Cornerstone Report
Transcript of Cornerstone Report
Cornerstone Report
July 15, 2020
Key Updates - Post Production Center
• Release 1.2.2 was implemented on June 28, 2020, which added
WSSC’s Fiscal Year 2021 Water/Sewer Rates
• Release 1.3 is scheduled for implementation on August 2, 2020,
which will resolve 16 defects
• 213 defects remain openo 16 high priority
o 73 medium priority
o 124 low priority
2
Technology Stabilization MetricsTechnical Scorecard
Category Measure DescriptionCurrent
Rating
System
Stability
Component failures
(Infrastructure)
Number of infrastructure components failures during last 30 days
Allowed: 0
Actual: 0
Component failures (Application)
Number of application component failures during last 30 days
Allowed: 0
Actual: 0
Production database availability
Number of unplanned database outages during last 30 days
Allowed: 0
Actual: 0
Release
Mgmt. Unplanned releases deployed
Number of unplanned releases deployed during last 30 days
Allowed: 3
Actual: 0
Green
Green
Green
Green
3
Technology Stabilization MetricsTechnical Scorecard
Category Measure DescriptionCurrent
Rating
Batch
Critical jobs system crash
Number of critical path processing crash during last 30 days due
to technical issues:
Allowed: 0
Actual: 0
Billing batch processing
Percent billing batch jobs completed within the predetermined
batch window during the last 30 days:
Allowed: 100%
Actual: 100%
Critical path batch processing
Percent Critical Path Batch processing completed within the
prescribed window during the last 30 days:
Allowed: 100%
Actual: 100%
Defects Severity 1 Defects Reported
Number of Severity 1 Incidents identified in last 30 days:
Allowed: 0
Actual: 0
Green
Green
Green
Green
4
Metric: Accounts Billed On-Time
5
Accounts Billed On-Time
• Accounts are considered billed on time if the
most recent bill was produced within 15
calendar days of the respective bill window close
date
• Performing within target range
• Very slight decrease of 0.14% from March to May
attributed to the COVID-19 response and shift
of staff time to other initiatives, along with
overtime reductions implemented as part of
COVID-19 savings plan
Metric: Payments Received
6
• Total amount of payments received, as of the end of each month
• Cash collection is down $12.8 million through May FY20 vs. May FY19
• Contributing factors: C2M conversion (early FY20) and COVID-19 suspension of collection activity (March-May)
$-
$20,000,000.00
$40,000,000.00
$60,000,000.00
$80,000,000.00
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
FY19 FY20
COVID impactC2M Conversion
Metric: Accounts/Amounts Past Due
7
Accounts Past Due (#)
Amounts Past Due ($ millions)
• Accounts are considered “Past Due” when a bill is 30
days past the bill due date
• Collection activities are suspended (i.e. turn-offs and
waiving late fees) in response to the COVID-19
pandemic
• From the end of April to the end of May, there was a
7.5% increase in the number of past due accounts, and
an 11.5% increase in the total past due amount
• Customer affordability enhancements are included in
the FY21 Approved Budget, increasing funding from
$2.8M to $3.2M
Metric: Number of Tasks
8
• A "To Do" is a task assigned in C2M. There is a wide
range of tasks, which typically indicate errors delaying
the mailing/generation of a bill
• Since/during the COVID-19 pandemic (March-May), staff
have been able to consistently complete/close more To
Do's than the system has generated.
• Early projections after C2M went live indicated that the
To Do backlog (not pictured) could grow to nearly
100K; staff has worked backlog down to below 12K.
* When C2M went-live (July 2019), a large backlog/large amount of work was created.
* To Do completion was low due to staff learning system and low # of resources.
0
10000
20000
30000
40000
50000
60000
70000
Jul-19 Sep-19 Nov-19 Jan-20 Mar-20 May-20
To Do's Generated To Do's Completed
Organizational Development Next Steps
9
• August: FY21 Targets for Metrics
• September: Customer Call Center Metrics
• October: Meter Services Metrics
Key Updates - Cornerstone Release 2
Cornerstone Release 2 – Enterprise Asset Management
(EAM)
• Business Requirements Gathering (Phase I & 2): Completed
• Business Requirements Reconciliation (Phase 3): Completed
reconciliation amongst stakeholder business units
• Cornerstone Release 2 Requirements have been Archived for use
with Future EAM Project: Completed
10
Key Updates – Cornerstone Release 2 Cont.
Alternative Asset Management Solutions:
1. Upgrading WSSC’s existing Oracle Work & Asset Management (WAM) solution to a
supportable version1. Estimated Cost: $250,000
2. Target Implementation: 09/06/2020
2. Sourcing and implementing an individual technology solution for Fleet within
General Services division1. Estimated Cost: Determination in progress
2. Target Implementation: Determination in progress
3. Sourcing and implementing an individual technology solution for Paving within
Engineering & Construction division1. Estimated Cost: Determination in progress
2. Target Implementation: Determination in progress
11