Corrigendum 2 SMR-MED1-CP109-2021L-PT - SAMEER
Transcript of Corrigendum 2 SMR-MED1-CP109-2021L-PT - SAMEER
Page 1 of 17
Society for Applied Microwave Electronics Engineering & Research
IIT Campus, Hill Side, Powai, Mumbai 400 076
CORRIGENDUM
TENDER NO.: SMR/MED1/CP109/2021L/PT
SUB. : Supply, Installation, testing & Commissioning (SITC
Basis) of HYDROGEN BRAZING/ANNEALING FURNACES
Qty: 02 Nos.
DUE ON : 16/03/2021
Sd/ Purchase officer
Page 2 of 17
Contents
SECTION - II : TECHNICAL SPECIFICATION ........................................................................................ 3
Page 3 of 17
SECTION - II : TECHNICAL SPECIFICATION
SCOPE: supply, installation, testing & commissioning (SITC Basis) of Hydrogen Brazing/Annealing
Furnaces and buyback offer for SAMEER old existing H2/Vacuum Furnace at actual for item NO.2
Item No. 01 : Hydrogen Brazing/Annealing Furnace
Size: 200 mm diameter x 300 mm height
Qty: 01
Heating Retort
Sr. No. Required Specifications State
Complied/Not Complied
Mention Deviation if any
1. Configuration Vertically Mounted Cylindrical
Construction
2. Retort (Working
Hot Zone)
200 mm diameter x 300 mm height
3. Material of
Construction
Inconel 600
4. Top Side Welded with dish end
5. Bottom Side Welded with mild steel flange which
will achieve sealing with bottom base
plate.
6. Lifting Hook Retort on the top should provide
with a lifting hook to lift the retort
whenever required.
7. Bottom Plate Bottom plate made of stainless Steel
SS304 with water cooling
arrangement with Viton 'O' ring
provided to achieve sealing with
retort flange
8. Pressure Relief
Valve
Pressure Relief Valve should provide
with a extended Inconel 600 Pipe to
release the excess pressure during
operation.
9. Max Charge 10 Kgs
10. Max. Design
Temperature
1200 C
11. Maximum
Operating
Temperature
1100 C
12. Number of Hot
Zones
03
13. Heating Rate 5-10 C/Min
14. Time to attend
Max. Temp.
110 mins@10 C/Mins
Page 4 of 17
Item No 02: Hydrogen Brazing/Annealing Furnace:
(300 mm diameter x 750 mm height)
Qty: 01
Heating Retort
Sr. No. Required Specification State
Complied/Not Complied
Mention Deviation if any
1. Configuration Vertically Mounted Cylindrical
Construction
2. Retort (Working
Hot Zone)
300 mm diameter x 750 mm height
3. Material of
Construction
Inconel 600
4. Top Side Welded with dish end
5. Bottom Side Welded with mild steel flange which
will achieve sealing with bottom base
plate.
6. Lifting Hook Retort on the top should provide with
a lifting hook to lift the retort
whenever required.
7. Bottom Plate Bottom plate made of stainless Steel
SS304 with water cooling
arrangement with Viton 'O' ring
provided to achieve sealing with
retort flange
8. Pressure Relief
Valve
Pressure Relief Valve should provide
with a extended Inconel 600 Pipe to
release the excess pressure during
operation.
9. Max Charge 40 Kgs.
10. Max. Design
Temperature
1200 C
11. Maximum
Operating
Temperature
1100 C
12. Number of Hot
Zones
03
13. Heating Rate 5-10 C/Min
14. Time to attend
Max. Temp.
110 mins@10 C/Mins
Page 5 of 17
ITEM NO.03: BUYBACK OFFER/CHARGE FOR SAMEER EXISTING VACUUM CUM
HYDROGEN FURNACE FOR ITEM NO.02 (H2 FURNACE)
Note: Above buyback offer for item No.2 (H2 furnace) is mandatory and should be
quoted in price bid, failing which tender may be rejected. Bidder may visit SAMEER
IIT Campus Powai Mumbai to inspect old furnace before submitting the offer.
BUYBACK work includes: Dismantling, Packing and Taking away in suitable
transportation old vacuum cum H2 furnace from SAMEER IIT Campus Powai Mumbai
premises.
Technical specifications for Item No.01 & Item No.02
S.N. Required Specifications State whether
Complied/Not
Complied,
Mention
Deviation if any
01 Method of Heating
Heating Bell
Heating Bell should be consisting of Kanthyal APM heating
elements (Strips/rods) arranged in suitable fashion
supported on fibrothal insulation in the heating bell to
achieve maximum operating temperature of 1100 C on the
retort. The heaters should arrange in three zones for
uniform temperature distribution on the retort. Make
proper arrangement to shifting heating bell at rest station
when furnace is OFF. Keep diameter of Heating bell as
smaller as per retort diameter.
02 Heating Insulation
Heat insulation should be of FIBROTHAL Vacuum formed
Board insulation arranged in a circular fashion to avoid
heat loss to the atmosphere. The entire insulation should
be supported on a metal structure, outer case
temperature should be room temperature during
operation of furnace..
03 Furnace Input Power
415 V +/- 10%, 3 Phase, 5 Wires, 50 HZ (Total Power
should be given by party for both the furnaces)
Page 6 of 17
04 Furnace Casing
The Furnace casing should be fabricated form 6 mm thick
commercial quality MS Plates duly reinforced structural
members make the casing rigid and strong so as to
withstand operational stresses, roof thrust and thermal
expansion. Bottom of the bell should provided with 20 mm
thick MS ring to support the bell while resting on the legs.
05 Temperature Measurement and Control
The temperature measurement and control should be
done by temperature programmable Controller of reputed
make like M/s. EUROTHERM/YOKOGAWA and by 3 Nos. of
PID controller (Salve Controller) to control the hot zone
independently. Each Zone should provide with "K" type
thermocouple to feed the signal to the programmer for
control purpose.
An over temperature controller with "K " type
thermocouple should also provided for over temperature
protection in case of heater failure or Thyristor power
failure for each zone. In total 3 Nos. of over temperature
controllers should provide.
The heating bell should be dividing into three zones of
control. The heating should be through a programmable
controller of reputed make like Eurothem, Honeywell etc
using three phase Thyristor control circuit with isolation
transformer. Provision for manual heating should also
exist. The process controller should be able to compare
the temperature set points with the thermocouple
readings and send appropriate signals to the power
controllers, Digital display of temperature with a
resolution of +/- 1 degree should be incorporate. Provision
for over temperature protection should be available i.e.
over temperature controller to be incorporated.
A process controller should take care of the automatic
sequence of operations and safety interlocks like over
temp, water, gas flow etc.
Also list out the safety interlocks that are proposed to
incorporated in the normal mode of operation.
Proper interlock should work at failure of any of the input.
The time to attend the Max operating temp 1100
Page 7 of 17
Centigrade should be around 110 mins. however provision
for varying the heating rate to say about 5 to 10 Deg
centigrade per minutes should also be available. The ramp
& soak should be controlled.
The schematic of the proposed electrical wiring form the
mains to the furnace should be indicated.
06 Support Structure
Support Structure made of Mild Steel should provide to
support the Retort and heating bell. The top support plate
made of chequered plate should have approx. dimension
to supported with mild steel channels.
07 Job Hearth Support/Plate
1) Job hearth plate should be mount on rod made Incone-
600l and 200 mm dia plate made Inconel-600 to take job
load 10 Kg. should be provided, It should be easily
demountable. Max Charge 10 Kgs. (FOR ITEM NO.01 Small
Furnace)
2) Job hearth plate should be mount on rod made Inconel-
600 and 300 mm dia plate made Inconel-600 to take job
load 40 Kg. should be provided, It should be easily
demountable. Max Charge 40 Kgs. (For ITEM NO.02 Big
Furnace)
for both furnaces below the support plate heat radiation
shields made of Molybdenum of 1 mm thick 3 Nos and 2
Nos. SS shield should be provided. ((Additional shields may
be provided the temperature of base plate, based on
thermal calculation)
Proper clamping arrangement should be provided
between Retort and base flange to avoided leak during
operation.
The entire Hearth Support should be support on the
bottom plate. Provision should be made to adjust the job
support plate with bottom radiation shields.
An Inconel-600 tube should be provided to introduce
Page 8 of 17
Hydrogen/Nitrogen into the Retort. Also Flexible "K" type
thermocouple should provide to check the job
temperature. Also provision to made on Control Panel to
monitor mili-volts signals to monitor temperature during
operation.
08 Atmosphere Control
The furnace should have provisions for the flow of
nitrogen and hydrogen gases through
programmed/manual valves and preset flow meters ( 5 to
100 Ltrs/mins) . The sequence of operation in case of
N2 floe: 5 to 60 Ltrs/Mins for purging
H2 Flow: 5 to 45 Ltrs/Mins during Operation
1) Loss of Hydrogen pressure in the chamber or
2) Power failure during operation should be clearly
mentioned
The furnace should have a N2 purge, H2 purge followed
brazing operation again N2 purge And power OFF.
The Ignition sequence for the hydrogen burn-OFF should
given.
The safety precautions to be mentioned, should the flame
be inadvertently extinguished. The Igniter should be
automatically tested to assure proper operation each time
run is started.
All gas plumbing and components should be of stainless
steel, high quality, and high-pressure standard fitting.
09 Furnace Control Panel
The control panel should be an independent unit which
should house PID controllers, Process controllers,
Ammeters, Voltmeters, Mimic Diagram, fault indicating
lamps, Ckt breakers, Fuses, Thyristor Ckt, audio alarms,
visible indications for furnace ON etc. The components in
the control panel should be reputed make like Siemens,
ABB or equivalents.
Page 9 of 17
10 MONO Rail System (Hoist Crane)
Suitable weight capacity Monorail System for both the
furnaces should consists of horizontal and vertical structures
fabricated from "C" channels and vertical channels should
grout to the ground. On the horizontal channels motor with
brakes and two speed arrangement (Micro & Normal speed
controlled on hand paddle switch). Overhead chain hoist pulley
block should provide for upward and downward movement
and also for the horizontal movement to lift and move the
heating bell to rest station and also to lift the retort up & down
for job loading and unloading.
Refer As per attached Drawing
11 JOB REST STATION
Rest Station for both the furnaces should be provided to keep
heating bell during job loading in furnace.
12 Gas Inlet System
Gas Inlet System should consist of SS Manifold, Which should
be connected to the Hydrogen and Nitrogen Cylinders with 2
Stage regulators (SAMEER Scope). The outlet of the manifold
should provide with manually operated isolation valves,
solenoid operated valve, flow meters (adjustable) for
Hydrogen and Nitrogen having flow range 5-100 ltrs/mins. All
stainless steel plumbing lines and fittings with pressure gauge,
pressure switch should be connected to the bottom base plate.
13 Hydrogen Flow System:
At the outlet end glass bowl should be provided with
resistance heater igniter & thermocouple. The resistance
heater ignites the output coming hydrogen and burns it. The
temperature of the hydrogen flame should be sensed by the
thermocouple & indicated on a digital temperature
indicator/controller. If flame gets OFF, the temperature given
signal & alarm start with H2 inlet solenoid valve to close, and
immediately the emergency N2 line solenoid valve to open
automatically to purge the Retort with N2 to dilute the H2
concentration.
Page 10 of 17
14 Power Supply
This whole furnace should be wired to operate on 415 VAC, 3
Phase, 50 HZ with Power neutral & Ground connections. The
maximum power consumption should be informed by vendor
for both the furnaces. A suitable triple pole mains fuse isolator
should be provided between the furnace & mains power
supply.
Isolation Transformer should be provided in heating Circuit.
15 Water Supply
Water cooling connections should be provided for electrical
feed through, flanges, O-Rings, Bottom plate, and other
components wherever required. with water pressure 3 to 4
Kgs/cm2
16 Emergency automatic solenoid valve operated N2 supply
During power failure there should be provided an automatic
solenoid valve operated N2 pursing for furnace. Automatically
H2 Supply stop and N2 Supply start during Power failure. After
Power resume again H2 line should open & N2 line stop.
17 SAFETY ISSUE
1) The Furnace shall be in conformance with all applicable
electrical, fire & safety standards.
2) The furnace shall be fitted with alarm devices for over
temp/any input failure. The Maximum temp should be settable
from the control panel.
3) The various safety interlocks incorporated should be listed
out.
4) The event of power failure during brazing operation, the
precautions that should be taken shall be listed out. The
sequence of operation after resumption of power should be
mentioned.
Page 11 of 17
18 Bidders are required to furnish following technical documents
1) Detailed description of furnace with drawing (Technical Bid)
2) General arrangement drawings of the furnace.
3) A picture of similar furnace
3) Detail descriptions of each component and sub components
5) Footprint of the entire furnace system.
6) Detailed descriptions of SAMEER's responsibilities for the
site preparation
7) Detailed descriptions of the safety issues addressed and
suggested by the vendor.
8) Testing plan
9) Maintenance & service
11) Shipment plan
State Yes/No
Special Terms & Conditions
The work consists of design, fabrication, delivery, installation, commissioning (SITC
Basis) of furnaces at SAMEER IIT Campus, Powai Mumbai as per specifications
given in this document.
1) Only after approval of the engineering drawings from SAMEER for both the
furnaces, the fabrication of furnace should commence.
2) The entire furnace operation should be demonstrated to the rated specifications
and for proper functioning of all the subsystems as per design. Only after this, the
furnace will be cleared for dispatch to SAMEER, IIT Campus, Powai, Mumbai.
Page 12 of 17
3) Delivery, unloading at SAMEER, Installation & commissioning of the furnace is to
be done at SAMEER, IIT Campus, Powai Mumbai, also clearly indicate installation
time after delivery of furnaces at SAMEER IIT Powai Mumbai.
4) The entire furnace operation should be demonstrated again at SAMEER IIT
Campus, Powai Mumbai.
5) Two sets of operating instructions & maintenance manuals should be provided.
Training to operate the furnace should be provided to at least three Engineers from
SAMEER at vendor site.
6) Please quote for minimum critical spares, which may be procured to meet
contingencies.
7) Quotation should be clear and wherever necessary options may be quoted.
8) All Govt levies & taxes and any other charges should be clearly indicated.
9) Indicative drawing of both furnaces attached for reference.
For any technical clarifications , you may contact following SAMEER Officials.
1. Mr. Chandrakant Nainwad, Scientific Officer-SE 022-2572 7204
2. Mr. R Krishnan, Scientist & HOD MED1 022-2572 7125
Page 13 of 17
Information required for Vendor Evaluation – To be submitted with Technical Bid
The Vendors will be evaluated by the team of experts from SAMEER based on the
essential requirements of vendor’s qualification as laid down below. Only on
satisfactory conditions of evaluation the bid will be considered. It is important to
note that this is one of the qualifying criteria.
Bidders are required to indicate whether the required information is furnished by
stating Yes / No in the remarks column.
The detail information as asked is to be furnished on the separate sheets.
A. Company Profile REMARKS
1 Name of the Organization:
Website:
2 Name of the Contact Person:
Name:
Address:
Telephone:
Fax:
E-Mail:
YES/NO
3 Year of Incorporation:
YES/NO
4 Type of Organisation
(Public Sector/Limited/Private Limited / Partnership / Propritery
/Society / Any Other):
YES/NO
5 Address of the Registered Office:
YES/NO
6 Number of Offices with addresses (Excluding Registered Office):
India
Abroad
YES/NO
7 Certificate of registration as a manufacturing unit
YES/NO
8 Permanent Account Number
YES/NO
9 GSTN:
YES/NO
10 Status of ISO9001/IS013485 Certification
YES/NO
Page 14 of 17
VENDOR QUALIFICATON: ESSENTIAL REQUIREMENTS REMARKS*
A. Vendor should have adequate manpower to undertake this work
The manpower strength at various levels to be furnished
a. B.E. / B.TECH.
b. DIPLOMA
c. SKILLED TECHNICIANS
d. UNSKILLED
YES/NO
B. Vendor should have adequate manufacturing facilities for part and subassembly
fabrication related to this work.
The list of machine tools and other electrical/electronic equipments available
to be furnished.
YES/NO
C. Vendor should have adequate inspection and quality control facilities for this work.
The list of quality control instruments available to be furnished.
YES/NO
D. Vendor should have adequate space for undertaking this work.
Available space – Covered & Open to be furnished.
YES/NO
E. Vendor should have sound financial back ground and a proven record. They should
have taken up similar or more complicated jobs and executed successfully.
List of five assignments done in last three years to be enclosed.
Enclose copies of purchase orders.
Audited Balance sheet of last three years to be furnished.
YES/NO
F. List of minimum 5 customers to be furnished by the Vendor for whom similar work
has been satisfactorily completed.
Give complete address & Telephone Number of the contact person
YES/NO
G.The industry should have service engineers to attend service calls for this
unit. The service network to be furnished.
*Strike out which is not applicable
Page 15 of 17
Page 16 of 17
Page 17 of 17
1) PHOTO OF H2 FURNCACE (EXISTING IN SAMEER)
2) JOB LOADING HERTH PLATE WITH LIFTING DOME