Coordination of work at M24
Valerie Depauw, monthly conference call October 13, 2014
2
On the menu today
confidential
Feedback on EUPVSEC 2014
Overview of deliverables
Organization of meeting in Lund
3
But first Bye Bye Webex? Not yet
confidential
Webex license will not be renewed by imecNext conf call October 13 via M$Office Lync I will plan some tests times beforehand
not working well... using webex as long as possible – till now still operational
Sorry Jerome...
4
EUPVSEC 2014Valerie and Christos were there
confidential
About the talk we gave on PNV (Only 12 min, sorry but I had to drop content ) Positive feedback But no big discussion
Our general impression Nanophotonics is still there but interest is not taking off
Many contributions, 1 dedicated parallel event... But no industry around Issue: random pyramids are already doing a great jobNeed to combine light trapping with another function
Thin-film c-Si not at its highest (rumor: Solexel to stop epi) But poly-Si is still there (record Voc > 650 mV at HZB) Other thin film competitions at high eff. (e.g. CIGS, perovskites)
5
EUPVSEC 2014Light-trapping in competition
About modeling? Plasmonics for PV keep declining, e.g. Schuster poster (Univ. York) Nanopyramids rock: @SERIS people agree with us Going above Lambertian is only interesting for very thin films (Catchpole, ANU) Good modeling of light trapping and randomness at Karlsruhe IT (C. Rockstuhl)
About samples? Large variety of approaches, many groups working on it. Mainly optical
demonstrators and passivating possibilities (e.g 2AV.2.34).
About solar cells? (next to us) @HZB black silicon Problems to integrate, worst results than reference @TUDelft same as above @ISE/nines-PV 0.1% higher efficiency than reference
2DV.4.9
1AO.2.1
Parallel
1CO.9.4
1CO.10.2
2AV.3.5
6
Light-trapping in competitionWhat about the future?
About solar cells, keep an eye on: @ Fraunhofer ISE! Solar cells to come?
Back grating inside a-Si:H layer (avoid passivation issue)TiO2 nanoparticles to be integrated into tunnel-oxide high-efficiency cell
@AMOLF/ECN: Mie resonators at front sideBut they benchmark to flat cells...
And us... we have potential!
1CO.10.4 / 2DO.2.3
7imec confidential
Progress meeting
8
Many deliverables are due yesterday
confidential
# WP Delivery In chargeD 3.2 Report: First batch of solar cells, non-
optimised opticallyReport on first batch of four solar cell technologies with one side patterned up to 30 x 30 mm2 (optically non-optimised) with LHL, NIL and HCL (to be used as input for go/no-go in MS 6)
3 18- Apr 14 1 Imec
D 1.7 Report: Modelled current enhancement prospects
Report on current enhancement prospects, including double-side patterning and tolerances to process non-idealities
1 20- June 14 3 FUNDP
D 2.4 Report: Experimental periodic patterned films
Report on the characteristics of optically optimized periodic structures, on areas up to 50 x 50 mm2, including inputs for WP3, following D 1.4
2 21- July 14 4 OBDU
D 2.5 Report: Experimental non-periodic patterned films
Report on the characteristics of optically optimized pseudo-periodic/random structures, on areas up to 50 x 50 mm2, including inputs for WP3, following D 1.5
2 24- Oct 14 5 Chalmers
D 4.2 Report: Cost of patterning Report on cost of adding a patterning step to solar cell fabrication
4 24- Oct 14 6- Total
D 3.4 Report: Second batch of cells, with non-periodic optimal patterns
Report on second batch of patterned cells integrating optically optimised non-periodic patterns, following D 2.5
3 27- Jan 15 7- LPICM
Now
After Lund meeting
9
new
Progress meeting in Lund
confidential
Global agenda Same course as for the previous times One novelty: conclusion slide/WP for each partner
Seminar topics? Proposals?
Round tables TBD during WPs Proposal: 1 or 2 “large table” sessions
+ time for small “face to face”
10
Progress meeting M24Agenda, in short
Day 1 Overview of WPs and a seminar (9h-17h15)
Morning Welcome WP1 and WP2 (2x 1h)
Afternoon WP3 (1h) Seminar WP4 (45 min)
EveningDinner at 18h30 in Lund centre
Day 2 Round tables and steering committee (9h-14h30)
Morning Round tables, 2 sessions + 1 free Closing remarks
Afternoon Steering committee
Max. end time max.15h
11
Your preparation
confidential
Follow the WP leaders requests Make slides on your results + a personal conclusion slide, for each WP you are involved in If you need: bring up table-topic
For members of steering committee: Put on the agenda topics you want to discuss (email of Valerie will follow shortly for this)
12
Any questions?
confidential
Practical questions to Kidong?
Other?
nanophotonics for ultra-thin crystalline silicon photovoltaics
This project has received funding from the European Union’s Seventh Programme for research, technological development and demonstration under grant agreement No 309127
14
Day 1: Thursday 23/10From 9h Hello! Meeting up
9h30 Welcome• Agenda • Global status
30 min KidongValerie
10h WP1• Overview + separate conclusion slide
of partners • Discussion
30+30 min Jerome
11h Break 30 min
11h30 WP2 (=WP1) 30+30 min Christian
12h30 --- Lunch --- 1h30
14h WP3 (=WP1) 30+30 min Pere
15h Break 15 min
15h15 Seminar on... (tbd) 45 min ?
16h Break 15 min
16h15 WP4 (=WP1) 45 min Patricia
17h Decision on topics for next day 15 min Valerie
17h15 Free time till dinner (time? tbd)
Time in bold = sharp!
15
Day 2: Friday 24/10
9h Round tables 1 + summary 40+20 min
10h30 Break 30 min
11h Round tables 2 + summary 40+20 min
12h Closing remarks 15 min Valerie
12h15 --- Lunch --- 30+30 min
13h30 Steering committee 15 min Steering committee members
14h30 End, good bye!
15h (Max. time)
16confidential
17
Focus for each WP
confidential
WP1 - Evaluate the records Jsc that can be obtained with nanopatterns + identify optima for HCL
How high? What is needed to go high? Decide what structure to focus on for cost
Find out what works best with HCL
WP2 - Get best patterns possible with wet etching Periodic: new NIL stamps Non-periodic: improve fill factor ... on all materials to be used for cells still need...
epifoils front-side tests and PECVD wet etching improvement
WP3 - Prepare for making higher efficiency cells in October Think what process changes will be needed
WP4 - Prepare data for model