Page 1: Coolidge airport arizonia 2005

Kodi Klips Saves Time & Money On Runway Repair Job

Coolidge Municipal Airport, Coolidge, Arizona, USA October 2005

Kodi Klips were used in the reconstruction of an aircraft parking apron at the Coolidge Municipal Airport in Coolidge, Arizona. DBA Construction Inc. was the general contractor on the project. New concrete was 3000 psi, 6-inch thick, reinforced PCCP using size 57 rock and placed at a 3-inch slump. All new pavement was reinforced in both directions with #4 bar spaced at 12-inch centers—for a total of 33,000 connections. Project officials estimated that it would take construction crews four days to connect the rebar with wire ties—and just one day to complete the connections with the Kodi Klip System.

Including the cost of the klips, rebar clipping and placement, the project was completed for 26% less than budgeted.