CONTRACTORS QUALITY CONTROL REPORT (QCR) … QC Daily Report.pdf · contractors quality control...
Transcript of CONTRACTORS QUALITY CONTROL REPORT (QCR) … QC Daily Report.pdf · contractors quality control...
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
91
01 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 21 F, Max 44 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIWorked on shutting down water and removing refrigerators
General Comments:DAILY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNo remarks today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNone today
PREPARATORY AND/OR INITIALS HELD TODAYHeld demo prep meeting today with AAI. See attached minutes of meeting. Will start next week with demo. They brought new license, number was okay by Jim LaFluer.
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours worked to date: 0.0
EQUIPMENT HOURS
No equipment hours were Reported todayTotal operating hours to date: 0.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
91
01 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
92
02 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 28 F, Max 53 F; No Precipitation; 29 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:EVERGREENE MANAGEMENTReview ed tree preservation plan w ith COE, Base and Base Arborist. Some trees are missing and mislabeled. Generally okay. Several additional trees w ere added to the removal due to the condition of the trees - old split trunks, and poor conditionsShould there be added costs for removal of these trees (No additional Did not f inish. NE area remains. Scheduled to f inish on Wednesday at 10:30 am.
AAIShutting dow n w ater, and removing refrigerators
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNone today
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
92
02 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0
EQUIPMENT HOURSNo equipment hours were Reported today
Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
93
03 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 39 F, Max 48 F; 0.12 IN Precipitation; 20 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIShutting dow n w ater and removing refrigerators
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
93
03 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
EQUIPMENT HOURS
No equipment hours were Reported todayTotal operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
94
04 Nov 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 32 F, Max 50 F; No Precipitation; 14 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIShutting dow n w ater and removing refrigerators
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
94
04 Nov 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
EQUIPMENT HOURS
No equipment hours were Reported todayTotal operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
95
05 Nov 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 54 F; No Precipitation; 13 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIShutting dow n w ater and removing refrigerators
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
95
05 Nov 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
EQUIPMENT HOURS
No equipment hours were Reported todayTotal operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
96
06 Nov 2004 - Saturday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 23 F, Max 39 F; No Precipitation; 29 MPH Wind
Parsons Evergreene Construction, L.L.C.
QC NARRATIVESNo QC Narratives were reported today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0
EQUIPMENT HOURSNo equipment hours were Reported today
Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance with the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
98
08 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 34 F, Max 41 F; 0.04 IN Precipitation; 8 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSWater to buildings 4204, 4210,4211 are connected to TLF units. Must be isolated - not just turned off at unit. Corp stop - need outage!
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYHeld preparatory meeting today for HazMat w ith Steven Galley and AAI - see attatched.
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSNo labor hours were Reported today
Total hours w orked to date: 0.0
EQUIPMENT HOURSNo equipment hours were Reported today
Total operating hours to date: 0.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 1 of 1
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
99
09 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 35 F, Max 46 F; No Precipitation; 12 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIDemolished building #4215
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP5410 All other Work for New Family
No activities were finished today
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 1.0 5.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
99
09 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
Asbestos Abatement OPERATING ENGINEER 1.0 10.0Total 2.0 15.0Total hours w orked to date: 15.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
001 Link Belt 2800 0.0 10.0Total 0.0 10.0Total operating hours to date: 10.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
100
10 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 34 F, Max 51 F; 0.15 IN Precipitation; 13 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIDemolished building 4264 - crunching and hauling demolition debris.
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSSent email to Jim LaFluer w ith UHF radio frequencies w e w ant to use onsite
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 2.0 20.0Asbestos Abatement OPERATING ENGINEER 1.0 10.0
Total 3.0 30.0Total hours w orked to date: 45.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
100
10 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
001 Link Belt 2800 0.0 10.0Total 0.0 10.0Total operating hours to date: 20.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
101
11 Nov 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 41 F, Max 49 F; 0.15 IN Precipitation; 9 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIDemolished garages for buildings #4215 and #4212. Worked on hauling demolition debris.
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSHeld w eekly QC meeting - see attached meeting minutes
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0
Total 3.0 30.0Total hours w orked to date: 75.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
101
11 Nov 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
001 Link Belt 2800 0.0 10.0002 Samsung 0.0 8.5
Total 0.0 18.5Total operating hours to date: 38.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
102
12 Nov 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 42 F, Max 48 F; No Precipitation; 12 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:Patterson - No w orkAAI - No w ork
General Comments:QUALITY CONTROL INSPECTION AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNo remarks
Safety Inspection / Safety Meetings:DAILY SAFETY ISSUESNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP51415 Demo Building #4210
No activities were finished today
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
102
12 Nov 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
LABOR HOURS
No labor hours were Reported todayTotal hours w orked to date: 75.0
EQUIPMENT HOURSNo equipment hours were Reported today
Total operating hours to date: 38.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
105
15 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 34 F, Max 55 F; 21 IN Precipitation; 24 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:ROMANS TRUCKING T - 3 - 4 loads of demoT - 6 - 4 loads of demo
AAIDemolished garage #4213 and building #4210. Crunching and heavy demo debris. Checked building for refrigerators.
General Comments:QUALITY CONTROL INSPECTION AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNo remarks
Safety Inspection / Safety Meetings:DAILY SAFETY ISSUESNo safety issues
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
105
15 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 1.0 3.5Asbestos Abatement OPERATING ENGINEER 2.0 20.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 5.0 44.5Total hours w orked to date: 119.5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
001 Link Belt 2800 0.0 10.0002 Samsung 3.0 7.0
Total 3.0 17.0Total operating hours to date: 55.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
106
16 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 51 F; No Precipitation; 17 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONStripping sage brush and hauling off to East side of golf course. Worked on moving piles of dirt.
AAIDemolished building #4211 All refrigerators removedWorked on hauling demo debrisShooting off w ater to building 4204 - broke 4 inch line to repair it
ROMAN'S TRUCKINGT -3 - 4 loads demoT - 6 - 4 loads demo
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSHit service line to building 4211, must shut off w ater to TLF and laundry. Emergency repair.Note - w e w ere afraid the above may happen and requested an outage but w ere denied.
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTION Held site safety meeting - see attached
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENone today
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
The following activity was started today:Activity No DescriptionP51440 Demo Building #4215
No activities were finished today
QC REQUIREMENTS
No QC requirements were completed today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
106
16 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 3.0 27.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 8.0 78.0Total hours w orked to date: 197.5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
001 Link Belt 2800 0.0 10.0002 Samsung 0.0 10.0004 T-6 0.0 10.5005 T-3 0.0 10.5
Total 0.0 41.0Total operating hours to date: 96.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
107
17 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 26 F, Max 37 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONHauling sage brush to east side of golf course and move dirt piles
AAIDemolished building 4204All refrigerators removedWorked on hauling demo debris
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS No safety issues today
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
107
17 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 2.0 20.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 2.0 11.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 8.0 72.0Total hours w orked to date: 269.5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
001 Link Belt 2800 0.0 10.0002 Samsung 0.0 10.0004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 11.0008 Dump Truck 0.0 11.0
Total 0.0 63.0Total operating hours to date: 159.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
108
18 Nov 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 32 F, Max 48 F; No Precipitation; 28 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONWorked on hauling sage brush to East side of golf courseWorked on moving piles
ROMAN'S TRUCKINGT -3 - loads demoT - 6 - 4 loads demo
AAIDemolished building 4271Worked on hauling demo debris and loading out refrigeratorsAll refrigerators removed from 4271 prior to demo
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSHeld w eekly QC meeting w ith COE - see attached meeting minutes
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Dust control is w orking w ell - no dust
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
The following activity was started today:Activity No DescriptionP51515 Demo Building #4264
No activities were finished today
QC REQUIREMENTS
No QC requirements were completed today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
108
18 Nov 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 4.0 40.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 2.0 21.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 10.0 102.0Total hours w orked to date: 371.5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
001 Link Belt 2800 0.0 10.0002 Samsung 0.0 10.0004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 11.0008 Dump Truck 0.0 11.0009 JD862 B SKAPER 0.0 10.0
Total 0.0 73.0Total operating hours to date: 232.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
109
19 Nov 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 42 F, Max 26 F; No Precipitation; 29 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONWorked on moving dirt from spoil piles to north side of project for f ill on lots.
AAI - No w ork
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Checked equipment to verify operation
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started today
The following activity was finished today:Activity No DescriptionP5305 Government Design Review & App
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
109
19 Nov 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Patterson OPERATING ENGINEER 2.0 20.0Total 2.0 20.0Total hours w orked to date: 391.5
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
006 544H Loader 0.0 9.0009 JD862 B SKAPER 0.0 11.0
Total 0.0 20.0Total operating hours to date: 252.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
112
22 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 37 F, Max 29 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONMove dirt and level different areas of projectHaul concrete pile on phase 5 w est side
ROMAN'S TRUCKINGT - 3 - 4 loads of demo and one load of demo
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Back up alarms on demo equipment
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP51520 Demo Building #4265P5310 Revised Housing - Site & Site
No activities were finished today
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today
No Punch List items were corrected today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
112
22 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Patterson OPERATING ENGINEER 4.0 39.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 12.5
Total 6.0 51.5Total hours w orked to date: 443.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
004 T-6 0.0 10.5005 T-3 0.0 2.0006 544H Loader 0.0 10.0010 JD Scraper 0.0 10.0011 JD Loader 544E 0.0 10.0
Total 0.0 42.5Total operating hours to date: 295.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
113
23 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 23 F, Max 46 F; No Precipitation; 20 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIWorked on hauling demo debris and cleaning concrete slabs
PATTERSONMoved dirt and hauled concrete to phase #4 sot they could crush
ROMAN'S TRUCKINGT - 3 - 4 loads of demo debris
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Vehicle safety inspection for all new site vehicles
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
113
23 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 4.0 40.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 4.0 39.0Roman's Trucking TRUCK DRIVER, GROUP 1 1.0 10.5
Total 11.0 109.5Total hours w orked to date: 552.5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
001 Link Belt 2800 5.0 5.0002 Samsung 4.0 6.0005 T-3 0.0 10.5006 544H Loader 0.0 10.0010 JD Scraper 0.0 3.0011 JD Loader 544E 0.0 10.0011 Bob Cat 4.0 6.0014 JD 330 Track Hoe 0.0 7.0
Total 13.0 57.5Total operating hours to date: 352.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
114
24 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 35 F, Max 44 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONWatered and compacted f ill dirt, cut a little more top soil off.
AAIWorked on demo and clean up
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS No safety issues today
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP51525 Demo Building #4266
No activities were finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
114
24 Nov 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 4.0 20.0Asbestos Abatement OPERATING ENGINEER 1.0 6.0Patterson OPERATING ENGINEER 2.0 28.0
Total 7.0 54.0Total hours w orked to date: 606.5
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
002 Samsung 0.0 6.0006 544H Loader 0.0 3.0010 JD Scraper 0.0 3.0011 JD Loader 544E 0.0 2.0014 JD 330 Track Hoe 0.0 2.0015 JD Smooth Drum Roller 0.0 6.0
Total 0.0 22.0Total operating hours to date: 374.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
119
29 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 24 F; 0.15 IN Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONMoved left over w ater main parts and pipeSew er man holes and storm drain man holesClean upMove to phase 5 - Ryan bringing w ater truck to Idaho
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSReceived some draw ings for distribution to surveyor, Evergreene, and COE
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Need more dust control at demo area - use more w ater
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP51430 Demo Building #4213P51435 Demo Building #4214P51530 Demo Building #4267P51535 Demo Building #4268
The following activity was finished today:Activity No DescriptionP5310 Revised Housing - Site & SiteP5410 All other Work for New Family
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
119
29 Nov 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.0Patterson OPERATING ENGINEER 1.0 9.0
Total 5.0 48.0Total hours w orked to date: 654.5
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
002 Samsung 0.0 0.0004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0010 JD Scraper 0.0 0.0011 JD Loader 544E 0.0 0.0014 JD 330 Track Hoe 0.0 0.0015 JD Smooth Drum Roller 0.0 0.0015 Peterbilt Water Truck 0.0 9.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0
Total 0.0 59.0Total operating hours to date: 433.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
120
30 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 17 F, Max 26 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONMove dirt from pile in middle of project to North side. North side needs 2' to 3' f ill w ater and compact
AAIWorked on demo loading and demo debris and clean up
ROMAN'S TRUCKINGT - 3 - 4 loads demoT - 6 - 4 loads demo
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Held site safety meeting
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP51200 Contractor MobilizationP5315 Government Final Desing Back CP5415 Government Design Review & App
No activities were finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
120
30 Nov 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 2.0 19.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 7.0 70.0Total hours w orked to date: 724.5
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0011 JD Loader 544E 0.0 10.0011 Bob Cat 0.0 2.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0
Total 0.0 62.0Total operating hours to date: 495.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
121
01 Dec 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 21 F, Max 30 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONMove dirt pile to North East side of project. Clean up and haul trees aw ay
AAIDemo, loading, demo debris, and clean up
ROMAN'S TRUCKINGT-3 - 4 loads of demoT-6 - loads of demo
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Back up alarms w orking on equipment
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP51425 Demo Building #4212P51540 Demo Building #4269P51545 Demo Building #4270
No activities were finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
121
01 Dec 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.5Patterson OPERATING ENGINEER 2.0 18.5Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 8.0 79.0Total hours w orked to date: 803.5
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0010 JD Scraper 0.0 9.5011 Bob Cat 0.0 2.0014 JD 330 Track Hoe 0.0 2.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0
Total 0.0 63.5Total operating hours to date: 559.0
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
122
02 Dec 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 24 F, Max 28 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONMove dirt and level out North East side of project
ROMAN'S TRUCKINGT-6 - 2 loads of demo T-3 - 3 loads of demo
AAIHauling demo debris and general clean up
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSHeld w eekly QC meeting, see minutes of meeting
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS No dust problems noted at demo area
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
122
02 Dec 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 2.0 20.0Asbestos Abatement OPERATING ENGINEER 1.0 10.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.0Patterson OPERATING ENGINEER 1.0 9.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 12.5
Total 7.0 60.5Total hours w orked to date: 864.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
004 T-6 0.0 4.5005 T-3 0.0 8.0006 544H Loader 0.0 9.0008 Dump Truck 0.0 4.0010 JD Scraper 0.0 5.0016 Samsung SE 280 7.0 3.0017 Link Belt 2800 Quantum 3.0 7.0
Total 10.0 40.5Total operating hours to date: 599.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
123
03 Dec 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 24 F, Max 30 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONMove dirt and level out North East side of project and haul rock to crusher
CONCRETE CRUSHERSet up crusher at MHAFB
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Inspect crusher equipement
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI&RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHNo activities were started or finished today
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
CONCRETE CRUSHER LABORERS 3.0 24.0
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
123
03 Dec 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
Patterson TRUCK DRIVER, GROUP 1 1.0 2.5Patterson OPERATING ENGINEER 1.0 2.5
Total 5.0 29.0Total hours w orked to date: 893.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
006 544H Loader 0.0 2.5008 Dump Truck 0.0 2.5
Total 0.0 5.0Total operating hours to date: 604.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
126
06 Dec 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 23 F, Max 39 F; No Precipitation; 29 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:PATTERSONWorked on moving piles of dirt, stripping move sage brush and hauling of dirt pile by West Gate Project
CONCRETE CRUSHERFinished setting up crusher and safety orienttion
ROMANS TRUCKINGT-3 - 4 loads of demoT-6 - 4 loads of demo
AC&G ENVIRONMENTALSee attached
AAIDemolished building 4257 and w orked on hauling demo debrisSamsung Loader w as delivered on siteWorked on tearing roofs and doors off of shedsWorked on general clean up
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSCrusher unit needs dust control w aterHas complete Job Hazard Analysis
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
The following activity was started today:Activity No DescriptionP51205 Abate Building #4204P51330 Asbestos Abatement 34 Bldg.
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
126
06 Dec 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
P51550 Demo Building #4271P51555 Demo Building #4273
The following activity was finished today:Activity No DescriptionP51200 Contractor Mobilization
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today
No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
CONCRETE CRUSHER LABORERS 2.0 20.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.0Patterson OPERATING ENGINEER 2.0 18.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 7.0 68.0Total hours w orked to date: 961.0
EQUIPMENT HOURS
The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours
004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0011 JD Loader 544E 0.0 9.0018 Volvo L150 8.0 2.0019 Cat320 8.0 2.0
Total 16.0 52.0Total operating hours to date: 656.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
127
07 Dec 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 32 F, Max 46 F; No Precipitation; 8 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:ROMANS TRUCKINGT- 3 - 4 loads of demoT- 6 - 4 loads of demo
CONCRETE CRUSHERBegan crushing 396 tons of concrete on site - w orked on crusher
AAIDemolished building 4256Worked on hauling demo debrisWorked on general clean upWorked on piling up fencing and steel
AC&GSee attached
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSHeld site safety meeting
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
The following activity was started today:Activity No Description
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
127
07 Dec 2004 - Tuesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
P51210 Abate Building #4210P51215 Abate Building #4211
No activities were finished today
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today
No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 4.0 40.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0CONCRETE CRUSHER OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 4.0 34.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 14.0 135.0Total hours w orked to date: 1,096.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0010 JD Scraper 0.0 7.0011 Bob Cat 6.0 4.0013 JD Track Hoe 790 0.0 9.0014 JD 330 Track Hoe 0.0 6.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0018 Volvo L150 5.0 5.0019 Cat320 5.0 5.0021 NordBerg Crusher 5.0 5.0022 Samsung SL-180 5.0 5.0023 Samsung SE50 5.0 5.0
Total 31.0 110.0Total operating hours to date: 766.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
128
08 Dec 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 36 F, Max 46 F; No Precipitation; 25 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AC&GSee attached
PATTERSONCut roads for phase 5 east loop. Hauled asphalt to end of run w ay - 10 loads. Used truck to haul dirt and rocks from road cut.
AAIDemolished building #4262. Worked on hauling demo debris. Worked on general cleanup
ROMAN'S TRUCKINGT -3 - 4 loads of demoT- 6 - 4 loads of demo
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo dust problems at demo or crusher w ith rain
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
The following activity was started today:Activity No DescriptionP51220 Abate Building #4215P51225 Abate Building #4254P51230 Abate Building #4255P51510 Demo Building #4263P51560 Demo Building #4274
No activities were finished today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
128
08 Dec 2004 - Wednesday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
QC REQUIREMENTS
No QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 3.0 30.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 4.0 37.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 11.0 108.0Total hours w orked to date: 1,204.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0010 JD Scraper 0.0 10.0011 Bob Cat 4.0 6.0014 JD 330 Track Hoe 0.0 9.0016 Samsung SE 280 1.0 9.0017 Link Belt 2800 Quantum 3.0 7.0022 Samsung SL-180 2.0 8.0023 Samsung SE50 2.0 8.0
Total 12.0 96.0Total operating hours to date: 862.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
129
09 Dec 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 39 F, Max 46 F; 0.61 IN Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AAIDemolished garages for building #4259Worked on hauling demo debrisWorked on pulling fencingWorked on moving steel to one spotWorked on cleaning slabs
CONCRETE CRUSHERCrushed 406 tons of concrete
ROMANS TRUCKINGT - 3 - 4 loads of demoT - 6 - 4 loads of demo
PATTERSONCut roads w ith scraper - 2 hoursDress road up w ith 544 H loader - 4 hoursLoad dump truck w ith 330 w ith asphalt - 12 loads to east loop
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSHeld w eekly QC meeting - see attached
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo dust control issues today
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
The following activity was started today:Activity No DescriptionP51235 Abate Building #4256
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
129
09 Dec 2004 - Thursday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
P51240 Abate Building #4257P51245 Abate Building #4258
No activities were finished today
QC REQUIREMENTSNo QC requirements were completed today
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued today
No Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURSThe following labor hours were Reported today: Number of Hours
Employer Labor Classif ication Employees Worked
Asbestos Abatement LABORERS 4.0 37.0Asbestos Abatement OPERATING ENGINEER 3.0 30.0CONCRETE CRUSHER OPERATING ENGINEER 2.0 18.0Patterson TRUCK DRIVER, GROUP 1 4.0 23.0Patterson OPERATING ENGINEER 4.0 23.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0
Total 19.0 152.0Total hours w orked to date: 1,356.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 4.0008 Dump Truck 0.0 9.0010 JD Scraper 0.0 2.0011 Bob Cat 8.0 2.0014 JD 330 Track Hoe 0.0 9.0016 Samsung SE 280 1.0 9.0017 Link Belt 2800 Quantum 1.0 9.0018 Volvo L150 4.0 5.0019 Cat320 4.0 5.0022 Samsung SL-180 6.0 4.0023 Samsung SE50 4.0 6.0
Total 28.0 85.0Total operating hours to date: 947.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
130
10 Dec 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 42 F, Max 57 F; No Precipitation; No Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:CONCRETE CRUSHERNo narrative w ritten
PATTERSONHauled asphalt to north end of runw ay - 9 loadsMove dirt pile by w est gate w ith loaderHauled 10 loads of gravel to east loop
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSNone today
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSSite very muddy- w arned all to w atch step
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISHThe following activity was started today:
Activity No DescriptionP51250 Abate Building #4261P51255 Abate Building #4262P51260 Abate Building #4263
The following activity was finished today:
Activity No DescriptionP5325 IDEQ - Environmental Protectio
QC REQUIREMENTSNo QC requirements were completed today
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
130
10 Dec 2004 - Friday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)
No QC Punch List items were issued todayNo Punch List items were corrected today
CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)
No contractors had their first or last day on site today
LABOR HOURS
The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked
CONCRETE CRUSHER OPERATING ENGINEER 2.0 10.0Patterson TRUCK DRIVER, GROUP 1 1.0 3.0Patterson OPERATING ENGINEER 2.0 18.0
Total 5.0 31.0Total hours w orked to date: 1,387.0
EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating
Serial Number Description Hours Hours
006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0014 JD 330 Track Hoe 0.0 9.0
Total 0.0 27.0Total operating hours to date: 974.5
ACCIDENT REPORTING (Describe accidents)
No accidents reported today
CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.
QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE
Page 2 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
133
13 Dec 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 42 F; No Precipitation; 28 MPH Wind
Evergreene Construction, L.C.
QC NARRATIVES
Activities in Progress:AC&G See attached
TRENCHING SERVICES INCTrenched off site near gas 3' to east tow ards on site man hole #27 at approximately 7' deep. Stopped and w aited for approval for on site trenching for next day
AAIDemolished building #4258 and 4255Worked on hauling demo debrisWorked on folding sheds and loading them into a double lined trailerHauled them to Simco road as ACM
PATTERSONHauled gravel - 5 loads Install 8" sew er main 30' and install man hole #15AContinue installing 8" sew er to man hole #27 26' of sew er installed to east side of gas main
General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today
QUALITY CONTROL TESTING AND RESULTSNone today
REMARKSCan not proceed w ith utilities from phase 4 into phase 5 w ith out w ritten NTP - verbal does not count
Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo dust control needs due to dampness
PREPARATORY AND/OR INITIALS HELD TODAYNone today
CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today
RFI & RFP STATUS UPDATENA
PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)
No preparatory or initial inspections were held today
ACTIVITY START/FINISH
The following activity was started today:Activity No DescriptionP51265 Abate Building #4264P51270 Abate Building #4269
Page 1 of 2
-
CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY
REPORT NUMBER
DATE
PROJECT CONTRACT NUMBER
133
13 Dec 2004 - Monday
DACA67-02-D-2012 0004D/B Replace Military Family Housing P5
P51275 Abate Building #4270P51500 Demo Building #4261P51505 Demo Building #4262P5330 NTP - Phase 5 Grade/Trench (EAP5335 NTP - Phase 5 Site
No a