General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-58
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING SCHEDULE C1 – INSTALLATION & TESTING OF TRACK WORK
Sheet 1 of 3
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C1.1 Obtain Notice of No Objection or Notice of No Objection with Comment(s) from the Engineer for Inspectionand Test Plan, Testing and Commissioning Management Plan.
C1.2 Completion of installation and site testing of the Trackwork, platform edge and level clearance of the following stations:
(a) PRI Area at Depot
(b) Depot
(c) East Valenzuela
(d) Quirino Highway
(e) Tandang Sora
(f) North Avenue
(g) Quezon Avenue
(h) East Avenue
(i) Anonas
(j) Katipunan
(k) Ortigas North
(l) Ortigas South
(m) Kalayaan Avenue
(n) Bonifacio Global City
Total of Sheet 1 of Schedule C1 carried forward to Sheet 2:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-59
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C1 – INSTALLATION & TESTING OF TRACK WORK
Sheet 2 of 3
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 1:
(o) Lawton
(p) Senate
(q) Terminal 3
C1.3 Completion of installation and site testing of the Trackwork, switches, turnout, crossovers, scissors, clearance from sidewalks and signal posts and catenary heights for the followings:
(a) Depot to East Valenzuela Station
(b) East Valenzuela Station to Quirino Highway Station
(c) Quirino Highway Station to Tandang Sora Station
(d) Tandang Sora Station to North Avenue Station
(e) North Avenue Station to Quezon Avenue Station
(f) Quezon Avenue Station to East Avenue Station
(g) East Avenue Station to Anonas Station
(h) Anonas Station to Katipunan Station
Total of Sheet 2 of Schedule C1:
Total of Sheet 1 and Sheet 2 of Schedule C1 carried forward to sheet 3:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-60
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C1 – INSTALLATION & TESTING OF TRACK WORK
Sheet 3 of 3
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 2:
(i) Katipunan Station to Ortigas North Station
(j) Ortigas North Station to Ortigas South Station
(k) Ortigas South Station to Kalayaan Avenue Station
(l) Kalayaan Avenue Station to Bonifacio Global City Station
(m) Bonifacio Global City Station to Lawton Station
(n) Lawton Station to Senate Station
(o) Senate Station to Food Terminal Inc. (FTI) Station. Demarcation point shall be at the Buffer stop toward FTI direction after Terminal 3 Turnout.
(p) Senate Station to Terminal 3 Station
C1.4 Obtain Notice of No Objection or Notice of No Objection With Comment(s) from the Engineer for Acceptance Test.
C1.5 Completion of the remaining works.
Total of Sheet 3 of Schedule C1:
Total of Sheet 1, Sheet 2 and Sheet 3 of Schedule C1 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-61
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C2– INSTALLATION & TESTING OF SIGNALING SYSTEM
Sheet 1 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C2.1 Obtain Notice of No Objection or Notice of No Objection with Comment(s) from the Engineer for InspectionTest Plan (ITP), prior to Testing and Commissioning Management Plan.
C2.2 Completion of installation, site testing and integrated testing for all sub-systems for the Signaling at theDepot, all station equipment &Waysidesuch as ATO and Interlocking including racks, point machines, track circuit, cabling and terminationsfor the followings:
(a) PRI Building and Track section Area at Depot
(b) Depot
(c) East Valenzuela
(d) Quirino Highway
(e) Tandang Sora
(f) North Avenue
(g) Quezon Avenue
(h) East Avenue
(i) Anonas
(j) Katipunan
Total of Sheet 1 of Schedule C2 carried forward to Sheet 2:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-62
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING SCHEDULE C2– INSTALLATION & TESTING OF SIGNALING SYSTEM
Sheet 2 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 1:
(k) Ortigas North
(l) Ortigas South
(m) Kalayaan Avenue
(n) Bonifacio Global City
(o) Lawton
(p) Senate
(q) Terminal 3
C2.3 Completion of installation, site testing, system integration testing of all sub-systems for the Signaling system at Stations and Wayside equipment including Train Detection System, On-board, train to wayside & train to train communication devices, junction boxes, cabling and terminations for the following:
(a) PRI Building and Track section Area (inclusive) at Depot (Exclusive)
(b) Depot(inclusive)to East Valenzuela Station (Exclusive)
(c) East Valenzuela Station (inclusive) to Quirino Highway Station (exclusive)
(d) Quirino Highway (inclusive) Station to Tandang Sora Station (exclusive)
Total of Sheet 2 of Schedule C2:
Total of Sheet 1 and Sheet 2 of Schedule C2 carried forward to sheet 3:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-63
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C2– INSTALLATION & TESTING OF SIGNALING SYSTEM
Sheet 3 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 2:
(e) Tandang Sora Station (inclusive) to North Avenue Station (exclusive)
(f) North Avenue Station (inclusive) to Quezon Avenue Station (exclusive)
(g) Quezon Avenue Station (inclusive) to East Avenue Station (exclusive)
(h) East Avenue Station (inclusive) to Anonas Station (exclusive)
(i) Anonas Station (inclusive) to Katipunan Station (exclusive)
(j) Katipunan Station (inclusive) to Ortigas North Station (exclusive)
(k) Ortigas North Station (inclusive) to Ortigas South Station (exclusive)
(l) Ortigas South Station (inclusive) to Kalayaan Avenue Station (exclusive)
(m) Kalayaan Avenue Station (inclusive) to Bonifacio Global City Station (exclusive)
Total of Sheet 3 of Schedule C2:
Total of Sheet 1, Sheet 2 and Sheet 3 of Schedule C2 carried forward to Sheet 4:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-64
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C2– INSTALLATION & TESTING OF SIGNALING SYSTEM
Sheet 4 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 3:
(n) Bonifacio Global City Station (inclusive) to Lawton Station (exclusive)
(o) Lawton Station (inclusive) to Senate Station (exclusive)
(p) Senate Station (inclusive) to Food Terminal Inc. (FTI) Station (exclusive)
Demarcation point shall be at the Buffer stop toward FTI direction after Terminal 3 Turnout.
(q) Senate Station (exclusive) to Terminal 3 Station (inclusive)
C2.4 Completion of installation, site testing and integrated testing for all sub-systems for Onboard equipment.
C2.5 Completion of System Acceptance Test.
C2.6 Completion of the remaining works.
Total of Sheet 4 of Schedule C2:
Total of Sheet 1, Sheet 2, Sheet 3 and Sheet 4 of Schedule C2 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-65
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING SCHEDULE C3 – INSTALLATION & TESTING OF TELECOMMUNICATION SYSTEM
Sheet 1 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C3.1 Obtain Notice of No Objection or Notice of No Objection with Comment(s) from the Engineer for Inspection Test Plan, Testing and Commissioning Management Plan.
C3.2 Completion of installation, site testing and integrated testing for all sub-systems for the Communications System for all indoor equipment and waysidefor the following:
(a) PRI Building and Track section Area at Depot
(b) Depot
(c) East Valenzuela
(d) Quirino Highway
(e) Tandang Sora
(f) North Avenue
(g) Quezon Avenue
(h) East Avenue
(i) Anonas
(j) Katipunan
(k) Ortigas North
Total of Sheet 1 of Schedule C3 carried forward to Sheet 2:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-66
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C3 – INSTALLATION & TESTING OF TELECOMMUNICATION SYSTEM
Sheet 2 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 1:
(k) Ortigas South
(l) Kalayaan Avenue
(m) Bonifacio Global City
(n) Lawton
(o) Senate
(p) Terminal 3
C3.3 Completion of installation, site testing and integrated testing for all sub-systems for the Communications System for all outdoor and waysideequipment for the following:
(a) PRI Building and Track section Area (inclusive) at Depot (Exclusive)
(b) Depot(inclusive) to East Valenzuela Station (Exclusive)
(c) East Valenzuela Station (inclusive) to Quirino Highway Station (exclusive)
(d) Quirino Highway (inclusive) Station to Tandang Sora Station (exclusive)
(e) Tandang Sora Station (inclusive) to North Avenue Station (exclusive)
Total of Sheet 2 of Schedule C3:
Total of Sheet 1 and Sheet 2 of Schedule C3 carried forward to sheet 3:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-67
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C3 – INSTALLATION & TESTING OF TELECOMMUNICATION SYSTEM
Sheet 3 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 2:
(e) North Avenue Station (inclusive) to Quezon Avenue Station (exclusive)
(f) Quezon Avenue Station (inclusive) to East Avenue Station (exclusive)
(g) East Avenue Station (inclusive) to Anonas Station (exclusive)
(h) Anonas Station (inclusive) to Katipunan Station (exclusive)
(i) Katipunan Station (inclusive) to Ortigas North Station (exclusive)
(j) Ortigas North Station (inclusive) to Ortigas South Station (exclusive)
(k) Ortigas South Station (exclusive) to Kalayaan Avenue Station (exclusive)
(l) Kalayaan Avenue Station (inclusive) to Bonifacio Global City Station (exclusive)
(m) Bonifacio Global City Station (inclusive) to Lawton Station (exclusive)
(n) Lawton Station (inclusive) to Senate Station (exclusive)
Total of Sheet 3 of Schedule C3:
Total of Sheet 1, Sheet 2 and Sheet 3 of Schedule C3 carried forward to Sheet 4:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-68
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C3 – INSTALLATION & TESTING OF TELECOMMUNICATION SYSTEM
Sheet 4 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 3:
(o) Senate Station (exclusive) to Terminal 3 Station (inclusive)
C3.4 Completion of System Acceptance Test.
C3.5 Completion of the remaining works.
Total of Sheet 4 of Schedule C3:
Total of Sheet 1, Sheet 2, Sheet 3 and Sheet 4 of Schedule C3 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-69
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C4– INSTALLATION AND TESTING OF POWER SUPPLY SYSTEM AT
SUBSTATIONS
Sheet 1 of 3
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C4.1 Obtain Notice of No Objection or Notice of No Objection With Comment(s) from the Engineer for Inspection Test Plan, Testing and Commissioning Management Plan.
C4.2 Completion of installation, site testing and integrated testing for all sub-systems for the BSS, TSS, SSS, SP and P-SCADA as follows:
(a) DC Breaker at Depot SSS for PRI
(b) AC Breaker at Depot SSS for PRI
(c) Depot TSS
(d) Depot BSS
(e) Depot SSS
(f) East Valenzuela TSS
(g) East Valenzuela SSS
(h) Quirino Highway TSS
(i) Quirino Highway SSS
(j) Tandang Sore TSS
(k) Tandang Sora SSS
(l) North Avenue TSS
(m) North Avenue SSS
(n) Quezon Avenue SSS
Total of Sheet 1 of Schedule C4 carried forward to Sheet 2:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-70
COST CENTRE C – INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C4– INSTALLATION AND TESTING OF POWER SUPPLY SYSTEM AT
SUBSTATIONS
Sheet 2 of 3
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 1:
(o) East Avenue TSS
(p) East Avenue SSS
(q) Anonas TSS
(r) Anonas SSS
(s) Katipunan TSS
(t) Katipunan SSS
(u) Ortigas North TSS
(v) Ortigas North SSS
(w) Ortigas South SSS
(x) Kalayaan Avenue TSS
(y) Kalayaan Avenue SSS
(z) Bonifacio Global City SSS
(aa) Lawton TSS
(ab) Lawton SSS
Total of Sheet 2 of Schedule C4:
Total of Sheet 1 and Sheet 2 of Schedule C4 carried forward to Sheet 3:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-71
COST CENTRE C – INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C4 – INSTALLATION AND TESTING OF POWER SUPPLY SYSTEM AT
SUBSTATIONS
Sheet 3 of 3
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 2:
(ac) Lawton SP
(ad) Senate TSS
(ae) Senate SSS
(af) Senate BSS
(ag) Terminal 3 TSS
(ah) Terminal 3 SSS
C4.3 Completion of System Acceptance Test.
C4.4 Completion of the remaining works.
Total of Sheet 3 of Schedule C4:
Total of Sheet 1, Sheet 2 and Sheet 3 of Schedule C4 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-72
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C5–INSTALLATION AND TESTING OF POWER DISTRIBUTION SYSTEM
Sheet 1 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C5.1 Obtain Notice of No Objection or Notice of No Objection with Comment(s) from the Engineer for InspectionTest Plan, Testing and Commissioning Management Plan.
C5.2 Completion of installation, site testing and integrated testing for all sub-systems for the 34.5Kv Distribution System and emergency power supply for the following:
(a) PRI at Depot
(b) Depot
(c) East Valenzuela
(d) Quirino Highway
(e) Tandang Sora
(f) North Avenue
(g) Quezon Avenue
(h) East Avenue
(i) Anonas
(j) Katipunan
Total of Sheet 1 of Schedule C5 carried forward to Sheet 2:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-73
COST CENTRE C – INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C5 –INSTALLATION AND TESTING OF POWER DISTRIBUTION SYSTEM
Sheet 2 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 1:
(k) Ortigas North
(l) Ortigas South
(m) Kalayaan Avenue
(n) Bonifacio Global City
(o) Lawton
(p) Senate
(q) Terminal 3
C5.3 Completion of installation, site testing and integrated testing for all sub-systems for the Distribution System and tunnel lighting for the following:
(a) Depotfor PRI
(b) Depot to East Valenzuela Station
(c) East Valenzuela Station to Quirino Highway Station
(d) Quirino Highway Station to Tandang Sora Station
(e) Tandang Sora Station to North Avenue Station
Total of Sheet 2 of Schedule C5:
Total of Sheet 1 and Sheet 2 of Schedule C5 carried forward to Sheet 3:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-74
COST CENTRE C – INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C5 –INSTALLATION AND TESTING OF POWER DISTRIBUTION SYSTEM
Sheet 3 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 2:
(f) North Avenue Station to Quezon Avenue Station
(g) Quezon Avenue Station to East Avenue Station
(h) East Avenue Station to Anonas Station
(i) Anonas Station to Katipunan Station
(j) Katipunan Station to Ortigas North Station
(k) Ortigas North Station to Ortigas South Station
(l) Ortigas South Station to Kalayaan Avenue Station
(m) Kalayaan Avenue Station to Bonifacio Global City Station
(n) Bonifacio Global City Station to Lawton Station
Total of Sheet 3 of Schedule C5:
Total of Sheet 1, Sheet 2 and Sheet 3 of Schedule C5 carried forward to Sheet 4:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-75
COST CENTRE C – INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C5 –INSTALLATION AND TESTING OF POWER DISTRIBUTION SYSTEM
Sheet 4 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 3:
(o) Lawton Station to Senate Station
(p) Senate Station to Food Terminal Inc. (FTI) Station
(q) Senate Station to Terminal 3 Station
C5.4 Completion of system Acceptance Test.
C5.5 Completion of the remaining works.
Total of Sheet 4 of Schedule C5:
Total of Sheet 1, Sheet 2, Sheet and Sheet 4 of Schedule C5 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-76
COST CENTRE C – INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C6 –INSTALLATION AND TESTING OF OVERHEAD CONTACT SYSTEM
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C6.1 Obtain Notice of No Objection or Notice of No Objection With Comment(s) from the Engineer for InspectionTest Plan, Testing and Commissioning Management Plan.
C6.2 Completion of installation, site testing and integrated testing for the Overhead Contact System for the following:
(a) Depot (part inclusive) to PRI (inclusive)
(b) Depot (inclusive) to East Valenzuela Station (Exclusive)
(c) East Valenzuela Station (inclusive) to North Avenue Station (inclusive)
(d) North Avenue Station (exclusive) Station to Terminal 3 Station (inclusive)
C6.3 Completion of System Acceptance Test.
C6.4 Completion of the remaining works.
Total of Schedule C6 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-77
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C7 – INSTALLATION & TESTING OF AUTOMATIC FARE COLLECTION
SYSTEM
Sheet 1 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C7.1 Obtain Notice of No Objection or Notice of No Objection With Comment(s) from the Engineer for InspectionTest Plan, Testing and Commissioning Management Plan.
C7.2 Completion of installation and testing of all AFC equipment at the Depot and all Station (i.e. Station computers and station assistance terminals, automatic gates, ticket vending machines, points of sale, handheld terminals, special tools for cash counting, special tools for card counting, furniture within AFC rooms, customer service rooms and BMS rooms, uninterruptible power supply (UPS), power supply distribution facilities, local area network (LAN) and interfaces to the Telecommunication backbone network, including the standalone AFC at PRI:
(a) PRI building at Depot
(b) Depot
(c) Training Center
(d) East Valenzuela
(e) Quirino Highway
(f) Tandang Sora
(g) North Avenue
(h) Quezon Avenue
(i) East Avenue
Total of Sheet 1 of Schedule C7 carried forward to Sheet 2:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-78
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C7 – INSTALLATION & TESTING OF AUTOMATIC FARE COLLECTION
SYSTEM
Sheet 2 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 1:
(j) Anonas
(k) Katipunan
(l) Ortigas North
(m) Ortigas South
(n) Kalayaan Avenue
(o) Bonifacio Global City
(p) Lawton
(q) Senate
(r) Terminal 3
C7.3 Completion of installation and testing of card initialization devices at the following :
(a) PRI building at Depot (standalone Testing)
(b) Depot
(c) Training Center
(d) East Valenzuela
(e) Quirino Highway
Total of Sheet 2 of Schedule C7:
Total of Sheet 1 and Sheet 2 of Schedule C7 carried forward to sheet 3:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-79
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C7 – INSTALLATION & TESTING OF AUTOMATIC FARE COLLECTION
SYSTEM
Sheet 3 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 2:
(f) Tandang Sora
(g) North Avenue
(h) Quezon Avenue
(i) East Avenue
(j) Anonas
(k) Katipunan
(l) Ortigas North
(m) Ortigas South
(n) Kalayaan Avenue
(o) Bonifacio Global City
(p) Lawton
(q) Senate
Total of Sheet 3 of Schedule C7:
Total of Sheet 1, Sheet 2 and Sheet 3 of Schedule C7 carried forward to Sheet 4:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-80
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C7 – INSTALLATION & TESTING OF AUTOMATIC FARE COLLECTION
SYSTEM
Sheet 4 of 4
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 3:
(r) Terminal 3
C7.4 Completion of System Acceptance Test.
C7.5 Completion of the remaining works.
Total of Sheet 4 of Schedule C7:
Total of Sheet 1, Sheet 2, Sheet 3 and Sheet 4 of Schedule C7 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-81
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C8 – INSTALLATION & TESTING OF PLATFORM SCREEN DOORS
SYSTEM
Sheet 1 of 2
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
C8.1 Obtain Notice of No Objection or Notice of No Objection With Comment(s) from the Engineer for InspectionTest Plan, Testing and Commissioning Management Plan.
C8.2 Completion of installation and integrated testing of the Platform Screen Doors System including testing with the ATO:
(a) PRI
(b) East Valenzuela
(c) Quirino Highway
(d) Tandang Sora
(e) North Avenue
(f) Quezon Avenue
(g) East Avenue
(h) Anonas
(i) Katipunan
(j) Ortigas North
Total of Sheet 1 of Schedule C7 carried forward to Sheet 2:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-82
COST CENTRE C –INSTALLATION, TESTING AND COMMISSIONING
SCHEDULE C8 – INSTALLATION & TESTING OF PLATFORM SCREEN DOORS
SYSTEM
Sheet 2 of 2
ITEM
DESCRIPTION
AMOUNT
FOREIGN CURRENCY
PHP
Total carried forward from Sheet 1:
(k) Ortigas South
(l) Kalayaan Avenue
(m) Bonifacio Global City
(n) Lawton
(o) Senate
(p) Terminal 3
C8.3 Completion of System Acceptance Test.
C8.4 Completion of the remaining works.
Total of Sheet 2 of Schedule C8:
Total of Sheet 1 and Sheet 2 of Schedule C8 carried forward to Summary of Cost Centre C:
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-95
COST CENTRE E – PROVISIONAL SUMS
LABOUR, MATERIALS AND EQUIPMENT COSTS FOR DAYWORK
The Bidder shall complete Schedules E1, E2 and E3. The Bidder may add details and/or items
which he considers necessary for the evaluation of Daywork, to the Schedules.
SCHEDULE E1 – LABOUR COST FOR DAYWORK
Labour Daily Rate
(PHP)
No. of Man-
days
Amount
FOREIGN CURRENCY
PHP
Supervisor 100
Assistant
Supervisor
100
Welder 100
Electrician 100
Carpenter 100
Skilled Worker 100
Unskilled
Worker
100
Total of Schedule E1 to be carried forward to
Summary of Cost Centre E:
Note.: The role is an example only, Contractor to specify roles.
The daily rates shall be inclusive of all direct costs, overheads and profit.
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-96
COST CENTRE E – PROVISIONAL SUMS
SCHEDULE E2 – MATERIAL COST FOR DAYWORK
Material Rate
(PHP)
Unit Quantity Amount
FOREIGN CURRENCY
PHP
Coarse
aggregate for
Concrete and
asphalt concrete
1,000
Fine aggregate
for Concrete
and asphalt
concrete
1,000
Portland
Cement 200
Reinforcing
Steel 50
Wood Pile 200
Section Steel 20
Corrugated
Steel Pipe 100
Total of Schedule E2 to be carried forward to Summary of
Cost Centre E:
The unit rates shall be inclusive of all direct costs, overheads and profit.
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PACKAGE CP106: E&M SYSTEMS AND TRACK WORKS
BF-97
COST CENTRE E – PROVISIONAL SUMS
SCHEDULE E3 – CONTRACTOR’S EQUIPMENT COST FOR DAYWORK
The Bidder may add details of equipment capacities where necessary.
Equipment Daily Rate
(PHP)
No. of Man-
days
Amount
FOREIGN CURRENCY
PHP
Backhoe Loader 100
Bulldozer 100
Dump Truck 100
Tyre Roller 100
Truck Crane 100
Water Distributor
Truck 100
Asphalt Finisher 100
Truck Mixer 100
Tractor Shovel 100
Air Compressor 100
Generator 100
Concrete Breaker 100
Winch 100
Submersible Pump 100
Tamper 100
Total of Schedule E3 to be carried forward to
Summary of Cost Centre E:
The daily rates shall be inclusive of all direct costs, overheads and profit.
Name of Bidder _________________________________________________________
Signature of Bidder ______________________________ Date ___________________
General Bid Bulletin No.1
Annex “C”
PC-5
ATTACHMENT 1 TO PARTICULAR CONDITIONS
PART A CONTRACT DATA
SCHEDULE OF KEY DATES
Week Nos. shown in the Schedule of Key Dates represent lapsed time in weeks from the
Commencement Date. The Week Nos. shall be converted to actual Calendar dates upon receipt
by the Contractor of the Engineer’s instruction to commence the Works.
The Contractor shall achieve the Key Dates within the working hours of the last day of the week
specified. The delay damages stipulated in Part A Contract Data of the Particular Conditions
are applicable for delays in achieving the Key Dates.
SCHEDULE OF KEY DATES
PO Section
Remaining Section
Key Date Description Week No.
KD -PO-1 Completion of all works in East Valenzuela Station in CP101 87
KD -PO-2 HV Power On 205
KD -PO-3 Completion of all sub-systems to enable CP107 to test
1st Train 227
KD -PO-4 Commencement of Trial Run 244
KD-PO-5 Completion of Trial Run for PO section 257
Key Date Description Week No.
KD -RS-1 HV Power On Quezon Avenue Station in CP102 222
KD -RS-2 HV Power On East Avenue Station in CP102 222
KD -RS-3 HV Power On Anonas Station in CP103 222
KD -RS-4 HV Power On Katipunan Station in CP103 222
General Bid Bulletin No.1
Annex “C”
PC-6
KD -RS-5 HV Power On Ortigas North Station in CP104 222
KD -RS-6 HV Power On Ortigas South Station in CP104 222
KD -RS-7 HV Power On Kalayaan Station in CP105 257
KD -RS-8 HV Power On Bonifacio Global City Station in CP105 257
KD -RS-9 HV Power On Lawton Station in CP108 257
KD -RS-10 HV Power On Senate Station in CP108 257
KD -RS-11 HV Power On T3 Station in CP109 270
KD-RS-12 Completion of all sub-systems for the first civil batchto enable
train testing by CP107 for Remaining Section 248
KD-RS-13 Commencement of Trial Run 309
KD-RS-14 Completion of Works 322
General Bid Bulletin No.1
Annex “C”
PC-7
ATTACHMENT 2 TO PARTICULAR CONDITIONS
SCHEDULE OF ACCESS DATES
PO Section
Remaining Section
Access Date Description Week No.
AD -PO-1 Access for Track Work in East Valenzuela Station in CP101 48
AD -PO-2 Access for Equipment rooms in East Valenzuela Station in CP101 70
AD -PO-3 Access to Depot 130
AD -PO-4 Access to Quirino Highway Station in CP101 165
AD -PO-5 Access to North Avenue Station in CP101 165
AD -PO-6 Access to Tandang Sora Station in CP101 165
Key Date Description Week No.
AD -RS-1 Access to Ortigas North Station in CP104 170
AD -RS-2 Access to Ortigas South Station in CP104 170
AD -RS-3 Access to Quezon Avenue Station in CP102 170
AD -RS-4 Access to East Avenue Station in CP102 170
AD -RS-5 Access to Anonas Station in CP103 170
AD -RS-6 Access to Katipunan Station in CP103 170
AD -RS-7 Access to Kalayaan Station in CP105 205
AD -RS-8 Access to Bonifacio Global City Station in CP105 205
AD -RS-9 Access to Lawton Station in CP108 205
AD -RS-10 Access to Senate Station in CP108 205
AD -RS-11 Access to T3 Station in CP109 218