breakdown Structure - Example

1.0 Site Preparation1.01 Mobilization1.02 Site Infrastructure/Setup...

2.0 Characterization/Investigation 3.0 Preparation For Dismantling

3.01 Preparations3.02 Engineering and Planning..3.10 Overhead Costs

4.0 Dismantling/Decommissioning5.0 Site Restoration

Page 19: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

19

Preparing A Cost Estimate:Work Element Definition Sheet – Example

WBS No. Sequential Number of specific ActivityWBS Title: Title of Tasks To Be PerformedWBS Description of the Work:

This section describes specific tasks necessary to complete the Activity.

WBS Deliverable:

Describes the End Point Criteria for the Specific Tasks.

Page 20: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

20

Preparing A Cost Estimate:Contingency

• Definition* “specific provision for unforeseeable elements of cost within the defined project scope; particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur.”

• Provides Funding Assurance• Not a Safety Factor & Expected to Be Spent • Industry Wide Acceptance • May be built into each activity or applied as line

item or project specific– DOE does not allow the project to control contingency

* Association for the Advancement of Cost Engineering International

Page 21: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

2121

Preparing A Cost Estimate:Contingency/Management Reserve

• DOE“the portion of the project budget that the government holds in reserve to accommodate unknowns regarding requirements and uncertainty that is outside the scope of the contract, but is within the scope of the project. Contingency maybe used for additional scope and work that is necessary to meet current requirements. Contingency is not used for new requirements.

The contractor uses management reserve. Management reserve is not allocated to work packages or planning packages, but is held in reserve by management to provide flexibility to manage within the contractor Performance Measurement Baseline. Management reserve is used to control the workflow and adjust work packages for rate changes and other unknowns, but is never used for additional scope outside of the authorized work scope.”

* DOE M 413.3-13-28-03

Page 22: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

Preparing A Cost Estimate:Overview

22

1.Define Work

Scope

3.Collect

Information

2.Determine

Options

6.Develop

UCF & ProductivityFactors

4.Define

Assumptions

5.ID Activities

& Tasks

7.Develop Activity

Estimates

9.Prepare Final CostEstimate/Schedule

8.Develop

Project Schedule

Page 23: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

23

Preparing A Cost Estimate:First Things First

– This Bounds the Cost Study and Describes The Overall Approach

– Determines What Scenarios will be included in the Cost Study such as Prompt Decon.

– Site Inventory / Drawings / Records– Interviews / Misc Data

1.Define Work

Scope

3.Collect

Information

2.Determine

Options

Page 24: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

24

Preparing A Cost Estimate:First Things First

Assumptions Affect Approach & Costs (+ or -)

– Technical– Scope, Contamination Levels, Quantities, Subcontracts– Scrap/Salvage, Plant Conditions– Radiation Conditions, Activation Modeling

– Cost– Present Year Dollars?, Rates, Escalation, Interest, etc.– Labor Costs (severance, security, salaries)

– Funding– Multi-year, Single Year, etc.

– End State– Remaining Contamination Levels– Remaining Site Condition

4.Define

Assumptions

3.Collect

Information

5.ID Activities

& Tasks

Page 25: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

25

Preparing A Cost Estimate:

Identify Activities or Tasks

– Use Inventory to Determine What Has to be removed.

– Group Tasks– Equipment Types– Divide Into Most Like Areas– Unique Factors

6.Develop

UCF & Prod. Factors

4.Define

Assumptions

5.ID Activities

& Tasks

Page 26: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

26

Preparing A Cost Estimate:Develop or Identify Unit Cost Factors

• Unit Cost Factors (UCF) – Determine the Cost for Specific Tasks Under Ideal

Conditions

• Example:

UCFRemoval of contaminated pump motors which are 300-

1000 pounds

Description of UCF:Motors for pumps 300 to 1,000 lbs will be manually removed by chain falls or small hoists. The motor will be transferred to the waste processing area for final disposition.

Page 27: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

27

Preparing A Cost Estimate:Incorporate Productivity Factors*

• Productivity Factors – Used to Adjust Activities or Tasks Based on Site Specific Conditions that affect worker performance:

– Heat Stress– Accessibility / Close environments– Controlled Access / Security– Examples

• Respiratory Protection: 10 to 50% inefficiency• ALARA 10 to 50% inefficiency• Protective Clothing 15 to 30% inefficiency• Accessibility 10 to 20% inefficiency• Work Breaks 8 to 10% inefficiency• Productivity 10 to 15% inefficiency

* Also Referred To As Work Difficulty Factors

Page 28: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

28

Preparing A Cost Estimate:Assemble the Cost Estimate – Site Inventory

111

11510

Collect Inventory and Other Data

6.Develop UCF & PF

8.Develop Project

Schedules

7.Develop

Activity Estimates

Page 29: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

29

Preparing A Cost Estimate:Assemble the Cost Estimate – Use UCF and PF

1 1 1 0.1 0.25 0.1 0.3 0.081

6.Develop UCF & PF

8.Develop

Project Schedules

7.Develop

Activity Estimates

Page 30: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

30

Preparing A Cost Estimate:Assemble the Cost Estimate – Integrate Results

2.00

69 36.00

1.00

38.20

0 .50 0. 1.00 40.0

20.00 0.0 45.23 139.00

18.00

45.23

39.2040.00

38.20

Page 31: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

31

Preparing A Cost Estimate:Assemble the Cost Estimate – Integrate Results

$65.24

Page 32: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

32

Removal of contaminated pump motors, 300-1000 pound

Motors for pumps 300 to 1,000 lb will be removed by chain falls or smallhoists. The motor will be transferred to the waste processing area.

Act Activity Act. CrtID Description Dur Dur---------------------------------------------------------------------------a Verify equipment de-energized & disconnected 30 30b Rig for removal 15 (a)c Remove motor from supports and pump 15 15d Remove motor, wrap in plastic and remove to waste processing area

20 20----- -----

Totals (Activity/Critical) 80 65

Duration adjustment(s):+ Respiratory protection adjustment( 50 % of critical duration ) 32+ Radiation/ALARA adjustment( 37.08333 % of critical duration ) 24

-----Adjusted work duration 121+ Protective clothing adjustment ( 30 % of adjusted duration ) 36

-----Productive work duration 157+ Work break adjustment( 8.33 % of productive duration ) 13

-----Total work duration 170 min

*** Total duration = 2.833 hr ***

Preparing A Cost Estimate - UCF Example

Page 33: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

33

Removal of contaminated pump motors,300-1000 pound (cont'd)

Crew Number Duration Rate Cost(hr) ($/hr)

--------------------------------------------------------------------------Laborers 2.00 2.833 $34.59 $195.99Craftsmen 2.00 2.833 $43.06 $243.98Foreman 0.50 2.833 $43.98 $62.30General Foreman 0.13 2.833 $44.98 $15.93Health Physics Technician 1.00 2.833 $46.00 $130.32

---------Total labor cost $648.52

Equipment Costs noneConsumables/Materials Costs-Blotting paper 100 @ $0.45/sq ft { 2} $45.00-Plastic sheets/bags 100 @ $0.11/sq ft { 3} $11.00

---------Subtotal cost of equipment and materials $56.00Overhead & profit on equipment and materials @ 16.500 % $9.24

---------Total costs, equipment & material $65.24

TOTAL COST Removal of contaminated pump motors, 300-1000 pound$713.76

Total labor cost $648.52Total equipment/material costs $65.24TOTAL CRAFT LABOR man-hours required per unit 15.936

Preparing A Cost Estimate - UCF Example

Page 34: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

34

Preparing A Cost Estimate:Assemble the Cost Estimate - Project Schedules

Calculate durations for completing a unit of work (based on working conditions)Assign number of crews to each Work Area or

taskCombine the work area inventory, number of

crews, and adjusted task durationsDevelop a Work Area “Total Task Duration”

Page 35: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

35

Preparing A Cost Estimate:Assemble the Cost Estimate – Integrate Project Schedules

EXAMPLE

Page 36: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

3636

Page 37: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

37

Preparing A Cost Estimate:Assemble the Cost Estimate – Final Estimate and Schedule

Page 38: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

38

Example: WBS ScheduleExample: WBS Schedule

38

WBS # Task Name

Labor Hours

(x 1000)

Budget (includes labor) (x 1000€)

T = - 3 Months T = 0

T = 3 Months

T = 6 Months

T= 9 Months

T = 12 Months

T = 15 Months

T = 18 Months

T = 24 Months

1 Decommission Research Reactor 20001.1 Pre-shutdown planning 301.2 Final Shutdown === Milestone1.3 Preliminary Studies 301.4 Project Execution 1905

1.4.1 Decommissioning Activities 17401.4.1.1 Decon/Remove Auxilary Systems 8701.4.1.2 Decon/Remove Reactor Systems 8701.4.2 Final Status Surveys 1501.4.3 Confirmatory Surveys 151.4.4 License Termination === Milestone1.5 Closeout Actions 35

1.5.1 Non-radiological remediation 251.5.2 Demobilization 51.5.3 Closeout Documentation 5

From IAEA Presentation

Page 39: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

39

Preparing A Cost Estimate:Assemble the Cost Estimate - Site Restoration / S&M

• Structural Damage / Degradation • Abandoned Facilities Will Quickly Degrade

– Breeding Ground for Vermin & Other Biological Hazards– Groundwater Intrusion– Safety Hazard / Personnel Intrusion– Dismantling cost increases with time.

• Surveillance & Maintenance Costs Must Be Factored Into Overall Costs

Page 40: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

40

Example: Decommissioning Cost Elements:1100 MWe PWR – 1999 U.S. Dollars

Example: Decommissioning Cost Elements:1100 MWe PWR – 1999 U.S. Dollars

Page 41: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

41

SUMMARY:• Quality CE and Up-Front Planning is Critical

• Don’t Underestimate The Value Of Your Assumptions

• Site Specific CE Necessary for Near Term D&D– Keep CE Up-To-Date (Decommissioning Is Imminent)

• Cost Study Used To Develop Baseline

• Don’t Reinvent – Use Proven Software and Expertise

• Contingency Is An Integral Part of the Cost Estimate

• Don’t Underestimate “soft” costs - Engineering and Licensing Support

Page 42: Cost Estimating Decommissioning Funding Cours… · 2 Cost Estimating & Decommissioning Funding – Understand Purpose And Types Of Estimates Advantages/Disadvantages – Understand

42

SUMMARY

CHEAP – FAST – GOOD