CONTRACTORS QUALITY CONTROL REPORT (QCR) DAILY LOG OF CONSTRUCTION - MILITARY REPORT NUMBER DATE PROJECT CONTRACT NUMBER 91 01 Nov 2004 - Monday DACA67-02-D-2012 0004 D/B Replace Military Family Housing P5 CONTRACTOR WEATHER Weather Caused No Delay Temperature Min 21 °F, Max 44 °F; No Precipitation; No Wind Evergreene Construction, L.C. QC NARRATIVES Activities in Progress: AAI Worked on shutting down water and removing refrigerators General Comments: DAILY CONTROL INSPECTIONS AND RESULTS None today QUALITY CONTROL TESTING AND RESULTS None today REMARKS No remarks today Safety Inspection / Safety Meetings: DAILY SAFETY INSPECTIONS None today PREPARATORY AND/OR INITIALS HELD TODAY Held demo prep meeting today with AAI. See attached minutes of meeting. Will start next week with demo. They brought new license, number was okay by Jim LaFluer. PREP/INITIAL DATES (Preparatory and initial dates held and advance notice) No preparatory or initial inspections were held today ACTIVITY START/FINISH No activities were started or finished today QC REQUIREMENTS No QC requirements were completed today QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected) No QC Punch List items were issued today No Punch List items were corrected today CONTRACTORS ON SITE (Report first and/or last day contractors were on site) No contractors had their first or last day on site today LABOR HOURS The following labor hours were Reported today: Number of Hours Employer Labor Classification Employees Worked Asbestos Abatement OPERATING ENGINEER 0.0 0.0 Total 0.0 0.0 Total hours worked to date: 0.0 EQUIPMENT HOURS No equipment hours were Reported today Total operating hours to date: 0.0 Page 1 of 2

Transcript of CONTRACTORS QUALITY CONTROL REPORT (QCR) … QC Daily Report.pdf · contractors quality control...

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    91

    01 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 21 F, Max 44 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIWorked on shutting down water and removing refrigerators

    General Comments:DAILY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNo remarks today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNone today

    PREPARATORY AND/OR INITIALS HELD TODAYHeld demo prep meeting today with AAI. See attached minutes of meeting. Will start next week with demo. They brought new license, number was okay by Jim LaFluer.

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors were on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours worked to date: 0.0

    EQUIPMENT HOURS

    No equipment hours were Reported todayTotal operating hours to date: 0.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    91

    01 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    92

    02 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 28 F, Max 53 F; No Precipitation; 29 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:EVERGREENE MANAGEMENTReview ed tree preservation plan w ith COE, Base and Base Arborist. Some trees are missing and mislabeled. Generally okay. Several additional trees w ere added to the removal due to the condition of the trees - old split trunks, and poor conditionsShould there be added costs for removal of these trees (No additional Did not f inish. NE area remains. Scheduled to f inish on Wednesday at 10:30 am.

    AAIShutting dow n w ater, and removing refrigerators

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNone today

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    92

    02 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0

    EQUIPMENT HOURSNo equipment hours were Reported today

    Total operating hours to date: 0.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    93

    03 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 39 F, Max 48 F; 0.12 IN Precipitation; 20 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIShutting dow n w ater and removing refrigerators

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    93

    03 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    EQUIPMENT HOURS

    No equipment hours were Reported todayTotal operating hours to date: 0.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    94

    04 Nov 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 32 F, Max 50 F; No Precipitation; 14 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIShutting dow n w ater and removing refrigerators

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    94

    04 Nov 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    EQUIPMENT HOURS

    No equipment hours were Reported todayTotal operating hours to date: 0.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    95

    05 Nov 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 54 F; No Precipitation; 13 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIShutting dow n w ater and removing refrigerators

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    95

    05 Nov 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    EQUIPMENT HOURS

    No equipment hours were Reported todayTotal operating hours to date: 0.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    96

    06 Nov 2004 - Saturday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 23 F, Max 39 F; No Precipitation; 29 MPH Wind

    Parsons Evergreene Construction, L.L.C.

    QC NARRATIVESNo QC Narratives were reported today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement OPERATING ENGINEER 0.0 0.0Total 0.0 0.0Total hours w orked to date: 0.0

    EQUIPMENT HOURSNo equipment hours were Reported today

    Total operating hours to date: 0.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance with the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 1 of 1

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    98

    08 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 34 F, Max 41 F; 0.04 IN Precipitation; 8 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSWater to buildings 4204, 4210,4211 are connected to TLF units. Must be isolated - not just turned off at unit. Corp stop - need outage!

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYHeld preparatory meeting today for HazMat w ith Steven Galley and AAI - see attatched.

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSNo labor hours were Reported today

    Total hours w orked to date: 0.0

    EQUIPMENT HOURSNo equipment hours were Reported today

    Total operating hours to date: 0.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 1 of 1

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    99

    09 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 35 F, Max 46 F; No Precipitation; 12 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIDemolished building #4215

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP5410 All other Work for New Family

    No activities were finished today

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 1.0 5.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    99

    09 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    Asbestos Abatement OPERATING ENGINEER 1.0 10.0Total 2.0 15.0Total hours w orked to date: 15.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    001 Link Belt 2800 0.0 10.0Total 0.0 10.0Total operating hours to date: 10.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    100

    10 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 34 F, Max 51 F; 0.15 IN Precipitation; 13 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIDemolished building 4264 - crunching and hauling demolition debris.

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSSent email to Jim LaFluer w ith UHF radio frequencies w e w ant to use onsite

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 2.0 20.0Asbestos Abatement OPERATING ENGINEER 1.0 10.0

    Total 3.0 30.0Total hours w orked to date: 45.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    100

    10 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    001 Link Belt 2800 0.0 10.0Total 0.0 10.0Total operating hours to date: 20.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    101

    11 Nov 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 41 F, Max 49 F; 0.15 IN Precipitation; 9 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIDemolished garages for buildings #4215 and #4212. Worked on hauling demolition debris.

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSHeld w eekly QC meeting - see attached meeting minutes

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0

    Total 3.0 30.0Total hours w orked to date: 75.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    101

    11 Nov 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    001 Link Belt 2800 0.0 10.0002 Samsung 0.0 8.5

    Total 0.0 18.5Total operating hours to date: 38.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    102

    12 Nov 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 42 F, Max 48 F; No Precipitation; 12 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:Patterson - No w orkAAI - No w ork

    General Comments:QUALITY CONTROL INSPECTION AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNo remarks

    Safety Inspection / Safety Meetings:DAILY SAFETY ISSUESNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP51415 Demo Building #4210

    No activities were finished today

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    102

    12 Nov 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    LABOR HOURS

    No labor hours were Reported todayTotal hours w orked to date: 75.0

    EQUIPMENT HOURSNo equipment hours were Reported today

    Total operating hours to date: 38.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    105

    15 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 34 F, Max 55 F; 21 IN Precipitation; 24 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:ROMANS TRUCKING T - 3 - 4 loads of demoT - 6 - 4 loads of demo

    AAIDemolished garage #4213 and building #4210. Crunching and heavy demo debris. Checked building for refrigerators.

    General Comments:QUALITY CONTROL INSPECTION AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNo remarks

    Safety Inspection / Safety Meetings:DAILY SAFETY ISSUESNo safety issues

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    105

    15 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 1.0 3.5Asbestos Abatement OPERATING ENGINEER 2.0 20.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 5.0 44.5Total hours w orked to date: 119.5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    001 Link Belt 2800 0.0 10.0002 Samsung 3.0 7.0

    Total 3.0 17.0Total operating hours to date: 55.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    106

    16 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 51 F; No Precipitation; 17 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONStripping sage brush and hauling off to East side of golf course. Worked on moving piles of dirt.

    AAIDemolished building #4211 All refrigerators removedWorked on hauling demo debrisShooting off w ater to building 4204 - broke 4 inch line to repair it

    ROMAN'S TRUCKINGT -3 - 4 loads demoT - 6 - 4 loads demo

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSHit service line to building 4211, must shut off w ater to TLF and laundry. Emergency repair.Note - w e w ere afraid the above may happen and requested an outage but w ere denied.

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTION Held site safety meeting - see attached

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENone today

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISH

    The following activity was started today:Activity No DescriptionP51440 Demo Building #4215

    No activities were finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    106

    16 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 3.0 27.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 8.0 78.0Total hours w orked to date: 197.5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    001 Link Belt 2800 0.0 10.0002 Samsung 0.0 10.0004 T-6 0.0 10.5005 T-3 0.0 10.5

    Total 0.0 41.0Total operating hours to date: 96.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    107

    17 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 26 F, Max 37 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONHauling sage brush to east side of golf course and move dirt piles

    AAIDemolished building 4204All refrigerators removedWorked on hauling demo debris

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS No safety issues today

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    107

    17 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 2.0 20.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 2.0 11.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 8.0 72.0Total hours w orked to date: 269.5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    001 Link Belt 2800 0.0 10.0002 Samsung 0.0 10.0004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 11.0008 Dump Truck 0.0 11.0

    Total 0.0 63.0Total operating hours to date: 159.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    108

    18 Nov 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 32 F, Max 48 F; No Precipitation; 28 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONWorked on hauling sage brush to East side of golf courseWorked on moving piles

    ROMAN'S TRUCKINGT -3 - loads demoT - 6 - 4 loads demo

    AAIDemolished building 4271Worked on hauling demo debris and loading out refrigeratorsAll refrigerators removed from 4271 prior to demo

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSHeld w eekly QC meeting w ith COE - see attached meeting minutes

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Dust control is w orking w ell - no dust

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISH

    The following activity was started today:Activity No DescriptionP51515 Demo Building #4264

    No activities were finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    108

    18 Nov 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 4.0 40.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 2.0 21.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 10.0 102.0Total hours w orked to date: 371.5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    001 Link Belt 2800 0.0 10.0002 Samsung 0.0 10.0004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 11.0008 Dump Truck 0.0 11.0009 JD862 B SKAPER 0.0 10.0

    Total 0.0 73.0Total operating hours to date: 232.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    109

    19 Nov 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 42 F, Max 26 F; No Precipitation; 29 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONWorked on moving dirt from spoil piles to north side of project for f ill on lots.

    AAI - No w ork

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Checked equipment to verify operation

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started today

    The following activity was finished today:Activity No DescriptionP5305 Government Design Review & App

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    109

    19 Nov 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Patterson OPERATING ENGINEER 2.0 20.0Total 2.0 20.0Total hours w orked to date: 391.5

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    006 544H Loader 0.0 9.0009 JD862 B SKAPER 0.0 11.0

    Total 0.0 20.0Total operating hours to date: 252.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    112

    22 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 37 F, Max 29 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONMove dirt and level different areas of projectHaul concrete pile on phase 5 w est side

    ROMAN'S TRUCKINGT - 3 - 4 loads of demo and one load of demo

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Back up alarms on demo equipment

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP51520 Demo Building #4265P5310 Revised Housing - Site & Site

    No activities were finished today

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued today

    No Punch List items were corrected today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    112

    22 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Patterson OPERATING ENGINEER 4.0 39.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 12.5

    Total 6.0 51.5Total hours w orked to date: 443.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    004 T-6 0.0 10.5005 T-3 0.0 2.0006 544H Loader 0.0 10.0010 JD Scraper 0.0 10.0011 JD Loader 544E 0.0 10.0

    Total 0.0 42.5Total operating hours to date: 295.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    113

    23 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 23 F, Max 46 F; No Precipitation; 20 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIWorked on hauling demo debris and cleaning concrete slabs

    PATTERSONMoved dirt and hauled concrete to phase #4 sot they could crush

    ROMAN'S TRUCKINGT - 3 - 4 loads of demo debris

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Vehicle safety inspection for all new site vehicles

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    113

    23 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 4.0 40.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 4.0 39.0Roman's Trucking TRUCK DRIVER, GROUP 1 1.0 10.5

    Total 11.0 109.5Total hours w orked to date: 552.5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    001 Link Belt 2800 5.0 5.0002 Samsung 4.0 6.0005 T-3 0.0 10.5006 544H Loader 0.0 10.0010 JD Scraper 0.0 3.0011 JD Loader 544E 0.0 10.0011 Bob Cat 4.0 6.0014 JD 330 Track Hoe 0.0 7.0

    Total 13.0 57.5Total operating hours to date: 352.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    114

    24 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 35 F, Max 44 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONWatered and compacted f ill dirt, cut a little more top soil off.

    AAIWorked on demo and clean up

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS No safety issues today

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP51525 Demo Building #4266

    No activities were finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    114

    24 Nov 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 4.0 20.0Asbestos Abatement OPERATING ENGINEER 1.0 6.0Patterson OPERATING ENGINEER 2.0 28.0

    Total 7.0 54.0Total hours w orked to date: 606.5

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    002 Samsung 0.0 6.0006 544H Loader 0.0 3.0010 JD Scraper 0.0 3.0011 JD Loader 544E 0.0 2.0014 JD 330 Track Hoe 0.0 2.0015 JD Smooth Drum Roller 0.0 6.0

    Total 0.0 22.0Total operating hours to date: 374.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    119

    29 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 24 F; 0.15 IN Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONMoved left over w ater main parts and pipeSew er man holes and storm drain man holesClean upMove to phase 5 - Ryan bringing w ater truck to Idaho

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSReceived some draw ings for distribution to surveyor, Evergreene, and COE

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Need more dust control at demo area - use more w ater

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP51430 Demo Building #4213P51435 Demo Building #4214P51530 Demo Building #4267P51535 Demo Building #4268

    The following activity was finished today:Activity No DescriptionP5310 Revised Housing - Site & SiteP5410 All other Work for New Family

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    119

    29 Nov 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    No Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.0Patterson OPERATING ENGINEER 1.0 9.0

    Total 5.0 48.0Total hours w orked to date: 654.5

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    002 Samsung 0.0 0.0004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0010 JD Scraper 0.0 0.0011 JD Loader 544E 0.0 0.0014 JD 330 Track Hoe 0.0 0.0015 JD Smooth Drum Roller 0.0 0.0015 Peterbilt Water Truck 0.0 9.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0

    Total 0.0 59.0Total operating hours to date: 433.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    120

    30 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 17 F, Max 26 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONMove dirt from pile in middle of project to North side. North side needs 2' to 3' f ill w ater and compact

    AAIWorked on demo loading and demo debris and clean up

    ROMAN'S TRUCKINGT - 3 - 4 loads demoT - 6 - 4 loads demo

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Held site safety meeting

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP51200 Contractor MobilizationP5315 Government Final Desing Back CP5415 Government Design Review & App

    No activities were finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    120

    30 Nov 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    No Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 2.0 19.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 7.0 70.0Total hours w orked to date: 724.5

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0011 JD Loader 544E 0.0 10.0011 Bob Cat 0.0 2.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0

    Total 0.0 62.0Total operating hours to date: 495.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    121

    01 Dec 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 21 F, Max 30 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONMove dirt pile to North East side of project. Clean up and haul trees aw ay

    AAIDemo, loading, demo debris, and clean up

    ROMAN'S TRUCKINGT-3 - 4 loads of demoT-6 - loads of demo

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Back up alarms w orking on equipment

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP51425 Demo Building #4212P51540 Demo Building #4269P51545 Demo Building #4270

    No activities were finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    121

    01 Dec 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    No Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 1.0 10.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.5Patterson OPERATING ENGINEER 2.0 18.5Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 8.0 79.0Total hours w orked to date: 803.5

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0010 JD Scraper 0.0 9.5011 Bob Cat 0.0 2.0014 JD 330 Track Hoe 0.0 2.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0

    Total 0.0 63.5Total operating hours to date: 559.0

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    122

    02 Dec 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 24 F, Max 28 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONMove dirt and level out North East side of project

    ROMAN'S TRUCKINGT-6 - 2 loads of demo T-3 - 3 loads of demo

    AAIHauling demo debris and general clean up

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSHeld w eekly QC meeting, see minutes of meeting

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS No dust problems noted at demo area

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    122

    02 Dec 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 2.0 20.0Asbestos Abatement OPERATING ENGINEER 1.0 10.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.0Patterson OPERATING ENGINEER 1.0 9.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 12.5

    Total 7.0 60.5Total hours w orked to date: 864.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    004 T-6 0.0 4.5005 T-3 0.0 8.0006 544H Loader 0.0 9.0008 Dump Truck 0.0 4.0010 JD Scraper 0.0 5.0016 Samsung SE 280 7.0 3.0017 Link Belt 2800 Quantum 3.0 7.0

    Total 10.0 40.5Total operating hours to date: 599.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    123

    03 Dec 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 24 F, Max 30 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONMove dirt and level out North East side of project and haul rock to crusher

    CONCRETE CRUSHERSet up crusher at MHAFB

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONS Inspect crusher equipement

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI&RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHNo activities were started or finished today

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    CONCRETE CRUSHER LABORERS 3.0 24.0

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    123

    03 Dec 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    Patterson TRUCK DRIVER, GROUP 1 1.0 2.5Patterson OPERATING ENGINEER 1.0 2.5

    Total 5.0 29.0Total hours w orked to date: 893.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    006 544H Loader 0.0 2.5008 Dump Truck 0.0 2.5

    Total 0.0 5.0Total operating hours to date: 604.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    126

    06 Dec 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 23 F, Max 39 F; No Precipitation; 29 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:PATTERSONWorked on moving piles of dirt, stripping move sage brush and hauling of dirt pile by West Gate Project

    CONCRETE CRUSHERFinished setting up crusher and safety orienttion

    ROMANS TRUCKINGT-3 - 4 loads of demoT-6 - 4 loads of demo

    AC&G ENVIRONMENTALSee attached

    AAIDemolished building 4257 and w orked on hauling demo debrisSamsung Loader w as delivered on siteWorked on tearing roofs and doors off of shedsWorked on general clean up

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSCrusher unit needs dust control w aterHas complete Job Hazard Analysis

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISH

    The following activity was started today:Activity No DescriptionP51205 Abate Building #4204P51330 Asbestos Abatement 34 Bldg.

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    126

    06 Dec 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    P51550 Demo Building #4271P51555 Demo Building #4273

    The following activity was finished today:Activity No DescriptionP51200 Contractor Mobilization

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued today

    No Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    CONCRETE CRUSHER LABORERS 2.0 20.0Patterson TRUCK DRIVER, GROUP 1 1.0 9.0Patterson OPERATING ENGINEER 2.0 18.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 7.0 68.0Total hours w orked to date: 961.0

    EQUIPMENT HOURS

    The following equipment hours were Reported today: Standby OperatingSerial Number Description Hours Hours

    004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0011 JD Loader 544E 0.0 9.0018 Volvo L150 8.0 2.0019 Cat320 8.0 2.0

    Total 16.0 52.0Total operating hours to date: 656.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    127

    07 Dec 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 32 F, Max 46 F; No Precipitation; 8 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:ROMANS TRUCKINGT- 3 - 4 loads of demoT- 6 - 4 loads of demo

    CONCRETE CRUSHERBegan crushing 396 tons of concrete on site - w orked on crusher

    AAIDemolished building 4256Worked on hauling demo debrisWorked on general clean upWorked on piling up fencing and steel

    AC&GSee attached

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSHeld site safety meeting

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISH

    The following activity was started today:Activity No Description

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    127

    07 Dec 2004 - Tuesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    P51210 Abate Building #4210P51215 Abate Building #4211

    No activities were finished today

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued today

    No Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 4.0 40.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0CONCRETE CRUSHER OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 4.0 34.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 14.0 135.0Total hours w orked to date: 1,096.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0010 JD Scraper 0.0 7.0011 Bob Cat 6.0 4.0013 JD Track Hoe 790 0.0 9.0014 JD 330 Track Hoe 0.0 6.0016 Samsung SE 280 0.0 10.0017 Link Belt 2800 Quantum 0.0 10.0018 Volvo L150 5.0 5.0019 Cat320 5.0 5.0021 NordBerg Crusher 5.0 5.0022 Samsung SL-180 5.0 5.0023 Samsung SE50 5.0 5.0

    Total 31.0 110.0Total operating hours to date: 766.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    128

    08 Dec 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 36 F, Max 46 F; No Precipitation; 25 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AC&GSee attached

    PATTERSONCut roads for phase 5 east loop. Hauled asphalt to end of run w ay - 10 loads. Used truck to haul dirt and rocks from road cut.

    AAIDemolished building #4262. Worked on hauling demo debris. Worked on general cleanup

    ROMAN'S TRUCKINGT -3 - 4 loads of demoT- 6 - 4 loads of demo

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo dust problems at demo or crusher w ith rain

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISH

    The following activity was started today:Activity No DescriptionP51220 Abate Building #4215P51225 Abate Building #4254P51230 Abate Building #4255P51510 Demo Building #4263P51560 Demo Building #4274

    No activities were finished today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    128

    08 Dec 2004 - Wednesday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    QC REQUIREMENTS

    No QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 3.0 30.0Asbestos Abatement OPERATING ENGINEER 2.0 20.0Patterson OPERATING ENGINEER 4.0 37.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 11.0 108.0Total hours w orked to date: 1,204.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0010 JD Scraper 0.0 10.0011 Bob Cat 4.0 6.0014 JD 330 Track Hoe 0.0 9.0016 Samsung SE 280 1.0 9.0017 Link Belt 2800 Quantum 3.0 7.0022 Samsung SL-180 2.0 8.0023 Samsung SE50 2.0 8.0

    Total 12.0 96.0Total operating hours to date: 862.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    129

    09 Dec 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 39 F, Max 46 F; 0.61 IN Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AAIDemolished garages for building #4259Worked on hauling demo debrisWorked on pulling fencingWorked on moving steel to one spotWorked on cleaning slabs

    CONCRETE CRUSHERCrushed 406 tons of concrete

    ROMANS TRUCKINGT - 3 - 4 loads of demoT - 6 - 4 loads of demo

    PATTERSONCut roads w ith scraper - 2 hoursDress road up w ith 544 H loader - 4 hoursLoad dump truck w ith 330 w ith asphalt - 12 loads to east loop

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSHeld w eekly QC meeting - see attached

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo dust control issues today

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISH

    The following activity was started today:Activity No DescriptionP51235 Abate Building #4256

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    129

    09 Dec 2004 - Thursday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    P51240 Abate Building #4257P51245 Abate Building #4258

    No activities were finished today

    QC REQUIREMENTSNo QC requirements were completed today

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued today

    No Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURSThe following labor hours were Reported today: Number of Hours

    Employer Labor Classif ication Employees Worked

    Asbestos Abatement LABORERS 4.0 37.0Asbestos Abatement OPERATING ENGINEER 3.0 30.0CONCRETE CRUSHER OPERATING ENGINEER 2.0 18.0Patterson TRUCK DRIVER, GROUP 1 4.0 23.0Patterson OPERATING ENGINEER 4.0 23.0Roman's Trucking TRUCK DRIVER, GROUP 1 2.0 21.0

    Total 19.0 152.0Total hours w orked to date: 1,356.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    004 T-6 0.0 10.5005 T-3 0.0 10.5006 544H Loader 0.0 4.0008 Dump Truck 0.0 9.0010 JD Scraper 0.0 2.0011 Bob Cat 8.0 2.0014 JD 330 Track Hoe 0.0 9.0016 Samsung SE 280 1.0 9.0017 Link Belt 2800 Quantum 1.0 9.0018 Volvo L150 4.0 5.0019 Cat320 4.0 5.0022 Samsung SL-180 6.0 4.0023 Samsung SE50 4.0 6.0

    Total 28.0 85.0Total operating hours to date: 947.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    130

    10 Dec 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 42 F, Max 57 F; No Precipitation; No Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:CONCRETE CRUSHERNo narrative w ritten

    PATTERSONHauled asphalt to north end of runw ay - 9 loadsMove dirt pile by w est gate w ith loaderHauled 10 loads of gravel to east loop

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSNone today

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSSite very muddy- w arned all to w atch step

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISHThe following activity was started today:

    Activity No DescriptionP51250 Abate Building #4261P51255 Abate Building #4262P51260 Abate Building #4263

    The following activity was finished today:

    Activity No DescriptionP5325 IDEQ - Environmental Protectio

    QC REQUIREMENTSNo QC requirements were completed today

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    130

    10 Dec 2004 - Friday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    QA/QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected)

    No QC Punch List items were issued todayNo Punch List items were corrected today

    CONTRACTORS ON SITE (Report f irst and/or last day contractors w ere on site)

    No contractors had their first or last day on site today

    LABOR HOURS

    The following labor hours were Reported today: Number of HoursEmployer Labor Classif ication Employees Worked

    CONCRETE CRUSHER OPERATING ENGINEER 2.0 10.0Patterson TRUCK DRIVER, GROUP 1 1.0 3.0Patterson OPERATING ENGINEER 2.0 18.0

    Total 5.0 31.0Total hours w orked to date: 1,387.0

    EQUIPMENT HOURSThe following equipment hours were Reported today: Standby Operating

    Serial Number Description Hours Hours

    006 544H Loader 0.0 9.0008 Dump Truck 0.0 9.0014 JD 330 Track Hoe 0.0 9.0

    Total 0.0 27.0Total operating hours to date: 974.5

    ACCIDENT REPORTING (Describe accidents)

    No accidents reported today

    CONTRACTOR CERTIFICATION On behalf of the contractor, I certify that this Report is complete and correct and all equipment andmaterial used and work performed during this Reporting period are in compliance w ith the contractplans and specifications, to the best of my knowledge, except as noted above.

    QC REPRESENTATIVE'S SIGNATURE DATE SUPERINTENDENT'S INITIALS DATE

    Page 2 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    133

    13 Dec 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    CONTRACTOR WEATHERWeather Caused No DelayTemperature Min 33 F, Max 42 F; No Precipitation; 28 MPH Wind

    Evergreene Construction, L.C.

    QC NARRATIVES

    Activities in Progress:AC&G See attached

    TRENCHING SERVICES INCTrenched off site near gas 3' to east tow ards on site man hole #27 at approximately 7' deep. Stopped and w aited for approval for on site trenching for next day

    AAIDemolished building #4258 and 4255Worked on hauling demo debrisWorked on folding sheds and loading them into a double lined trailerHauled them to Simco road as ACM

    PATTERSONHauled gravel - 5 loads Install 8" sew er main 30' and install man hole #15AContinue installing 8" sew er to man hole #27 26' of sew er installed to east side of gas main

    General Comments:QUALITY CONTROL INSPECTIONS AND RESULTSNone today

    QUALITY CONTROL TESTING AND RESULTSNone today

    REMARKSCan not proceed w ith utilities from phase 4 into phase 5 w ith out w ritten NTP - verbal does not count

    Safety Inspection / Safety Meetings:DAILY SAFETY INSPECTIONSNo dust control needs due to dampness

    PREPARATORY AND/OR INITIALS HELD TODAYNone today

    CONTRACTORS FIRST AND/OR LAST DAY ONSITENone today

    RFI & RFP STATUS UPDATENA

    PREP/INITIAL DATES (Preparatory and initial dates held and advance notice)

    No preparatory or initial inspections were held today

    ACTIVITY START/FINISH

    The following activity was started today:Activity No DescriptionP51265 Abate Building #4264P51270 Abate Building #4269

    Page 1 of 2

  • CONTRACTORS QUALITY CONTROL REPORT (QCR)DAILY LOG OF CONSTRUCTION - MILITARY

    REPORT NUMBER

    DATE

    PROJECT CONTRACT NUMBER

    133

    13 Dec 2004 - Monday

    DACA67-02-D-2012 0004D/B Replace Military Family Housing P5

    P51275 Abate Building #4270P51500 Demo Building #4261P51505 Demo Building #4262P5330 NTP - Phase 5 Grade/Trench (EAP5335 NTP - Phase 5 Site

    No a