Corporate Spill Contingency Plan
Transcript of Corporate Spill Contingency Plan
Corporate Spill Contingency Plan
Document Code: 12002-PDR-SSHE-503-005-R01
December 2016
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed, visit PTTEP intranet for the latest version. Page D
Revision History
Rev. Description of Revision Authorised by Date
0 New CSH Dec 2011
1 Add
List of approved dispersants in Thailand
Request form of dispersant application for approval in Thailand
Tier2 Equipment Stockpile
Update
- Role & Responsibility of Corporate and asset during exploration drilling phase
- Role & Responsibility of Corporate and asset during production drilling phase
- Role & Responsibility of Corporate and asset for Tier 2 & 3 Equipment Request
- Tier2 and Tier3 Communication Flow and appendices
TSH Dec 2016
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed, visit PTTEP intranet for the latest version. Page E
TABLE OF CONTENTS
1. PURPOSE ................................................................................................................................ 1
2. SCOPE ..................................................................................................................................... 1
3. REFERENCES ......................................................................................................................... 1
4. DEFINITIONS .......................................................................................................................... 2
5. ROLES AND RESPONSIBILITIES .......................................................................................... 5
6. CORPORATE SPILL CONTINGENCY PLAN ......................................................................... 5
APPENDIX A: TIER 2 SPILL RESPONSE EQUIPMENT FOR THAILAND DOMESTIC ASSET .......... 13
APPENDIX B: STSC SPILL RESPONSE EQUIPMENT REQUEST FLOW FOR THAILAND (IESG) .. 15
APPENDIX C: STSC SPILL RESPONSE EQUIPMENT REQUEST FORM (IESG) ....................... 16
APPENDIX D: REQUEST FORM OF DISPERSANT APPLICATION FOR APPROVAL IN THAILAND ..17
APPENDIX E: LIST OF APPROVED DISPERSANT IN THAILAND ............................................... 18
APPENDIX F: CONTACT FOR EQUIPMENT MOBILIZATION UNDER IESG MEMBERSHIP ...... 21
APPENDIX G: OIL SPILL INTERNAL NOTIFICATION EXAMPLE ................................................. 29
APPENDIX H: EMERGENCY REPORT FORM TO PTT ................................................................. 31
APPENDIX I: OSRL NOTIFICATION AND MOBILISATION PROCEDURE ................................... 35
APPENDIX J: OIL SPILL CONTRACTS PTTEP’S NOMINATED CALL-OUT AUTHORITIES ....... 40
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 1 of 42
1. PURPOSE
Spill contingency planning is the process of developing a suitable spill response that is in compliance
with the PTT group’s requirement, local regulatory framework and commensurate with the spill risks of
an organization or facility (IPIECA-IOGP, 2015). PTT Exploration and Production (PTTEP) Corporate
developed this document to provide spill response protocol and communication for PTTEP Corporate
level manage spill risks arising from their operations that have the potential to impact the environment.
2. SCOPE
This document is to be used for spill management planning of exploration, development and
production activities for both onshore and offshore operations of any Asset. Spill encompass
petroleum hydrocarbons which are identified either as products from PTTEP or liquid hydrocarbon
used as fuel. In addition, other petroleum hydrocarbon materials/chemicals shall comply with the
requirements of this document as well.
Compliance to the specifications described in this document is mandated for all PTTEP operating
assets and its subsidiaries. Where PTTEP is a Joint Venture (JV) Partner or Joint Operator with under
PTTEP’s operational or financial control, compliance to this guide is mandated where PTTEP has
legal obligations on the management of spill risks, unless otherwise specified in the operational
agreement.
3. REFERENCES
This document is used in conjunction of the following documents:
PTTEP SSHE CONTROLLING DOCUMENTS
Document Number Document Title
SSHE-106-STD-340 SSHE Training and Competency Standard
SSHE-106-STD-400 SSHE Risk Management Standard
SSHE-106-STD-500 Emergency and Crisis Management Standard
SSHE-106-STD-600 Incident Management Standard
SSHE-106-PDR-501 Crisis Management Plan
SSHE-106-PDR-502 Emergency Management Plan
SSHE-106-PDR-521 Waste Management Procedure
SSHE-106-GDL-526 Net Environmental Benefit Analysis Guideline
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 2 of 42
OTHER REFERENCE DOCUMENTS
Document Number Document Title
1 IPIECA_IOGP Oil Spill Response Joint Industry Project
http://www.oilspillresponseproject.org/
2 ITOPF Technical Information
http://www.itopf.com/knowledge-resources/documents-guides/
3 Oil Spill Response Field Guides
https://www.oilspillresponse.com/technical-library/?tag=Field%20Guides
4. DEFINITIONS
In this document, the terms used have the following meanings:
GENERAL DEFINITIONS
Terminology Description
Spill Response Plan (SRP) Refers to spill contingency plan. This document specifies details
on how to manage oil spill incidents and maintenance of
emergency response resources specific to oil spill scenarios. In
different countries, this document may have different titles, such
as Oil Spill Response Plan or Oil Pollution Emergency Plan.
However, the purpose and information contained are similar.
Spill Spill is defined as any loss of containment that reached the
environment. The spill volume reported should reflect the volume
of material that reached the environment only (i.e. not inclusive of
any released volume retained within secondary or other
confinement). Reported volume reaching the environment is
irrespective of the quantity recovered (i.e. represents the gross
volume reaching the environment, not a net volume remaining in
the environment).
Spills of produced water or process wastewater are excluded.
Loss of containment resulting from acts of sabotage (such as theft
of oil from pipelines and storage) shall be reported. Loss as a
result of “acts of terrorism”/ attacks on infrastructure should not be
reported.
Intentional discharges of drill cutting (only offshore operations
exceed 12 nautical miles) during drilling activities are excluded.
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 3 of 42
Planning scenario Selected scenarios derived from the risk assessment result that is
used as the basis for planning of oil spill response. The selection
should represent the full range of response challenges and risks
against which response strategies and a tiered capability can be
defined.
Worst credible case
discharge
Scenario with the largest release that could reasonably be
expected from a facility or operation. Such events may lead to the
most severe consequences.
Emergency Response
Team (ERT)
Site emergency response team responsible to conduct the tactical
/ in-field responses.
Emergency Management
Team (EMT)
Asset emergency management team responsible for strategic
responses.
Crisis Management Team
(CMT)
Asset crisis management team responsible to respond to an
actual or potential incident (whether of PTTEP origin or not) be in
Local, National or International, on a scale that may become of
significant concern to Company business.
Net Environmental Benefit
Analysis (NEBA)
This is a process used by the spill response community for
making the best response options to minimise impacts of oil spills
on people and the environment.
More details of definition are addressed in Incident Management Standard, SSHE-106-STD-600.
ORGANISATION AND DEPARTMENTS
Terminology Description
Corporate Refers to the PTTEP business groups hierarchically above
asset level, and located in the PTTEP headquarters,
Bangkok.
Function Group Refers to a corporate level business group. These may
have associated divisions, departments, or operational
assets within their hierarchy.
Division A business group may have one or more distinct groups
within its hierarchy. These are referred to as divisions.
Asset Refers to an operating asset, site, or location within a
respective Function Group.
Department A subgroup within a Function Group, division or asset.
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 4 of 42
LANGUAGE
May Indicates a possible course of action
Should Indicates a preferred course of action
Shall Indicates a course of action with a mandatory status
COMMON ACRONYMS
Set out below are common specific terms presented in alphabetical order:
CMT Crisis Management Team
DSV Drilling Supervisor
EMT Emergency Management Team
GSX Geoscience and Exploration Group
IC Incident Commander
IESG Oil Industry Environmental Safety Group Association
IOGP International Association of Oil & Gas Producers
IPIECA Global oil and gas industry association for environmental
and social issues
ITOPF International Tanker Owners Pollution Federation Limited
JV Joint Venture
MD Marine Department
NEBA Net Environmental Benefit Analysis
OIM Offshore Installation Manager
OSC On Scene Commander
OSRL Oil Spill Response Limited
OSRO Oil Spill Response Organisation
PCD Pollution Control Department
PTTEP PTT Exploration and Production Public Company Limited
STSC South Area Sub-Committee of IESG
SRP Spill Response Plan
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 5 of 42
5. ROLES AND RESPONSIBILITIES
DOCUMENT OWNER
The owner of this Procedure is the VP, Environmental Management Department, with responsibilities
for:
Approval and issuance of the Procedure and its revisions.
Ensuring effective implementation of the Procedure.
CUSTODIAN OF DOCUMENT
The custodian of this Procedure is Manager, Environmental Applications Section, with responsibilities
for:
Identifying deficiencies or potential improvements.
Initiating periodic revision.
Maintaining revision history and document status register.
Note: Roles and Responsibilities of relevant personnel shall follow the Emergency and Crisis
Management Standard (SSHE-106-STD-500).
6. CORPORATE SPILL CONTINGENCY PLAN
Corporate Spill Response Plan describes the spill response protocol for managing spills arising from
PTTEP Assets that require Corporate level support. Activation of spill response at the Corporate level
is required when the Tier 1 spill response resources prepared by asset are overwhelmed or
complexities raises to a level that is beyond the capability of the operating asset. This usually
encompasses Tier 2 and Tier 3 spill incidents, although there are instances where Tier 1 spills may
require Corporate support (as necessary). Sensitivity map of oil spill contingency planning for risk
assessment can be found in EIA report or environmental sensitivity map provided by local academic,
government or international studies.
SPILL RESPONSE MANAGEMENT PHILOSOPHY
Generally, spill incident in oil and gas exploration and production business is classified based on the
3-Tiered response system in accordance with the IOGP approach. PTTEP applies the IOGP approach
regarding tier classification into SSHE Risk Management Standard (SSHE-106-STD-400), Emergency
and Crisis Management Standard (SSHE-106-STD-500), and PTTEP Incident Management Standard
(SSHE-106-STD-600) which has more details and definition about severity or impact to people,
environment, asset and reputation.
Assets shall prepare the appropriate / adequate equipment / material / trained personnel for Tier 1 as
a minimum, either pool or individual stock basis depending on their risk assessment results in the
planning scenarios. These requirements shall adhere to the National Oil Spill Response Plan for the
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 6 of 42
country of operation and PTTEP standards. Each of the Asset Spill Contingency Plan shall be
reviewed by PTTEP Corporate for advisory and alignment with this procedure.
When the spill is assessed to likely lead to Tier 2 or 3 situations, Asset shall notify and request for
EMT or CMT setup immediately to ensure that any supplementary equipment / materials required for
combating the spill from national and / or international organizations are secured in timely manner.
6.1.1 SPILL MANAGEMENT ORGANISATION
All PTTEP Assets shall follow the spill management organisation as similar as provided in Figure 1.
6.1.2 RESPONSIBILITIES OF THE SPILL MANAGEMENT TEAM
The roles and responsibilities of the Corporate Spill Management Team members referred to the
Emergency Management Team Specific Duties in the Emergency Management Plan (SSHE-106-
PDR-502) and Crisis Management Plan (SSHE-106-PDR-501) for handling spills under Tier 2 and 3
classifications respectively. For Tier 1 response teams, these shall be referred in the Site/Asset Spill
Response Plan.
In production phase, on-scene commander of Tier 1 spill incident is OIM or Field Manager. While
incident becomes Tier 2 or 3, incident commander will be SVP/EVP of affected asset as per role &
responsibility described in Emergency Management Plan (SSHE-106-PDR-502) and Crisis
Management Plan (SSHE-106-PDR-501).
For spill incident during drilling activities in production phase, on-scene commander will be Offshore
Installation Manager (OIM)/Drilling Supervisor (DSV) for Tier 1, and incident commander will be VP of
affected asset. Drilling contractor under well operation division shall provide on-site spill response
equipment / personnel as compulsory to ensure that Tier 1 can be handle. While incident becomes
Tier 2 or 3, incident commander will be asset SVP as per role & responsibility in Emergency
Management Plan (SSHE-106-PDR-502). EVP of affected asset shall be in CMT in Tier 3 situation to
align with Crisis Management Plan (SSHE-106-PDR-501).
For spill contingency plan in exploration phase, spill response equipment or services from reliable
local contractor is recommended to prepare by GSX under advisory of corporate SSHE Division. On-
scene commander of Tier 1 is Offshore Installation Manager (OIM)/Drilling Supervisor (DSV) or VP of
GSX. Incident commander for Tier 2 is SVP, and Tier 3 EVP of GSX will manage the crisis as a
member of CMT.
6.1.3 SPILL NOTIFICATION PROCESS
The international assets shall determine and perform the in-country notification process for all internal (PTTEP
Corporate) and external communications, including communication to regulatory bodies. The communication
protocol with regulatory bodies shall be informed and updated to corporate to ensure the effectiveness of spill
response plan. It is the responsibility of the Asset to understand and outline in their Spill Contingency Plan the
regulated notification timelines to the regulatory bodies. This is applicable for all spills from Tiers 1, 2 and 3.
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 7 of 42
For spilled incident reporting to regulatory bodies in Thailand domestic assets, asset have to notify was
firstly department of Mineral Fuels (DMF) and Corporate. Contact numbers are provided in Appendix.
Once incident likely uncontrolled, asset and corporate will support each other regarding update situation
to additional regulatory bodies (Marine department for spill to water, Disaster prevention and mitigation
department for spill on land) to control incident. Any update situation to medias, report to PTT Group or
seek for mutual aid agreement for Tier 2 or 3 will be handle by Corporate.
For all Tiers 2/3 spill, the assets shall also inform the Bangkok Telephone Operator as soon as practically
possible. This is to ensure the Asset receives immediate support from Corporate for any required
assistance, and allows the Corporate level Emergency Management Team (EMT) and Crisis Management
Team (CMT) to be set up in a timely manner. Spill notification process is provided in Figure 2.
PTTEP (Core Team) Support Team
Tier 3
Crisis Management Team Global or International
Resource
CEO - CMT Leader • Multi-national governments
• Spill-related International
organization/committee
• Mutual aid agreement
• Private spill response
organization (on-call)
• Concerned Authorities
• All EVPs • CCR - Media • TSH - SSHE • CLG - Legal • FRM - Risk Management
Tier 2 Emergency Management Team
Local or National
Resource
SVP Affected Asset Incident Commander (IC)
• National governments
• Spill-related national
organization/committee
• Mutual aid agreement
• Private spill response
organization (on-call)
• Concerned Authorities
• Media Response Team • Relative Response Team • SSHE • Production • Logistic • Drilling • Well Services • Geology • Construction
Tier 1 Site Emergency Response
Team
PTTEP or At site
Response
Field Manager
On-Scene Commander (OC)
• Response Equipment
• Manpower
• Intervention Team Fire Fighting • Logistic/Marine • Shutdown Team • Medical Team • Other Support Team(s)
Figure 1: Tier, Organization and Resource
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 8 of 42
Figure 2: Spill Notification and Tier Justification
Oil Spill Emergency
OSC
Informs the BKK Telephone
Operator (Emergency Report Form)
Concerned Authorities
(According to requirements of each country)
Bangkok Telephone Operator
Record the Emergency Details in the
Emergency Report Form
Inform Asset Duty
Inform CCT Leader
Asset SVP
Activates the EMT and inform EVP
Asset Duty
Closely follow-up situation
with OSC and keep updating
to Asset VP
EVP
Inform CEO and consult on activating
Crisis, and keep updating the
situation
Identify Spill Tiers
Asset VP
Considers activating of spill tiers with Asset Duty
Asset Duty
Consider spill tier with OSC
Informs VP
CEO
Activates the CMT, as required
Informs the related parties of the
crisis
Related Stakeholders i.e. authorities, media etc.
Crisis Communication Team (CCT) Duty
Tier 2 / 3 Tier 1
Tier 3
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 9 of 42
6.1.4 SPILL RESPONSE RESOURCES
Spill response resources may come from local, regional or international sources. These resources
shall be pre-identified in the Asset’s Spill Contingency Plan based on their operation specific risk
assessment, regulatory requirements and planning scenarios. In some operating area, dispersant
application into water or land may require approval from regulatory body prior to use.
For domestic assets, request for dispersant application in Tier 1 will be asset’s responsibility. Once
the incident reach Tier 2 or 3, or after activate EMT/CMT, Corporate will be responsible for dispersant
approval authorization process. This could difference from other international asset which may require
the difference process for approval to comply with local regulation. The approval form of dispersant
application for domestic asset is provided in Appendix. To avoid the delay of dispersant application,
the completeness of information and appropriate volume of dispersant application filled in the request
form will expedite the approval period. In general, consideration result would be sent to requestor
within 5 hours after received by PCD.
Approval Flow for Dispersant Application (Domestic Asset)
6.1.4.1 PTTEP Resources (Tier 1)
For Tier 1 spill, the Asset shall provide and ensure the availability of spill response resources on each
location as identified in their planning scenario. The identification of necessary spill response
resources (equipment, materials and trained personnel) shall be documented in the Asset Spill
Contingency Plan. PTTEP Site representative shall ensure the readiness of the Spill Contingency
Plan and ensure there are sufficient equipment and resources for combating spill up to a Tier 1
scenario. The Site Response Team shall be trained to conduct prompt response and are familiar with
all available spill response equipment.
Should the spill escalate beyond Tier 1 level, additional resources and support are required to
manage the spill.
Fill form and submit
to Pollution Control
Department (PCD)
Approved?
Apply Dispersant as
per approval
condition
Yes
No
Review or revised
concern/ non-
approval conditions
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 10 of 42
6.1.4.2 Local and National Resources (Tier 2)
For Domestic Asset, PTTEP Corporate shall provide and seek all other available equipment and
resource to support in their spill response. These resources shall be included in the Spill Contingency
Plan and these may specify equipment and personnel from:
Nearby field operators
Regional operators
National level regulators/ agencies
National oil spill response organisations (Tier 2 OSROs)
Where possible, the asset and corporate should ensure that agreements are pre-arranged with these
Tier 2 resources in order to secure support to respond to the spill.
In principal, PTT Group is member of the Oil Industry Environmental Safety Group Association (IESG)
in Thailand (Tier 2 OSRO). All PTTEP's Assets in Thailand are able to call out resources and some
trained personnel from outsource under IESG’s contract by using STSC Spill Response Equipment
Request Form as provided in Appendix.
It is recognised that some overseas Assets may also be legally bounded to attain membership for
their local Tier 2 organisations / contractors as specified by the laws and regulations of the operating
country. All Assets shall adhere to the in-country legislative requirements and ensure familiarity of the
call out procedure for the respective Tier 2 organisations / contractors.
Further, Assets in Thailand may also request resources from the Marine Department through
activation of the National Oil Spill Response Plan. This allows the Asset to have access to the
national resource which includes equipment, vessels and technical specialists. Similarly, overseas
Assets should ascertain similar processes to access to the national resources of their country. All
these resources shall be identified in the Asset Spill Contingency Plan and the methods to activate
these resources shall be documented.
For International Asset, resources assistance will be needed for Tier 2 (in case national resources
are not capable or request for unforeseen situation) and Tier 3 Spill. The International Service
Provider for PTTEP currently is the Oil Spill Response Limited (OSRL) Group and for requesting, shall
be by the PTTEP authorised persons. The OSRL activation protocol and form are provided in
Appendix.
6.1.4.3 International Resources (Tier 3)
International resources assistance will be required in the event Tier 2 resources are overwhelmed.
PTTEP has access to resources from Oil Spill Response Limited (OSRL) via PTT Group membership.
The OSRL activation protocol and form are provided in Appendix. Only authorised personnel within
PTT Group could activate OSRL's services. As such, Corporate will assist Asset in securing OSRL
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 11 of 42
resources for response. For planning purpose, the Assets shall take into account the lead time
required for mobilisation of OSRL resources in their Spill Contingency Plan.
However, the global alliance from PTTEP, OSRL, requires lead time for internal preparation and
logistic. Following table is the capability, and approximated lead time of OSRL’s nearest support site
to nearest airport where PTTEP’s Spill Site located. Flight time from these airports to PTTEP incident
locations and contingency time; e.g. custom clearance and immigration; are not included. Estimation
lead time mobilisation of global assistance of OSRL is detailed in Table 1.
Country Airport Mobilisation time (hrs)
Flight time (hrs)
Total time (hrs)
Algeria Houari Boumediene (DAAG) 6 9 15
Australia Darwin 5 8 13
Canada 1st day to St John’s(YYT)
2nd day to Calgary International (YCC)
6 15.5 >25
Mozambique Maputo 5 20.5 25.5
Myanmar Yangon 5 4 9
Thailand Suvarnabhumi Airport 5 4 7
Table 1: Estimated mobilisation time for international assistance for OSRL
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 12 of 42
APPENDICES
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 13 of 42
APPENDIX A: TIER 2 SPILL RESPONSE EQUIPMENT FOR THAILAND DOMESTIC ASSET
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 14 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 15 of 42
APPENDIX B: STSC SPILL RESPONSE EQUIPMENT REQUEST FLOW FOR THAILAND (IESG)
In the event of a spill at the domestic assets, the STSC can provide oil spill response equipment. The flowchart below reflects the steps involved in requesting for support from STSC.
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 16 of 42
APPENDIX C: STSC SPILL RESPONSE EQUIPMENT REQUEST FORM (IESG)
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 17 of 42
APPENDIX D: REQUEST FORM OF DISPERSANT APPLICATION FOR APPROVAL IN THAILAND
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 18 of 42
APPENDIX E: LIST OF APPROVED DISPERSANTS IN THAILAND
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 19 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 20 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 21 of 42
APPENDIX F: CONTRACT FOR EQUIPMENT MOBILIZATION UNDER IESG MEMBERSHIP
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 22 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 23 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 24 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 25 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 26 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 27 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 28 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 29 of 42
APPENDIX G: OIL SPILL INTERNAL NOTIFICATION EXAMPLE
Figure A-1: Oil Spill Internal Notification Flowchart Example (Offshore Thailand Asset)
The flowchart above illustrates the notification flow when an incident happens at the offshore Thailand Asset. The red-dotted box constitutes the initial communication to the Asset Duty and varies for the different Assets. This will therefore need to be customized according to the Asset operations. However, in all cases, such emergencies involve the same notification flow between Asset VP, SVP,
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 30 of 42
EVP and CEO and therefore are generally the same even for the different Assets as illustrated in the green-dotted box.
In the example flowchart above:
1. The OSC of the affected site shall contact Bangkok Telephone Operator and Asset Duty as
soon as possible and notify the concerned authorities immediately as necessary.
2. Upon receiving the emergency call, Bangkok Telephone Operator will immediately contact
Asset Duty of the Affected Asset and the Crisis Communication Duty. The Emergency Report
Form should be used to record the details of emergency which received from OSC of the
affected Site. (APPENDIX H: EMERGENCY REPORT FORM).
3. If the case occurs at the other functions such as construction/drilling or exploration site, the
Duty Person of such function shall be called.
4. Inform the Crisis Communication Team Leader of the emergency for further announcement.
5. Asset Duty will consider the tier level of the emergency (in conjunction with the OSC and VP
or SVP). If the emergency is minor or classified as Tier 1, the Asset Duty should follow up the
situation with Site, until the situation is back to normal and inform the VP and SVP
respectively.
6. If the emergency is defined as Tier 2 or above, the Asset SVP of Affected Site shall activate
EMT via the Telephone Operator, i.e., SSHE, Logistic, Media Response, Relative Response
and specific supports such as Drilling, Well Services, Construction, etc.
7. The SVP of Affected Site will be acting as the IC of the EMT.
8. The SVP of Affected Site shall inform the EVP who will be acting as the CMT member.
9. PTTEP Corporation will provide support regarding advisor(s), coordination with national and
international oil spill response organization.
10. The Affected Site EVP shall notify CEO and may consider activating CMT members under the
CEO decision.
11. CEO will then inform relevant parties such as the concerned authorities, media and other
stake holders.
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 31 of 42
APPENDIX H: EMERGENCY REPORT FORM TO PTT
Oil Spill Response and East Asia Response Limited (OSRL)
Singapore Base: +65 6266 1566 (Tel) +65 6266 2312 (Fax)
Southampton Base: +44 23 8033 1551 (Tel) +44 23 8033 1972 (Fax)
PTT Public Company Limited (PTT)
Communication Centre: +66(0)2537 3111/3222/3333/3444 (Tel) +66(0)2537 3498-9 (Fax)
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 32 of 42
Mobilisation Authorisation
To: PTT Communication Center Date:
Tel: +66 (0) 2537 3111/222/333/444/555 Fax: +66 (0) 2537 3498 - 9
From: Position:
Company: Contact Number:
Subject: Mobilisation of OSRL Incident name:
I, (Name in Block Capitals)
hereby authorise to request PTT for the activation of OSRL and its resources in connection
with the oil spill incident of (Name of Ship/Oil Rig or Terminal)
as of (Time) on (Date)
OSRL shall work under the direction of:
Name:
Position:
Company:
Signature Position
Company name
To: OSRL Date:
Tel: Singapore Base: +65 6266 1566
Southampton Base: +44 23 8033 1551
Fax: Singapore Base: +65 6266 2312
Southampton Base: +44 23 8033 1972
From: PTT Public Company Limited Contact Number: +66 (0) 2537 8844/55
Subject: Mobilisation of OSRL Incident name:
I, (Name in Block Capitals)
hereby authorize the activation of OSRL and its resources in connection with the oil spill
incident of (Name of Ship/Oil Rig or Terminal)
as of (Time) on (Date)
Signature Position
PTT Public Company Limited
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 33 of 42
PTT Public Company Limited (PTT)
Communication Centre: +66(0)2537 3111/3222/3333/3444 (Tel)
+66(0)2537 3498-9 (Fax)
Oil Spill Response and East Asia Response Limited (OSRL)
Singapore Base: +65 6266 1566 (Tel) +65 6266 2312 (Fax)
Southampton Base: +44 23 8033 1551 (Tel) +44 23 8033 1972 (Fax)
Notification Form – Page 1 of 2
To: PTT Communication Center Date:
Cc: OSRL Warning! Ensure telephone contact has been established with the
Duty Manager before using Email communication.
From: Position:
Company: Contact Number:
Subject: For Your Information Incident name:
OBLIGATORY INFORMATION REQUIRED – COMPLETE ALL DETAILS
Name of person in charge
Position
Company
Contact telephone number
Contact fax number
Email address
Spill Details
Location of spill
Description of slick (size/direction appearance)
Latitude / Longitude
Situation (cross box)
Date & Time of spill
Source of spill
Quantity (if know)
Spill status (cross box)
Action taken so far
Oil type & characteristics
Name
Viscosity
API/SG
Pour point
Asphaltene
Weather
Wind speed and direction
Sea state
Sea temperature
Tides
Forecast
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 34 of 42
PTT Public Company Limited (PTT)
Communication Centre: +66(0)2537 3111/3222/3333/3444 (Tel)
+66(0)2537 3498-9 (Fax)
Oil Spill Response and East Asia Response Limited (OSRL)
Singapore Base: +65 6266 1566 (Tel) +65 6266 2312 (Fax)
Southampton Base: +44 23 8033 1551 (Tel) +44 23 8033 1972 (Fax)
Notification Form – Page 2 of 2
ADDITIONAL INFORMATION REQUIRED – COMPLETE DETAILS IF KNOW
Resources at risk
Clean up resources
On site / Ordered
Nearest airport (if know)
Runway length
Handling facilities
Customs
Handling agent
Vessel availability
Equipment deployment
Recovered oil storage
Equipment logistics
Transport
Secure storage
Port of embarkation
Location of command centre
Other designated contacts
Special requirements of country
Security
Visa
Medical advise
Vaccinations
Others (specify)
Climate information
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 35 of 42
APPENDIX I: OSRL NOTIFICATION AND MOBILISATION PROCEDURE
OSRL Request Step
PTTEP is a participant member with OSRL, and therefore has immediate access to Tier 3 technical
advice, resources and expertise 365 days a year on a 24 hours basis. The following steps should be
followed to request for OSRL’s support:
1. In the event of an incident, a call should be placed to one of the following numbers. The Duty
Manager (DM) will call Client back within 10 minutes of receiving notification of the call.
Emergency Contact (TELEPHONE) Singapore +65 6266 1566
Southampton +44 (0)23 8033 1551
Emergency Contact (FAX) Singapore +65 6266 2312
Southampton +44 (0)23 8033 1972
2. Complete the Notification (Page 100) and Mobilisation Authorisation forms (Page 102) as
necessary, which can be sent to OSRL by fax or email. Under the Participant Member
Agreement which governs the mobilization of resources from OSRL, OSRL must receive
official notification to mobilize from one of PTTEP’s Nominated Call-out Authorities,
summarized in the table on the next page. These are individuals within PTTEP who have
been appointed to approve the expenditure of mobilizing Tier 3 equipment.
National and International Resources Contact List
Organisation Tel Fax
Department of Mineral Fuels
(DMF)
+66(0)2794 3472
+66(0)2794 3474
Department of Disaster
Prevention and Mitigation Hotline 1784
Marine Department (MD) 1194 (24 hrs), +66(0)2234 8342,
+66(0)2233 1311-8 ext 330 and 331
IESG +66(0)2239 7955 - 56 +66(0)2239 7917
PTT Command Centre +66(0)2537-3111 / 3222 / 3333 +66(0)2537 3498
OSRL Singapore base +65 6266 1566 +65 6266 2312
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 36 of 42
PTTEP Call-out Authorities and Contact Information
Name Position/Job Title Contact No. Email
Kesara Limmeechokchai Senior Vice President : Safety, Security, Health & Environment Division
Tel: +66 (0) 2 537 4753/ +66 (0) 818181957
Mobile: +66 (0) 2 537 4753/ +66 (0) 818181957
Luck Pasutanavin Vice President, Safety Operation Department
Tel: +66 2 537 4441
Mobile: +66 (0) 2936 2678
Lawan Pornsakulsakdi Vice President, Environment Management Department
Tel: +66(0) 81 801 4149 [email protected]
Narongrit Apinyovichien Manager, SSHE +66818180593
+6625374552
Piya Sukhumpanumet Senior VP, Myanmar Asset +9595128851
+66818181964
Khomsan Lertwiriyaprapa SSHE Manager, Myanmar Asset Tel: +66 2-537-4000 ext. 804-3816/ +66 2-537-4000 ext. 804-3816
Nirandorn Rojanasomsith Vice President, Australia Asset +66 892025894
+66 2-537-4413
Paul McCormick SSHE Manager, Australia Asset +61417958520
+61893209564
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 37 of 42
OSRL Related Forms
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 38 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 39 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 40 of 42
APPENDIX J: OIL SPILL CONTRACTS PTTEP’S NOMINATED CALL-OUT AUTHORITIES
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 41 of 42
Corporate Spill Contingency Plan
12002-PDR-SSHE-503-005-R01
December 2016
Revision No: 1 UNCONTROLLED when printed visit PTTEP intranet for latest version Page 42 of 42
4
2018 PS1 SSHE Performance(as of 31/12/18)
SSHE MS
Element 2 & 6
Staff
1,066,675
Contractor
9,043,772
2018 Total MH
10,110,446
Cumulative MH without LTI 7,544,960
LTIF (Number/MMhrs)Base 0.14 - Stretch 0
YTD
0.10
TRIR (Number/MMhrs)Base 0.85 - Stretch 0.56
YTD
0.40 (1 LWDC, 2 RWDCs, 1 MTC)
Spill Rate (Ton/MMt Production)Base 0.22 - Stretch 0
YTD
0.0392 (77.34 liter)*
EIA Compliance Audit &
Monitoring100% (66/66)
External Complaint (Number)YTD
0
Security Incident (Number)Base 3 - Stretch 0
YTD
6
Occupational Illness (Number)
YTD
3
MAE Prevention Tool1/8
5
0
1
2
3
2010 2011 2012 2013 2014 2015 2016 2017 2018
No
. P
er
Mil
lio
n M
an
-ho
urs
YearPTTEP LTIF IOGP LTIF S1 LTIF PTTEP TRIR IOGP TRIR S1 TRIR
S1 Compared to IOGP & PTTEP Company
Safety Performance Trend (LTIF and TRIR)
SSHE Indicators
% S1 Rate compared with IOGP Average
2014 2015 2016 2017 2018(Compared with 2017 IOGP)
LTIF ZERO LTI 52% Better ZERO LTI ZERO LTI 63% Better
TRIR 40% Better 83% Better 55% Better 75% Better 58% Better
For 2018 S1 personal injury performance shown that LTIF was increased 1 case
(2017 = 0 case) whilst TRIR was increased 2 cases (2017 = 2 cases) or by rate 67%
when compared to 2017 S1 performance.
8
Fatality (case)
Total Recordable Injury (case)
Lost Time Injury (case)
First Aid Case
Near miss
No. of SOC (Unsafe/Safe act)
Man hour (hrs.)
S1 Personal Safety Pyramid
0
0
3
4
11
16,184/489,287
Company: 1,041,595Contractor: 6,545,837
2016
0
0
2
3
4
24,935/570,472
Company: 1,012,484 Contractor: 7,518,610
2017
0
1
4
7
16
38,404/(6,174/134,195)
Company: 1,066,675 Contractor: 9,043,772
As of 31 Dec. 2018
10
Incident Summary & Analysis
11
68
35
99
12.3313.80
10.11
32
4
01
5
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
0
20
40
60
80
100
2016 2017 2018
Man
hou
r (Pe
r mill
ion)
No.
Inci
dent
(cas
es)
Year
S1 Incident Summary – 3 years rolling
Total Incidents Manhour (Per Million) Serious incident (TRIs) High Potential Incidents
Incident Summary & Analysis
No. Incident per Million man hourYear
2016 2017 2018
Total Incidents 5.52 2.54 8.51
TRIs 0.24 0.14 0.40
HPIs 0.00 0.07 0.49
LWDC = 1 case
RWDC = 2 cases
MTC = 1 case
RWDC = 2 cases
MTC = 1 case
RWDC = 2 cases
Land Transportation: the mobile crane truck crashed with trailer
truck
• Electrical: Electric shocked
• Land Transportation:
- The pickup ran out off-road track and roll over
- MML Trailer ran off the road.
- The power line pulled by mobile crane
• Well operation: Hydrocarbon leak from A-Annulus
12
0.00
2.00
4.00
6.00
8.00
10.00
ART GBN GBS SPR S1 SPH AA ZOC ZPQ
Ma
n h
ou
r (P
er
mil
lio
n)
Assets
2018 Asset Man Hour
S1 Man hour by
Company & Contractor
Asset Man hour (hrs.)
ART 1,695,470
GBN 3,304,115
GBS 973,681
SPR 600,493
S1 10,110,451
SPH 518,588
AA 407,400
ZOC 645,314
ZPQ 559,548
• S1 is the asset which contribute
the most of working hours in
each year.
• 89% of S1 Man hours
contributing to “Contractors “
Incident Summary & Analysis
13
15.92 15.1322.59
14.999.79
5.78
154.64
17.05
30.38
ART GBN GBS SPR S1 SPH AA ZOC ZPQ
No
. In
cid
en
t p
er
Millio
n m
an
ho
ur
Assets
2018 Incident per million man hour by Assets
AssetTotal incident
(cases)
ART 27
GBN 50
GBS 22
SPR 9
S1 99
SPH 3
AA 63
ZOC 11
ZPQ 17
Incident Summary & Analysis
• S1 average incident occur
approx. 10 cases per million
man hour when comparing to
other asset.
14
2016 - 2018 Incident Classification
1 2 17
2 5
58
59
6
12
0
10
20
30
40
50
60
No.
of I
ncid
ent (
s)
2016 2017 2018
Responsible party
Incident Summary & Analysis
1. Production activity 31%
2. Land Transportation 22%
3. Drilling/Work over/Well service
19%
Top 3 Activity:
1. Equipment failure 22%
2. Vehicle related 15%
3. Struck by 10%
Top 3 Event Category:
1. Design
2. Communication and
3. Organizational
Top 3 root cause:
15
• 91% of S1 Injury cases (10/11) happened to Contractors.
• Top 3 Root cause of injury case are Communication, Risk assessment and Competency
2018 S1 Injuries cases (11 cases)
Incident Summary & Analysis
73% cause by Hand and
Finger injuries (8 in 11 cases)
27% were from being
exposure biological (3 in 11
cases)
27% happened from
Drilling/Workover/Well Service
(3 in 11 cases)
LWDC, 1
RWDC, 2
MTC, 1
FAC, 7
63% cause by Hand and
Finger injuries (5 in 8 cases)18% cause by Abrasion
and Fracture (2 in 11 cases)
Common Causal Factors of the Incident
0 5 10 15 20
Failure to warn of hazard
Inadequate communication
Inadequate hazard…
Inadequate/defective guards…
Inadequate supervision
Inadequate/defective…
Improper working position…
%
16
2018 S1 Land Transportation
Incident Summary & Analysis
Incident classification
0 1 0
3
23
02
0
LWDC RWDC MTC HPI PropertyDamage
Spill Nearmiss
LOPCTire 3
Type of Vehicle
RT, 3
HV, 8LV, 14
Incident contributing by
3rd Parties 10 cases
and 3 cases occurred
from Company and for
Contractor occurred 12
cases from 25 cases
7
10
6
2
06:01 -12:00 HRS.12:01 - 18:00 HRS.18:01 - 24:00 HRS.00:01 - 06:00 HRS.
Time of Incident 1. Competency - Improper/lack of decision making and/or judgment 18%
3. Human factor - Lack of Attention/Distracted by other concerns/stress 5%
2. Organization- Inadequate hazard identification or risk assessment 8%- Inadequate communication 8%- Inadequate work standards/procedures 7%- Inadequate supervision 7%
Causal Factors
17
2018 S1 Spill & Leak
Incident Summary & Analysis
1. Corrosion 64%
2. Erosion 20%
3. Mechanical failure 8%
Top 3 Cause of leak
9
5
9
6
PropertyDamage
Spill LOPC Tire 3 LOPC Tire 4
ClassificationHydraulic
oil, 1
crude oil , 9
2-Phase, 2
Produced Water, 9
Spill / Leak Type
Piping30%
Pipe spool30%
Elbow15%
Fitting10%
Welding point Pressure
gauge5%
Loading Arm5%
Flexible hose 5%
18
Incident Summary & Analysis
• 2018 S1 had incident occurred more than previous year (2017 = 35 cases) by 65%
• 2018 S1 is the asset which contribute the most of working hours in each year.
• 89% of S1 Man hours contributing to “Contractors “
• 2018 S1 Average Incident occur approx. 10 cases per million man hour
• 3-year rolling total incident analysis (2016-2018)
o Property damage/loss is the most incident classification happened 59%
o Top 3 activity: Production , Land transportation and Drilling/well operation
o Root Cause of incident: Design, Communication and Organizational
• 2018 Injury incident
• 91% of injury cases (10/11) happened to Contractors
o 73% happened with Wrist, Hand, Fingers and 27% of the event category injuries from were from being exposure
biological (Bee/ wasp)
o Root cause is Communication
• 2018 S1 Land Transportation
o Most Incident happened from Light Vehicle (LV) 14 cases from 25 cases
o 3rd Parties/community contributed incident 10 cases from 25 cases
o Cause of incident -- Improper/lack of decision making and/or judgment
• 2018 S1 Spill & Leak
o Spill & Leak came from Flowlines (7/25 cases), Processing unit (4/25 cases) and Manifold (2/25 cases)
o Most cause of leak is Corrosion by 64%
19
Ways Forward
• Road Safety campaign
• SSHE Leadership for Frontline Supervisors
• Hazard Identification and Risk Management – Improve for new e-JSA
• Improve Safety Observation and Hazard reporting Card
• Asset Integrity (i.e. Closely monitoring and Inspection)
• Focus on Security Management (i.e. Security staff capability enhancement)